Princeton Plasma Physics Laboratory 100 Stellarator Road Princeton, N.J. 08543

June 24, 2019

TO: Interested Parties

SUBJECT: Request for Proposal (RFP) 19-093-M for “FLARE Platform Construction”

The Trustees of Princeton University, a U.S. Department of Energy Prime Contractor, represented by Princeton Plasma Physics Laboratory (PPPL) has a requirement for a qualified Subcontractor to Construct PPPL FLARE Project Platform. The work will be performed at Princeton Plasma Physics Laboratory, 100 Stellarator Road100 Stellarator Road, Princeton, NJ 08543.

Any contractual agreement entered into as a result of this Solicitation will be a Firm-Fixed-Price (FFP) Subcontract issued under Prime Contract No. DE-AC02- 09CH11466 between the U.S. Department of Energy (DOE) and the Trustees of Princeton University.

The term of the proposed Subcontract is from date of commencement through completion, estimated to be two (3) months.

It is recommended that you first review the RFP’s Statement of Work (RFP Section I). If after this review you determine the work is within your ability and you have an interest, you should then carefully review the Sample Subcontract (RFP Section II) and the “Instructions for Proposal Preparation” (RFP Section III).

PROPOSALS WILL BE DUE TO THE PPPL RFP COORDINATOR (M. CHEN)

BY

4:00 PM EST ON JULY 08, 2019.

Please complete and return to me by email the attachment, “Acknowledgement of Request for Proposals (RFP) 19-093-M” form NLT COB (5:00 PM EST) on Friday, June 28, 2019.

If there are any questions pertaining to these matters I may be contacted at (609) 243-2428, fax (609) 243-2021, and by e-mail mchen2@pppl.gov .

Regards, Michael Chen Procurement Specialist mailto:mchen2@pppl.gov

PRINCETON UNIVERSITY

PRINCETON PLASMA PHYSICS LABORATORY

PO BOX 451

PRINCETON, NEW JERSEY 08543

ACKNOWLEDGMENT OF REQUEST FOR PROPOSAL (RFP) 19-093-M for

“FLARE Platform Construction”

Please complete and return this Acknowledgement Form to Princeton Plasma Physics Laboratory’s RFP (19-093-M) Procurement Specialist, Michael Chen.

Return by e-mail (mchen2@pppl.gov) NLT 04:00 PM EST, Friday, June 28, 2019.

We intend to submit a proposal in response to RFP 19-093-M by 4:00 PM EST, Monday, July 08, 2019.

We do not intend to submit a proposal in response to the

RFP.

The name, e-mail address and telephone number of the individual who will serve as our firm’s point of contact for this RFP is provided below.

Name of Firm:

Point of Contact:

E-mail address: Phone:

Name:

Title:

Date:

REQUEST FOR PROPOSAL (RFP) 19-093-M

For

FLARE Platform Construction

TABLE OF CONTENTS

SECTION I Statement of Work for “FLARE Platform Structure”, C-FAC-SOW-132, and Revision 1, dated April 11, 2019.

SECTION II SAMPLE SUBCONTRACT

SAMPLE SUBCONTRACT GENERAL PROVISIONS

SECTION III INSTRUCTIONS FOR PROPOSAL PREPARATION

SECTION IV REPRESENTATIONS AND CERTIFICATIONS BOOKLET

SECTION V OFFEROR INFORMATION AND PRICING FORM

SECTION I

Statement of Work for FLARE Platform Structure (C-FAC-SOW-132) 1

SSTTAATTEEMM EENNTT OOFF WWOORRKK

FOR

FLARE PLATFORM STRUCTURE

CAT: □A1 □A2 ☒A3

UNIQUE PROJECT IDENTIFIER: C-FAC-SOW-132

Reference Work Planning #: 2356

REVISION 1

DATED April 11, 2019

PREPARED BY:

Cognizant Individual (COG): Jongsoo Yoo

REVIEWED BY:

Responsible Engineer: Tom Kozob

ES&H: William Slavin

Quality & Assurance: Barry Jedic

APPROVED BY:

Supervisor / Project Manager: Scott Bentivegna

PRINCETON UNIVERSITY

PLASMA PHYSICS LABORATORY

P.O. BOX 451

PRINCETON, N.J. 08543

609-243-2000

Jongsoo Yoo Digitally signed by Jongsoo Yoo Date: 2019.05.07 10:09:44 -04'00'

Thomas A. Kozub Digitally signed by Thomas A.

Kozub Date: 2019.05.07 10:27:08 -04'00'

William V. Slavin Digitally signed by William V. Slavin DN: cn=William V. Slavin, o=ES&H, ou=PPPL, email=bslavin@pppl.gov, c=US Date: 2019.05.07 10:54:40 -04'00'

Barry Jedic Digitally signed by Barry Jedic Date: 2019.05.07 10:58:23 -04'00'

Scott Bentivegna Digitally signed by Scott Bentivegna Date: 2019.05.07 11:47:17 -04'00'

Statement of Work for FLARE Platform Structure (C-FAC-SOW-132) 2

Record of Revisions

Revision Date Responsible Ind. Description of Change 0 10/30/2015 David Pryor Initial Release 1 4/3/2019 Jongsoo Yoo 1) The cover page is changed to include the category of this project. The work planning form number is also changed, as this project has transferred to the

FLARE.

2) 1.0: The installation of experiment is now the third quarter of 2019. The same change was made in 6.3.

3) 1.0: The scope of work has been reduced to exclude upper trolley beams and trolleys.

4) The drawing number has been corrected to D-

FL600-002.

5) In section 1.4 in Attachment No.1, the ISO 1991- 2008 standard has changed to the ISO 9001-2015 standard, or PPPL approved equivalence.

6) No change has made to the rest of SOW.

Statement of Work for FLARE Platform Structure (C-FAC-SOW-132) 3

1.0 INTRODUCTION AND SCOPE

The Subcontractor shall provide all materials, labor, supervision, equipment, and expertise required to erect a multi-level aluminum platform within the PPPL C.S. Building. The platform will support operation and maintenance to the FLARE experiment currently under development. Construction of the platform shall be sequenced with installation of the experiment scheduled for the third quarter of year 2019.

The platform design is provided by the drawing, FLARE Platform D-FL600-002. The work scope is to build the entire system in the drawing except the section 7 on sheet 4 (trolley beams and trolleys), because the design of this part has not been fully reviewed and is subject to future modification.

2.0 APPLICABLE DOCUMENTS

2.1 ASTM – American Society for Testing and Materials

a. ASTM B 26 Standard Specification for Aluminum Alloy Sand Castings

b. ASTM B 209 Aluminum and Aluminum-Alloy Sheet and Plate

c. ASTM B 210 Aluminum and Aluminum-Alloy Drawn Seamless Tubes

d. ASTM B 211 Aluminum and Aluminum-Alloy Bar, Rod, and Wire

e. ASTM B 221 Aluminum and Aluminum-Alloy Extruded Bars, Rods, Wire, Profiles, and Tubes

f. ASTM B 241 Aluminum and Aluminum-Alloy Seamless Pipe and Seamless

Extruded Tube

g. ASTM B 247 Aluminum and Aluminum-Alloy Die Forgings, Hand Forgings, and

Rolled Ring Forgings

h. ASTM B 308 Aluminum-Alloy 6061-T6 Standard Structural Profiles

i. ASTM B 429 Aluminum Alloy Extruded Structural Pipe and Tube

j. ASTM E 84 Standard Test Method for Surface burning Characteristics of Building

Materials

k. ASTM E894 Standard Test Method for Anchorage of Permanent Metal Railing

Systems and Rails for Buildings

l. ASTM E935 Standard Test Methods for Performance of Permanent Metal Railing

Systems and Rails for Buildings

m. ASTM D638 Tensile Properties of Plastics

n. ASTM D790 Flexural Properties of Unreinforced and Reinforced Plastics

o. ASTM D2344 Apparent Interlaminar Shear Strength of Parallel Fiber Composites by

Short Beam Method

p. ASTM D495 High Voltage, Low-Current, Dry Arc Resistance of Solid Electrical

Insulation

q. ASTM D696 Coefficient of Linear Thermal Expansion for Plastics

r. ASTM E84 Surface Burning Characteristics of Building Materials

s. ASTM F593 Standard Specification for Stainless Steel Bolts, Hex Cap Screws, and

Studs

t. ASTM F594 Standard Specification for Stainless Steel Nuts

2.1 OSHA – Occupational Safety and health Act, Code of Federal Regulation 29 CFR 1926, Construction Industry Regulations

2.2 ICC, International Code Council

a. IBC, International Building Code and Referenced Standards

Statement of Work for FLARE Platform Structure (C-FAC-SOW-132) 4

2.3 NFPA, National Fire Protection Association

a. NFPA 5000 Building Construction and Safety Code

2.4 PPPL ES&H 5008 (http://www.pppl.gov/eshis/ESHD_MANUAL/sm.html)

3.0 APPLICABLE DRAWINGS

FLARE Platform D-FL600-002 Rev 0. Dated 10/20/2015

4.0 RESPONSIBILITIES

4.1 Princeton Plasma Physics Laboratory

4.1.1 All construction activities must be coordinated with the Princeton Technical

Representative (PTR) to minimize systems down time and shall not have any negative impact on experimental operations.

4.1.2 All communications on technical matters shall be directed to the assigned PTR

4.1.3 All communications on administrative matters shall be directed to the PPPL Procurement

Representative.

4.1.4 PPPL permits all employees to issue a “STOP WORK” Order, if unsafe work practices are observed.

4.2 Subcontractor

4.2.1 The Subcontractor shall provide a Single point of contact for any communication between PPPL and the Subcontractor.

4.2.2 The Subcontractor shall provide all labor, materials, equipment, and construction supervision services necessary to complete the proposed work in accordance of this Statement of Work, the Technical Specifications, the referenced standards, and the project requirements.

4.2.3 The Subcontractor shall submit a fixed price bid for the scope detailed within the Statement of Work and referenced Construction Documents. The Subcontractor is responsible to verify and confirm the scope of work within this Statement of Work and referenced Construction Documents adequately represent the intent of this project. All questions regarding the scope of work should be received prior to bid.

4.2.4 The Subcontractor shall identify any facility changes, modifications, or obstructions to be mitigated prior to acceptance of the subcontract, in order to safely and efficiently perform work.

4.2.5 The Subcontractor shall dispose of all construction debris in accordance with Federal, State, and Local requirements.

4.2.6 All work should be completed during normal working hours of 7:00 AM to 3:30PM, Monday through Friday. The Subcontractor shall submit a construction schedule as part of their bid package. Revisions to this schedule shall be submitted as construction progress.

4.2.7 A government issued Photo ID is required for Subcontractor access to PPPL.

Statement of Work for FLARE Platform Structure (C-FAC-SOW-132) 5

4.2.8 The Subcontractor shall notify and obtain PPPL approval for any lower-tier Subcontractor proposed for this project, prior to their arrival on site.

5.0 REQUIREMENTS

5.1 PERFORMANCE REQUIREMENTS

5.1.1 PERFORMANCE CHARACTERISTICS

The platform has been designed per IBC and ASCE 7 to withstand the dead, live, and seismic loading parameters noted within the construction drawings.

5.1.2 OPERATING ENVIRONMENT

All materials shall be able to withstand impact from an industrial moderately corrosive environment.

5.1.3 DESIGN LIFE

Thirty years.

5.1.4 RELIABILITY

Not applicable

5.1.5 MAINTAINABILITY

All connections shall be bolted connections for disassembly as needed during operations.

Hoist rails shall be provided as noted within the construction drawings for maintenance of the experiment’s various components. In addition, removable guard rails shall be provided at all unprotected edges as well as horizontal life lines for anchorage of fall protection during maintenance operations.

5.1.6 HUMAN FACTORS

Not applicable.

5.1.7 SUSTAINABILITY

PPPL’s prime contract requires the purchase of certain types of environmentally preferable products such as, but not limited to, EPEAT-registered electronic devices, ENERGYSTAR and FEMP-listed energy-consuming equipment, Water-Sense listed products, bio-based materials, EPA-designated recycled content products, non ozone-depleting chemicals and non-toxic or less toxic alternatives when practical. Where such products are available and meet the technical requirements of the work, they should be specified to the maximum extent practical. In addition, SOWs for architecture and facility design, construction, demolition and maintenance services should include the use of sustainable design practices, inventory, tracking and reporting of recyclables, and the specification on sustainable building materials and equipment to the maximum extent practical. Additional information on environmentally preferable products is available online at https://pppl.princeton.edu/PPPL_Environmentally_Preferable_Purchasing.

5.2 EQUIPMENT DEFINITION

5.2.1 SPECIFICATIONS AND STANDARDS

Statement of Work for FLARE Platform Structure (C-FAC-SOW-132) 6

See the attached construction documents and specifications for additional information.

5.2.2 GENERAL DESIGN FEATURES

The platform will support operation and maintenance to the FLARE experiment. The platform consists of two levels. Stairs are located at the ground level of the PPPL CS High Bay as well as the FLARE control room. The lower platform surrounds the experiment and provides access to the experiments two end bells. The upper platform provides access to ports located at the top of the experiment and includes trolley rails to open and close each end bell.

5.2.3 MATERIALS

All materials shall be non-magnetic and adequately grounded to avoid inaccurate measurements or malfunctions during operation of the experiment. Unless noted otherwise materials shall be as follows:

Structural Aluminum Wide Flange: Alloy 6061-T6 Structural Aluminum Channel: Alloy 6061-T6 Structural Aluminum Tube: Alloy 6061-T6 Structural Aluminum Angle: Alloy 6061-T6 Structural Aluminum Tube: Alloy 6061-T6 Structural Aluminum Pipe: Alloy 6063-T6 Plate and Sheet: Alloy 6061-T6 Die and Hand Forgings: Alloy 6061-T6 Castings: Alloy A356.0-T6 Fasteners: Stainless Steel Type 304 Welding Filler: Alloy 5356 Grout: Nonmetallic, Shrinkage-Resistant Grout: ASTM C 1107/C 1107M, factory packaged, nonmetallic aggregate grout, noncorrosive and nonstaining, mixed with water to consistency suitable for application and a 30-minute working time.

Grating: Polyester glass-fiber-reinforced plastic

5.2.4 ELECTROMAGNETIC INTERFERENCE AND SUSCEPTIBILITY

Grounding shall be completed by others and is not a part of this contract. G10 insulators shall be provided within this contract at all connections as detailed within the construction drawings to support grounding efforts.

5.2.5 IDENTIFICATION AND MARKING

Mark and match-mark materials for field assembly.

5.2.6 WORKMANSHIP

A preinstallation Conference shall be conducted at PPPL.

Coordinate installation of anchorage items to be embedded in or attached to other construction without delaying the Work. Provide setting diagrams, sheet metal templates, instructions, and directions for installation.

Statement of Work for FLARE Platform Structure (C-FAC-SOW-132) 7

Prior to setting baseplates, clean concrete of bond-reducing materials, and roughen surfaces. Clean bottom surface of plates. Set plates for structural members on setting nuts. Snug-tighten anchors after supported members have been positioned and plumbed. Promptly pack grout solidly between bearing surfaces and plates so no voids remain. Neatly finish exposed surfaces; protect grout and allow to cure. Comply with manufacturer's written installation instructions for shrinkage-resistant grouts.

Align and adjust various members that form part of complete frame or structure before permanently fastening. Before assembly, clean bearing surfaces and other surfaces that are in permanent contact with members. Perform necessary adjustments to compensate for discrepancies in elevations and alignment. Level and plumb individual members of structure. Splice members only where indicated.

6.0 TEST AND INSPECTION REQUIREMENTS

6.1 PERFORMANCE TESTS

The Subcontractor shall engage a qualified testing agency to perform shop tests and inspections. Provide testing agency with access to places where structural-aluminum work is being fabricated or produced to perform tests and inspections.

6.2 ACCEPTANCE TESTS

A walkthrough inspection shall be completed by PPPL generating a punch list of areas which require action.

In addition, PPPL shall visually inspect shop-welded connections according to AWS D1.2.

6.3 SUPPLIER HOLD POINTS

The contractor shall erect the lower level of the platform and hold until the FLARE experiment has been installed and inspected third quarter of year 2019. Proceeding installation of the experiment, the upper portion of the platform shall be finished. The lower portion of the platform consists of structural elements up to elevation 111’-2” including the entry stairs from the FLARE control room as well as the stairs leading from ground level. Temporary guardrails shall be provided as necessary at all unprotected edges exposed between phases and all hazards shall be safed. The upper portion of the platform consists of the remaining structural members including the trolley rails and posts. See the attached construction documents for post splice details and further information.

6.4 QUALITY CONTROL RECEIPT INSPECTIONS

Not applicable

7.0 QUALIFICATIONS

Documentation of the Subcontractor’s experience installing similar scope system shall be submitted. This includes qualifications for the installer, fabricator, and testing agency.

Welding Procedure Specifications (WPSs), Welding Qualification Records (WQRs), and Welding Personnel qualifications (WPQs) shall be provided according to AWS D1.2, "Structural Welding Code - Aluminum," for each welded joint qualified whether prequalified or by testing, including the power source (constant current or constant voltage). In addition the Subcontractor shall submit welding certificates. All welding documentation must be approved by PPPL prior to the start of welding. Welding shall be performed in accordance with the requirements of AWS D1.2. Welding performed onsite shall also meet the requirements of PPPL Procedure No. ENG-037. Visual weld inspection shall be performed in accordance with the acceptance criteria of AWS D1.2 for statically loaded structures.

Statement of Work for FLARE Platform Structure (C-FAC-SOW-132) 8

Prior to bringing equipment such as cranes, forklifts, manlifts, or special purpose vehicles on site the Subcontractor shall submit for review operator training qualifications as well as equipment maintenance and inspection records. Inspection records shall include model and serial number of the specific piece of equipment. In addition the equipment manual shall be submitted for review and provided on site along with the equipment.

For all hoisting and rigging, a lift plan shall be required for review. The lift plan shall include:

Periodic equipment inspection reports Monthly hook and wire rope inspection reports Lift data sheet detailing loads, center of gravity, attachment points, component capacities, calculations, lift angle, and swing location. Requires signature by the Subcontractor’s Lift Engineer.

Qualifications of the Rigger and Signal Person. An officer from the Subcontractor’s firm shall sign that the stated Rigger and Signal Person are qualified per OSHA 1926.1400.

Equipment manual and load charts.

For additional requirements not mentioned refer to engineering standards ES-MECH-007, ES- MECH-010, ES-MECH-011, ES-MECH-012. PPPL Engineering Standards may be found online at http://bp.pppl.gov/EngStds.html.

8.0 ENVIRONMENT, SAFETY, AND HEALTH

8.1 All work shall comply with PPPL ESHD 5008. The manual is available on the internet at:

http://www.pppl.gov/eshis/ESHD_MANUAL/sm.html .

8.2 Subcontractor will prepare a written Integrated Safety Management (ISM) Plan (construction project safety and health plan) that implements the requirements noted and will obtain approval of the plan by the PPPL Construction Manager prior to commencement of any work covered by the Plan. In the Plan, the Subcontractor must designate the individual(s) responsible for its on-site implementation, specify qualifications for those individuals, and provide a list of those project activities for which subsequent job hazard analyses are to be performed. The level of detail within the ISM Plan should be commensurate with the size, complexity and risk level of the construction project.

8.3 The Subcontractor shall identify for approval by the PPPL Construction Manager competent persons for activities as required by applicable OSHA standards. These should be included in the ISM plan.

8.4 The Subcontractor shall comply with:

the specific PPPL documents, requirements, permits and courses listed in this Statement of Work;

the completed Subcontractor ISM Plan, and all applicable Federal, State, and local laws, regulations and requirements whether or not they are specifically listed in the Statement of Work or subcontract.

8.5 All work shall be in accordance with all OSHA, DOE and PPPL requirements. Care shall be taken to protect personnel, employees and surroundings. OSHA 300 Logs shall be submitted as part of the Subcontractor’s bid package.

8.6 Subcontractor’s personnel working on-site at PPPL for more than 40 hours will be required to

Statement of Work for FLARE Platform Structure (C-FAC-SOW-132) 9 successfully complete PPPL’s General Employee (safety) Training and receive a PPPL Identification Badge. Attendance may also be required at Radiation Safety, Fall Protection, Confined Space, Fire Watch, Electrical Utilization Training, Lockout/Tagout and other training.

The Princeton Technical Representative is responsible for determining training requirements and scheduling attendance. Time spent in attendance of PPPL directed training is chargeable to PPPL at the appropriate hourly rate. PPPL Identification Badges are to be returned to PPPL upon completion of subcontract.

8.7 Prepare and have approved by the PPPL Construction Manager, a Job Hazard Analyses (JHAs) in accordance with PPPL procedure ESH-004 prior to commencement of affected work. The JHAs must identify foreseeable hazards and protective measures and address further hazards revealed by supplemental information provided by the PPPL Construction Manager. The JHA form can be found at the following web site:

http://bp.pppl.gov/JHA_online.doc

8.8 The Subcontractor shall ensure workers are aware of foreseeable hazards and the protective measures as defined by JHAs and require that workers acknowledge being so informed.

8.9 The Subcontractor shall ensure that workers not following safe work practices are subject to

Subcontractor’s disciplinary process.

8.10 The Subcontractor shall maintain a designated representative onsite during all active construction that is knowledgeable of the associated hazards and has the authority to act on behalf of the Subcontractor and who makes frequent and regular inspections of the construction work site to identify and correct any instance of a noncompliance with project safety and health requirements.

8.11 The Subcontractor shall instruct workers to report to the Construction Subcontractor’s designated representative hazards not previously identified or evaluated. If immediate corrective action is not possible or the hazards fall outside the project scope, the Construction Subcontractor must immediately notify the affected workers, post appropriate warning signs, modify the appropriate JHAs, and implement needed interim control measures as well as notify the PPPL Construction Manager of the action taken. The Construction Subcontractor or the designated representative must stop work in the affected area until appropriate protective measures are established.

8.12 The Subcontractor shall provide approval drawings and/or other documentation of protective measures for which applicable OSHA standards require preparation by a Professional Engineer or other qualified individual. These should be included in the ISM Plan and include but are not limited to Scaffolding and Fall Protection barriers and anchors.

8.13 All Subcontractor vehicles and equipment must be in good working order with no leaks of any kind. Any spills must be reported immediately to PPPL and work stopped until spill is addressed.

The Subcontractor is responsible for remediation costs caused by negligence and or faulty equipment. PPPL Environmental Services will determine the proper method of remediation.

8.14 No burning or welding is permitted without a PPPL Flame permit.

Statement of Work for FLARE Platform Structure (C-FAC-SOW-132) 10

8.15 All waste including paints and other chemicals must be disposed of in accordance with local, state and Federal regulations and PPPL requirements.

8.16 Safety data sheets for all paints adhesives, chemicals, stains and solvents must be provided prior to the start of work.

8.17 PPPL has safety programs that include the following areas: Confined Space Permites, Digging Permits, Penetration and Fire Seal permits, Flame permits, Radiation Work permits, Lock-out/Tagout of energy sources, and restrictions on working alone. The Subcontractor must confirm with their PPPL contact person that all prerequisites have been met before initiating any activity that involves these areas.

8.18 Barricade tape, when needed, shall only be red "Danger" tape where personnel hazards exist.

Yellow "Caution" tape may only be used for equipment protection. All barricade tape will be posted with the name and phone number of a contact. The PPPL representative may provide the contact information.

8.19 PPPL ES&H Training Courses

Subcontractor shall have trained their employees regarding the qualifications needed to perform this work. PPPL ES&H training courses that are applicable to the Subcontractor's work scope are also available. If PPPL decides that training of employees is inadequate, PPPL reserves the right to require Subcontractor to obtain certified training.

8.20 Additional ES&H Controls

The subcontractor's safety record will be considered in the proposal/bid evaluations. Request supporting information.

The subcontractor's number of reportable injury/illness cases, in the last year or even longer, shall be included in the proposal/bid evaluation requirements.

Lower tier Subcontractors shall follow all ES&H requirements.

9.0 QUALITY ASSURANCE REQUIREMENTS

9.1. Subcontractor shall perform work on this project only with tradesmen with a demonstrated history of the quality of work required with the specified products on previous jobs.

9.2. The Subcontractor is responsible for inspecting all work in progress to ensure compliance with this Statement of Work.

9.3. The assigned PPPL Construction Coordinator and the Subcontractors representative/foreman are required to hold daily job briefings. The briefings shall be held at the start of a shift, as schedule permits.

9.4. Shop Drawings detailing fabrication of structural-aluminum components shall be issued to assure quality and design intent:

Include details of cuts, connections, splices, camber, holes, and other pertinent data.

Statement of Work for FLARE Platform Structure (C-FAC-SOW-132) 11

Include embedment Drawings.

Indicate welds by standard AWS symbols, distinguishing between shop and field welds, and show size, length, and type of each weld. Show backing bars that are to be removed and supplemental fillet welds where backing bars are to remain.

Indicate type, size, and length of bolts, distinguishing between shop and field bolts.

Identify pretensioned and slip-critical, high-strength bolted connections.

All shop drawings shall be developed using computer generated software and submitted via PDF and AutoCAD format.

9.5. Additional product submittals shall be provided as requested.

9.6. The Subcontractor shall submit the manufacturer's Material Test Reports showing actual relevant chemical, mechanical, and electrical properties of materials used and providing traceability to the actual material. One copy is to be submitted to PPPL upon Subcontractor acceptance for use. Note: For specialty materials, typically non-metals, where test reports are not readily available from the manufacturer, their certificate of analysis or certificate of grade, as appropriate, may suffice, subject to PPPL concurrence.

In cases where material certifications are not available, prior approval from PPPL is required prior to use. The following materials will require documentation:

• 6061 T6

• G10

• 304 stainless steel fasteners

• Welding Filler: Alloy 5356

9.7. The Supplier shall provide fasteners that comply with internationally recognized standards.

Fasteners shall exhibit grade marks and the manufacturer’s identification symbol (headstamp) as specified in the referenced standard. Additionally, fasteners with a tensile rating of 100ksi or greater have been designated as “high strength”. If “high strength” fasteners (e.g. grade 5, grade 8) are designated for use, Certified Material Test Reports shall be provided regardless of application. Fasteners shall exhibit grade marks and the manufacturer’s identification symbol (headstamp) as specified in the referenced Material Specification. Fasteners having a headmark that is displayed on the suspect fastener list (attached) will not be accepted.

9.8. The PTR will review the documentation and work done at the completion of the job to ensure all the requirements of the SOW have been met.

10.0 SHIPPING STORAGE AND HANDLING

Limited storage area will be available for materials and tools. The Subcontractor will be responsible for complying with the manufacturer’s recommendations for protecting materials from damage while stored and during installation. Protect mechanical finishes on exposed surfaces from damage by applying a strippable, temporary protective covering before shipping.

Statement of Work for FLARE Platform Structure (C-FAC-SOW-132) 12

11.0 WARRANTY

All materials shall be warranted to the manufacturer’s original warranty or a minimum of 5 years.

Defective materials shall be replaced at no additional cost to PPPL. All repairs required due to improper installation shall be completed by the Subcontractor at no additional cost to PPPL.

12.0 ATTACHMENTS

12.1 Attachment No. 1 Detail Specifications

Statement of Work for FLARE Platform Structure (C-FAC-SOW-132) 13

13.0 DOCUMENTATION AND DELIVERABLES

Deliverables List

PO / Subcontract / BOA / BPA #:

# Physical Deliverables Required When Deliverable Is Required

Deliverable Received

1 Platform Structure Components Prior to Start Exceptions (Add justification for any missing physical deliverables that will not be received):

# Document Deliverables Required

When Deliverable Is Required

Deliverable format (paper, electronic etc.)

Storage Location for Deliverable

Deliverable Received

1 OSHA 300 Log (section 8.5) N P,E Ops Center 2 Integrated Safety Management Plan

(ISM) (section 8.2) N P,E Ops Center

3 Installer Qualifications & Certifications (section 7.0)

N P,E Ops Center

4 Construction Schedule (section 4.2.6) N/D P,E Ops Center 5 Competent Person(s) Letter (as req’d)

(section 8.3) PS P,E Ops Center

6 Job Hazard Analysis (JHA) (section 8.7)

PS P,E Ops Center

7 OSHA Training Records (as req’d) (section 7.0)

PS/D P,E Ops Center

8 Shop & Fabrication Drawings (section 8.12, 9.4, attachment 1 sections 06610-1.3, 067413 -1.4)

PS/D P,E Ops Center

9 Safety Data Sheets (as req’d) (section 8.16)

PS/D P,E Ops Center

10 Product Data and Specifications (as req’d) (attachment 1, sections 06610- 1.3, 067413 -1.4)

PS/D P,E Ops Center

11 List of Lower Tier Subcontractors (as req’d) (section 4.2.8)

PS/D P,E Ops Center

12 Equipment model, serial number, and manual (as req’d) (section 7.0)

PS/D P,E Ops Center

13 Equipment Maintenance and Inspection Records (as req’d) (section 7.0)

PS/D P,E Ops Center

14 Equipment Operator Training Qualifications or Certifications (as req’d) (section 7.0)

PS/D P,E Ops Center

Statement of Work for FLARE Platform Structure (C-FAC-SOW-132) 14

16 Lift Plan (as req’d) (section 7.0) PS/D P,E Ops Center 17 Welding Specifications, Records, and

Qualifications (section 7.0) PS/D P,E Ops Center

18 PPPL Permits (as req’d) (section 8.0) PS/D P,E Ops Center 20 Material test reports or equivalent

(section 9.6) PS/D P,E Ops Center

Exceptions (Add justification for any missing document deliverables that will not be received):

*Legend N = Notice to Proceed Requirement PS = Prior to Start of Construction D = During Construction/As Required C = Project Completion P,E = Paper or Electronic

Princeton Technical Representative/COG:

(Sign-off and provide to the Operations Center when job is completed and deliverables are dispositioned and placed/filed in Operations Center (or other Project, Department or Division designated file center).

Statement of Work for FLARE Platform Structure (C-FAC-SOW-132) 15

ATTACHMENT No. 1

PPPL

Detail Specifications

Statement of Work for FLARE Platform Structure (C-FAC-SOW-132) 16

SECTION 06610 - FIBERGLASS REINFORCED PLASTICS (FRP) FABRICATIONS PULTRUDED TUBE

GUARDRAIL AND HANDRAIL

PART 1 - GENERAL

1.1 SCOPE OF WORK

A. This specification is for a pultruded fiberglass railing system in compliance with 2015 IBC, and OSHA 1910.23.

1.2 REFERENCES

A. The publications listed below (latest revision applicable) form a part of this specification to the extent referenced herein. The publications are referred to within the text by the designation only.

AMERICAN SOCIETY FOR TESTING AND MATERIALS (ASTM) Test Methods:

ASTM D-638-Tensile Properties of Plastics

ASTM D-790-Flexural Properties of Unreinforced and Reinforced Plastics

ASTM D-2344-Apparent Interlaminar Shear Strength of Parallel Fiber Composites by Short Beam Method

ASTM D-495-High Voltage, Low-Current, Dry Arc Resistance of Solid Electrical Insulation

ASTM D-696-Coefficient of Linear Thermal Expansion for Plastics

ASTM E-84-Surface Burning Characteristics of Building Materials

1.3 SUBMITTALS

A. The Subcontractor shall furnish shop drawings of all fabricated railings and accessories in accordance with the provisions of this Section.

B. The Subcontractor shall furnish manufacturer's shop drawings clearly showing material sizes, types, styles, part or catalog numbers, complete details for the fabrication of and erection of components including, but not limited to, location, lengths, type and sizes of fasteners, clip angles, member sizes, and connection details.

C. The Subcontractor shall submit the manufacturer’s published literature including structural design data, structural properties data, corrosion resistance tables, certificates of compliance, test reports as applicable, and design calculations for systems not sized or designed in the contract documents, sealed by a Professional Engineer.

D. The Subcontractor may be requested to submit sample pieces of each item specified herein for

Statement of Work for FLARE Platform Structure (C-FAC-SOW-132) 17 acceptance by the ENGINEER as to quality and color. Sample pieces shall be manufactured by the method to be used in the WORK.

1.4 QUALITY ASSURANCE

A. All items to be provided under this Section shall be furnished only by manufacturers having a minimum of ten (10) years experience in the design and manufacture of similar products and systems.

Additionally, if requested, a record of at least five (5) previous, separate, similar successful installations in the last five (5) years shall be provided.

B. Manufacturer shall offer a 3 year limited warranty on all FRP products against defects in materials and workmanship.

C. Manufacturer shall be certified to the ISO 9001-2015 standard, or PPPL approved equivalence.

D. Manufacturer shall provide proof of certification from at least two other quality assurance programs for its facilities or products (DNV, ABS, USCG, AARR).

1.5 PRODUCT DELIVERY AND STORAGE

A. Delivery of Materials: Manufactured materials shall be delivered in original, unbroken pallets, packages, containers, or bundles bearing the label of the manufacturer. Adhesives, resins and their catalysts and hardeners shall be crated or boxed separately and noted as such to facilitate their movement to a dry indoor storage facility.

B. Storage of Products: All materials shall be carefully handled to prevent them from abrasion, cracking, chipping, twisting, other deformations, and other types of damage. Adhesives, resins and their catalysts are to be stored in dry indoor storage facilities between 70 and 85 degrees Fahrenheit (21 to 29 degrees Celsius) until they are required.

PART 2 - PRODUCTS

2.2 GENERAL

A. All posts and rails are to be FRP structural shapes manufactured by the pultrusion process. The structural shapes shall be composed of fiberglass reinforcement and resin in qualities, quantities, properties, arrangements and dimensions as necessary to meet the design requirements and dimensions specified in the Contract Documents.

B. Fiberglass reinforcement shall be a combination of continuous roving, continuous strand mat, and surfacing veil in sufficient quantities as needed by the application and/or physical properties required.

C. Resins shall be, non-fire retardant isophthalic polyester used to produce NSF Standard 61 certified shapes; ISOFR, fire retardant isophthalic polyester; VE, non-fire retardant vinyl ester used to produce NSF Standard 61 certified shapes or VEFR, fire retardant vinyl ester with chemical formulation necessary to provide the corrosion resistance, strength and other physical properties as required.

Statement of Work for FLARE Platform Structure (C-FAC-SOW-132) 18

D. All finished surfaces of FRP items and fabrications shall be smooth, resin-rich, free of voids and without dry spots, cracks, crazes or unreinforced areas. All glass fibers shall be well covered with resin to protect against their exposure due to wear or weathering.

E. All pultruded structural shapes shall be further protected from ultraviolet (UV) attack with 1) integral

UV inhibitors in the resin, 2) a synthetic surfacing veil to help produce a resin rich surface, and 3) an appropriate UV resistant coating for outdoor exposures.

F. All FRP products shall have a tested flame spread rating of 25 or less per ASTM E-84 Tunnel Test, (except for non-fire retardant isophthalic polyester and vinyl ester NSF Standard 61 certified shapes).

G. Top and bottom rails for guards are to be 1.75" x 0.125" (44.4 mm x 3.2 mm) wall square tube, the posts are to be 2.125" x 0.1875" (53.9 mm x 4.8 mm) wall square tube and kick plate is to be ½" deep x 4" wide with two reinforcing ribs. Offset rail used as handrail to be 1.5” x 0.25” (38.1 mm x 6.4

mm) wall round tube.

H. The completed railing installation shall meet the following load requirements with a minimum factor of safety of 2.0:

Concentrated Load: 200 lb (891 N) applied in any direction at any point on the rail.

Uniform Load: 50 lb/lf (730.5 N/m) applied in any direction on the rail.

Loads are assumed not to act concurrently.

I. All rails, posts, and kick plates are to be integrally pigmented yellow.

J. Pultruded structural shapes used in the railing systems are to have the minimum longitudinal mechanical properties listed below:

Property ASTM Method Value Units

Tensile Strength D-638 30,000 (206) psi (MPa)

Tensile Modulus D-638 2.5 x 106 (17.2) psi (GPa)

Flexural Strength D-790 30,000 (206) psi (MPa)

Flexural Modulus D-790 1.8 x 106 (12.4) psi (GPa)

Flexural Modulus (Full Section) N/A 2.8 x 106 (19.3) psi (GPa)

Short Beam Shear (Transverse) D-2344 4,500 (31) psi (MPa)

Shear Modulus (Transverse) N/A 4.5 x 105 (3.1) psi (GPa)

Coefficient of Thermal Expansion D-696 8.0 x 10-6 (1.4 x 10 -6) in/in/°F (cm/cm/°C)

Flame Spread E-84 25 or less N/A

K. All fasteners used in the railing system are to be 316 SS. Rivets to be 18-8 SS.

Statement of Work for FLARE Platform Structure (C-FAC-SOW-132) 19

PART 3 - EXECUTION

3.0 FABRICATION

A. The post/rail connection for guards is to be fabricated such that the rails are unbroken and continuous through the post without the use of packs or splices. The bottom rail is to be installed through the post at a prepared hole made to fit the outside dimensions of the rail. The top rail is to fit into a machined, u-shaped pocket formed into top of the post such that the rail is located at the center of the post. All exposed post corners are to be radiused to eliminate sharp edges. The rails are to be joined to the post through a combination of bonding and riveting. The offset handrail is to be fabricated such that the rail is continuous with the use of connectors and splices. No sharp, protruding edges are to remain after assembly of the railing system. Spacing of the posts and offset handrail supports shall not exceed 6'-0" (1.83 m).

B. The bases of the posts are to be attached according to the contract drawings. The bases of the posts are to be reinforced to a height of 8.5" (254 mm). The offset handrails are to be attached to guards or walls with brackets.

C. When required, rails for guards are to be spliced using a 10" (152.4 mm) length of 1.5" x 1/8" (38.1 mm x 3.2 mm) FRP square tube bonded and riveted into place using epoxy adhesive. Rail for offset handrail to be spliced using a 5” (127 mm) length of 1” (25.4 mm) FRP round rod.

D. To avoid embrittlement at cold temperatures and loss of strength at high temperatures, no PVC or CPVC connectors should not be used as a load carrying component of the railing system.

E. All shop fabricated cuts are to be sealed to provide maximum corrosion resistance. Field cuts are to be similarly coated by the contractor in accordance with the manufacturer’s instructions.

Statement of Work for FLARE Platform Structure (C-FAC-SOW-132) 20

SECTION 067413 - FIBERGLASS REINFORCED GRATINGS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract apply to this Section.

1.2 SUMMARY

A. Section includes glass-fiber-reinforced-plastic gratings.

1.3 COORDINATION

A. Coordinate installation of anchorages for gratings, grating frames, and supports. Furnish setting drawings, templates, and directions for installing anchorages, including sleeves, concrete inserts, anchor bolts, and items with integral anchors, that are to be embedded in concrete or masonry. Deliver such items to Project site in time for installation.

1.4 ACTION SUBMITTALS

A. Product Data: For glass-fiber-reinforced-plastic gratings.

B. Shop Drawings: Include plans, sections, details, and attachments to other work.

C. Delegated-Design Submittal: For gratings, including manufacturer's published load tables.

1.5 FIELD CONDITIONS

A. Field Measurements: Verify actual locations of walls and other construction contiguous with gratings by field measurements before fabrication.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Structural Performance: Gratings shall withstand the effects of gravity loads and the following loads and stresses within limits and under conditions indicated.

1. Floors: Uniform load of 250 lbf/sq. ft. (11.97 kN/sq. m).

2. Limit deflection to L/360 or 1/4 inch (6.4 mm), whichever is less.

Statement of Work for FLARE Platform Structure (C-FAC-SOW-132) 21

2.2 GLASS-FIBER-REINFORCED-PLASTIC GRATINGS

A. Pultruded Glass-Fiber-Reinforced Gratings: Bar gratings assembled from components made by simultaneously pulling glass fibers and extruding thermosetting plastic resin through a heated die under pressure to produce a product without voids and with a high glass-fiber content.

1. Configuration: T3320; 2-inch (51-mm) T-bars spaced 1-1/2 inches (38 mm) o.c. (33 percent open).

2. Weight: 3.61 lb/sq. ft. (17.63 kg/sq. m)

3. Resin Type: Polyester.

a. Flame-Spread Index: 25 or less when tested according to ASTM E 84.

4. Color: Yellow.

5. Traffic Surface: Applied abrasive finish.

2.3 FASTENERS

A. General: Unless otherwise indicated, provide Type 304 stainless-steel fasteners.

B. Stainless-Steel Bolts and Nuts: Regular hexagon-head annealed stainless-steel bolts, nuts, and, where indicated, flat washers; ASTM F 593 (ASTM F 738M) for bolts and ASTM F 594 (ASTM F 836M) for nuts, Alloy Group 1 (A1).

2.4 FABRICATION

A. Shop Assembly: Shop fabricate grating sections to greatest extent possible to minimize field splicing and assembly. Disassemble units only as necessary for shipping and handling limitations. Use connections that maintain structural value of joined pieces. Clearly mark units for reassembly and coordinated installation.

B. Cut, drill, and punch material cleanly and accurately. Remove burrs and ease edges to a radius of approximately 1/32 inch (1 mm) unless otherwise indicated. Remove sharp or rough areas on exposed surfaces.

C. Form gratings from materials of size, thickness, and shapes indicated, but not less than that needed to support indicated loads.

D. Fit exposed connections accurately together to form hairline joints.

E. Provide for anchorage of type indicated; coordinate with supporting structure. Fabricate and space the anchoring devices to secure gratings, frames, and supports rigidly in place and to support indicated loads.

F. Fabricate cutouts in grating sections for penetrations indicated. Arrange cutouts to permit grating removal without disturbing items penetrating gratings.

2.5 GRATING FRAMES AND SUPPORTS

A. Frames and Supports for Glass-Fiber-Reinforced-Plastic Gratings: Fabricate from glass-fiber-reinforced-plastic shapes of sizes, shapes, and profiles indicated and as necessary to receive gratings.

Statement of Work for FLARE Platform Structure (C-FAC-SOW-132) 22

Miter connections for perimeter angle frames. Cut, drill, and tap units to receive hardware and similar items.

1. Unless otherwise indicated, use shapes made from same resin as gratings.

PART 3 - EXECUTION

3.1 INSTALLATION, GENERAL

A. Fastening to In-Place Construction: Provide anchorage devices and fasteners where necessary for securing gratings to in-place construction. Include threaded fasteners for concrete and masonry inserts, through-bolts, lag bolts, and other connectors.

B. Cutting, Fitting, and Placement: Perform cutting, drilling, and fitting required for installing gratings. Set units accurately in location, alignment, and elevation; measured from established lines and levels and free of rack.

C. Provide temporary bracing or anchors in formwork for items that are to be built into concrete or masonry.

D. Fit exposed connections accurately together to form hairline joints.

3.2 INSTALLING GLASS-FIBER-REINFORCED-PLASTIC GRATINGS

A. Comply with manufacturer's written instructions for installing gratings. Use manufacturer's standard stainless-steel anchor clips and hold-down devices for bolted connections.

END OF SECTION 067413

Statement of Work for FLARE Platform Structure (C-FAC-SOW-132) 23

Scale: 1/4":1'-0"

FLOOR PLAN EL 111'-2"

Scale: 1/4":1'-0"

PARTIAL PLAN EL 120'-0"

Sht. 2

Sht. 2

Sht. 2

Sht. 2

Sht. 3

Sht. 3

Sht. 3

Sht. 3

Sht. 3

Sht. 3

Sht. 4

SIM.

Sht. 3

Sht. 3

Sht. 4

Sht. 4

Sht. 4

Sht. 4 lmorris Fab_Stamp

Scale: 1/4":1'-0"

ELEVATION

Scale:1/4":1'-0"

ELEVATION

REMOVABLE FRP GUARDRAIL DETAIL

Scale: 1":1'-0"

TYPICAL SPLICE DETAIL @ 10"X10" POST

Scale: 1 1/2":1'-0"

Sht. 3

Sht. 3

Sht. 3

Sht. 3

Sht. 4

TYPICAL CONNECTION DETAILS

C15 KNEE BRACE CONNECTION

WF12/S12 KNEE BRACE CONNECTION

WF8 KNEE BRACE CONNECTION

WF TO WF CONNECTION

Scale: 1":1'-0"

Scale: 1":1'-0"

Scale: 1":1'-0"

Scale: 1":1'-0"

6" POST PLAN

6" POST SECTION

Scale: 1 1/2":1'-0"

TYPICAL BASE PLATE DETAILS

10" POST PLAN

10" POST SECTION

Scale: 1 1/2":1'-0"

SECTION

Scale: 1 1/2":1'-0"

SECTION

SECTION

Scale: 1":1'-0"

Scale: 1":1'-0"

SECTION

Scale: 1":1'-0"

SECTION

G10 INSULATOR TYPICAL DETAIL

Scale: 1":1'-0"

Scale: 1":1'-0"

SECTION

Sht. 4

Scale: 1 1/2":1'-0"

SECTION

Scale: 1":1'-0"

SECTION

Scale: 1":1'-0"

SECTION

Sht. 4

SECTION

Scale: 1":1'-0"

Sht. 4

SECTION

Scale: 1":1'-0"

Scale: 1":1'-0"

SECTION

SECTION II

PRINCETON PLASMA Part I PHYSICS LABORATORY Sample Subcontract

SUBCONTRACT AGREEMENT

FOR CONSTRUCTION

Name and Address of Subcontractor Subcontract No.: S0XXXXX

Effective:

FLARE Platform Construction

This is a subcontract (the "Subcontract") between the party above named (the "Subcontractor") and The Trustees of Princeton University, represented by the Princeton Plasma Physics Laboratory (“PPPL”) (hereinafter called "Princeton", "Princeton Plasma Physics Laboratory’, "PPPL", or "Buyer"), the latter acting under Prime Contract No. DE-ACO2-09CH11466 with the United States of America (hereinafter called the "Government"), represented by the United States Department of Energy (hereinafter called the "Department").

PPPL and Subcontractor may be collectively referred to as the “parties”.

This Subcontract does not bind nor purport to bind the Government of the United States.

The parties do mutually agree as follows:

ARTICLE I - STATEMENT OF WORK

1. The Subcontractor agrees to provide all necessary material, equipment, labor and supervision and perform the requirements of PPPL Statement of Work for “FLARE Platform Structure”, C-FAC-SOW-132, Revision 1, dated April 11, 2019 (Subcontract Part II) and other requirements that may be incorporated into this Subcontract.

2. The parties have agreed that the Subcontractor’s safety supervisor must be an OSHA competent person as defined by 29 CFR 1926.32(f).

3. The parties have further agreed that the following individuals are hereby designated as a

“Key Person” as defined in General Provisions Clause A27 (Subcontract Part II).

Project Manager:

On-Site Supervisor:

Safety Supervisor:

ARTICLE II - SUBCONTRACT FIXED-PRICE

The Subcontractor agrees to perform the work defined in Article I - STATEMENT OF WORK for the Firm Fixed Price of ________________________________________ dollars ($_____________).

ARTICLE III - TIME OF PERFORMANCE

The parties agree that Subcontractor shall complete all work required by this subcontract no later than 180 calendar days after date of Subcontract award.

ARTICLE IV - CONSTRUCTION SCHEDULE

The Subcontractor shall, within fifteen 15 calendar days after date of subcontract award on the Subcontract or another period of time determined by PPPL, prepare and submit to PPPL for approval three copies of a practicable schedule showing the order in which the Subcontractor proposes to perform the work, and the dates on which the Subcontractor contemplates starting and completing the several salient features of the work (including acquiring materials, plant, and equipment). The schedule shall be in the form of a progress chart of suitable scale to indicate appropriately the percentage of work scheduled for completion by any given date during the period. If the Subcontractor fails to submit a schedule within the time prescribed, PPPL may withhold approval of progress payments until the Contractor submits the required schedule.

If, in the opinion of PPPL, the Subcontractor falls behind the approved schedule, the Subcontractor shall take steps necessary to comply with the approved schedule without additional cost or price increase to PPPL.

ARTICLE V - TECHNICAL AND ADMINISTRATIVE REPRESENTATIVES

1. The following technical and administrative representatives are designated for this subcontract:

Subcontractor Representative:

Phone Number EMail

Princeton’s Representatives:

Technical (a.k.a.

PTR):

Phone Number Email

Administrative (a.k.a.

Procurement Specialist):

Michael Chen (609) 243-2428 mchen2@pppl.gov

2. Princeton’s Technical Representative (PTR) will be…