PPQ for AE.doc

DOC document 101 KB Posted

Attached to
Southern Region Facilities Architect-Engineer Multiple Award Contracts Federal contract opportunity
Solicitation number
1243ZP20R0001
Issued by
Department of Agriculture Forest Service

View the file

Other files for this federal contract opportunity

Other files attached to Southern Region Facilities Architect-Engineer Multiple Award Contracts, newest first.
File Type Posted
Request for Qualifications Revision 4.pdf PDF
Questions and Responses May 12 2020.pdf PDF
Request for Qualifications Revision 3.pdf PDF
Request for Qualifications Revision 2.pdf PDF
Revised Request for Qualifications.pdf PDF
Questions and Responses April 28.pdf PDF
Questions and Responses April 20.pdf PDF
A-E Fee Limitation.pdf PDF
Request for Qualifications.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Contractor Performance Report Contractor Information:

Firm Name:

Role:
Prime Contractor Sub Contractor Joint Venture

Other (Explain):

Point of Contact at the Firm:

POC Phone Number:

POC Email:

Project Information:

Contract/Task Order Number:

Contract Type:
Firm Fixed Price Cost Reimbursement

Other (Explain) :

Project Title:

Project Description:

Project Location:

Award Date:

Completion Date:

Actual Completion Date:

Explain Difference:

Original Contract Price:

Final Contract Price:

Explain Difference:

Client’s Assessment of the Contractor Client Information:

Business/Organization Name:

Point of Contact for the Client:

Title:

Phone Number:

Email:

Point of Contact’s Role in the Project:

Date Questionnaire Completed:

Client’s Signature:

Rating Scale:

EXCEPTIONAL

(5) Performance EXCEEDS MOST contractual requirements to the Government’s benefit. The performance of areas being assessed was accomplished with few minor issues or concerns.

VERY GOOD

(4) Performance EXCEEDS SOME contractual requirements to the Government’s benefit. The performance of areas being assessed was accomplished with few minor issues or concerns, for which the Contractor’s corrective actions were highly effective.

SATISFACTORY

(3) Performance MEETS contractual requirements. The performance of the areas being assessed contains minor issues or concerns, for which corrective actions taken by the Contractor were effective.

MARGINAL

(2) Performance MEETS SOME contractual requirements. The performance of the areas being assessed includes significant problems, issues, or concerns for which corrective actions taken by the Contractor were only somewhat effective.

UNSATISFACTORY

(1) Performance DOES NOT MEET contractual requirement. The performance of the areas being assessed includes serious problems, issues, or concerns for which the Contractor’s corrective actions were ineffective.

NOT APPLICABLE (N/A)
Performance information not recent or relevant as defined in the Solicitation. Unable to provide assessment.

Quality of Product or Service:

N/A
1
2
3
4
5

Quality of Deliverable

Adequacy of the QC Plan

Implementation of the QC Plan

Quality of QC Documentation

Identification/Correction of Deficient Work

Adequacy of Submittals

Plans are Coordinated with Specifications

Use of Specified Materials

Comments:

Cost Control:

N/A
1
2
3
4
5

Ability to meet the terms and conditions within the contractually agreed price(s)

Ability to design within funding limitations

Proposed innovative alternative methods/processes that reduced cost, improved maintainability or other factors that benefited the client

Comments:

Schedule:

N/A
1
2
3
4
5

Adequacy of Initial Milestone Schedule

Adherence to Approved Schedule

Resolution of Delays

Submission of Required Documentation

Submission of Updated and Revised Schedules

Comments:

Management / Business Relations:

N/A
1
2
3
4
5

Management of Resources/Personnel

Key Personnel were Utilized Appropriately and Effectively

Coordination and Control of Subcontractors

Professional Conduct

Review/Resolution of Subcontractor’s Issues

Change Order Activity (By Contractor)

Maintains an Adequate Work Force

Responsiveness to Corrective Actions

Identifies and Mitigates Risk

Comments:

Regulatory Compliance:

N/A
1
2
3
4
5

Complied With Contract Clause Requirements

Complied With Reporting Requirements

Complied With Design Requirements

Compliance With Labor Laws And Regulations

Complied With Safety Laws And Regulations

Correction Of Noted Deficiencies

Comments:

Overall Rating:

N/A
1
2
3
4
5

Overall Rating

Comments:

Recommendation

Given what you know today about the contractor’s ability to perform the work required, would you recommend the selection of this firm for similar requirements in the future?
Would
Would Not