This statement of work outlines requirements for upgrading animal holding facilities at the Poisonous Plant Research Laboratory in Logan, Utah. Key work includes constructing three small loafing sheds for sheep, removing and replacing over 300 square feet of flooring, and performing asphalt services such as crack sealing and sealing over 107,000 square feet of asphalt area. Additional requirements include providing all labor, equipment, and materials, complying with applicable codes, and completing work within an estimated 210 calendar day timeframe. The related federal contract opportunity notice indicates the upcoming solicitation will be a total small business set-aside for NAICS code 238990 with a size standard of $19 million. The solicitation is expected to issue around 15 days after the closing date of this pre-solicitation notice and will be accessible on SAM.gov.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Construction Pre-Solicitation Notice Upgade Animal Fac Logan.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
United States Department of Agriculture Agricultural Research Service
(Draft) STATEMENT OF WORK
Upgrade Animal Holding Facilities Complex
Poisonous Plant Research Laboratory
Logan, UT
Date: January 10, 2024
STATEMENT OF WORK
1.0 CONTRACT PROJECT:
a. Project Number: TBD
b. Project Title: Upgrade Animal Holding Facilities Complex
c. Project Location: Poisonous Plant Research Laboratory 1150 E 1400 N, Logan, UT 84322-6300
2.0 PROJECT CONTACT PERSONS:
TBD
3.0 PROJECT DESCRIPTION:
Construct Small Loafing Sheds for Sheep, Remove and Replace Flooring, Asphalt Services
4.0 PROJECT REQUIREMENTS:
a. Do not disturb hazardous materials and report condition immediately to the Contracting Officer’s Representative (COR) regarding potentially hazardous conditions that are uncovered. Stop work in the area of the questionable material or condition until identification and direction is provided.
b. The Contractor’s work shall adhere to the criteria stated within these project requirements, drawings, and specifications. All construction shall comply with applicable federal, state, and local code requirements as well as current industry standards, (i.e., IBC, NEC, NSPC, NFPA, EPA, ASTM, GSA, AASHTO, etc.) and health and safety codes, in effect at the time of contract award.
c. Access the site between 7:00 am and 5:00 pm Monday through Friday excluding federal holidays. Contractor staff must sign-in on the first day of arrival and then sign-out on the final day of the project, upon completion.
4.1 Background & Site Description:
The work to be completed is at the Poisonous Plant Research Laboratory at the southwest corner of 1400 N and 1200 E in Logan, UT.
4.1 Bid Schedule:
Provide all labor, equipment and materials to perform this Statement of Work and Schedule of Items.
4.2 Description of Work:
a. Construct Three Small Loafing Sheds for Sheep (12’ X 24’ open fronted loafing sheds, 4” x 4” x 10 GA steel for the frame and rafters)
Excavation of site, construction of 4 ft stem wall (12’ x 24’ x 8 “) with rebar and a footing (20” x 11”), 5 weld plates per building (8” x 8” x ½”), shed to be built on stem wall
Sheds shall have an interior kickboard wall that is 3 feet tall made out of 2x6 boards, 1 ½” angle iron to secure 2 X 6s at ends.
Sheds shall be enclosed on three sides with tin (3 ft wide) and have a tin roof (2 x 4s to secure tin down)
Sheds shall have a roughly 2 ft overhang off the back of the roof to allow for drainage.
Refer to photo below for details, photo below does not show stem wall.
b. Remove and Replace Flooring
Remove 104 square yards of carpet and replace with carpet tiles (brand Mohawk/Aladdin;
style Get Moving/Datum; and color Atmosphere/Shale), remove and replace 200 linear feet of 4” rubber base (color black) (photos below show room and rubber base)
Remove 340 square feet of carpet, prepare floor, and replace with luxury vinyl plank (brand Karndean; style Looselay Longboard; color neutral oak) (photo below shows room)
c. Asphalt Services
Blow out cracks / Apply crackseal to all major cracks greater than 1/8” wide with hot pour crackfiller (includes asphalt to concrete horizontal edges).
Blow out cracks / Apply GAP MASTIK to all major cracks greater than 1/4” wide with hot pour crackfiller (includes asphalt to concrete horizontal edges).
Clean off debris / apply two coats of seal coat (Tuffcoat is a high performance emulsion based asphalt seal coat, consisting of an industry leading aggregate blend, mineralogy, surface active agents and catalysts. Tuff Coat boasts a 60% residue, weighs in at 11.44 pounds per gallon) to entire indicated asphalt area approximately 107,000 square feet
Layout / Restripe parking lot in white paint to match existing layout (up to 50 stalls, 2 handicap stencils, I hash area)
Details: restripe lots as is (all lines, handicap symbols, cross walk)
Notes: green lines represent edge seal adjacent to concrete.
4.3 Government Furnished Equipment\Services
a. Government will furnish a reasonable amount of electricity and water.
5.0 GENERAL REQUIREMENTS:
5.1 Permits: Where governing regulations and imposed codes and standards require notices, permits, licenses, inspections, tests, and similar items or actions in order to lawfully proceed with the required work, the Contractor shall obtain items and take those actions in accordance with the regulations of the governing authority. The costs of such permits, licenses, inspections, etc., are the obligation of the Contractor.
5.2 Existing Installations / Demolition: Contractor shall modify existing installations as needed to accommodate the new installation. Contractor shall coordinate modification of existing installations with Government. All disturbances of existing systems shall be thoroughly coordinated with the Government to prevent disturbances that might jeopardize on-going operations and research. Government reserves the right to retain any equipment / materials removed as part of the scope of work. Contractor shall coordinate any equipment / materials to be retained with Government prior to starting demolition operations.
Contractor shall legally dispose all any materials removed that will not be retained.
5.3 Installation: It shall be the responsibility of the Contractor to complete work in accordance with Federal, State, and Local Code Standards. Additional procedures and materials may be required than is indicated herein. If any item specified herein conflicts with the applicable codes and recommendations, the Contractor shall bring it to the attention of the Contracting Officer Representative for immediate resolution.
5.4 Submittals: Provide manufacturer’s descriptive literature/shop drawings for all materials to the Location Monitor for review. The descriptive literature shall be annotated/ highlighted to show its conformance with contract requirements. Submittals are required for new materials and will be stamped and/or signed by the general contractor prior to submission to the Government. Contractor is responsible for any costs incurred for equipment ordered without prior approval.
5.5 Quality Control: The work performed under this contract shall be subject to continuous audit by the Location Monitor. Quality control is the exclusive responsibility of the Contractor. The Contractor shall retain and pay for the services of an independent inspector or testing laboratory to perform all tests expressly required by this contract.
5.6 Protection of Work and Property/Safety Requirements:
a. The Contractor shall protect the work, the site, and all existing property and structures within the limits of the construction activities or that may be affected thereby until acceptance of the work. Any damage to property shall be repaired at the Contractor’s expense, to pre-damaged condition to the satisfaction of the Location Monitor.
b. Safety and health matters, as they relate to the work, are the exclusive responsibility of the Contractor. The Contractor shall furnish, erect, and maintain barricades, warning lights, signs, guards, or take other precautions as may be required by law or local authorities of the protection and security.
c. Contractor is responsible for verifying location of any underground utilities and is responsible for any damaged caused to such utilities.
5.7 Temporary Facilities:
a. Temporary utilities (water and electricity) may be furnished to the Contractor by the Government, if so requested. The Contractor shall maintain and protect all such utilities during the course of construction and shall repair or replace any items damaged through its own negligence.
b. Should the Contractor require any power or utility shutdowns during construction, the
Contractor shall obtain approval for such shutdown from the Location Monitor fourteen
(14) calendar days prior to the need.
5.8 Materials and Equipment:
a. The material and equipment to be furnished under these contract documents shall be the standard products of manufacturers regularly engaged in the production of such materials and equipment and shall be the manufacturer’s latest standard design.
b. All materials and equipment to be incorporated in the work shall be handled and stored by the manufacturer, fabricator, supplies and Contractor before during and after shipment in a manner to prevent any injury, theft or damage of any kind to the materials and equipment. All materials and equipment furnished by the Contractor shall be subject to inspection and approval by the CO/Location Monitor.
c. Government will not furnish any labor or equipment to unload or move materials or supplies.
5.9 Cleanup: The construction site shall be kept clean and free of debris at all times. Restore areas disturbed as nearly as possible to the original appearance and condition. Upon completion of the project, and prior to final inspection, the Contractor shall remove from the premises all unused material, trash, and debris resulting from the work to the satisfaction of the Location Monitor.
5.10 Warranty:
a. Submit data concerning the standard one year warranty for workmanship, including the warranty periods (dates), and warranty contacts with names, addresses and telephone numbers.
5.11 Final Payment/Contract Closeout: The following documents are REQUIRED PRIOR TO
FINAL PAYMENT (other documents may also be required):
a. General contractor’s minimum one (1) year warranty on work.
b. Release of liens
c. Final Invoice
6.0 Project Schedule:
The Contract time for this project is estimate to by no longer than 210 calendar days from
Notice to Proceed.