This Statement of Work (SOW) details gutter and downspout cleaning and minor repair services for 32 residential buildings at Carl Schurz Siedlung, operated by the U.S. Consulate General Frankfurt, Germany. The contractor must remove all debris (leaves, dirt, twigs, nests, sediment, and obstructions) from gutters, valleys, and downspouts; inspect gutter systems for damage, leaks, rust, sagging, or separation; and perform minor repairs identified during inspection on a time-and-materials basis. Minor repair work includes re-securing loose or sagging gutters and brackets, re-aligning gutter sections or downspouts, sealing minor leaks using weatherproof sealant, reattaching or replacing hardware such as screws and brackets, and patching small holes or minor corrosion spots. The contractor must provide all labor, materials, supervision, and equipment at no cost to the government, with sealants, fasteners, brackets, and patching materials matching the existing gutter system type and finish where practicable.
The total period of performance is 60 calendar days, beginning from contract award (Zero Day), with pre-construction submittals due within 10 days of award and government review completed within 5 days. Material procurement requires 5 days for ordering and 5 days for shipping. Mobilization and construction phases allow 5 days advance notice for crew information and 30 days on-site for the scope of work. Work must be performed during normal U.S. Consulate hours (0800-1630 Monday through Friday, excluding holidays) unless alternate hours are agreed upon with the Contracting Officer's Representative (COR). The contractor must comply with U.S. OSHA Regulations, U.S. Army Corps of Engineers Safety Manual (EM 385-1-1), applicable international building codes, and local German labor laws. All contractor personnel require Visit Authorization Requests (VAR) prior to entry, and vehicles require separate clearance authorization. The contractor must prepare and submit a Project Safety Plan for COR and Post Occupational Safety and Health Officer (POSHO) approval, provide Personal Protective Equipment for all employees, and ensure all personnel complete mandatory online safety briefing prior to project commencement. A German and English-speaking Project Site Manager must be identified and approved by the COR.
View the file
On GovTribe
Work with this file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
09/15/2026 STATEMENT of WORK 1
UNCLASSIFIED
MAINTENANCE & REPAIR STATEMENT of WORK
Frankfurt, Germany
Gutter and Downspout Cleaning and Minor Repair Services
Carl Schurz Siedlung
CONTENTS:
PART ONE GENERAL
PART TWO PRODUCTS
PART THREE EXECUTION
PART FOUR SCHEDULE
U.S. CONSULATE GERNERAL FRANKFURT, GERMANY
FACILITY MANAGEMENT
09/15/2026 STATEMENT of WORK 2
PART ONE – GENERAL
C.1.1 SUMMARY:
A. The U.S. Consulate General Frankfurt requires cleaning, inspecting, minor repair, and maintenance of the rain gutters and downspouts of 32 residential buildings at the Carl
Schurz Siedlung to ensure proper stormwater drainage and prevent water damage to the facility. The Contractor shall provide all necessary labor, materials, supervision, and equipment to complete the project. Work includes, but is not limited to:
1. Remove all debris (leaves, dirt, twigs, nests, sediment, and other obstructions) from all gutters, valleys, and downspouts
2. Inspect gutters, downspouts, hangers, brackets, seams, and joints for damage, leaks, rust, sagging, or separation from the structure
3. Perform minor repairs identified during cleaning and inspection
a. Minor repairs shall be billed on a time-and-materials basis
C.1.2 SUBMITTALS:
A. Contractor’s crew individual identification information for visitor access requests.
B. Submit list of all subcontractors with evidence of subcontractor's insurance coverage.
C. Project schedule showing work phasing and proposed daily progress.
C.1.3 CONTRACT ADMINISTRTION
A. The Contractor shall not perform any work outside this Statement of Work unless authorized in writing by the Contracting Officer (CO).
B. The CO will issue a Notice to Proceed (NTP).
C. The Contracting Officer’s Representative (COR) will oversee daily execution and ensure compliance.
D. Any proposed changes must be submitted in writing and approved before work proceeds.
E. The Contractor shall identify a Project Site Manager who shall be responsible for the overall management of the project and shall represent the Contractor on the site during construction. The Project Site Manager is required to be German and English-speaking and shall be approved by the COR.
C.1.4 QUALITY CONTROL:
A. The Contractor shall be responsible for the professional quality, technical accuracy, and the coordination of all construction and other services furnished under this contract. The
Contractor shall, without additional compensation, correct or revise any errors or deficiencies in its construction and other services.
B. The Work shall be governed by the U.S. Consulate General Frankfurt, Germany. All work is to be in compliance with International Codes and standards, which includes the most recent published edition of the OBO Building code, National Fire Prevention Association
(NFPA), International Fire Code (IFC), International Building Code (IBC) , International
Mechanical Code (IMC), International Plumbing Code (IPC), National Electrical
Installation Standards (NEiS), National Electrical Safety Code (NESC), Standard for
Electrical Safety in the Workplace (NFPA-70E) and National Electric Code (NFPA-70) as amended by OBO, also are applicable. Should there be a discrepancy between the US
Government Specifications and the applicable Building Code, the more stringent of the two shall govern.
C.1.5 STORAGE OF MATERIALS:
A. The Contractor is responsible for safe and secure storage of materials.
B. On-site staging must be coordinated with the COR.
C. Temporary utilities must be connected and disconnected in coordination with Facility
Management.
09/15/2026 STATEMENT of WORK 3
C.1.6 PROJECT SAFTEY:
A. Contractor is responsible for safety and shall comply with US Consulate General requirements, US Army Corp of Engineers (USACE) Safety Manual (EM 385-1-1), U.S.
OSHA Regulations and all local labor laws, regulations, customs and practices pertaining to labor, safety and similar matters. Contractor shall prepare a Project Safety Plan to cover total project safety to be reviewed and approved by the Contracting Officer Representative
(COR), and U.S. Consulate Post Occupational Safety and Health Officer (POSHO).
B. Contractor shall furnish Personal Protective Equipment (PPE) for each employee as required for the specific job type and in accordance with (IAW) relevant OSHA regulations.
C. All external personnel assigned to a project are required to participate in a mandatory online safety briefing conducted by the POSHO Safety Office. This safety training must be completed prior to the project start date and the commencement of any work activities.
1. Personnel joining the team after the project has commenced must also complete this training before undertaking any tasks.
2. Work conducted without prior safety training is strictly prohibited and will be immediately suspended upon discovery.
3. The safety briefing may be found at the following link;
https://forms.office.com/g/shZ4sLh5Kn
D. Electrical Safety: All electrical work must always be conducted in a "de-energized" state whenever possible and secured using the Lockout/Tagout (LOTO) system/procedure.
Energized work must be handled with special precautions as outlined below.
1. Locks and tags must be applied to the equipment's energy isolation points or control panels. The tags must prominently display a warning message, along with the company name and the technician’s name. LOTO devices may only be removed by the individual who applied them.
2. Energized Work can only be performed if the supervisor requests an Energized
Work Permit (EWP) at the Post Occupational Safety and Health Officer (POSHO) at least 24 hours prior to the scheduled start of work. The COR must assist the contractor in obtaining the necessary documents.
E. Hot Work: A hot work permit must be requested from the contractor at least 24 hours prior to the start of the work. The COR must assist the contractor in obtaining the necessary documents.
F. Confined Space: To enter confined spaces, the contractor must complete the required approval documents Post Approved Confined Spaces (PACS) entry permit at least 48 hours before entry and must be approved by the POSHO. The COR must assist the contractor in obtaining the necessary documents.
G. Fall Prevention: For fall heights, suitable protective measures must be taken to minimize the risk of accidents.
1. Elimination (Physically remove the hazard)
2. Substitution (Replace the hazard)
3. Engineering Controls (Isolate people from Hazard)
4. Administrative Controls (Change the way people work)
5. PPE (Protect the worker with Personal Protective Equipment)
H. Temporary Ladders, Chutes, Scaffolds, Hoists and Cranes:
1. Furnish and maintain temporary ramps, scaffolds, hoists, or chutes as required for proper execution of Work.
2. Restrict debris removal to Consulate -approved area of building site.
3. Restrict location of equipment to areas as approved by the COR.
4. Such apparatus, equipment, and construction shall meet requirements of applicable federal, state, and local safety and labor laws.
https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fforms.office.com%2Fg%2FshZ4sLh5Kn&data=05%7C02%7CGordonC%40state.gov%7Cb6fba24aa43b4491a9fb08dd6c54b610%7C66cf50745afe48d1a691a12b2121f44b%7C0%7C0%7C638785833271511729%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=hJDLz8Z2ulRo65nRCJAhfwVW5Dk2NOLU9U%2BhWE1PyJ4%3D&reserved=0
09/15/2026 STATEMENT of WORK 4
5. Ladders are required to be non-conductive fiberglass construction with a load capacity (duty rating) of no less than 250 pounds (113kg).
6. Scaffolding:
a. Initial Inspection: After the scaffolding is completed, it must be inspected by a qualified person to verify proper assembly and safe functionality. This inspection ensures compliance with all safety requirements and standards.
b. Marking and Documentation: After the final inspection, the scaffolding must be clearly marked in a visible location (preferably at the access point). The label must include at least the following information:
i. Whether the scaffolding is authorized for use or not
ii. The name and signature of the authorized person who performed the inspection
iii. The address and phone number of the scaffolding contractor
iv. The type of scaffolding, load class, and width class
v. Any usage restrictions
vi. Warning notices
vii. The date of inspection
c. Scaffold users are required to conduct a daily visual inspection and, if necessary, a functional check by a qualified person before use. This inspection is to identify any obvious defects and ensure safe functionality based on the specific intended use. The inspection must be documented.
C.1.10 PROJECT SECURITY:
A. Personnel Clearances:
1. A Visit Authorization Request (VAR) will be required for all contractor personnel prior to entry. Contractors shall forward the following information to the COR:
full name, date and place of birth, Government Identification Card, name of employer, position/discipline.
B. Vehicle Clearances: Submit authorization requests, to include dates, vehicle type, license number, and driver name, for each motorized vehicular implement used on-site.
C. Access to Site: Contractor shall have limited access to or be admitted into the compound outside the areas designated for the project except with permission by the Consulate.
D. Procurement/Storage: Materials shall be procured by NON-SECURE or local means and stored NON-SECURE. All materials may be inspected prior to use on the project.
PART TWO - PRODUCTS
C.2.1 GENERAL
A. The Contractor shall provide all necessary labor, material, equipment, and components necessary to ensure the installation of complete and operable systems. No materials or labor will be supplied or furnished by the Consulate.
B. All materials and equipment incorporated into the project shall be new unless noted otherwise. The Contractor shall transport and safeguard all materials and equipment required for construction.
C.2.2 PRODUCTS
A. Sealant, fasteners, brackets, straps, and patching material as part of the minor repair service. Materials shall match existing gutter system type and finish where practicable.
09/15/2026 STATEMENT of WORK 5
PART THREE – EXECUTION
C.3.1 CONSTRUCTION REQUIREMENTS
A. No construction shall begin until approvals of the Pre-Construction Submittals are accepted by the COR.
B. The Contractor will be provided with a storage and staging area as determined by the COR.
The Contractor shall be responsible for restoring the area to its original condition at the completion of the work. The Contractor shall be responsible for repair of any damage incurred to buildings or pavement as a result of storage activities. The Contractor is responsible for obtaining any additional off compound storage areas as required.
C. The Contractor shall always keep the work area free from accumulation of waste materials.
Upon completion, the Contractor shall remove any temporary facilities and leave the project site in a clean and orderly condition acceptable to the COR.
D. The Contractor shall perform the work at the site during the U. S. Consulate's normal workday hours, (0800-16:30 Monday – Friday excluding holidays) unless alternate work hours are agreed upon with the COR.
E. Protections and Damage Plan: The Contractor shall be responsible to protect all U.S.
Government property to include: all furniture, furnishings, and interior and exterior architectural finishes from damage. Any damage caused by the Contractor to architectural interior and exterior finishes will be returned to original condition by the Contractor at
Contractor expense. In addition to the architectural finishes, the Contractor shall protect all non-included mechanical and electrical equipment and controls from damage throughout the duration of work. Prior to commencing the work, the Contractor along with
Consulate representatives shall survey the site that will be impacted by the project work and document existing conditions. It shall be the Contractor’s responsibility to document in writing all pre-existing damaged surfaces prior to the start of the project work and to provide a copy of the documentation to the COR prior to project start.
C.3.2 SERVICE
A. Cleaning
1. Remove all debris (leaves, dirt, twigs, nests, sediment, and other obstructions) from all gutters, valleys, and downspouts
2. Flush gutters and downspouts with water to confirm free-flowing drainage
3. Clear downspout extensions and underground drain connections
4. Properly bag and remove all debris from the property; no debris shall be left on roofs, in landscaping, or on grounds
B. Inspection
1. Inspect gutters, downspouts, hangers, brackets, seams, and joints for damage, leaks, rust, sagging, or separation from the structure Flush gutters and downspouts with water to confirm free-flowing drainage
C. Minor Repairs
1. Re-secure loose, sagging, or detached gutters, brackets, and hangers
2. Re-align misaligned gutter sections or downspouts to restore proper water flow/pitch
3. Seal minor leaks, gaps, or separated seams and joints using appropriate weatherproof sealant
4. Reattach or replace minor hardware (screws, brackets, straps, hangers) as needed
5. Patch small holes or minor corrosion spots not requiring section replacement
PART FOUR - SCHEDULE
09/15/2026 STATEMENT of WORK 6
C.4.1 PERIOD OF PERFORMANCE: Calendar days
A. The work shall be executed in a diligent manner in accordance with a negotiated firm fixed price and performance period as outlined below.
1. Solicitation & Award of Contract:
a. Award Zero Day
2. Pre-Construction Submittals:
a. Insurance, Schedule, & Product Data: 10 days after
Award
b. Government Review: 5 days
3. Material Procurement:
a. Material Order 5 days
b. Material Shipping 5 days
4. Mobilization & Construction:
a. Crew Information 5 days in advance
b. Scope of Work 30 days on-site
TOTAL PERIOD of PERFORMACE: 60 days
END OF SOW