The document is a Post-Award Schedule for a GSA lease solicitation (4WA0675) detailing the timeline for design, construction, and space acceptance. The schedule outlines 10 key activities spanning 322 total working days, starting within 5 working days of lease award. Critical milestones include 83 working days for Lessor-Provided Design Intent Drawings, 60 working days for Government Review of Construction Drawings, 102 working days for Lessor Completion of Construction Work, and 14 working days for Government Inspection and Acceptance of the finished space.

The solicitation seeks 25,000-26,250 square feet of office space in the Seattle metropolitan area (including Burien, SeaTac, Tukwila, and Renton), with specific location boundaries and requirements. Key agency requirements include on-site parking for three government vehicles, proximity to public transit, airport access, security level specifications, and space configuration guidelines. The lease term is 17 years with a 15-year firm term, and the government will utilize an 8-year amortization period for Tenant Improvements and Building Specific Amortized Capital, with allowances of $78.41 per ABOA SF for TI and $12.00 per ABOA SF for BSAC.

View the file

Other files

File Type Posted
4WA0675 - MEPS - DA - Updated.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AAAP POST-AWARD SCHEDULE, PAGE 1 OF 1 PSA VERSION - REV (10/22)

AAAP Project Specific Advertisement (PSA) Attachment: Post-Award Schedule

This attachment details the post-award schedule for this project. It hereby replaces the Attachment referenced in section

1.05 of the RLP (R100) and should be used when reviewing section 4.01 of the Lease (L100).

The below post-award schedule commences within 5 working days of lease award. The time frames below apply to the management of the design and construction process, concluding at the date of acceptance for the space.

Activity Working Days

Lessor-Provided Design Intent Drawings 83

Government (GSA and Client) Review and Approval of Lessor Provided Design Intent Drawings

Lessor Preparation and Submission of Construction Documents 13

Government Review of Construction Drawings 60

Lessor Preparation and Submission of the TI and BSAC Price Proposal

Government Reviews and Approves Pricing 15

Government Issues Notice to Proceed with Construction 5

Lessor Completes Construction of TIs and Completion of Other Required Construction Work

Government Inspects and Accepts Finished Space 14

AAAP POST-AWARD SCHEDULE, PAGE 2 OF 2 PSA VERSION - REV (10/22)

Total Work Days from Lease Award to Government Acceptance 322