Communications site plan - North.pdf

PDF 2 MB Posted

Attached to
Overhead Power Lines
Solicitation number
Power1
Issued by

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1075445152E Line

1075445152E Rectangle

1075445152E Rectangle

1075445152E Line

1075445152E Rectangle

1075445152E Line

1075445152E Line

1075445152E Callout New trafficc rated communications handhole.

1075445152E Callout 2 - 4" schedule 40 PVC conduits.

1075445152E Line

1075445152E Callout New handhole

1075445152E Polygonal Line

1075445152E Line

1075445152E Line

1075445152E Callout 2 - 4" schedule 40 PVC conduits from handhole- Install up and into bldg below the existing work surface.

1075445152E Callout 1 - 4" schedule 40 PVC conduit between handhole and the fence.

1075445152E Callout Remove concrete as needed to install conduit. Replace with topsoil and grass seed.

1075445152E Callout Install conduit inside of fence, turn up to 3' above grade and provide a weatherhead.

1075445152E Typewritten Text Communications Site Plan - North

1075445152E Typewritten Text Project: WYTD972007 Repair OH Electrical Lines 5 November 20

1075445152E Typewritten Text General Notes:

1. All conduit is a minimum of 24" below grade. Provide marking tape 12" above conduits.

2. Provide pull strings in all conduits.

3. Maintain 12" of separation between these conduits and electrical conduits.

4. Maintain 3" of seperation between communications conduits.

5. Communications handholes shall be traffic rated unless they are more than 10' from any adjacent pavement and not noted as such.

6. Field verify existing dimensions and conditions.

7. Hand dig around existing utilities a minimum of 24" on each side.

8. Contact the Contracting Officer's representative a minimum of 5 days prior to performing any underground excavations to have existing utilities located. Mark the location of the proposed excavations a minimum of 3 days prior to performing any work and submit a site plan of the area to be excavated with an FA Form 103, Work Clearance Request.