AAAP POST-AWARD SCHEDULE, PAGE 1 OF 1 PSA VERSION - REV (10/22)
AAAP Project Specific Advertisement (PSA) Attachment: Post-Award Schedule
This attachment details the post-award schedule for this project. It hereby replaces the Attachment referenced in section
1.05 of the RLP (R100) and should be used when reviewing section 4.01 of the Lease (L100).
The below post-award schedule commences within 5 working days of lease award. The time frames below apply to the management of the design and construction process, concluding at the date of acceptance for the space.
Activity Working Days
Lessor-Provided Design Intent Drawings 40
Government (GSA and Client) Review and Approval of Lessor Provided Design Intent Drawings 50
Lessor Preparation and Submission of Construction Documents 55
Government Review of Construction Drawings 55
Lessor Preparation and Submission of the TI and BSAC Price Proposal 30
Government Reviews and Approves Pricing 40
Government Issues Notice to Proceed with Construction 10
Lessor Completes Construction of TIs and Completion of Other Required Construction Work 180
Government Inspects and Accepts Finished Space 15
AAAP POST-AWARD SCHEDULE, PAGE 2 OF 2 PSA VERSION - REV (10/22)
Total Work Days from Lease Award to Government Acceptance 475