This file contains a Request for Information (RFI) issued post-cancellation of Solicitation No. W9127N26BA019 for TDA AWS Backup Debris Management. The RFI consists of thirteen questions designed to gather feedback from potential contractors regarding barriers to bidding on the cancelled solicitation.

The questions address multiple constraining factors identified in the original solicitation, including the Washington State Professional Engineer (PE) requirement, prescriptive Products and Services (P&S) specifications that limited manufacturer willingness to build the product, CMMC Level 2 cybersecurity certification requirements, Buy American Act compliance, and solicitation access challenges. Additional questions seek contractor input on alternative approaches that would increase bidding likelihood if the requirement is re-solicited, identification of high-risk components, constructability challenges, potential cost impacts of regulatory requirements, and whether alternative acquisition strategies such as Design-Build would improve contractor participation and pricing. The RFI does not specify a response deadline, award date, pricing terms, or other contract execution details, as it is a post-cancellation feedback mechanism intended to inform potential future re-solicitation of this debris management requirement.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFI/Question # RFI / Question 1 Why did you not provide a bid?

Did the Washington State PE Requirement cause issues when preparing your bid or deciding not to bid?

What P&S requirements were too prescriptive that caused the manufacturers not to be willing to build this product?

What alternatives, if approved, would make you more likely to submit a bid/proposal for this requirement if re-solicited?

Was the CMMC Level 2 requirement a limiting factor? Why or why not? Did it add to cost, if so what percent?

Were there problems gaining access to the solicitation drawings because of the CMMC Level 2 requirement? If so, what were the difficulties or limiting factors? Did this requirement prevent you from submitting a bid?

If not willing to obtain CMMC Level 2 Self Certification, why not? Is there a particular barrier that makes the process difficult or undesirable for them?

8 What elements or criteria in the solicitation were the limiting factors? Why?

9 Was the Buy American Act requirement a limiting factor? Why or why not?

What do you consider to be the highest risks parts or components on this project and how would you like to see changes made?

11 What would you like to see to make this project objective more successful?

Would a different acquisitions type (Design-Build) be more favorable to contractors to bid and decrease price?

What other constructability challenges would you highlight for the government to consider changes?

Requests for Information (RFI's) Post-Cancellation of Solicitation No. W9127N26BA019 TDA AWS Backup Debris Management