This notice provides preliminary information for an upcoming federal highway construction project in Flathead County, Montana. The project involves resurfacing approximately 10 miles of the North Fork River Road, grading and milling placement on Glacier Drive near Polebridge, and grading with milling placement on the Blankenship and Belton Stage Road. Prospective offerors are encouraged to view the project sites in fall 2022 due to limited winter access. The solicitation will be released in winter 2022-2023 via SAM.gov and has an estimated price range of $1 million to $5 million. All technical questions must be submitted to the Western Federal Lands Highway Division and general questions directed to their contracts office. The tentative completion date is fall 2023 once the solicitation is issued.

View the file

Other files

File Type Posted
MT_FLATHEAD_486(1)_Preliminary_NotForConstruction.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Western Federal Lands Highway Division 610 E. Fifth Street

Vancouver, WA 98661 Phone 360-619-7700

Fax 360-619-7846

NOTICE TO PROSPECTIVE BIDDERS

RE: NORTH FORK OF THE FLATHEAD RIVER MT FLATHEAD 486(1)&

BLANKENSHIP AND BELTON STAGE ROAD RESURFACING MT FLAP FLATHD

2021(1) Solicitation No. 69056722B000016

The attached preliminary plans are being furnished to aid prospective Bidders in identifying the location and type of work for this project. The project will be advertised during a period when viewing of the project may not be possible due to snow. Therefore, prospective Offerors are encouraged to view the project during fall as conditions permit. After November 11, 2022 access will be weather dependent; contact David Prunty at 406-758-5790, Flathead County Road Department for current road conditions. No Federal Highway Administration personnel will be available for show-me tours.

Project Location and Type of Work - All project work is located on or along the North Fork River road in Flathead County Montana o North Fork River Road- (Milepost 50 to 55) Work consists of grading, drainage, material pit development, gravel surfacing, traffic control, and signage.

o Glacier Drive (Located near Polebridge Montana) - work consists grading, placing government provided millings, drainage, traffic control, stripping, and signage.

o Blankenship/Belton Stage Road – work consists of grading, drainage, and placing government furnished millings.

Technical Questions – All technical questions must be submitted by email wfl.plans-spec@dot.gov .

General Questions - Contact our office at wfl.contracts@dot.gov or at 360-619-7520.

Solicitation documents - Documents will be available during the winter of 2022/2023. Please monitor the SAM site for actual date of solicitation release (https://beta.sam.gov/). To receive automatic notification through SAM, you must login and select “Follow” feature and follow the steps as indicated.

Thank you for your interest in this project.

Date August 18th, 2022