Post Award Schedule - AAAP Advertisement 6VA0715.pdf
PDF 185 KB Posted
- Solicitation number
- 6VA0715
About this file
This document is a Post-Award Schedule attachment for an AAAP (Adaptive and Flexible Real Property Lease) Project Specific Advertisement (PSA), detailing the timeline for design and construction activities following lease award.
The schedule establishes a 205 working day timeline commencing within 5 working days of lease award, governing the management of the design and construction process through government acceptance of the space. Key milestones include: Lessor-Provided Design Intent Drawings (25 days); Government (GSA and Client) Review and Approval (15 days); Lessor Preparation and Submission of Construction Documents (20 days); Government Review of Construction Drawings (15 days); Lessor Preparation and Submission of TI and BSAC Price Proposal (15 days); Government Review and Approval of Pricing (20 days); Government Notice to Proceed with Construction (5 days); Lessor Completion of Construction of TIs and Other Required Construction Work (80 days); and Government Inspection and Acceptance of Finished Space (10 days). This attachment replaces the attachment referenced in section 1.05 of the RLP (R100) and should be used when reviewing section 4.01 of the Lease (L100). The document is the PSA Version-Rev (04/26).
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Delineated Area Map.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AAAP POST-AWARD SCHEDULE, PAGE 1 OF 1 PSA VERSION - REV (04/26)
AAAP Project Specific Advertisement (PSA) Attachment: Post-Award Schedule
This attachment details the post-award schedule for this project. It hereby replaces the Attachment referenced in section
1.05 of the RLP (R100) and should be used when reviewing section 4.01 of the Lease (L100).
The below post-award schedule commences within 5 working days of lease award. The time frames below apply to the management of the design and construction process, concluding at the date of acceptance for the space.
Activity Working Days
Lessor-Provided Design Intent Drawings 25
Government (GSA and Client) Review and Approval of Lessor Provided Design Intent Drawings
Lessor Preparation and Submission of Construction Documents 20
Government Review of Construction Drawings 15
Lessor Preparation and Submission of the TI and BSAC Price Proposal 15
Government Reviews and Approves Pricing 20
Government Issues Notice to Proceed with Construction 5
Lessor Completes Construction of TIs and Completion of Other Required Construction Work
Government Inspects and Accepts Finished Space 10
Total Workdays from Lease Award to Government Acceptance 205