Pre-Solicitation.pdf

PDF 337 KB Posted

Attached to
UT FTBL 7133(1) Canyon Rims Road
Solicitation number
6982AF23B000007
Issued by

About this file

This pre-solicitation notice provides details for the UT FTBL 7133(1) Canyon Rims Road project. The project consists of rehabilitating 9.28 miles of Needles Overlook Road under Schedule A, continuing another 1.52 miles under Option X, and constructing turn lanes and acceleration/deceleration lanes along 0.82 miles of US 191 under Option Y. Work includes pavement patching, chip sealing, reclamation and overlay, slope flattening, drainage improvements, clearing, signing, striping, and revegetation. The Notice identifies estimated quantities for embankment construction and asphalt paving under Schedule A. The related federal contract opportunity lists the solicitation and project numbers, names the Department of Transportation Federal Highway Administration as the agency, and describes the opportunity as a pre-solicitation for the UT FTBL 7133(1) Canyon Rims Road project located in eastern Utah.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

This is not a solicitation and plans and specifications are not available.

PROJECT NUMBER: UT FTBL 7133(1)

PROJECT NAME: CANYON RIMS ROAD

PROJECT DETAILS:

The UT FTBL 7133(1) Canyon Rims Road project is located approximately 32 miles southeast of Moab, UT in Eastern Utah. The project crosses through Utah Department of Transportation (UDOT) Right of Way (ROW) and Bureau of Land Management (BLM) lands, providing access to land managed by the U.S. Bureau of Land Management as part of the Canyon Rims Special Recreation Management Area. The project consists of two segments of Needles Overlook Road, broken into Schedule A and Option X, and one Segment of US 191 at the intersection of Needles Overlook Road, identified as Option Y.

Schedule A and Option X Needles Overlook Road is 22 miles of paved BLM recreational roadway located on top of a large plateau encompassing 100,273 acres south of Moab, Utah. Needles Overlook Road provides access to the Needles Overlook, Anticline Overlook Road, Anticline Overlook, two campgrounds, and several trailheads. It begins at the intersection with US 191 and continues west/northwest to the Needles Overlook.

Schedule A Schedule A rehabilitates 9.28 Miles of Needles Overlook Road, beginning from the end of the road at the existing Needles Overlook parking area, continuing east 6.98 miles to the intersection with Anticline Overlook Road, and then extending an additional 2.3 Miles to the East. The work elements include pavement patching, pavement chip sealing, full depth reclamation and pavement overlay, roadway embankment slope flattening, ditch and shoulder reconditioning, minor drainage improvements, selective clearing to reduce vegetation adjacent to the roadway, signing, striping, and delineator replacement, new pavement markings, and revegetation at locations of fill slope flattening. The Needles Overlook parking areas will also receive new surface treatment and pavement markings.

Option X Option X begins where Schedule A ends and continues an additional 1.52 miles east along Needles Overlook Road. The work elements include full depth reclamation and pavement overlay, roadway fill slope flattening, shoulder reconditioning, signing, striping, and delineator replacement, and revegetation at locations of fill slope flattening.

Approximately 10 miles of existing Needles Overlook Road, between the end of Option X and the intersection with US 191, will not be improved under this project.

Option Y Option Y constructs a full turn lane build-out at the T intersection of US 191 and Needles Overlook Road and provides a dedicated left-turn, acceleration, and deceleration lanes on US 191 for 0.82 miles. The work includes building embankment, minor drainage improvements, new asphalt pavement and chip seal, chip sealing the existing pavement of US 191, signing, striping and delineator replacement, and cattle guardrail and fence replacement.

PRINCIPAL WORK ITEMS (Schedule A):

20420-0000 Embankment Construction: 2,800 CUYD 40101-0600 Asphalt Concrete Pavement, Gyratory Mix, 1/2-Inch Nominal

Maximum Size Aggregate, 0.3 to <3 Million ESAL: 3,500 TON 40702-0300 Chip Seal Type 1C: 86,000 SQYD 40711-0000 Emulsified Asphalt: 275 TON 41801-2000 Asphalt Concrete Pavement Patch Type 2: 2,200 SQYD

PRINCIPAL WORK ITEMS (Option X):

20420-0000 Embankment Construction: 2,170 CUYD 40101-0600 Asphalt Concrete Pavement, Gyratory Mix, 1/2-Inch Nominal

Maximum Size Aggregate, 0.3 to <3 Million ESAL: 2,100 TON

PRINCIPAL WORK ITEMS (Option Y):

20401-0000 Roadway Excavation: 12,000 CUYD 30202-2000 Roadway Aggregate Method 2: 5,100 TON 40101-5600 Asphalt Concrete Pavement, Gyratory Mix, 1/2-Inch Nominal

Maximum Size Aggregate, 0.3 to <3 Million ESAL: 3,600 TON 63503-0400 Temporary Traffic Control, Concrete Barrier: 4,600 LNFT

SCHEDULE:

The anticipated advertisement date for the project is February 2023 with construction anticipated from April 2023 to September 2023.

ESTIMATED COST RANGE:

Total estimated cost between $5,000,000 and $10,000,000

File details come from the government source that posted it. Updated .