Post Award Schedule - AAAP Advertisement 6NC0195.pdf

PDF 185 KB Posted

Attached to
Lease of Office Space within Raleigh, NC. Request for Lease Proposals (RLP) #26NAT02
Solicitation number
6NC0195
Issued by

About this file

This is a Project Specific Advertisement (PSA) attachment that establishes the post-award schedule for a GSA lease project involving tenant improvement (TI) and base, structural, and architectural components (BSAC) work. The schedule commences within 5 working days of lease award and governs the design and construction process through final government acceptance of the space. The total timeline spans 205 working days from lease award to government acceptance.

The post-award schedule specifies sequential activities with defined timeframes: Lessor-Provided Design Intent Drawings (25 days), Government GSA and Client review and approval (15 days), Lessor preparation and submission of construction documents (20 days), Government review of construction drawings (15 days), Lessor submission of TI and BSAC price proposal (15 days), Government pricing review and approval (20 days), Government issuance of Notice to Proceed (5 days), Lessor construction completion (80 days), and Government inspection and acceptance (10 days). This attachment supersedes the attachment referenced in section 1.05 of the RLP (R100) and should be used when reviewing section 4.01 of the Lease (L100).

View the file

Other files

File Type Posted
Delineated Area Map.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AAAP POST-AWARD SCHEDULE, PAGE 1 OF 1 PSA VERSION - REV (04/26)

AAAP Project Specific Advertisement (PSA) Attachment: Post-Award Schedule

This attachment details the post-award schedule for this project. It hereby replaces the Attachment referenced in section

1.05 of the RLP (R100) and should be used when reviewing section 4.01 of the Lease (L100).

The below post-award schedule commences within 5 working days of lease award. The time frames below apply to the management of the design and construction process, concluding at the date of acceptance for the space.

Activity Working Days

Lessor-Provided Design Intent Drawings 25

Government (GSA and Client) Review and Approval of Lessor Provided Design Intent Drawings

Lessor Preparation and Submission of Construction Documents 20

Government Review of Construction Drawings 15

Lessor Preparation and Submission of the TI and BSAC Price Proposal 15

Government Reviews and Approves Pricing 20

Government Issues Notice to Proceed with Construction 5

Lessor Completes Construction of TIs and Completion of Other Required Construction Work

Government Inspects and Accepts Finished Space 10

Total Workdays from Lease Award to Government Acceptance 205