This is an Amendment of Solicitation/Modification of Contract (Standard Form 30) issued by the American Embassy Tirana GSO/Procurement office on July 8, 2026, for Purchase Requisition PR1653390.
The amendment removes "Installation of new gutters and downspouts" from the Statement of Work and extends the deadline for submission of quotes to July 15, 2026, at 11:00 local Tirana time. The contract involves four renovation work items at the CMR (Chancery/Residence) facility: (1) Renovation of concrete floor at CMR garage; (2) CMR guest bathroom renovation; (3) Painting the exterior walls of CMR (approximately 870 square meters including exterior walls and under-roof overhang); and (4) Replacing stone pavers and installing new ones at walkways throughout CMR. The pricing structure is a firm fixed price with all labor, materials, equipment, insurances, overhead, and profit included. Pricing is quoted in ALL (Albanian Lek) with a 20% VAT applied. The specification for the painting work (Line Item 3) requires minor masonry repairs and painting of all exterior walls, with recommendations for high-quality exterior finish paint or elastomeric paint, with contractor recommendations to be closely reviewed. Contracting Officer Chris Carlisle signed the amendment on July 8, 2026. Contractors must acknowledge receipt of this amendment prior to the submission deadline or risk rejection of their offer.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| RFQ CMR Make Ready_JUNE25.2026.docx | DOCX document |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
PAGE OF
PAGES 1 2
2. AMENDMENT/MODIFICATION
NO.
A00001
3. EFFECTIVE DATE
July 8, 2026
4. REQUISITION/PURCHASE REQ.
NO. PR1653390
5. PROJECT NO. (If applicable)
6. ISSUED BY
CODE
7. ADMINISTERED BY (If other than Item
6) CODE
American Embassy Tirana GSO/Procurement Rr. Stavro Vinjau, Nr. 14 Tirana, Albania
American Embassy Tirana GSO/Procurement Rr. Stavro Vinjau, Nr. 14 Tirana, Albania
8. NAME AND ADDRESS OF CONTRACTOR (NO., street,city,county,State,and ZIP Code)
9a. AMENDMENT OF SOLICITATION NO.
PR1653390
X
9b. DATED (SEE ITEM 11) June 25, 2026
10a. MODIFICATION OF CONTRACT/ORDER
NO.
10b. DATED (SEE ITEM 13)
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
[X ] The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers [X] is extended, [] is not extended Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing Items 8 and 15, and returning _1_ copies of the amendment;(b) By acknowledging receipt of this amendment on each copy of the offer submitted; or(c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers.
FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b)
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor [ ] is not, [ ] is required to sign this document and return ___ copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
The purpose of this modification is to remove Installation of new gutters and downspouts from the SOW
Deadline for submission of quotes is changed to July 15, 2026 @ 11:00 local Tirana time:
See next page: Continuation sheet of SF30
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
16A. NAME OF CONTRACTING OFFICER
Chris Carlisle
15B. NAME OF CONTRACTOR/OFFEROR
BY
(Signature of person authorized to sign)
15C.DATE
SIGNED
16B. UNITED STATES OF AMERICA
BY ____________
16C.DATE
SIGNED
0708/2026
NSN 7540-01-152-8070 Standard Form 30 (revised 10/83) Previous edition unusable Prescribed by GSA FAR (48 CFR)
07/08/2026 11:38 GMT
Carlisle, Chris (CarlisleCJ@state.gov)
Continuation sheet of SF30
Section A. Price – Line item 3 is replaced as follows:
A. PRICE
The Contractor shall complete all work, including furnishing all labor, material, equipment, and services required under this purchase order for the following firm fixed price and within the time specified. This price shall include all labor, materials, all insurances, overhead, and profit.
# Description
Price in
ALL
1 Renovation of concrete floor at CMR garage.
2 CMR guest bathroom renovation.
3 Painting the exterior walls of CMR.
Replacing of the stone pavers and installing new ones at the walkways throughout CMR.
Total Price (including all labor, materials, overhead and profit)
VAT 20%
Grand Total
Attachment 1 – Specification
Point 3.0 is replaced as follows:
3.0 Painting the exterior walls of CMR
3.1 General Requirements
The work involves minor masonry repairs and painting of all exterior walls of the residence.
The total area to be painted is approximately 870 square meters, which includes exterior walls and under roof overhang.
• Exterior walls 750 sq. meters + under roof overhang: 120 sq. meters
Any high-quality exterior finish paint can be used. Please analyze current surface before suggesting new products. However, the contractor can take into consideration the use of Elastomeric paint, which is considered the best paint for outside use. Recommendations are highly valued and will be closely reviewed.
http://www.house-painting-info.com/elastomeric-paint.html
3.1 General Requirements