This is a Pre-solicitation Notice for a maintenance dredging contract issued by the U.S. Army Corps of Engineers, Galveston District Office.

The contract W912HY26BA019 requires performance of maintenance dredging and shoaling remediation within the Gulf Intracoastal Waterway (GIWW) between High Island and Causeway in West Galveston Bay, with dredged material placed in nearby placement areas along the GIWW. Schedule 1 consists of approximately 959,000 cubic yards of dredging with a completion timeline of 270 calendar days after Notice to Proceed. Five optional work items are available: Option 1 addresses the Galveston Alternate Route (40,000 CY, +15 days); Option 2 covers Offats Bayou Channel (86,000 CY, +25 days); Option 3 includes Ferry Channel/Bolivar Ferry Channel (102,000 CY, +30 days); Options 4 and 5 provide alternative placement at Joycelyn Nungaray Beneficial Use area for Schedule 1 Sections 1 & 2 (+5 days) and Section 3 (+10 days) respectively. The solicitation will be issued on or about September 15, 2026, with responses due on or about October 15, 2026. This is a Firm Fixed Price contract subject to fund availability. The applicable NAICS code is 237990 (Other Heavy and Civil Construction) with a Small Business Size Standard of $37,000,000. Contractors must be registered at SAM.gov, provide Performance and Payment Bonds within 5 calendar days of award, furnish pre-award documents within 2 working days after bid opening, and commence work within 10 calendar days of Notice to Proceed acknowledgement. Liquidated damages apply for schedule delays. Prior government contract experience is not required. Contract Specialist: Ashley Griffin (ashley.l.griffin@usace.army.mil); Contracting Officer: Ms. Mirian Tudor (mirian.r.tudor@usace.army.mil). Solicitation documents are available through the PIEE suite at https://piee.eb.mil/.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pre-solicitation Notice

W912HY26BA019

The U. S. Army Corps of Engineers, Galveston District Office requires a contract for

USACE Galveston District, Gulf Intracoastal Waterway, Texas High Island to Causeway and Channel to Port Bolivar Pipeline Maintenance Dredging

THE WORK CONSISTS OF:

Perform maintenance dredging and to address shoaling within tributary channels. All material from this project will be placed within nearby placement areas along the GIWW.

Requirement consists of Schedule No. 1 and Five (5) Options, if exercised.

Schedule 1 - Maintenance dredging of the Gulf Intracoastal Waterway (GIWW) between High Island and Causeway in West Galveston Bay totaling approximately 959,000 CY.

Completion Time for Schedule No. 1: 270 Calendar Days after the Notice to Proceed is issued to the contractor.

Option 1 - Galveston Alternate Route. Maintenance dredging of approximately 40,000 CY. An additional 15 calendar days will be added to contract duration if exercised.

Option 2 - Offats Bayou Channel. Maintenance dredging of approximately 86,000 CY.

An additional 25 calendar days will be added to contract duration if exercised.

Option 3 - Ferry Channel (Bolivar Ferry Channel) Maintenance dredging of approximately 102,000 CY. An additional 30 calendar days will be added to contract duration if exercised.

Option 4 – Joycelyn Nungaray Beneficial Use Placement. This option is if the government opts to have the dredge material from Schedule No. 1 Sections 1 & 2 placed within the Joycelyn Nungaray BU placement area in lieu of the Schedule No. 1 placement areas assigned. An additional 5 calendar days will be added to contract duration if exercised.

Option 5 - Joycelyn Nungaray Beneficial Use Placement. This option is if the government opts to have the dredge material from Schedule No. 1 Section 3 placed within the Joycelyn Nungaray BU placement area in lieu of the Schedule No. 1 placement areas assigned. An additional 10 calendar days will be added to contract duration if exercised.

1. If the contractor fails to complete the work within the time specified, the contractor shall pay liquidated damages to the Government in an amount to be determined for each calendar day of delay until the work is completed or accepted.

2. Bonding Requirements - The Contractor will be required to provide the Performance and Payment Bonds within 5 calendar days after award. The contractor shall begin work within 10 calendar days after acknowledgement of the Notice to Proceed.

3. Furnish pre-award documents within 2 working days after Bid Opening.

Prior Government contract work is not required for submitting a response to the solicitation.

The solicitation issued will be Firm Fixed Price. This solicitation is subject to the availability of funds. The solicitation will be issued on or about September 15, 2026. Response date on or about October 15, 2026.

The North American Industrial Classification System (NAICS) Code applicable to this project is 237990 – Other Heavy and Civil Construction. The Small Business Size Standard is $37,000,000.00.

All offerors must be registered at SAM.gov (https://www.sam.gov) to be eligible for award. Additionally, contractors can register as an interested vendor on specific procurements. The contract specialist for this solicitation is Ashley Griffin, at ashley.l.griffin@usace.army.mil. The contracting officer is Ms. Mirian Tudor at mirian.r.tudor@usace.army.mil.

Contractors may view and/or download the solicitation, plans, specifications, and all amendments at the Solicitation Module of the Procurement Integrated Enterprise Environment (PIEE) suite at https://piee.eb.mil/. Plans and specifications will not be available in paper format or on compact disc. It is the offeror’s responsibility to monitor the PIEE Solicitation Module daily (using the above link) for information regarding this solicitation.

https://www.sam.gov/ mailto:ashley.l.griffin@usace.army.mil mailto:mirian.r.tudor@usace.army.mil https://piee.eb.mil/

The U. S. Army Corps of Engineers, Galveston District Office requires a contract for USACE Galveston District, Gulf Intracoastal Waterway, Texas High Island to Causeway and Channel to Port Bolivar Pipeline Maintenance Dredging

File details come from the government source that posted it. Updated .