About this file

This is a Pre-Bid Conference Attendance document for IFB114424, a locally administered project (LAP) by the City of Fairfax in partnership with VDOT (Virginia Department of Transportation) and FHWA (Federal Highway Administration). The project, titled "University Drive Bike Lanes - South Street to Kenmore Drive," involves the design and construction of bicycle and pedestrian improvements along University Drive, including pavement microsurfacing, restriping for on-road bike lanes, sharrows, ADA-compliant curb ramps, and green bike lane colored pavement between Layton Hall Drive and North Street. The pre-bid meeting was held on July 14, 2026, at 11:00 A.M. via Microsoft Teams, with six contractors and four City of Fairfax representatives in attendance. The bid inquiry deadline is July 22, 2026, with bids due August 10, 2026, by 2:00 P.M. Substantial completion is required within 180 days of notice to proceed, and final completion within 210 days, with liquidated damages assessed at $600 per calendar day for delays.

The project is funded through VDOT and FHWA with State Project No. EN22-151-221, C501 and TAP-5B01-(338), and VDOT UPC 121556. This is a unit price contract requiring bidders to include all mobilization costs, which must account for multiple mobilizations due to scheduling constraints and phasing. Special provisions require all microsurfacing operations and re-striping in high-traffic areas to be performed exclusively between 9:00 P.M. and 5:00 A.M., with daytime work in active City streets limited to 9:00 A.M. to 3:00 P.M. Monday-Thursday and 9:00 A.M. to 2:00 P.M. on Fridays. Bidders must obtain Noise Variance Permits and incorporate nighttime premiums and specialized lighting costs into their bids. Materials must conform to 2020 VDOT Specifications and include pre-formed thermoplastic bike lane color pavement marking material from approved manufacturers. Buy America provisions apply to iron and steel products, and contractors must submit mandatory VDOT C-series forms for FHWA/VDOT reimbursement.

View the file

Other files

File Type Posted
SQ105-000611-01.docx DOCX document
cn801-000100-00.docx DOCX document
SS321-002020-02.docx DOCX document
SS220-002020-01.docx DOCX document
SS235-002020-01.docx DOCX document
SP107-001510-06.docx DOCX document
cn105-000150-00.docx DOCX document
UPC 121556 C-105 form.pdf PDF
2 - Appendix A - Approved by City Attorney 6.2026.pdf PDF
SS236-002020-01.docx DOCX document
SP0F0-000100-00.docx DOCX document
SQ107-001300-00.docx DOCX document
SS246-002020-02.docx DOCX document
cq107-000130-00.docx DOCX document
SS315-002020-05.docx DOCX document
SP107-000120-00.docx DOCX document
SS318-002020-01.docx DOCX document
3 - UPC 121556 PW Standards & Specifications.pdf PDF
cn105-000140-00.docx DOCX document
SS407-002020-02.docx DOCX document
SS317-002020-01.docx DOCX document
12 - Bid Submission Form.pdf PDF
SS223-002020-02.docx DOCX document
SP109-000100-05.docx DOCX document
SS411-002020-01 .docx DOCX document
7 - IFB 114424 University Dr Bike Lanes Final Plans - UPC 121556.pdf PDF
SS234-002020-01.docx DOCX document
SS308-002020-01.docx DOCX document
10 - Standard Labor and Material Payment Bond - Fairfax City.pdf PDF
SP107-003100-00.docx DOCX document
cn100-000026-09.docx DOCX document
UPC 121556 C-76 form.pdf PDF
SS512-002020-03.docx DOCX document
SS211-002020-03.docx DOCX document
1 - IFB 114424 University Dr Bike Lanes - UPC 121556.pdf PDF
cn103-000100-01.docx DOCX document
SP100-000051-00.docx DOCX document
5 - UPC 121556 Project Special Provisions.pdf PDF
SP0F0-000130-02.docx DOCX document
SS109-002020-01.docx DOCX document
UPC 121556 C-48 form.pdf PDF
SS319-002020-02.docx DOCX document
11 - Fairfax City Performance Bond.pdf PDF
SS248-002020-02.docx DOCX document
SS704-002020-02.docx DOCX document
SP0F0-000150-01.docx DOCX document
SS305-002020-02.docx DOCX document
SS309-002020-01 .docx DOCX document
UPC 121556 C-104 form.pdf PDF
Show all 49

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

IFB114424

PRE-BID ATTENDANCE

JUNE 14, 2026

Name Representing

Ben Custead WG Construction

David Weller Sagres Construction Corp.

Geoff Giffin Kimley-Horm

Phil Frazier Arthur Construction

Chloe Ritter Fairfax City

Sunny Sarna Fairfax City

Walt Harrison Fairfax City

Patti Innocenti Fairfax City

PRE-BID MEETING AGENDA

PROJECT: University Drive Bike Lanes – South Street to Kenmore Drive

OWNER: City of Fairfax (Locally Administered Project - LAP)

FUNDING: VDOT / FHWA

STATE PROJECT NO: EN22-151-221, C501 / TAP-5B01-(338) VDOT UPC: 121556

DATE: July 14, 2026 TIME: 11:00 A.M.

LOCATION: Online Via Microsoft Teams:

https://teams.microsoft.com/meet/231497717348804?p=T5C5

3cxNaClXCR7Ki0

I. ATTENDEES & VIRTUAL SIGN-IN

• Virtual Sign-In: All participants must enter their Name, Title, and Firm in the Teams Chat box for the official record.

• Plan Holders List: Ensure your firm is registered on the City’s procurement portal and eVA to receive all mandatory addenda.

II. INTRODUCTIONS

• City of Fairfax: Transportation Capital Projects & Construction Management

• Kimley-Horn & Associates: Engineer of Record – Megan Waring, PE

• Oversight Partners: VDOT Locally Administered Projects (LAP) & FHWA

III. GENERAL INFORMATION & LAP FRAMEWORK

• VDOT LAP Compliance: This project follows the VDOT LAP Manual. Strict adherence to federal/state reporting and Civil Rights (DBE) is required.

• Construction documentation must satisfy the City of Fairfax, VDOT, and FHWA audit requirements.

• Addenda: Discussions today are non-binding. Any changes to the IFB will be issued via written addendum.

IV. PROJECT SCOPE & IDENTIFICATION

Improvements: This project is for the design of bicycle and pedestrian improvements along University Drive. Pavement markings will be eradicated and the surface will be microsurfaced and restriped to add on-road bike lanes between Layton Hall Drive and North Street and sharrows between North Street and South Street. Pedestrian facilities at the University Drive and Layton Hall Drive intersection will include ADA-compliant curb ramps and curb modifications with a pedestrian crossing on the south leg of the University Drive.

https://teams.microsoft.com/meet/231497717348804?p=T5C5

• Technical Standards: 2020 VDOT Specifications, 2016 VDOT Standards, City PFM, 2011 WAPM, and PROWAG/ADA compliance.

V. SITE CONSTRAINTS & RESTRICTED WORK AREAS

Special Work Hours and Scheduling

1. Nighttime Operations: The Bidder is advised that all micro-surfacing operations under this contract shall be performed exclusively during nighttime hours, defined as 9:00 PM to 5:00 AM.

The Contractor shall be responsible for providing all necessary lighting, safety equipment, and traffic control measures required for night work in accordance with Local, VDOT standards.

2. Operational Window: All re-striping in high-traffic areas, including but not limited to the intersection with North Street and Main Street, must be completed within the 9:00 PM to 5:00

AM window to ensure the roadway is fully marked and operational for the morning commute.

3. Bidders must account for all costs associated with nighttime premiums, specialized lighting, and expedited striping sequences in their unit price bids.

4. Permits: The Contractor shall obtain any necessary Noise Variance Permits from the City for work occurring between 9:00 PM and 5:00 AM.

d. Work in active City streets - shall be from 9:00 AM to 3:00 PM Monday-Thursday and 9:00 AM to 2:00 PM on Fridays unless otherwise directed by the City, no work shall take place in City streets on weekends or holidays unless pre-approved in writing by the Director of Public Works..

VI. SPECIAL PROVISION FOR GREEN BIKE LANE COLORED PAVEMENT

October 15, 2025

I. DESCRIPTION

Work consists of coloring asphalt pavement for bike lanes as required in Contract Documents and as directed by the Engineer.

II. MATERIALS

Bike lane color pavement marking material is to be pre-formed thermoplastic that provides durable skid-resistant surface, has long-lasting color retention, and is for use in low to high vehicular traffic areas. Bike lane color pavement marking material is to be PreMark as manufactured by Ennis-Flint, Federal Green manufactured by Integrated Traffic Systems or Swarco Preform Thermoplastic by Swarco Industries, Inc., or approved equivalent. Bike lane color pavement marking material is to be bike lane green. Color must be homogeneous throughout thickness of material and must be such that end result of finished product visually provides surface which is uniform in color over entire surface area and which is an approximate match to specified color. Manufacturer is to demonstrate in writing, and by providing references, that pre-formed thermoplastic material has been satisfactorily used for minimum period of 2 years in areas where weather conditions are similar to those experienced in Fairfax, Virginia area.

This material shall conform to VDOT Thermoplastic Type B, Class II paint as outlined in Sections

246.03 (c) and 704.03 (b) of the 2020 VDOT Road and Bridge Specifications.

III. PROCEDURES

Preparation of pavement surface, equipment, materials, and method of application and repair of color pavement marking material, will be as required by manufacturer.

IV. MEASUREMENT AND PAYMENT

Green bike lane paint will be measured for payment will be number of square feet of bike lane color pavement marking system constructed. Unit price bid for green bike lane paint shall include preparation of pavement surface; layout;

furnishing and installing bike lane color pavement marking material; repairing damaged or improperly installed pavement marking material; protecting completed work from traffic; site cleanup; and furnishing all labor, material and equipment necessary to complete work.

Payment will be made under:

Pay Item

Green Bike Lane Paint

Pay Unit

Square Feet

END OF SECTION

VII. BIDDING & PRICING

• Basis of Bid: Unit Price Contract. Bidders must complete the Base Bid

• Mobilization: Must include all costs for multiple mobilizations necessitated by schedules, utility delays, and phasing.

VIII. QUALITY ASSURANCE & COMPLIANCE

• Materials Testing: Contractor’s responsibility per VDOT Inspection Manual.

• Buy America: Applies to all iron and steel products and many others. VDOT Special Provision SP107-003100-00 Revised October 3, 2025

• Documentation: Mandatory submission of VDOT C-series forms (C-25, C-31, C-48, C-49, etc.) for reimbursement through FHWA/VDOT funds.

IX. SCHEDULE & LIQUIDATED DAMAGES

• Inquiry Deadline: July 22, 2026, COB

• Bid Due Date: August 10, 2026, by 2:00PM

• Substantial Completion: Within 180 days of full NTP.

• Final Completion: Within 210 Days of full NTP

• Liquidated Damages: $600 per calendar day.

X. QUESTIONS & ANSWERS

No questions.

PRE-BID MEETING AGENDA
I. ATTENDEES & VIRTUAL SIGN-IN
II. INTRODUCTIONS
III. GENERAL INFORMATION & LAP FRAMEWORK
IV. PROJECT SCOPE & IDENTIFICATION
V. SITE CONSTRAINTS & RESTRICTED WORK AREAS
I. DESCRIPTION
II. MATERIALS
III. PROCEDURES
IV. MEASUREMENT AND PAYMENT
Pay Item
Pay Unit
VII. BIDDING & PRICING
VIII. QUALITY ASSURANCE & COMPLIANCE
IX. SCHEDULE & LIQUIDATED DAMAGES
X. QUESTIONS & ANSWERS