This document provides details regarding a pre-solicitation notice for upgrades and renovations to the Waste Water Treatment Plant at Fort McCoy, Wisconsin. The U.S. Army Corps of Engineers Engineering District Omaha will issue Request for Proposal W9128F-20-R-0073 on or about May 27, 2020 to complete replacements and upgrades including replacing the Influent Wet Well, constructing an Oxidation Ditch, replacing sludge pumps, replacing the UV disinfection system, installing additional air diffusers, constructing a new building to house blowers, and installing new PLC control systems. The work must be completed within 665 calendar days of receiving the Notice to Proceed, and liquidated damages will apply for failure to meet the deadline. Firms will be evaluated based on specialized experience, project management plan, key personnel, small business participation, and past performance using an adjectival method, while price will be evaluated separately for reasonableness and realism in a best value determination. The estimated construction cost is between $8-12 million.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W9128F20R0073

On or about 27 May 2020, this office will issue Request for Proposal (RFP) for Waste Water Treatment Plant Renovations, Fort McCoy, Wisconsin. The solicitation will close on or about 29 June 2020.

This solicitation is UNRESTRICTED. All contractors must be registered and have an active and verified account in the System for Award Management (SAM) in order to receive a contract award from any DoD activity. Contractors may access the Internet site at: https://www.sam.gov/ to register and/or obtain information about the SAM program. Contractors must ensure that the applicable NAICS code 237110 is included in their profile prior to submission of offer.

Provisions in the solicitation documents will provide a site visit date and detailed information (meeting place, time, points of contact, and access requirements).

DO NOT submit requests for plans and specifications to the site visit personnel. See ‘Obtaining Solicitation Documents’ below.

Project Description (approx. quantities):

This acquisition is for the following upgrades, replacements, and construction at the Ft McCoy Wisconsin, Waste Water Treatment Plant (WWTP): Replace the Influent Wet Well , Construct an Oxidation Ditch, Replace the Sludge Pumps, Replace the existing UV disinfection system with a more energy efficient system, Install additional air diffusers, Construct a new building to house the blowers for the converted Aerobic Digester and the new RAS and WAS pumps and control systems. Install PLC system(s) for all new process equipment control and provide control/feedback loop to existing Control Building for eventual integration (by others) into future supervisory control and data acquisition.

The Contractor will be required to commence work within 10 days after Notice to Proceed (NTP) and complete the work in the proposed number of calendar days (Not to Exceed 665 calendar days) after receipt of NTP. Provisions will be included for Liquidated Damages in case of failure to complete the work in the time allowed. Performance and Payment Bonds will be required.

The above project description is for information only. Project scope of work is subject to change.

RFP Evaluation Criteria:

Firms participating in the solicitation will submit technical requirements in accordance with Section 00 22 00 PROPOSAL SUBMISSION REQUIREMENTS, INSTRUCTIONS AND EVALUATION. Submissions will be evaluated based on a best value approach considering technical elements for evaluation (i.e., Specialized Experience, Project Management Plan ,Key Personnel, Small Business Participation, and Past Performance). An adjectival method of evaluation will be used to evaluate all technical factors. Price will be evaluated separately for https://www.sam.gov/ reasonableness and realism. A Best Value selection will be considered after reviewing price and technical factors.

The estimated construction cost of this project is between $8,000,000 and $12,000,000.

Bidders (Offerors):

Please be advised of online registration requirement in the SAM, https://www.sam.gov/ and directed solicitation provisions concerning representations and certifications. Representations and certifications are required to be updated annually as a minimum to keep information current, accurate and complete. The electronic annual representations and certifications are effective until one year from date of submission or update to SAM.

Obtaining Solicitation Documents:

Solicitation documents will be posted to the web via Contract Opportunities (Beta.SAM>Contract Opportunities) at https://beta.sam.gov/search?index=opp.

Find solicitation announcement in Contract Opportunities (https://beta.sam.gov/search?index=opp):

1. Use the “Keywords” search function to locate the project (by entering the solicitation number) or use the advanced search features offered in the “Federal Organizations” (towards the middle of the page) or use the “Federal Organizations” search feature followed by the “Advanced Search” feature.

2. By using the “Sign In” feature, it allows additional search features and allows you to keep your searches. Sign In might be required on some solicitations that are considered restricted.

3. Once you have located your project, click on hyperlinked title of the solicitation to view the project. Files may be downloaded from the “Attachments/Links” section of the solicitation.

Questions should be sent to the Contracting Specialist, Mr. Phillip Wickham, at phillip.l.wickham@usace.army.mil.

Telephone calls will not be accepted.