PR15862528_LoraWAN Antenna Mast (Fuel and Water monitoring Project) Solicitation.pdf

PDF 1 MB Posted

Attached to
Supply and installation of a LoraWAN Antenna Mast for U. S. Embassy Harare, Zimbabwe
Solicitation number
PR15862528
Issued by

About this file

This is a Request for Quotations (RFQ) for the supply and installation of LoraWAN Antenna Masts at six residential locations in Harare, Zimbabwe, issued by the U.S. Embassy Harare's GSO Procurement & Contracting office. Quotations are due by March 12, 2026, at 5:00 PM local time, with award anticipated at the lowest acceptable price to a responsible offeror. The contract is firm fixed-price for commercial services, unrestricted with no set-asides noted. Offerors must submit completed SF-1449 forms, pricing schedules, Section 1 technical requirements, Section 5 representations and certifications, proof of SAM registration, and Defense Base Act insurance information. The estimated contract value is not specified in the document, though pricing includes six service line items (CLINs 001-007) covering geotechnical analysis, foundation work, antenna structure construction, equipment installation, landscaping, and technical documentation, each for six locations at $0.00 placeholder rates requiring offeror input.

The scope of work requires design, construction, and installation of 15-meter self-standing masts at six residences with climbing ladders, lightning arresters, grounding systems, and weatherproof electrical panels (220V, minimum 14" x 12" x 8" with cooling fans and digital temperature controllers). The contractor must install 100 meters of 3 x 2.5mm SWA cable per house from residences to panel boards, perform all excavation and landscaping restoration, equip masts with antennas and conduits supplied by the Embassy, provide structural engineering with sealed drawings, maintain continuous system operation during construction, and deliver as-built documentation and two-year workmanship guarantees. All work must comply with International Building Code 2021 and ANSI/TIA-222-G standards, be completed within 120 calendar days of Notice to Proceed, and include a preventive maintenance agreement for the first year. The contractor bears full responsibility for permits, licensing, site security, health and safety compliance, and personnel safety equipment, with performance monitored against no more than one customer complaint per month.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation for Supply and Installation of a LoraWAN Antenna Mast: RFQ # PR15862528

SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS

OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30

1. REQUISITION NUMBER

PR15862828

2. CONTRACT NO.

3. AWARD/EFFECTIVE

DATE

4. ORDER NUMBER

5. SOLICITATION NUMBER

PR15862828

6. SOLICITATION ISSUE DATE

February 25, 2026

7. FOR SOLICITATION

INFORMATION CALL:

a. NAME

HarareGSOProcurement@state.gov

POC: Damian Richard

b. TELEPHONE NUMBER (No collect calls)

+2638677011000

8. OFFER DUE DATE/ LOCAL

TIME

March 12, 2026 at 5pm

9. ISSUED BY CODE 10. THIS ACQUISITION IS UNRESTRICTED OR SET ASIDE: ____ % FOR:

United States Embassy Harare

SMALL BUSINESS WOMEN-OWNED SMALL BUSINESS

2 Lorraine Drive, Bluffhill

Harare, Zimbabwe

HUBZONE SMALL

BUSINESS

(WOSB) ELLIGIBLE UNDER THE WOMEN-OWNED

SMALL BUSINESS PROGRAM NAICS:

SERVICE-DISABLED

VETERAN-OWNED

SMALL BUSINESS

EDWOSB

8 (A) SIZE STANDARD:

11. DELIVERY FOR FOB DESTINAT-

TION UNLESS BLOCK IS

MARKED

SEE SCHEDULE

12. DISCOUNT TERMS 13a. THIS CONTRACT IS A

RATED ORDER UNDER

DPAS (15 CFR 700)

13b. RATING

14. METHOD OF SOLICITATION

RFQ IFB RFP

15. DELIVER TO CODE 16. ADMINISTERED BY CODE

United States Embassy, Harare

2 Lorraine Drive, Bluffhill

Harare, Zimbabwe

United States Embassy, Harare

2 Lorraine Drive, Bluffhill

Harare, Zimbabwe

17a. CONTRACTOR/

OFFERER

TELEPHONE NO.

CODE FACILITY

CODE

18a. PAYMENT WILL BE MADE BY

United States Embassy, Harare

2 Lorraine Drive, Bluffhill Harare, Zimbabwe Att: Financial Management Officer

CODE

17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN

OFFER

18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK

BELOW IS CHECKED SEE ADDENDUM

19.

ITEM NO.

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

QUANTI

T

Y

22.

UNIT

23.

UNIT PRICE

24.

AMOUNT

Solicitation for the supply and installation of a LoraWAN Antenna Mast (Fuel and Water Monitoring Project) as detailed in Pricing Schedule and SOW on pages 7 to 15 of the solicitation.

(Use Reverse and/or Attach Additional Sheets as Necessary)

25. ACCOUNTING AND APPROPRIATION DATA

26. TOTAL AWARD AMOUNT (For Govt. Use Only)

27a.SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA ARE ARE NOT ATTACHED

27b.CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED

28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN ____ COPIES

TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND DELIVER ALL ITEMS

SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY ADDITIONAL SHEETS

SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED HEREIN.

29. AWARD OF CONTRACT: REF. _________________ OFFER DATED

____________. YOUR OFFER ON SOLICITATION (BLOCK 5), INCLUDING ANY

ADDITIONS OR CHANGES WHICH ARE SET FORTH HEREIN, IS ACCEPTED AS TO

ITEMS:

30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER)

30b. NAME AND TITLE OF SIGNER (Type or print)

30c. DATE SIGNED

31b. NAME OF CONTRACTING OFFICER (Type or print)

Damian Richard 31c. DATE SIGNED mailto:HarareGSOProcurement@state.gov

19.

ITEM NO.

20.

SCHEDULE OF SUPPLIES/SERVICES

21.

QUANTITY

22.

UNIT

23.

UNIT PRICE

24.

AMOUNT

32a. QUANTITY IN COLUMN 21 HAS BEEN

RECEIVED INSPECTED ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: _______________________________

32b. SIGNATURE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT

REPRESENTATIVE

32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f. TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE

32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE

33. SHIP NUMBER 34. VOUCHER NUMBER 35. AMOUNT VERIFIED

CORRECT FOR

36. PAYMENT 37. CHECK NUMBER

PARTIAL FINAL

COMPLETE PARTIAL FINAL

38. S/R ACCOUNT NO.

39. S/R VOUCHER NO. 40. PAID BY

41.a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT 42a. RECEIVED BY (Print)

41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER

41C. DATE

42b. RECEIVED AT (Location)

42c. DATE REC’D (YY/MM/DD) 42d. TOTAL CONTAINERS

TABLE OF CONTENTS

SECTION 1 - THE SCHEDULE

• SF 1449 cover sheet

• Continuation To SF-1449, RFQ Number PR15862528, Prices, Block 23

• Continuation To SF-1449, RFQ Number PR15862528 , Schedule Of Supplies/Services, Block 20 Description/Specifications/Work Statement

• Attachment 1 to Description/Specifications/Performance Work Statement, Government

Furnished Property

SECTION 2 - CONTRACT CLAUSES

• Contract Clauses

• Addendum to Contract Clauses - FAR and DOSAR Clauses not Prescribed in Part 12

SECTION 3 - SOLICITATION PROVISIONS

• Solicitation Provisions

• Addendum to Solicitation Provisions - FAR and DOSAR Provisions not Prescribed in

Part 12

SECTION 4 - EVALUATION FACTORS

• Evaluation Factors

• Addendum to Evaluation Factors - FAR and DOSAR Provisions not Prescribed in Part 12

SECTION 5 - REPRESENTATIONS AND CERTIFICATIONS

• Offeror Representations and Certifications

• Addendum to Offeror Representations and Certifications - FAR and DOSAR Provisions not Prescribed in Part 12

SECTION 1 - THE SCHEDULE

CONTINUATION TO SF-1449

RFQ NUMBER PR15862528

PRICES, BLOCK 23

I. PERFORMANCE WORK STATEMENT

A. The purpose of this firm fixed price purchase order is to for the supply and fitting of a LoraWAN

Antenna Mast in accordance with scope of work on page.

QUALITY ASSURANCE AND SURVEILLANCE PLAN (QASP)

This plan provides an effective method to promote satisfactory contractor performance. The QASP provides a method for the Contracting Officer's Representative (COR) to monitor Contractor performance, advise the Contractor of unsatisfactory performance, and notify the Contracting

Officer of continued unsatisfactory performance. The Contractor, not the Government, is responsible for management and quality control to meet the terms of the contract. The role of the

Government is to monitor quality to ensure that contract standards are achieved.

Performance Objective Scope of Work

Paragraphs Performance Threshold

Services.

Performs all supplying and fitting of LoraWAN Antenna Mast set forth in the scope of work.

Page 8 to page 15

All required services are performed and no more than one

(1) customer complaint is received per month.

1. SURVEILLANCE. The COR will receive and document all complaints from Government personnel regarding the services provided. If appropriate, the COR will send the complaints to the

Contractor for corrective action.

2. STANDARD. The performance standard is that the Government receives no more than one (1) customer complaint per month. The COR shall notify the Contracting Officer of the complaints so that the Contracting Officer may take appropriate action to enforce the inspection clause (FAR

52.212.4, Contract Terms and Conditions - Commercial Products and Commercial Services (NOV

2023), if any of the services exceed the standard.

3. PROCEDURES.

(a) If any Government personnel observe unacceptable services, either incomplete work or required services not being performed they should immediately contact the COR.

(b) The COR will complete appropriate documentation to record the complaint.

(c) If the COR determines the complaint is invalid, the COR will advise the complainant. The COR will retain the annotated copy of the written complaint for his/her files.

https://www.acquisition.gov/far/52.212-4 https://www.acquisition.gov/far/52.212-4

(d) If the COR determines the complaint is valid, the COR will inform the Contractor and give the Contractor additional time to correct the defect, if additional time is available.

The COR shall determine how much time is reasonable.

(e) The COR shall, as a minimum, orally notify the Contractor of any valid complaints.

(f) If the Contractor disagrees with the complaint after investigation of the site and challenges the validity of the complaint, the Contractor will notify the COR. The COR will review the matter to determine the validity of the complaint.

(g) The COR will consider complaints as resolved unless notified otherwise by the complainant.

(h) Repeat customer complaints are not permitted for any services. If a repeat customer complaint is received for the same deficiency during the service period, the COR will contact the Contracting Officer for appropriate action under the Inspection clause.

II. PRICING

CLIN Description No. of Services

Unit Price Per Service

Total Price

Geotechnical analysis and detailed design 6 $0.00

Antenna Foundation and concrete works 6 $0.00

003 Antenna structure construction (15m) 6 $0.00

004 Equipping and power installation works 6 $0.00

005 Landscaping and area rehabilitation 6 $0.00

006 Technical documentation 6 $0.00

007 Insurance 008 Total

III. VALUE ADDED TAX

VALUE ADDED TAX. Value Added Tax (VAT) is not applicable to this contract and shall not be included in the CLIN rates or Invoices because the U.S. Embassy has a tax exemption certificate from the host government.

RFQ NUMBER PR15862528

SCHEDULE OF SUPPLIES/SERVICES, BLOCK 20

DESCRIPTION/SPECIFICATIONS/WORK STATEMENT

INTRODUCTION

1.0 Overview:

The U.S. Embassy Harare has a requirement for a contractor to design, construct and install a 15-meter-tall self-standing Mast at six residences in Harare. The contractor is required to supply all labor and materials to complete the installation work. The Mast will have Electric panel boards, earthing, conduits and they should be serviceable. The US embassy will also require the contractor to install

LoraWAN Antennas and to install power lines from respective houses to the Mast panel boards. The scope of work includes:

• Designing of the mast foundations, foundation reinforcement and designing of the mast itself

• Excavation and installation of new mast base according to the mast design requirements at an approved location at the respective residents.

• Assemble the new tower structure according to applicable industry standards. The tower parts will have been previously sourced, inventoried, and prepared for assembly in its entirety to avoid any delays in erection.

• The new tower structure will have a climbing ladder, pre-painted members, lightning arrester and grounding tape, and warning lights. This list is not exhaustive, but the mast must conform to local applicable standards

• Contractor is responsible for all work as needed for a complete project.

• Maintain and submit as-built plans showing at end of project.

• Disruption of site shall be kept to a minimum and cleanup will happen daily as the residences are occupied.

• A Preventive Maintenance agreement for the first year shall be included and immediately implemented after construction of the replacement tower is completed.

• The contractor shall supply six weatherproof, outdoor electrical panels, with cooling fans, 220v, of minimum dimension 14” x 12” x 8”. The cooling fan must turn on at 300 deg Celsius and each panel should have 220 VAC outlets and a digital temperature controller.

• The contractor shall be required to install 100m of 3 x 2.5mm SWA cable at six different houses. The cable will run from the house to the electric panel and the contractor will be required to supply all termination accessories at both the house and the electric panel. The scope of these works include excavations of cable trenches for laying the cables, backfilling with river sand, laying of marking tape and reinstating the general landscaping to what it was before the project.

• The contractor will be required to equip the mast and install antennas, gateways, electric panels, conduits and all cables. The embassy will provide the antennas, gateways and communication cables while the contractor shall provide all materials to equip the mast.

1.1 Engineering requirements.

1.1.1.1 Structural Design Services.

Contractor shall subcontract a structural engineer to certify the structural design of the new mast and its foundation. The structural engineer shall develop Structural Drawings and

Structural Calculations deliverables to be submitted to the USG for review and approval prior to the procurement of materials. As a requirement for obtaining an OBO building permit, the final Structural Drawings and the coversheet of the Structural Calculations for the tower and foundations shall bear the seal (professional credential) and signature of the structural engineer responsible for their preparation.

1.1.1.2 The Structural Calculations report shall identify all design standards used to design the mast structure and foundation. The report shall include complete calculations of design wind pressures acting on the tower, as well as identify all other design loads, including but not limited to, design loads for access platforms, ladders, guardrails, and fall protection tie-off points. The report shall include representative framing connection designs, as well as connections of the tower framing to the foundation. The Structural Calculations shall address the design of new foundation elements, as well as the stability of any adjacent foundations that may be affected by the new excavation or loads imposed by the new tower structure.

1.1.1.3 The structural Drawings shall include general notes listing design standards and critical design parameters, as well as plans, elevations, and sections to convey the design intent. These drawings shall provide structural framing connection details, as well as details for guardrails, ladders, and platform decks. These details should identify welded and bolted joint configurations, dimensions, and material specifications. The Structural

Drawings shall identify the intended bolted joint standards and clarify intention for maintaining tightness of bolted connections for the structure that will be subject to cyclic wind loading. The Structural Drawings shall clearly indicate the intended material specifications for structural components, as well as specifications for metal (hot-dipped galvanized) and paint coating systems rated for extreme levels of exposure to an oceanfront atmosphere, hot climate, and ultraviolet radiation (ISO 9223 Corrosivity Category CX).

1.1.1.4 The Contractor’s Structural Engineer shall review all associated shop drawings, product data, and any other construction submittal associated with the structural design of the tower and its foundation. All submittals shall bear their review stamp and recommendation for approval prior to the submittals’ transmission to the COR for USG approval.

1.1.2 Loading

The Antennas and the fixing members will not exceed 30kg

1.2 The Antenna will be constructed at six residences in Harare. The exact location of the residences will be shared with the selected vendor

1.3 All inspections will be requested through the COR.

2.0 GENERAL REQUIREMENTS

2.1 The Contractor shall provide a quantity of construction personnel, transportation, equipment, materials, tools, and supervisors as needed to complete the services and technical requirements in the Statement of Work (SOW). It is expected that the Contractor shall partner closely with Embassy personnel.

2.2 The work shall be executed in a diligent manner in accordance with a negotiated firm fixed price and performance period. The period of performance for all Phases of the project shall be completed in 120 Calendar days from Notice to Proceed (NTP).

Allowance for sourcing and shipping materials is included in the completion timeframe.

All work shall be executed in a diligent manner in accordance with a negotiated firm fixed price and performance period. This price will include every aspect of the work described in the Statement of Work (SOW) including all required structural and geotechnical engineering.

2.3 The Contractor shall have limited access to or be admitted into any structure outside the areas designated for the project except with permission by the Embassy. The Contractor shall address the impact of the consequent disruption.

2.4 The Contractor shall be required to prepare and submit reports, bill of materials, product literature, drawings, specifications, quality control schedules, safety plan and construction costs. These documents shall provide the necessary interfaces, coordination, and communication between the Embassy and Contractor for the delivery of a completed project.

2.5 Subcontractors. Contractor shall be responsible for the conduct and workmanship of subcontractors engaged in the project, and for subcontractor’s compliance with the terms of this Statement of Work. The Contractor is responsible for the behavior and workmanship of subcontractors while on Embassy property.

2.6 The Contractor work shall in accordance with U.S. codes and standards. The COR will review and comment on the Contractor’s submissions using the following codes and standards:

• International Building Code, 2021 Edition as amended by the 2023 OBO International

Code Supplement – this includes the ANSI/TIA-222-G for the design of antenna towers.

The contractor is responsible for being familiar with these codes. Should there be a discrepancy between the US Embassy specifications and the applicable Building Code, the more stringent of the two shall govern. Work not in compliance with the Codes shall be deemed to be unacceptable.

2.7 Work Hours: Normal Embassy work week is from Monday through Friday from 08:00 to

17:00. Unless otherwise agreed with COR, the work shall be executed during normal

Embassy work hours. At night, weekend, or holiday work shall not be permitted except as arranged in advance with the COR. Embassy holiday schedule is available from the COR.

3.0 RESPONSIBILITIES OF THE CONTRACTOR

3.1 Communication: The Contractor shall designate and make available a representative to meet with the Contracting Officer’s Representative (COR) weekly to discuss the Progress of the Project or other matters pertaining to the Project. The contractor shall follow up all telephone conversations affecting the scope of work with an email summary of the conversation sent to the COR.

3.2 The Contractor shall prepare and maintain a Project Schedule to address the cost and schedule for the project. The Project Schedule is intended to document the entire project from beginning to end. Within 5 days of Notice to Proceed, the contractor shall provide to the COR a project schedule showing start to completion including significant milestones.

3.3 Install all equipment according to manufacturer’s recommendations. Printed or electronic copies of product and installation information shall be required prior to purchase or installation.

3.4 The contractor is responsible for disposing of the construction debris outside of the

Embassy Residences. Include, but not limited to soils, rock excavation, packing materials and scrap steel.

3.5 Any cost associated with services subcontracted by the Contractor shall be borne by and be the complete responsibility of the Contractor under the fixed price of this contract.

3.6 The Contractor is responsible to properly layout and prepare for the work based on locations provided by COR. When pursuing the work, the contractor is to take extra care so as not to damage existing structure.

3.7 The Contractor shall be and remain liable to the USG in accordance with applicable laws for all damages to the Embassy property caused by the Contractor's negligent performance of any of the services furnished under this contract. The rights and remedies for the USG provided for under this contract are in addition to any other rights and remedies provided by the law.

3.8 The Contractor’s senior representative shall be responsible for briefing COR on the status of the Work.

3.9 The Contractor shall ensure that the overall program is executed smoothly, delivered on schedule, and within the project budget. The Contractor shall coordinate the efforts of all sub-contractors to ensure successful completion of this program within schedule and cost.

3.10 Structural Modifications: The contractor and his structural engineer are required to investigate each new opening, stairway support point, and equipment location for adequate structural support and ensure that their proposed work does not compromise the structural integrity of adjacent structures. The engineer should sketch or report the methods towards resolution before the work is done.

3.11 Submittals: The contractor is responsible to submit shop drawings prior to fabrication and release of any materials for the COR Review and approval. The COR review, however, does not relieve of the contractor’s responsibility for the engineering work as to provide a complete working system.

3.12 Drawings: All unclassified drawings and unclassified documents must be returned to the

COR at completion of the task order. In addition, all documentation produced for this project shall become the property of the USG at the completion of the project.

3.13 Injury Reporting: The Contractor is responsible for safety and shall comply with all local labor laws, regulations, customs and practices pertaining to labor, safety and similar matters. The Contractor shall promptly report all accidents resulting in lost time, disabling, or fatal injuries to the COR

3.14 Site Security. The Contractor is responsible for on-site security as necessary to ensure no unauthorized access to their work sites. The Contractor is 100% responsible for securing their working materials and equipment. Any damage to facilities or infrastructure, which happens due to a lack of security, will be the responsibility of the Contractor to correct.

3.15 Health and Safety. The Contractor shall be solely responsible for risk assessments, managing health, and safety issues associated with this project. The Contractor must provide cold water to all workers at the job sites. Based on hazard assessments, Contractors shall provide or afford each affected employee personal protective equipment (PPE) that will protect the employee from hazards. At a minimum PPE shall consist of eye protection, hard hats, and closed toe shoes. If the workers arrive on-site with sandals or athletic shoes, the Contractor is expected to provide rubber boots to them or send them home. All construction workers and management personnel must wear hard hats at all times on the construction sites. Contractor provided rubber boots and rubber gloves shall be worn when working around concrete placement. Other PPE such as gloves, dust masks, air respirators (sewage work) are also recommended. These items must be provided at the

Contractor’s expense. Workers may use discretion if they feel unsafe in using the equipment in a hostile environment. Any worker at an elevated location above 4 meters, with the exception of a portable ladder, must be provided and utilize a safety harness.

4.0 CONSTRUCTION SERVICES

4.1 The Contractor shall survey the area where construction will take place and become thoroughly familiarized with the existing conditions and conditions that will affect the construction. The

Contractor shall be responsible for all permit requirements, licensing requirements, and the quality and availability of materials, sub-contractors, and equipment that may be needed to execute the contract.

4.2 The Contractor is responsible to locate all existing utility lines prior to any excavation. Prior to disconnecting any existing utility services, the Contractor is responsible to provide 48-hour advance notice to the COR.

4.3 The Contractor shall inspect and evaluate all available drawings and specifications pertaining to the project. The Contractor shall field verify all dimensions for construction relevant to the project.

4.4 All materials and equipment incorporated into the project shall be brand new. The

Contractor shall transport and safeguard all materials and equipment required for construction as instructed by the manufacturer’s instructions. Materials and equipment needed for a complete installation shall be the responsibility of the Contractor.

4.5 The Contractor shall always keep the work area free from accumulation of

SBU - CONTRACTING AND ACQUISITIONS

waste materials daily. Upon completing construction, the Contractor shall remove all temporary facilities and leave the project site in a clean and orderly condition acceptable to

Post. Any repair of damage caused as a result of this project will be the responsibility of the

Contractor.

4.6 The Contractor shall maintain continuous usage of existing systems during construction.

4.7 Deliverables to Accompany Close-Out of Construction: The Contractor shall provide one copy of the following to the COR:

4.7.1 As-Built Drawings: The contractor shall provide one set of marked up

(As-Built) drawings reflecting the work as constructed. The drawings shall be digitally submitted in PDF format and in Autocad.

4.7.2 Contractor & Manufacturer’s Contact List: The Contractor shall provide a list containing contractor’s & manufacturers’ contact information for future repair and maintenance.

4.7.3 Maintenance Instructions: Provide two copies to Embassy only.

4.7.4 Manufacturers’ Equipment Warranties and Identification of Warranty

Items: Two-year workmanship guarantee in writing covering all equipment, materials, and labor in the event any workmanship or equipment items are found defective.

END OF STATEMENT OF WORK

SECTION 2 - CONTRACT CLAUSES

52.212-4 CONTRACT TERMS AND CONDITIONS – COMMERCIAL ITEMS

(NOV 2023) IS INCORPORATED BY REFERENCE. (SEE SF-1449,

BLOCK 27A)

FAR 52.212-5 Contract Terms and Conditions Required to Implement Statutes or Executive Orders—Commercial Products and Commercial Services (JAN 2025)

(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses, which are incorporated in this contract by reference, to implement provisions of law or

Executive orders applicable to acquisitions of commercial products and commercial services:

(1) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or

Statements (Jan 2017) (section 743 of Division E, Title VII, of the Consolidated and Further

Continuing Appropriations Act, 2015 (Pub. L. 113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).

(2) 52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or

Provided by Kaspersky Lab Covered Entities (Dec 2023) (Section 1634 of Pub. L. 115-91).

(3) 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video

Surveillance Services or Equipment. (Nov 2021) (Section 889(a)(1)(A) of Pub. L. 115-232).

(4) 52.209-10, Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015).

(5) 52.232-40, Providing Accelerated Payments to Small Business Subcontractors (Mar 2023) ( 31

U.S.C. 3903 and 10 U.S.C. 3801).

(6) 52.233-3, Protest After Award (Aug 1996) (31 U.S.C. 3553).

(7) 52.233-4, Applicable Law for Breach of Contract Claim (Oct 2004) (Public Laws 108-77 and

108-78 ( 19 U.S.C. 3805 note)).

(b) The Contractor shall comply with the FAR clauses in this paragraph (b) that the Contracting

Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services:

__ (1) 52.203-6, Restrictions on Subcontractor Sales to the Government (Jun

2020), with Alternate I (Nov 2021) (41 U.S.C. 4704 and 10 U.S.C. 4655).

__ (2) 52.203-13, Contractor Code of Business Ethics and Conduct (Nov 2021) (41 U.S.C. 3509)).

__ (3) 52.203-15, Whistleblower Protections under the American Recovery and Reinvestment Act of 2009 (Jun 2010) (Section 1553 of Pub. L. 111-5). (Applies to contracts funded by the American

Recovery and Reinvestment Act of 2009.)

_X_ (4) 52.203-17, Contractor Employee Whistleblower Rights (Nov 2023) ( 41 U.S.C. 4712);

this clause does not apply to contracts of DoD, NASA, the Coast Guard, or applicable elements of the intelligence community—see FAR 3.900(a).

_X_ (5) 52.204-10, Reporting Executive Compensation and First-Tier Subcontract Awards (Jun

2020) (Pub. L. 109-282) ( 31 U.S.C. 6101 note).

__ (6) [Reserved].

__ (7) 52.204-14, Service Contract Reporting Requirements (Oct 2016) (Pub. L. 111-117, section

743 of Div. C).

https://www.acquisition.gov/far/52.203-19#FAR_52_203_19 https://www.acquisition.gov/far/52.204-23#FAR_52_204_23 https://www.acquisition.gov/far/52.204-25#FAR_52_204_25 https://www.acquisition.gov/far/52.209-10#FAR_52_209_10 https://www.acquisition.gov/far/52.232-40#FAR_52_232_40 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title31-section3903&num=0&edition=prelim https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title31-section3903&num=0&edition=prelim https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title10-section3801&num=0&edition=prelim https://www.acquisition.gov/far/52.233-3#FAR_52_233_3 https://www.acquisition.gov/far/52.233-4#FAR_52_233_4 https://www.acquisition.gov/far/52.203-6#FAR_52_203_6 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title10-section4655&num=0&edition=prelim https://www.acquisition.gov/far/52.203-13#FAR_52_203_13 https://www.acquisition.gov/far/52.203-15#FAR_52_203_15 https://www.acquisition.gov/far/52.203-17#FAR_52_203_17 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title41-section4712&num=0&edition=prelim https://www.acquisition.gov/far/3.900#FAR_3_900 https://www.acquisition.gov/far/52.204-10#FAR_52_204_10 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title31-section6101&num=0&edition=prelim https://www.acquisition.gov/far/52.204-14#FAR_52_204_14

__ (8) 52.204-15, Service Contract Reporting Requirements for Indefinite-Delivery

Contracts (Oct 2016) (Pub. L. 111-117, section 743 of Div. C).

_X_ (9) 52.204-27, Prohibition on a ByteDance Covered Application (Jun 2023) (Section 102 of

Division R of Pub. L. 117-328).

__ (10) 52.204-28, Federal Acquisition Supply Chain Security Act Orders—Federal Supply

Schedules, Governmentwide Acquisition Contracts, and Multi-Agency Contracts. (Dec

2023) ( Pub. L. 115–390, title II).

__ (11)

(i) 52.204-30, Federal Acquisition Supply Chain Security Act Orders—Prohibition. (Dec

2023) ( Pub. L. 115–390, title II).

__ (ii) Alternate I (Dec 2023) of 52.204-30.

_X_ (12) 52.209-6, Protecting the Government's Interest When Subcontracting With Contractors

Debarred, Suspended, Proposed for Debarment, or Voluntarily Excluded. (Jan 2025)

( 31 U.S.C. 6101 note).

__ (13) 52.209-9, Updates of Publicly Available Information Regarding Responsibility

Matters (Oct 2018) ( 41 U.S.C. 2313).

__ (14) [Reserved].

__ (15) 52.219-3, Notice of HUBZone Set-Aside or Sole-Source Award (Oct 2022)

( 15 U.S.C. 657a).

__ (16) 52.219-4, Notice of Price Evaluation Preference for HUBZone Small Business Concerns

(Oct 2022) (if the offeror elects to waive the preference, it shall so indicate in its offer)

(15 U.S.C. 657a).

__ (17) [Reserved]

__ (18)

(i) 52.219-6, Notice of Total Small Business Set-Aside (Nov 2020) (15 U.S.C. 644).

__ (ii) Alternate I (Mar 2020) of 52.219-6.

__ (19)

(i) 52.219-7, Notice of Partial Small Business Set-Aside (Nov 2020) (15 U.S.C. 644).

__ (ii) Alternate I (Mar 2020) of 52.219-7.

__ (20) 52.219-8, Utilization of Small Business Concerns (Jan 2025)( 15 U.S.C. 637(d)(2) and

(3)).

__ (21)

(i) 52.219-9, Small Business Subcontracting Plan (Jan 2025) ( 15 U.S.C. 637(d)(4)).

__ (ii) Alternate I (Nov 2016) of 52.219-9.

__ (iii) Alternate II (Nov 2016) of 52.219-9.

__ (iv) Alternate III (Jun 2020) of 52.219-9.

__ (v) Alternate IV (Jan 2025) of 52.219-9.

__ (22)

(i) 52.219-13, Notice of Set-Aside of Orders (Mar 2020) (15 U.S.C. 644(r)).

__ (ii) Alternate I (Mar 2020) of 52.219-13.

__ (23) 52.219-14, Limitations on Subcontracting (Oct 2022) (15 U.S.C. 657s).

__ (24) 52.219-16, Liquidated Damages—Subcontracting Plan (Sep

2021) (15 U.S.C. 637(d)(4)(F)(i)).

__ (25) 52.219-27, Notice of Set-Aside for, or Sole-Source Award to, Service-Disabled Veteran-

Owned Small Business (SDVOSB) Concerns Eligible Under the SDVOSB Program (Feb 2024)

(15 U.S.C. 657f).

https://www.acquisition.gov/far/52.204-15#FAR_52_204_15 https://www.acquisition.gov/far/52.204-27#FAR_52_204_27 https://www.acquisition.gov/far/52.204-28#FAR_52_204_28 https://www.govinfo.gov/link/plaw/115/public/390 https://www.acquisition.gov/far/52.204-30#FAR_52_204_30 https://www.govinfo.gov/link/plaw/115/public/390 https://www.acquisition.gov/far/52.204-30#FAR_52_204_30 https://www.acquisition.gov/far/52.209-6#FAR_52_209_6 https://www.govinfo.gov/link/uscode/31/6101 https://www.acquisition.gov/far/52.209-9#FAR_52_209_9 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title41-section2313&num=0&edition=prelim https://www.acquisition.gov/far/52.219-3#FAR_52_219_3 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title15-section637a&num=0&edition=prelim https://www.acquisition.gov/far/52.219-4#FAR_52_219_4 https://www.acquisition.gov/far/52.219-6#FAR_52_219_6 https://www.acquisition.gov/far/52.219-6#FAR_52_219_6 https://www.acquisition.gov/far/52.219-7#FAR_52_219_7 https://www.acquisition.gov/far/52.219-7#FAR_52_219_7 https://www.acquisition.gov/far/52.219-8#FAR_52_219_8 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title15-section637&num=0&edition=prelim https://www.acquisition.gov/far/52.219-9#FAR_52_219_9 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title15-section637&num=0&edition=prelim https://www.acquisition.gov/far/52.219-9#FAR_52_219_9 https://www.acquisition.gov/far/52.219-9#FAR_52_219_9 https://www.acquisition.gov/far/52.219-9#FAR_52_219_9 https://www.acquisition.gov/far/52.219-9#FAR_52_219_9 https://www.acquisition.gov/far/52.219-13#FAR_52_219_13 https://www.acquisition.gov/far/52.219-13#FAR_52_219_13 https://www.acquisition.gov/far/52.219-14#FAR_52_219_14 https://www.acquisition.gov/far/52.219-16#FAR_52_219_16 https://www.acquisition.gov/far/52.219-27#FAR_52_219_27

__ (26)

(i) 52.219-28, Postaward Small Business Program Representation (Jan

2025) (15 U.S.C. 632(a)(2)).

__ (ii) Alternate I (Mar 2020) of 52.219-28.

__ (27) 52.219-29, Notice of Set-Aside for, or Sole-Source Award to, Economically

Disadvantaged Women-Owned Small Business Concerns (Oct 2022) (15 U.S.C. 637(m)).

__ (28) 52.219-30, Notice of Set-Aside for, or Sole-Source Award to, Women-Owned Small

Business Concerns Eligible Under the Women-Owned Small Business Program (Oct 2022)

(15 U.S.C. 637(m)).

__ (29) 52.219-32, Orders Issued Directly Under Small Business Reserves (Mar

2020) ( 15 U.S.C. 644(r)).

__ (30) 52.219-33, Nonmanufacturer Rule (Sep 2021) ( 15 U.S.C. 637(a)(17)).

__ (31) 52.222-3, Convict Labor (Jun 2003) (E.O.11755).

_X_ (32) 52.222-19, Child Labor—Cooperation with Authorities and Remedies (Jan 2025)( E.O.

13126).

__ (33) 52.222-21, Prohibition of Segregated Facilities (Apr 2015).

__ (34)

(i) 52.222-26, Equal Opportunity (Sep 2016) (E.O.11246).

__ (ii) Alternate I (Feb 1999) of 52.222-26.

__ (35)

(i) 52.222-35, Equal Opportunity for Veterans (Jun 2020) ( 38 U.S.C. 4212).

__ (ii) Alternate I (Jul 2014) of 52.222-35.

__ (36)

(i) 52.222-36, Equal Opportunity for Workers with Disabilities (Jun 2020) ( 29 U.S.C. 793).

__ (ii) Alternate I (Jul 2014) of 52.222-36.

__ (37) 52.222-37, Employment Reports on Veterans (Jun 2020) ( 38 U.S.C. 4212).

__ (38) 52.222-40, Notification of Employee Rights Under the National Labor Relations Act (Dec

2010) (E.O. 13496).

_X_ (39)

(i) 52.222-50, Combating Trafficking in Persons (Nov 2021) (22 U.S.C. chapter 78 and E.O.

13627).

__ (ii) Alternate I (Mar 2015) of 52.222-50 (22 U.S.C. chapter 78 and E.O. 13627).

__ (40) 52.222-54, Employment Eligibility Verification (Jan 2025) ( Executive Order 12989).

(Not applicable to the acquisition of commercially available off-the-shelf items or certain other types of commercial products or commercial services as prescribed in FAR 22.1803.)

__ (41)

(i) 52.223-9, Estimate of Percentage of Recovered Material Content for EPA–Designated Items

(May 2008) ( 42 U.S.C. 6962(c)(3)(A)(ii)). (Not applicable to the acquisition of commercially available off-the-shelf items.)

__ (ii) Alternate I (May 2008) of 52.223-9 (42 U.S.C. 6962(i)(2)(C)). (Not applicable to the acquisition of commercially available off-the-shelf items.)

__ (42) 52.223-11, Ozone-Depleting Substances and High Global Warming Potential

Hydrofluorocarbons (May 2024) ( 42 U.S.C. 7671, et seq.).

__ (43) 52.223-12, Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air

Conditioners (May 2024) ( 42 U.S.C. 7671, et seq.).

__ (44) 52.223-20, Aerosols (May 2024) ( 42 U.S.C. 7671, et seq.).

https://www.acquisition.gov/far/52.219-28#FAR_52_219_28 https://www.acquisition.gov/far/52.219-28#FAR_52_219_28 https://www.acquisition.gov/far/52.219-29#FAR_52_219_29 https://www.acquisition.gov/far/52.219-30#FAR_52_219_30 https://www.acquisition.gov/far/52.219-32#FAR_52_219_32 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title15-section644&num=0&edition=prelim https://www.acquisition.gov/far/52.219-33#FAR_52_219_33 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title15-section637&num=0&edition=prelim https://www.acquisition.gov/far/52.222-3#FAR_52_222_3 https://www.acquisition.gov/far/52.222-19#FAR_52_222_19 https://www.federalregister.gov/executive-order/13126 https://www.federalregister.gov/executive-order/13126 https://www.acquisition.gov/far/52.222-21#FAR_52_222_21 https://www.acquisition.gov/far/52.222-26#FAR_52_222_26 https://www.acquisition.gov/far/52.222-26#FAR_52_222_26 https://www.acquisition.gov/far/52.222-35#FAR_52_222_35 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title38-section4212&num=0&edition=prelim https://www.acquisition.gov/far/52.222-35#FAR_52_222_35 https://www.acquisition.gov/far/52.222-36#FAR_52_222_36 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title29-section793&num=0&edition=prelim https://www.acquisition.gov/far/52.222-36#FAR_52_222_36 https://www.acquisition.gov/far/52.222-37#FAR_52_222_37 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title38-section4212&num=0&edition=prelim https://www.acquisition.gov/far/52.222-40#FAR_52_222_40 https://www.acquisition.gov/far/52.222-50#FAR_52_222_50 https://www.acquisition.gov/far/52.222-50#FAR_52_222_50 https://www.acquisition.gov/far/52.222-54#FAR_52_222_54 https://www.federalregister.gov/executive-order/12989 https://www.acquisition.gov/far/22.1803#FAR_22_1803 https://www.acquisition.gov/far/52.223-9#FAR_52_223_9 https://www.acquisition.gov/far/52.223-9#FAR_52_223_9 https://www.acquisition.gov/far/52.223-11#FAR_52_223_11 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7671&num=0&edition=prelim https://www.acquisition.gov/far/52.223-12#FAR_52_223_12 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7671&num=0&edition=prelim https://www.acquisition.gov/far/52.223-20#FAR_52_223_20 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7671&num=0&edition=prelim

__ (45) 52.223-21, Foams (May 2024) ( 42 U.S.C. 7671, et seq.).

__ (46) 52.223-23, Sustainable Products and Services (May 2024) ( E.O. 14057, 7 U.S.C.

8102, 42 U.S.C. 6962, 42 U.S.C. 8259b, and 42 U.S.C. 7671l).

__ (47)

(i) 52.224-3 Privacy Training (Jan 2017) ( 5 U.S.C. 552 a).

__ (ii) Alternate I (Jan 2017) of 52.224-3.

__ (48)

(i) 52.225-1, Buy American-Supplies (Oct 2022) (41 U.S.C. chapter 83).

__ (ii) Alternate I (Oct 2022) of 52.225-1.

__ (49)

(i) 52.225-3, Buy American-Free Trade Agreements-Israeli Trade Act (NOV 2023) ( 19 U.S.C.

3301 note, 19 U.S.C. 2112 note, 19 U.S.C. 3805 note, 19 U.S.C. 4001 note, 19 U.S.C. chapter

29 (sections 4501-4732), Public Law 103-182, 108-77, 108-78, 108-286, 108-302, 109-53, 109-

169, 109-283, 110-138, 112-41, 112-42, and 112-43.

__ (ii) Alternate I [Reserved].

__ (iii) Alternate II (Jan 2025) of 52.225-3.

__ (iv) Alternate III (Feb 2024) of 52.225-3.

__ (v) Alternate IV (Oct 2022) of 52.225-3.

__ (50) 52.225-5, Trade Agreements (NOV 2023) ( 19 U.S.C. 2501, et seq., 19 U.S.C. 3301 note).

_X_ (51) 52.225-13, Restrictions on Certain Foreign Purchases (Feb 2021) (E.O.’s, proclamations, and statutes administered by the Office of Foreign Assets Control of the

Department of the Treasury).

__ (52) 52.225-26, Contractors Performing Private Security Functions Outside the United

States (Oct 2016) (Section 862, as amended, of the National Defense Authorization Act for Fiscal

Year 2008; 10 U.S.C. Subtitle A, Part V, Subpart G Note).

__ (53) 52.226-4, Notice of Disaster or Emergency Area Set-Aside (Nov 2007) (42 U.S.C. 5150).

__ (54) 52.226-5, Restrictions on Subcontracting Outside Disaster or Emergency Area (Nov

2007) (42 U.S.C. 5150).

__ (55) 52.226-8, Encouraging Contractor Policies to Ban Text Messaging While

Driving (May 2024) ( E.O. 13513).

__ (56) 52.229-12, Tax on Certain Foreign Procurements (Feb 2021).

__ (57) 52.232-29, Terms for Financing of Purchases of Commercial Products and Commercial

Services (Nov 2021) (41 U.S.C. 4505, 10 U.S.C. 3805).

__ (58) 52.232-30, Installment Payments for Commercial Products and Commercial

Services (Nov 2021) (41 U.S.C. 4505, 10 U.S.C. 3805).

_X_ (59) 52.232-33, Payment by Electronic Funds Transfer-System for Award

Management (Oct2018) ( 31 U.S.C. 3332).

__ (60) 52.232-34, Payment by Electronic Funds Transfer-Other than System for Award

Management (Jul 2013) (31 U.S.C. 3332).

__ (61) 52.232-36, Payment by Third Party (May 2014) (31 U.S.C. 3332).

_X_ (62) 52.239-1, Privacy or Security Safeguards (Aug 1996) ( 5 U.S.C. 552a).

__ (63) 52.240-1, Prohibition on Unmanned Aircraft Systems Manufactured or Assembled by

American Security Drone Act-Covered Foreign Entities (Nov 2024) (Sections 1821-1826, Pub. L.

118-31, 41 U.S.C. 3901 note prec.).

__ (64) 52.242-5, Payments to Small Business Subcontractors (Jan 2017) (15 U.S.C. 637(d)(13)).

https://www.acquisition.gov/far/52.223-21#FAR_52_223_21 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7671&num=0&edition=prelim https://www.acquisition.gov/far/52.223-23#FAR_52_223_23 https://www.federalregister.gov/executive-order/14057 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title7-section8102&num=0&edition=prelim https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title7-section8102&num=0&edition=prelim https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section6962&num=0&edition=prelim https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section8259&num=0&edition=prelim https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title42-section7671&num=0&edition=prelim https://www.acquisition.gov/far/52.224-3#FAR_52_224_3 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title5-section552&num=0&edition=prelim https://www.acquisition.gov/far/52.224-3#FAR_52_224_3 https://www.acquisition.gov/far/52.225-1#FAR_52_225_1 https://www.acquisition.gov/far/52.225-1#FAR_52_225_1 https://www.acquisition.gov/far/52.225-3#FAR_52_225_3 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title19-section3301&num=0&edition=prelim https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title19-section3301&num=0&edition=prelim https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title19-section2112&num=0&edition=prelim https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title19-section3805&num=0&edition=prelim https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title19-section4001&num=0&edition=prelim http://uscode.house.gov/view.xhtml?req=granuleid%3AUSC-prelim-title19-chapter29&saved=%7CZ3JhbnVsZWlkOlVTQy1wcmVsaW0tdGl0bGU0MC1jaGFwdGVyMzctZnJvbnQ%3D%7C%7C%7C0%7Cfalse%7Cprelim&edition=prelim http://uscode.house.gov/view.xhtml?req=granuleid%3AUSC-prelim-title19-chapter29&saved=%7CZ3JhbnVsZWlkOlVTQy1wcmVsaW0tdGl0bGU0MC1jaGFwdGVyMzctZnJvbnQ%3D%7C%7C%7C0%7Cfalse%7Cprelim&edition=prelim https://www.acquisition.gov/far/52.225-3#FAR_52_225_3 https://www.acquisition.gov/far/52.225-3#FAR_52_225_3 https://www.acquisition.gov/far/52.225-3#FAR_52_225_3 https://www.acquisition.gov/far/52.225-5#FAR_52_225_5 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title19-section2501&num=0&edition=prelim http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title19-section3301&num=0&edition=prelim https://www.acquisition.gov/far/52.225-13#FAR_52_225_13 https://www.acquisition.gov/far/52.225-26#FAR_52_225_26 https://www.acquisition.gov/far/52.226-4#FAR_52_226_4 https://www.acquisition.gov/far/52.226-5#FAR_52_226_5 https://www.acquisition.gov/far/52.226-8#FAR_52_226_8 https://www.federalregister.gov/executive-order/13513 https://www.acquisition.gov/far/52.229-12#FAR_52_229_12 https://www.acquisition.gov/far/52.232-29#FAR_52_232_29 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title10-section3805&num=0&edition=prelim https://www.acquisition.gov/far/52.232-30#FAR_52_232_30 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title10-section3805&num=0&edition=prelim https://www.acquisition.gov/far/52.232-33#FAR_52_232_33 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title31-section3332&num=0&edition=prelim https://www.acquisition.gov/far/52.232-34#FAR_52_232_34 https://www.acquisition.gov/far/52.232-36#FAR_52_232_36 https://www.acquisition.gov/far/52.239-1#FAR_52_239_1 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title5-section552a&num=0&edition=prelim https://www.acquisition.gov/far/52.240-1#FAR_52_240_1 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title41-section3901&num=0&edition=prelim https://www.acquisition.gov/far/52.242-5#FAR_52_242_5

__ (65)

(i) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (Nov 2021) ( 46

U.S.C. 55305 and 10 U.S.C. 2631).

__ (ii) Alternate I (Apr 2003) of 52.247-64.

__ (iii) Alternate II (Nov 2021) of 52.247-64.

(c) The Contractor shall comply with the FAR clauses in this paragraph (c), applicable to commercial services, that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services:

[Contracting Officer check as appropriate.]

__ (1) 52.222-41, Service Contract Labor Standards (Aug 2018) (41 U.S.C. chapter67).

__ (2) 52.222-42, Statement of Equivalent Rates for Federal Hires (May 2014) (29 U.S.C. 206 and

41 U.S.C. chapter 67).

__ (3) 52.222-43, Fair Labor Standards Act and Service Contract Labor Standards-Price

Adjustment (Multiple Year and Option Contracts) (Aug 2018) (29 U.S.C. 206 and

41 U.S.C. chapter 67).

__ (4) 52.222-44, Fair Labor Standards Act and Service Contract Labor Standards-Price

Adjustment (May 2014) ( 29U.S.C.206 and 41 U.S.C. chapter 67).

__ (5) 52.222-51, Exemption from Application of the Service Contract Labor Standards to

Contracts for Maintenance, Calibration, or Repair of Certain Equipment-Requirements

(May 2014) (41 U.S.C. chapter 67).

__ (6) 52.222-53, Exemption from Application of the Service Contract Labor Standards to

Contracts for Certain Services-Requirements (May 2014) (41 U.S.C. chapter 67).

__ (7) 52.222-55, Minimum Wages for Contractor Workers Under Executive Order 14026 (Jan

2022).

__ (8) 52.222-62, Paid Sick Leave Under Executive Order 13706 (Jan 2022) (E.O. 13706).

__ (9) 52.226-6, Promoting Excess Food Donation to Nonprofit Organizations (Jun 2020)

(42 U.S.C. 1792).

__ (10) 52.247-69, Reporting Requirement for U.S.-Flag Air Carriers Regarding Training to

Prevent Human Trafficking (Jan 2025) ( 49 U.S.C. 40118(g)).

(d) Comptroller General Examination of Record. The Contractor shall comply with the provisions of this paragraph (d) if this contract was awarded using other than sealed bid, is in excess of the simplified acquisition threshold, as defined in FAR 2.101, on the date of award of this contract, and does not contain the clause at 52.215-2, Audit and Records-Negotiation.

(1) The Comptroller General of the United States, or an authorized representative of the

Comptroller General, shall have access to and right to examine any of the Contractor’s directly pertinent records involving transactions related to this contract.

(2) The Contractor shall make available at its offices at all reasonable times the records, materials, and other evidence for examination, audit, or reproduction, until 3 years after final payment under this contract or for any shorter period specified in FAR subpart 4.7, Contractor Records Retention, of the other clauses of this contract. If this contract is completely or partially terminated, the records relating to the work terminated shall be made available for 3 years after any resulting final termination settlement. Records relating to appeals under the disputes clause or to litigation or the settlement of claims arising under or relating to this contract shall be made available until such appeals, litigation, or claims are finally resolved.

https://www.acquisition.gov/far/52.247-64#FAR_52_247_64 https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title46-section55305&num=0&edition=prelim https://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title46-section55305&num=0&edition=prelim https://www.acquisition.gov/far/52.247-64#FAR_52_247_64 https://www.acquisition.gov/far/52.247-64#FAR_52_247_64 https://www.acquisition.gov/far/52.222-41#FAR_52_222_41 https://www.acquisition.gov/far/52.222-42#FAR_52_222_42 https://www.acquisition.gov/far/52.222-43#FAR_52_222_43 https://www.acquisition.gov/far/52.222-44#FAR_52_222_44 http://uscode.house.gov/view.xhtml?req=granuleid:USC-prelim-title29-section206&num=0&edition=prelim https://www.acquisition.gov/far/52.222-51#FAR_52_222_51 https://www.acquisition.gov/far/52.222-53#FAR_52_222_53 https://www.acquisition.gov/far/52.222-55#FAR_52_222_55 https://www.acquisition.gov/far/52.222-62#FAR_52_222_62 https://www.acquisition.gov/far/52.226-6#FAR_52_226_6 https://www.acquisition.gov/far/52.247-69#FAR_52_247_69 https://www.govinfo.gov/link/uscode/49/40118 https://www.acquisition.gov/far/2.101#FAR_2_101 https://www.acquisition.gov/far/52.215-2#FAR_52_215_2 https://www.acquisition.gov/far/subpart-4.7#FAR_Subpart_4_7

(3) As used in this clause, records include books, documents, accounting procedures and practices, and other data, regardless of type and regardless of form. This does not require the Contractor to create or maintain any record that the Contractor does not maintain in the ordinary course of business or pursuant to a provision of law.

(e)

(1) Notwithstanding…

This is the start of the file's text. The full file is on GovTribe.