PR5421889_SOW_(medical_unit).pdf
PDF 812 KB Posted
- Attached to
- Repairs and adjustments at the Medical Unit
- Solicitation number
- PR5421889
- Issued by
-
Department of State US Embassy Sao Paulo
About this file
The company will be responsible to perform facility improvements for the local Medical Unit (200 m) in Sao Paulo. Services will include but not be limited to architectural plumbing civil and electrical upgrades
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK Page 1 of 27
Repair and Adjustments of the São Paulo Medical Unit
SCOPE OF WORK
GENERAL CONSTRUCTION SERVICES
For
Repair and Adjustments of
Medical Unit
U.S. US GOVERNMENT GENERAL
SÃO PAULO, BRAZIL
08/01/2016
SCOPE OF WORK Page 2 of 27
1.0 INTRODUCTION - PROJECT SYNOPSIS
1.1 The U.S. General Consulate in Sao Paulo (Brazil) makes public its intention to hire a company with reliable and proven experience in facilities maintenance and repair services. The company will be responsible to perform facility improvements for the local Medical Unit (200 m²) in Sao Paulo. Services will include but not be limited to architectural, plumbing, civil, and electrical upgrades. The selected company shall complete all work, including furnishing all labor, material, equipment, tools, and services as called for and required by the terms and conditions of this document and attachments hereto.
1.2 The present Scope of Work [SOW] will instruct and guide all parties interested in making business with the US Consulate General in Sao Paulo (Brazil) for Facilities Maintenance and Repair services. This document includes information about local requirements (host country) and several other requirements thereof, subject to the service request (specifications, work orders, liabilities, charges, payments, currency, visitations, schedules, etc.). This document also establishes rights and obligations of the US US GOVERNMENT General in Sao Paulo, always hereinafter referred to as US GOVERNMENT and by the executor, always hereinafter indicated as CONTRACTOR.
1.3 The US General Consulate in Sao Paulo is located at Henry Dunant Street, #700, in Santo Amaro district, Sao Paulo, Brazil (ZIP 0470-011). All site visits shall be requested through the US Consulate’s Facility Manager [FM] or Contracting Officer Representative [COR].
1.4 Work shall be completed as expeditiously as possible. CONTRACTOR shall coordinate with COR for work phasing and job sequencing with all work to commence and to be completed in a sequential manner. The actual time for performance and completion shall be negotiated and set forth in the contract at time of award.
1.5 CONTRACTOR shall be required to submit a construction plan with a timeline for completion of the project to the COR for review and approval prior to commencement of work at the site.
1.6 CONTRACTOR may be allowed to overlap phases of the project upon exhibition of sufficient capability to execute all work simultaneously with the approval of the COR.
SCOPE OF WORK Page 3 of 27
2.0 GENERAL REQUIREMENTS
2.1 CONTRACTOR will be required to provide all equipment, materials, tools and qualified personnel to supervise and execute all of the technical requirements described in this Scope of Work [SOW].
2.2 The work will be executed in a diligent, professional and craftsman like manner in accordance with a negotiated firm fixed price and performance period. The period of performance for all phases of the project shall be completed in accordance with the proposed and approved Construction Plan as stated in the Contract Award.
2.3 CONTRACTOR will have limited access to or be admitted into any structure outside the areas designated for the project except with the permission of the COR. The CONTRACTOR shall be required to minimize the impact and disruption to normal operations of the US
GOVERNMENT during the project.
2.4 CONTRACTOR will be required to prepare and submit reports, bill of materials, product literature, drawings, specifications, quality control schedules, safety plan and construction costs. These documents shall provide the necessary interfaces, coordination, and communication between the COR and CONTRACTOR for the delivery of a completed project.
SCOPE OF WORK Page 4 of 27
3.0 GOVERNMENT MATERIAL (GM)
3.1 Pursuant to Contract Clause FAR 52-245-2, Government-Furnished Property (Short Form), the Government will furnish the following materials and equipment for the installation by the CONTRACTOR.
3.2 CONTRACTOR will provide adequate quantities of materials in addition to the inventory of materials currently stored at the site to provide a complete the project as specified.
SCOPE OF WORK Page 5 of 27
4.0 CONTRACT ADMINISTRATION
4.1 The Contracting Officer (CO) is the sole person designated with authority to administrate contracts for the United States Government (USG). The CO will designate a Contracting
Officer’s Representative (COR) to act as the CO’s on site representative.
4.2 The Contracting Officer’s Representative has the authority to direct the CONTRACTOR within the scope of the contract and coordinate between the USG and the CONTRACTOR.
4.3 The CONTRACTOR shall not conduct any work that is beyond this Scope of Work (SOW) and accompanying specifications unless directed in writing by the CO. Any work done by the
CONTRACTOR beyond this SOW and accompanying specifications without written direction from the CO will be at the CONTRACTOR’s own risk and at no cost to the US GOVERNMENT.
4.4 The CO shall provide a written Notice to Proceed (NTP) to the CONTRACTOR. No work shall be initiated until the NTP is issued by the CO.
4.5 The CONTRACTOR will be furnished evidence of COR appointments, including explicit authority delegated to the COR and the COR’s responsibilities.
4.6 The CO does not make representations or warranties of whatsoever kind or nature, either expressed or implied, as to the quality, level of completion, accuracy, extent of compliance with the standards, codes and requirements described or referred to in this SOW, or the extent of coordination between or among the documents provided to the CONTRACTOR.
4.7 The CO’s review, approval, or acceptance of, nor payment for the services required under this contract shall be construed to operate as a waiver of any rights under this contract or any cause of action against the CONTRACTOR arising out of the performance of this contract.
4.8 The CO has the right to inspect and test all services called for by the contract, to the extent practicable at all times and places during the term of the contract. The office of Overseas
Buildings Operations (OBO) may perform Quality Assurance Inspections (QAI) and tests during construction to confirm the work is installed according to the SOW.
4.9 The CO has the authority to issue a temporary stop order during the execution of any particular phase of this SOW. This authority may be executed when the USG requires time for official functions, or is in possession of specific credible information indicating that the lives of USG personnel are immediately threatened and that the execution of the project will increase the US GOVERNMENT's vulnerability. The CONTRACTOR shall promptly notify the
CO that work has been stopped.
4.10 If any of the CONTRACTOR’s services do not conform to the contract requirements, the CO may require the CONTRACTOR to perform the services again in conformity with the contract requirements. The CO may by contract or otherwise, perform the services and charge the
SCOPE OF WORK Page 6 of 27
CONTRACTOR any cost incurred by the US GOVERNMENT that is directly related to the performance of such service or terminate the contract for default.
4.11 The USG has the right to terminate this contract of convenience at any time in whole, or from time to time, if the CO determines it is in the interest of the US GOVERNMENT.
5.0 RESPONSIBILITY OF THE CONTRACTOR
5.1 CONTRACTOR must be responsible for the professional quality, technical accuracy, and the coordination of all construction and other services furnished under this contract. The
CONTRACTOR shall, without additional compensation, correct or revise any errors or deficiencies in its construction and other services.
5.2 CONTRACTOR needs to identify a Project Site Manager who will be responsible for the overall management of the project and represent the CONTRACTOR on the site during construction. The Project Site Manager has to be approved by the COR.
5.3 The Project Site Manager must attend all project meetings, prepare Status Reports on the project and submit them to the COR. Status Reports will contain meeting minutes, accomplishments, proposed actions, requested or proposed change orders, and any other pertinent information required to report the progress of performance.
5.4 All documentation produced for this project will become the ownership of the US
GOVERNMENT at the completion of this project.
5.5 CONTRACTOR must verify that all materials, equipment, and systems provide operational dependability. The CONTRACTOR assures the completed construction shall be easily maintained or replaced with readily available materials and services.
5.6 Any cost associated with services subcontracted by the CONTRACTOR must be borne by and be the complete responsibility of the CONTRACTOR under the fixed price of this contract.
5.7 CONTRACTOR is responsible for safety and is his obligation to comply with all local labor laws, regulations, customs and practices pertaining to labor, safety and similar matters. The
CONTRACTOR will promptly report all accidents resulting in lost time, disabling, or fatal injuries to the COR.
5.8 CONTRACTOR shall be liable to the US GOVERNMENT in accordance with applicable law for all damages to US GOVERNMENT property, equipment, or personnel caused by the
CONTRACTOR's negligent performance of any of the services furnished under this contract as well as third parties operating on US GOVERNMENT property with permission of the USG.
The rights and remedies for the US GOVERNMENT provided for under this contract are in addition to any other rights and remedies provided by law.
SCOPE OF WORK Page 7 of 27
6.0 SCOPE OF WORK (SOW)
6.1 Demolition
6.1.1 CONTRACTOR will be responsible (and therefore should incorporate expenses related to labor costs) for assembling, disassembling and transporting to designated areas inside the
US Consulate in Sao Paulo, all existing furniture and equipment standing at the area to be refurbished (tables, chairs, shelves, sofas, appliances, cabinets, shelves, printers, scanners, beds, etc.).
6.1.2 CONTRACTOR will remove non loadbearing walls (drywalls), vinyl wall base, floor tiles, wood doors, door jambs, acoustic ceiling tiles, light fixtures, etc. (the demolition plan is included in
ANNEX ARQ 02/13). CONTRACTOR will also be responsible for removing the infrastructure running inside the affected drywalls including the adjacent infrastructure in the nearby areas that may also be affected by the drywall removal process (acoustic ceiling tiles, light fixtures, air ducts, floors tiles, electrical wires, telecom cables, power outlets, conduits, sprinkler heads, etc.). The withdrawal of the infrastructure that feeds or just runs through the refurbishing area (infrastructure expected to be replaced or re-allocated to meet the new layout proposed for the Medical Unit) should be assessed and appraised by the
CONTRACTOR either during the technical visit that will be scheduled for the site or through technical documentation available in electronic and hard copies stored at the US Consulate files. It is the CONTRACTOR's responsibility to investigate and confirm if the information provided in the SOW is accurate. It is the CONTRACTOR´s responsibility to double-check if the information provided in the SOW (sizes, dimensions, locations, high, materials, quantities, elevations, etc.) matches the real information available in the refurbishing area.
CONTRACTOR cannot start any work till the current infrastructure running through the remodeled area (electrical, telecom, fire, HVAC, plumbing, etc.) are thoroughly inspected, understood, and identified (switches, power outlets, light fixtures, potable water lines, telecom cables, sprinklers heads, air ducts, sewer lines, conduits, alarms, etc.).
CONTRACTOR will need to comply with a demolition schedule that shall be submitted for the
US GOVERNMENT approval 15 days after the contract is officially awarded. The demolition process shall be authorized by the US GOVERNMENT on written (CO, COR, or COTR) and only after the US GOVERNMENT staff shuts down and off all the main sources that keeps the
Medical Unit infrastructure operational (water, power, air condition, computers, etc.). The shutting down an off process is the US GOVERNMENT sole and exclusive responsibility.
6.1.3 CONTRACTOR shall remove with maximum care pieces and parts from the Medical Unit infrastructure that might be reused later in the refurbishing process such as doors, door jambs, door hardware, light fixtures, ceiling tiles, exit signs, etc. CONTRACTOR can either reuse the existing wood doors and door hardware (including door jambs) if no damage or defects is reported with it after the removal process is completed or deliver new ones
(similar or better standards concerning material, model, texture, size, dimensions, color, etc.). Eleven doors (11) will remain in the same place where they are currently located. Four
SCOPE OF WORK Page 8 of 27 doors (4) will be relocated internally to meet the new provision of the proposed layout for the rooms within the Medical Unit (see ANNEX ARQ 03/13).
6.1.4 CONTRACTOR will be responsible for removing 180 square meters of floor tiles consisting of carpet tiles, PVC tiles, and hospital vinyl flooring. Ceramic floor tiles located at rooms 2130
(bathroom) and 2128 (storage area) inside the Safe Haven (room 2127), will remain as is.
The carpet tiles inside in room 2127 will also remain as is (see ANNEX ARQ 02/13).
6.1.5 CONTRACTOR will be responsible for opening trenches in the concrete floor and brick walls to fit and run the required infrastructure for telecom, electrical, and water network (water lines, sewage lines, vent pipes, power outlets, light switches, junction boxes, electrical and telecom conduits). New sinks, new sewers, and new potable water lines will be installed particularly in rooms 2131 (Exam Room #1), 2132 (Exam Room #2), and 2133 (Pharmacy).
The design project will be handled by the CONTRACTOR (DWG and PDF files) and submitted to the US GOVERNMENT for approval purposes (architectural, electrical, plumbing, fire, telecom, and HVCA drawings). The drawings submitted to the US GOVERNMENT (in scale) will indicate the exact location, dimensions, quantities, position, distances, elevations, and materials selected by the CONTRACTOR for the improvements of the infrastructure inside the Medical Unit.
6.1.6 All materials and parts removed from the site during the demolition process that are neither damaged nor broken and will not be recycled by the CONTRACTOR (sirens, smoke detectors, lamps, sockets, switches, ceiling tiles, air intakes, emergency signs, strobe lights, alarms, etc.) shall be handled to the US GOVERNMENT instead of discarding them in a landfill.
6.2 Installation of Electrical Circuits
6.2.1 Panel and Transformer Relocation
6.2.2 Nowadays, the circuits of Rooms 2127, 2128, 2129 and 2130, are powered by the panels 2-
ELB-13 (OUT OF THIS SCOPE) and 2-ELB-14, which will be affected with the relocation thereof. The part of CONTRACTOR's responsibility in this scope is to relocate the panel 2-
ELB-14 and 2XRM-00515KVA Transformer located at room 2127 to the room 2193, see
ATTACHED Drawing MED UNIT- ELECTRICAL INFO. Sheet ELE 01/03. Reminding that today these feeding circuits described in the Electric Drawing MED UNIT- ELECTRICAL INFO. SHEET
ELE 01/03.
6.2.3 CONTRACTOR is responsible for all costs relating to these changes;
6.2.4 Predicted Circuits
6.2.5 The CONTRACTOR shall provide all the modifications requested in the Drawings MED UNIT-
ELECTRICAL INFO.- Sheets ELE 01/03 and ELE 02/03.
SCOPE OF WORK Page 9 of 27
6.2.6 The CONTRACTOR understands the needs for special circuits according with specific function requested in electrical codes, should be inserted into the CONTRACTOR project, see
ATTACHED Drawing MED UNIT- ELECTRICAL INFO. Sheet ELE 02/03.
6.2.7 The CONTRACTOR shall maintain all existing circuits of the offices according to the
ATTACHED Drawing MED UNIT- ELECTRICAL INFO. Sheet ELE 02/03, so as removing or relocating in accordance with the drawing information.
6.2.8 The US GOVERNMENT understands that, after removing the drywall walls, the paths of the affected circuits should be remade and therefore included in the CONTRACTOR project
(Meant for the project, the architectural design presentation in scale, with details of dimensions, materials and locations in the electric blueprint):
• The choice of the temporary paths for distribution circuits in use;
• The choice of new ways of distribution of these affected circuits;
• All costs related to these changes.
6.2.9 Temporary Circuits
6.2.10 The US GOVERNMENT establishes the rule that during the project implementation process, the improvement of work and adjustments related to the Medical Unit cannot or should interfere with the operation and smooth progress of the activities undertaken by other agencies operating within the American US GOVERNMENT. It is the CONTRACTOR to note that the shutdown (at the beginning of the work) and the reconnection of electrical circuits
(after work), to be made outside of business hours (possibly on the weekend), and furthermore that all off circuit in this period (circuit that may or may affect or interfere the operation of other agencies) should provide a temporary parallel connection in the project implementation period, in order to allow the safe operation of US agencies and US
GOVERNMENT Staffs at construction site.
6.2.11 The US GOVERNMENT forwards the files listed below, by way of clarification, that the
CONTRACTOR can plan and organize the shutdown and restart of existing electrical circuits at the project site. It is the responsibility of the CONTRACTOR, forward, along with the construction schedule, the details and procedures to be adopted for the shutdown process and restart the power grid.
MED UNIT- ELECTRICAL INFO. Sheet ELE 01/03 - Relocation Panel Transformer;
MED UNIT- ELECTRICAL INFO. Sheet ELE 02/03 - Electrical outlets and circuits;
MED UNIT- ELECTRICAL INFO. Sheet ELE 03/03 – Existing Panels.
6.3 Lighting
6.3.1 The light fixtures of the rooms should be maintained and its future locations should be made in accordance with the CONTRACTOR's Project requiring only that the CONTRACTOR check the current position in relation to the final layout. If there is a need for new light fixtures, SCOPE OF WORK Page 10 of 27
CONTRACTOR is responsible to provides them, fitting the CONTRACTOR all costs that can be generated (design, checks, relocation etc).
6.3.2 There will be the need to change some light switches, so it is the CONTRACTOR (in your project) to review these positions and all costs necessary to be carried out the work.
6.3.3 The CONTRACTOR shall use the MED UNIT- LIGHT FIXTURES - SHEET LIF 01/01 as guidelines for the lighting design.
6.3.4 All the infrastructure (material and labor) necessary to adapt the lighting project will be the responsibility of the CONTRACTOR and therefore must comply with the specifications required by the Brazilians Codes ABNT (NBR) for environments that fall in the category of wards or hospitals.
6.4 Alarms
6.4.1 All infrastructure alarms (Fire and security) should only be removed or relocated in cases where the devices are present in the demolished walls or acoustic ceiling tiles removed from the local, leaving the CONTRACTOR pay all relocation costs and / or replacement if applicable.
6.4.2 In the case of fire alarm system (strobes, sirens and smoke sensors), is the charge of the
CONTRACTOR, in the case of relocation / replacement of these devices (strobes, sirens and smoke sensors), follow the standards observed by the US GOVERNMENT (the same type of material and the same installation procedure) or meet the standards of existing regulations on this matter.
6.4.3 In the other areas, the fire alarm system (acoustic ceilings and walls) must be maintained and preserved with due care.
6.4.4 The CONTRACTOR provides the ATTACHMENT MED UNIT- FIRE ALARM EQUIPMENTS
POSITIONS - SHEET 01/01 as part of the relevant information that the CONTRACTOR shall take into consideration in their design.
6.5 Telecommunication
6.5.1 The contracted company will be responsible for the following items of this scope:
Item #1. Perform the withdrawal of the former CAT6 cables from the cable tray (under the lining in the project area), which are not in use, or they will lose their usefulness in this project, noting that the US GOVERNMENT Telecom Technician always be informed before this withdrawn.
Remove all cables and conduits that originate in the following rooms and end in Room #
2144 (Telecom Room):
SCOPE OF WORK Page 11 of 27
1.1 Room # 2131 (Future - Exam 1);
1.2 Room # 2132 (Future - Exam 2);
1.3 Room # 2133 (Future - Lab-Pharm);
1.4 Room # 2134 (Future - Nurse Station);
Item #2. Install galvanized pipe 1 inch interconnecting the existing CAT6 cable tray (on the ceiling) to the following rooms:
• 2131
• 2132
• 2133
• 2134A / B / C
(See ANNEX MED UNIT – TELECOM – SHEET 01/01).
Item #3.
3.1 - Install 4 CAT6 cables in each case 4 "X 2" in the following colors:
•Blue
•Red
•Green
•Yellow in the following rooms:
• 2131
• 2132
• 2133
• 2134-A / B / C
(Totaling 24 CAT6 cables).
6.5.2 These CAT6 cables must be connected from their rooms to the Telecommunications room #
2144.
6.5.3 The CONTRACTOR must leave a surplus of about 0.5 cable Metro in each box 4 "X 2" and should also leave a surplus of approximately 6 meters of cable inside the rack (telecom room
# 2144)
6.5.4 The blue cables should be in telephone blocks (Block located outside the rack at room
Telecom # 2144) for the appropriate terminations.
6.5.5 The US GOVERNMENT Technician will be responsible for making connections in their rooms and into the rack in the telecommunications room.
Item#4. Identification of each CAT6 cable with the respective rooms, for example:
• room # 2133 -
Blue cable 2133/1
Red cable 2133/2
Green cable 2133/3
SCOPE OF WORK Page 12 of 27
Yellow cable 2133/4
• observing the same IDs at both ends (telecom room # 2144 and workstation).
NOTE: Room # 2134 because it is an environment with more than one workstation consider computers / connections A, B and C. (See ANNEX MED UNIT – TELECOM – SHEET 01/01)
Item #5. The CONTRACTOR shall maintain all existing TELECOM points in order ANNEX MED
UNIT – TELECOM – SHEET 01/01.
6.5.6 The CONTRACTOR provides the ANNEX MED UNIT – TELECOM – SHEET 01/01 as part of the relevant information that the CONTRACTOR shall take into consideration in its design.
6.6 Air conditioning
6.6.1 CONTRACTOR shall verify the need to separate the air conditioning and its return Laboratory
/ Pharmacy room (room 2133) from the other rooms. This check should be performed (MED
UNIT – HVAC EXISTING LAY-OUT – SHEET 01/02 and 02/02) and the project must follow the
CURRENT Brazilians regulations (due to the possible risk of biological contamination).
6.6.2 A referendum on this item should be made in the proposal in order to inform the US
GOVERNMENT about the decision taken by the CONTRACTOR in the development of their project and consequent costs presented in the proposal.
6.6.3 Reminding the CONTRACTOR that in case of need for installation of exclusive equipment it is up the CONTRACTOR the use Cassete Split of Air Conditioning machines since that it’s properly calculated.
6.6.4 CONTRACTOR is responsible for the evaluation and if necessary the relocation of their proper controls to their offices, and they should be installed near the access doors.
6.6.5 The US GOVERNMENT remember that all calculations for the viability of these changes so as
Any extra cost is the sole responsibility of CONTRACTOR.
6.7 Cold Water and Sewer Connections
CONTRACTOR will install all needed plumbing infrastructure (pipes, drains, fittings, bends, joints, angles, valves, etc.) to supply, control, and transport potable water, sewage, and sanitary gases from the new sinks in the Medical Unit. CONTRACTOR may want to use the water supply and sewage outlet currently serving room 2132 to feed or derive the connections required for the new sinks at rooms 2131 and 2133 (see ANNEX PB 01/03 and
PB 02/03). CONTRACTOR is responsible for developing the Medical Unit plumbing design and submitting the drawings (raise diagram in scale) to the US GOVERNMENT for review and approval before any work is performed at the job site or any material is acquired at all. The following Brazilian Standards for Construction and Building Codes (ABNT/NBR) will be observed for the plumbing project: 5626, 5647-1, 5647-2, 5647-3, 5647-4, 5688, 7362-1, SCOPE OF WORK Page 13 of 27
7362-2, 7362-4, 7367, 8160, 9814, 10570, and 14486. Equivalent or more stringent international codes will be accepted only when indicated with details on the commercial proposal (International Building Codes - IBC, International Organization for Standardization -
ISO, BOCA, UBC, ASTM, etc.).
6.8 Metals (Faucets, Valves, Flexible Hoses, Drain Baskets, Strainer, and Siphons)
Metal finishing is required for all plumbing device accessories that belong to the hydraulic network such as faucets, valves, strainers, siphons, drains, etc. (see ANNEX PB 03/03).
CONTRACTOR shall furnish them in bright stainless steel (polished) similar to DECA standards or better (DECA is a local reliable Brazilian plumbing trade maker). The cold water lines feeding into the sinks will be embedded in masonry walls. Sink water faucets will be connected to the water lines by means of braided stainless steel flexible pigtail. The following Brazilian Standards for Construction and Building Codes (ABNT/NBR) will be observed for the plumbing project: 14162, 15423, 15491, 15857, 12483, 14011, 14390, 14877, 14878, 15200 and 15267. Equivalent or more stringent international codes will be accepted only when indicated with details on the bid proposal (International Building Codes
- IBC, International Organization for Standardization - ISO, BOCA, UBC, ASTM, etc.).
6.9 Drywall Walls
6.9.1 CONTRACTOR will provide all materials (plasterboard panels, runners, studs, anchors, ribbons, joint tapes, brackets, screws, etc.); hire skilled certified labor; and use appropriate working tools (ANNEX ARQ 05/13). The plasterboard panels must be anchored into vertical studs, horizontal tracks, guides and runners made of zinc coated (galvanized by hot dip process) following the installation guidelines recommended by the drywall manufacturer, the Brazilian Standards for Construction and Building Codes (ABNT/NBR) or any equivalent or more stringent international code.
6.9.2 Plasterboard shall be delivered and installed in panels with minimum gage of 12.5 mm thick
(STM-12.5).
6.9.3 All openings, gaps, joints and spaces reported on the surface of the plasterboard panels after the installation process of the walls should be treated (sealed, closed, and sanded) with specific compound material for drywalls (plaster, tape and jointing materials). The surface should be leveled, polished and delivered free of burrs, bumps, wrinkles or imperfections.
The outer edges of the walls shall be protected with perforated reinforcing channels (L-shape) in order to absorb impacts against the edges of the walls (see ANNEX ARQ 05/13).
The following Brazilian Standards for Construction and Building Codes (ABNT/NBR) will be observed for in the drywall project: 15758-1 (2009) 15758-2, 15758-3, 15758-3 (2009), 14.715- (2010), 14715-2 (2010), 15217 (2010), 9575, 15884). Equivalent or more stringent international codes will be accepted only when indicated with details on the bid proposal
SCOPE OF WORK Page 14 of 27
(International Building Codes - IBC, International Organization for Standardization - ISO, BOCA, UBC, ASTM, etc.).
6.10 Doors, Jambs, Windows and Window Frames
6.10.1 Doors: CONTRACTOR shall provide and install solid wood doors where the doors are needed
(see instructions in ANNEX ARQ 03/13). CONTRACTOR shall provide doors with similar or higher standards of the existing doors inside the Medical Unit. The new doors shall have the similar specification regarding the type of material, size, texture, color, fire proof (60 minutes), etc.
6.10.2 Hardware: CONTRACTOR shall provide locks designed specifically for infirmary rooms
(examination, laboratory, waiting room, etc.) complying with the governing regulations.
Three doors located in the escape route shall be furnished with panic bars, locks and mechanical springs (arm closers). All doors shall be mounted over metallic jambs by means of a set of 3 plain bearing brass hinges (with 5 Knuckles, full mortise, made of stainless steel or galvanized steel and steel removable pin as well, having square corners). CONTRACTOR shall comply with similar or higher standards adopted by the US GOVERNMENT for door hardware.
6.10.3 Door jambs, door frames, and door casing shall be bolted or welded to the vertical studs and door headers of the drywall structural system installed to support the gypsum board panels.
Lintels and door frames shall be built with double studs to enhance structural strength (see
ANNEX ARQ 06/13). The double steel studs shall be inner filled with or without a piece of timber plank over the door jambs (optional).
6.10.4 Window: CONTRACTOR shall install a passage/teller window type between rooms 2137 and
2138 where the Physician assistant will proceed with the pre-screening process of patients, exams, and documents. The passage/teller window type should follow similar or higher standards of the windows installed in the Cashiers and Citibank offices (rooms 2355 and
2125). The window frame shall be built 800mm high by 850mm wide; consisting of either laminated or tempered glaze 3 mm thick; with two sliding leaves (hangers and locks provided for each leave); black aluminum jamb and frame, and a MDF wooden reception shelf (counter) having the wood surface covered with smooth laminated Formica. The wood counter shall be mounted on both sides of the wall, inside and outside, of the reception desk
(see ANNEX ARQ 07/13). CONTRACTOR shall provide architectural scaled detail drawings of the passage/teller window and wood shelf (counter) both in DWG and PDF files. The drawings shall be submitted in advance for the US GOVERNMENT review and approval before the CONTRACTOR starts acquiring any material or proceeds with the fabrication process. Only after receiving an official written note from the US GOVERNMENT, the
CONTRACTOR is authorized to proceed with the project.
6.10.5 Samples of all materials must be submitted to the US GOVERNMENT with the technical specification of it (catalogs, brochures or data sheets) before the CONTRACTOR procures any
SCOPE OF WORK Page 15 of 27 quantity of material. CONTRACTOR shall proceed with the acquisition process only after an official approval written note is issued by the US GOVERNMENT.
6.10.6 CONTRACTOR is allowed to reuse all doors (15) existing within the construction site. Eleven doors (11) will remain in the same location and will require no work at all (P2, P4, P5, P6, P7, P8, P9, P10, P11, P14 and P15). Four doors (4) shall be transferred to a new location as per guidelines indicated in ANNEX ARQ 03/13 (P1, P3, P12 and P13). During the site visit, CONTRACTOR shall examine and carefully evaluate, if two solid doors (P1 and P13), to be installed at the Medical Unit escape route can be reused or shall be replaced by new solid wood doors due to incompatibilities that might exist with respect to the height or size of the hole of the new lock to be installed on it; the swing side of the door opening; requirements for the panic bars; etc. It is the CONTRACTOR’s responsibility to asses and selects the best option that will meet the requirements for the wood door (reuse existing doors or replace them all by new solid wood doors).
6.11 Acoustic Ceiling Tiles
6.11.1 CONTRACTOR shall make the necessary adjustments or replacements of acoustic ceiling tiles within the area affected by this project. CONTRACTOR shall follow the exact same standards or most similar ones trying to match the standards used by the US GOVERNMENT (channels, rods, brackets, beams, joists, tiles, tracks, color, texture, etc.). The following Brazilian
Standards for Construction and Building Codes (NBR) will be observed: 15758-1 (2009 )
15758-2 , 15758-3 , 15758-3 (2009 ) , 14.715- (2010 ) 14715-2 (2010 ) , 15,217 (2010 ) , 9575
, 9574 , 15885 ). Equivalent or more stringent international codes will be accepted only when indicated with details on the bid proposal (International Building Codes - IBC, International Organization for Standardization - ISO, BOCA, UBC, ASTM, etc.).
6.11.2 It is the CONTRACTOR's responsibility to evaluate and predict where the changes of the acoustic ceiling tile system will be needed. There is no need to replace the entire ceiling tile system (channels, rods, brackets, beams, joists, tiles, tracks, etc.) in areas that do not expect or will not have any type of intervention or modification in the internal drywalls (rooms
2127, 2128, 2129, 2130, 2133, 2135, and 2139).
6.11.3 CONTRACTOR shall leave in a longitudinal upper section of the demolished drywall (acting as a fake beam), approximately 90mm below the alignment with the drop down ceiling tiles.
The longitudinal upper section will serve as a transitional element between the acoustic ceiling tiles of adjacent rooms where the drywall is expected to be removed (this method is recommended for the drywalls dividing rooms 2137-2105 and 2138-2105). This solution will save additional ceiling tile work if the longitudinal upper section is implemented in the indicated sections. Details of the upper longitudinal drywall section separating two adjacent rooms are illustrated in the architectural drawing included in ANNEX ARQ 08 13.
SCOPE OF WORK Page 16 of 27
6.12 Floor Tiles and Wall Base
6.12.1 CONTRACTOR shall replace the entire floor and baseboard located within the Medical Unit area where the refurbishment will take place. The Medical Unit area has a surface floor of approximately 160 square meters which are currently covered with three types of floor tiles:
carpet tiles, vinyl tiles, and vinyl blankets.
6.12.2 All preparation involving the ground floor and sub-floor required for the installation of vinyl blankets (hospital flooring) will be the CONTRACTOR solely and exclusively responsibility
(fixing cracks, leveling the floor, repairing unattached grouts, etc.).
6.12.3 The hospital vinyl flooring material (vinyl blankets) should add all features that meet the current health requirements for hospital environments, laboratories, sick bays, drugstore, etc. There are several areas with different characteristics and needs in the hospital environment (such as reception areas, administrative areas, corridors, treatment rooms, laboratories, recovery rooms, exam room, etc.). For each area, the Brazilian Standards for
Construction and Building Codes (ABNT/NBR) and the National Health Department (ANVISA) recommends a specific type of flooring that shall be carefully observed by the CONTRACTOR.
6.12.4 It is recommended the use of homogeneous vinyl flooring available in 2 m wide, 25 m long and 2 mm thick (rolls). The edge of the vinyl sheets shall be welded together (hot melted at
600 °C) with a vinyl weld bead of approximately 4 mm. The vinyl sheets shall be laid over the wall base at the same high as the baseboard (rounded corners 75 mm high) making it one single monolithic floor piece with watertight and waterproof features. CONTRACTOR shall apply surface restauration composition products that will eliminate the use of wax and provide the surface recovery by polishing it only.
6.12.5 The surface floor for rooms 2105, 2131, 2132, 2133, 2134, 2135, 2136, 2137, 2138 and 2139 will be replaced by hospital vinyl flooring (roller or blanket type). The floor finishing for rooms 2127, 2128, 2129 and 2130 will remain as is. Rooms 2127 and 2130 will remain with current textile carpet tiles as well and rooms 2128 and 2129 will remain with the existing ceramic tiles (see ANNEX ARQ 09 of 13).
6.13 Treating and Painting the Walls
6.13.1 All internal and external walls of the Medical Unit shall be treated and painted by the
CONTRACTOR applying three layers of coat
6.13.2 After treating the walls (removal of cracks, breaks, gaps, stains, dirt, dust, etc.), CONTRACTOR shall paint the walls with acrylic paint, PVA, or latex coat using the correct type of paint corresponding to the material type the treated surface is made of (wood, gypsum, masonry, metal, concrete, etc.).
SCOPE OF WORK Page 17 of 27
6.13.3 Color of the walls will be defined by the local medical team either during the site visit scheduled with the CONTRACTOR to inspect and appraise the construction site general conditions or at the time the pre-construction meeting takes place in the US GOVERNMENT facilities. CONTRACTOR shall select reliable trademarks locally available taking into account the cost/benefit ratio (price, maintenance, availability, life span, etc.).
6.14 Furniture
6.14.1 CONTRACTOR is responsible to design, fabricate, and install 3 units of MDF hospital cabinets
(lower module, upper module, countertops, drawers, shelves, workbench, etc.), with built-in sink (stainless steel sink bowl) that will be installed at rooms 2131 (Examination), 2132
(Examination) and 2133 (Laboratory/Pharmacy). CONTRACTOR shall include on the bid proposal costs related to material, delivery charges, and specialized labor.
6.14.2 The design and layout of the MDF cabinets shall follow the guidelines that will be provided by the Medical Unit experts in Sao Paulo concerning the cabinet accessories (hinges, handles, countertops, doors, drawers, sinks, water taps, drains, etc.), materials (wood, granite, stainless steel, porcelain, formica, glazing, etc.), dimensions (length, height, width, thickness, etc.) and layout (shelves, drawers, and doors). For budgetary purposes, the
CONTRACTOR shall refer to sketches indicated in ANNEX ARQ 10/13 and ARQ 11/13. These sketches are just preliminary drawings that shall not be considered the final design. The material types listed below shall be used as guidelines for the proposal but will need to be confirmed during the site visit:
- MDF wood panels: drawers, shelves, doors, counter tops (workstation), etc.
- Stainless Steel: hinges, handles, tracks, sink bowl, water faucet, water valves, drains, etc.
6.14.3 CONTRACTOR will be authorized to acquire the materials and start the manufacturing process of the MDF cabinets after the architectural drawings are revised and officially approved by the US GOVERNMENT on written.
6.15 Disposal of Construction Materials and Site Cleanup
6.15.1 CONTRACTOR shall separate, remove and transport all the construction debris to a landfill licensed by the city of Sao Paulo authorities.
6.15.2 The construction area as well as the entire surrounding area affected by the Medical Unit refurbishing process (offices, corridors, walkways, furniture, doors, windows, floors, etc.)
must be delivered clean and free of dust, dirt, debris or stains that have been generated by the job.
SCOPE OF WORK Page 18 of 27
7.0 PRE-CONSTRUCTION REQUIREMENTS
7.1 It’s a CONTRACTOR responsibility examine all the documents and to arrange any required site visits to fully inform themselves of all the conditions and limitations applied to the work needed to submit a proposal for the work. CONTRACTOR is responsible for all costs associated with existing conditions.
7.2 CONTRACTOR is required to demonstrate in the bid proposal that the CONTRACTOR is experienced and capable of performing all of the requirements as specified in the SOW.
7.3 CONTRACTOR is required to submit a timeline for completion of the project.
7.4 CONTRACTOR is required to submit a list of the company’s principle officers and project manager and their qualifications.
7.5 CONTRACTOR is required to submit a list of materials and equipment and their specifications that he proposes to use in the project.
7.6 CONTRACTOR is required to demonstrate that he has all required licenses and permits to perform the required work stated in the SOW.
SCOPE OF WORK Page 19 of 27
8.0 CONSTRUCTION REQUIREMENTS
8.1 The CONTRACTOR will be responsible to notify the COR in writing and receive approval of any work that will be performed that will impact normal US GOVERNMENT operations.
CONTRACTOR will be liable for any damages caused by the interruption of normal US
GOVERNMENT operations without prior written approval of work by the COR.
8.2 The CONTRACTOR will be responsible to provide all materials, equipment and qualified personnel to manage, administer, supervise and complete the project. The work shall be executed in a diligent, professional and craftsman like manner in accordance with a negotiated firm fixed price and performance period.
8.3 All materials and equipment incorporated into the project must be new unless noted otherwise. The CONTRACTOR shall transport and safeguard all materials and equipment required for construction.
8.4 Equipment and materials must be carefully handled, properly stored, and adequately protected to prevent damage before and during installation, in accordance with the manufacturer's recommendations. Damaged or defective items have to be replaced. The
CONTRACTOR will be responsible for security of all materials and equipment.
8.5 Receipt of Materials - Shipment of equipment, materials, and supplies shall be addressed to the CONTRACTOR - not the US GOVERNMENT. The CONTRACTOR must be on hand to accept shipments; the USG will not accept shipments.
8.6 The CONTRACTOR will be provided with a storage and staging area as determined by the
COR. The CONTRACTOR shall be responsible for restoring the area to its original condition at the completion of the work. The CONTRACTOR shall be responsible for repair of any damage incurred to buildings or pavement as a result of storage activities. The
CONTRACTOR is responsible for obtaining any additional off compound storage areas as required.
8.7 The CONTRACTOR shall at all times keep the work area free from accumulation of waste materials. Upon completing construction, the CONTRACTOR has to remove all temporary facilities and leave the project site in a clean and orderly condition acceptable to the COR.
8.8 The CONTRACTOR shall perform the work at the site during the US GOVERNMENT's normal workday hours, unless agreed upon with the COR.
8.9 The CONTRACTOR shall be responsible for connection of temporary utilities to existing utilities including water and power lines (if necessary for the work). All temporary connections to local water and power lines have been coordinated with the COR. The
CONTRACTOR must pay all costs incurred in connecting, converting, and transferring the utilities to the work. The CONTRACTOR will be responsible for making connections including
SCOPE OF WORK Page 20 of 27 providing back flow preventer devices on connections to domestic water lines, providing transformers, and for disconnections.
8.10 At the end of each work day, or notification of a temporary stop order, the CONTRACTOR will lower and secure all temporary work platforms and/or harnesses. CONTRACTOR must notify the COR of the need and location to barricade or restrict access to areas due to the project. The CONTRACTOR must remove the need for temporary barricades as soon as possible.
8.11 Storm Protection - Should warnings of wind of gale force or stronger be issued, the
CONTRACTOR must take every practicable precaution to minimize danger to person, the work and adjacent property. Precautions shall include, but not be limited to, closing all openings, removing all loose materials, tools and equipment from exposed locations, and other temporary work.
8.12 Cleanup - The CONTRACTOR must keep the work area, including storage areas, free from accumulations of waste materials on a daily basis and comply with all federal, state and local regulations pertaining to the storage, transport and disposal of wastes. The CONTRACTOR will not use US GOVERNMENT waste disposal facilities including garbage cans, trash piles or dumpsters.
8.13 Landscape Restoration - The surfaces of all unpaved areas disturbed by construction activities must be sodded with an approved grass native to the sodded area as approved by the COR. These shall include areas which existing pavement is removed, areas where excavation takes place, and areas where existing sod is killed or compacted by construction activities. Landscape shrubs killed or damaged by construction activities will be replaced with same species and size.
SCOPE OF WORK Page 21 of 27
SCOPE OF WORK Page 22 of 27
9.0 CRITERIA
9.1 The CONTRACTOR must work in accordance with U.S. codes and standards. The COR will review and comment on the CONTRACTOR’s submissions using the following codes and standards:
American Society for Testing & Materials (ASTM);
International Building Code (IBC, ISO, etc.);
International Mechanical Code;
International Plumbing Code;
National Electrical Code (NFPA);
Brazilian standards of reference for this project are the NBRs, ABNT, IPT, INMETRO and the specifications required by the City of Sao Paulo.
9.2 All proposals in conformity with all technical specifications and with the reasonable schedule will be recommended to the Contracting Officer as a Technical Compliance Conformity.
9.4 The Awarded CONTRACTOR will be first advice by CO thru a designated letter and following, the CONTRACTOR will received a Notice to Proceed (NTP)
SCOPE OF WORK Page 23 of 27
10.0 DELIVERABLE SCHEDULE
10.1 The CONTRACTOR should commence work under this contract promptly, execute the work diligently, and achieve final completion and acceptance including final cleanup of the premises within the period specified.
10.2 Milestones:
CONTRACTOR Pre-Proposal Site Visit TBD
CONTRACTOR Delivery the Proposed Quotation TBD
Award of Contract & Notice to proceed TBD
Pre-Construction Submittals TBD
US GOVERNMENT Submittal Review TBD
Construction Begins TBD
Construction TBD
10.3 Project Completion: Furnish one copy of maintenance and operating information, CONTRACTOR’s one year workmanship guarantee and product literature of all items installed.
SCOPE OF WORK Page 24 of 27
SCOPE OF WORK Page 25 of 27
11.0 PROJECT SECURITY
11.1 The work to be performed under this contract requires that the CONTRACTOR, its employees and sub-CONTRACTORs submit personnel information to the USG. Information submitted by the CONTRACTOR will not be disclosed beyond the need to ensure the security and safety of
USG personnel assigned to the US US GOVERNMENT of Sao Paulo.
11.2 The CONTRACTOR will submit this information including construction vehicle requirements within 10 days of the Notice to Proceed. During construction all new names and vehicles information’s must be submitted to the COR with at least 24 hours (1 working day) in advanced of the needed date of access.
11.3 COR will notify the CONTRACTOR of the approved list of employees as soon as possible, CONTRACTOR will not be penalized for any delays due to clearing of his personnel.
11.4 CONTRACTOR will be required to submit the following information to the COR for each employee that will be required to enter the US US GOVERNMENT Compound-
Employees Full Legal Name
Clear and legible copy of the persons General Register (Brazilian ID Card)
Clear and legible copy of the Registration Physical of Person (Company ID Card, CPF)
11.4 CONTRACTOR will be required to submit the following information to the COR for each vehicle that will be required to enter the US US GOVERNMENT Compound-
Vehicle Number Plate
Color
Manufacture
Model
Driver o Full Legal Name o Driver’s License Number o Drivers National ID Number
NOTE – Driver’s Information NOT needed if driver is already listed on the list of Cleared
CONTRACTOR’s Employees
SCOPE OF WORK Page 26 of 27
12.0 PAYMENTS
12.1 The CONTRACTOR shall submit all payment invoices, with the appropriate backup documents to the COR. The COR will determine if the invoice is complete and proper as submitted. The COR also will determine if billed services have been satisfactorily performed and if expenses billed are correct. If it is determined that the amount billed is incorrect, the
COR will return the invoices to the CONTRACTOR within seven days and request the
CONTRACTOR to submit a revised invoice.
12.3 The CONTRACTOR will specifically identify his last invoice "Final Invoice." The Final invoice shall include the remaining payment claimed to be due under the basic contract and all modifications issued, if any. The final invoice shall also have the CONTRACTOR's Release of
Claims Certificate attached.
SCOPE OF WORK Page 27 of 27
13.0 ATTACHMENTS
13.1 MED UNIT – ARQ
13.2 MED UNIT - ELECTRICAL
13.3 MED UNIT - FIRE ALARM
13.4 MED UNIT - HVAC
13.5 MED UNIT - LIGHT FIXTURES
13.6 MED UNIT - PLUMBING
13.7 MED UNIT - TELECOM
File details come from the government source that posted it. Updated .