This document is a Performance Work Statement (PWS) for the maintenance, repair, and chemical balancing of swimming pools and an in-ground hot tub chlorination systems at the Aquatics Center on Peterson Space Force Base in Colorado.
The key details are:
- The contractor will provide all management, tools, materials, equipment, and labor to maintain, repair, and chemically balance the main pool, wader pool, and in-ground hot tub at the Aquatics Center.
- The contractor must have proper certifications, including a Certified Pool/Spa Operator (CPO) or Aquatic Facility Operator (AFO) certification, and be familiar with the specific equipment at the facility.
- The contractor will perform routine maintenance and service calls, respond to emergencies, conduct chemical testing, and maintain healthy water balance for the pools and hot tub.
- The contractor is responsible for providing all required materials and parts, as well as managing hazardous materials and waste in accordance with environmental regulations.
- The PWS includes performance objectives, government-furnished property, hours of operation, and contractor personnel requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sources Sought Pool Mx.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE WORK STATEMENT FOR
MAINTENANCE, REPAIR, AND CHEMICAL BALANCING OF SWIMMING POOLS AND IN-GROUND
HOT TUB CHLORINATION SYSTEMS
6 March 2024
PETERSON SPACE FORCE BASE COLORADO
PERFORMANCE WORK STATEMENT FOR
MAINTENANCE, REPAIR, AND CHEMICAL BALANCING OF SWIMMING POOLS AND IN-GROUND HOT TUB CHLORINATION SYSTEMS
1. DESCRIPTION OF SERVICES. The Contractor will provide all management, tools, materials (including chemicals), equipment and labor necessary to maintain, repair, chemically balance and test the swimming pool chlorination system for the main pool, the wader pool, and in-ground hot tub (herein after the main and wader pools can be referred to as pools) for the Aquatics Center, Building 404, as defined in this Performance Work Statement (PWS) for Peterson Space Force Base (PSFB), Colorado. The Contractor shall have proper certifications (PWS para. 8.3 & 8.4) and have extensive knowledge pertaining to commercial swimming pool systems including related mechanical equipment, hydraulics, water chemistry, and overall operation. Perform in accordance with (IAW) all applicable industry standards, federal, state, and local requirements as required in the performance of the work. Work must be performed IAW 1) Colorado Department of Public Health and Environment 5 CCR 1003-5, “State Board of Health Regulations Pertaining to Swimming Pools and Mineral Bath”, Standards of the National Sanitation Foundation, and 2) the current Air Force Manual (AFMAN) 48-114, Recreational Waters and Mission Training Pool. If the bodies of water (Wader, Hot Tub, and/or Main Pool) becomes inoperable for 28 days or longer and no service needed the vendor will not invoice for water maintenance/ routine service and/or for chemicals for that or those bodies of water.
1.1 OPERATIONAL REQUIREMENTS AND SPECIFIC TASKS.
1.1.1 During routine maintenance checks or routine/emergency service calls, report any repairs needed or inoperable parts to the 21st Civil Engineer Squadron (CES) Contracting Officer Representative (COR). The monthly fixed price includes all inspections, maintenance, repairs, replacements, parts/chemicals, and routine service calls. All replacement parts/materials required in the performance of this Pool Chlorination Service requirement shall be provided as an integral part of performance. The contractor is liable for all maintenance supplies up to $500 per visit. The main pool must be operational 95% of the time, the wader pool and hot tub must be operational 90% of the Aquatic Center operation time (see Appendix 1). The Contractor will notify the COR each time they arrive on site for routine maintenance or routine/emergency service calls.
1.1.2 Routine Maintenance. Schedule routine maintenance during normal duty hours (see para 5.1.1) to perform all required checks and balances of the main pool, wader pool and in-ground hot tub for the Aquatics Center, building 404, as defined in this Performance Work Statement and hot tub chlorination systems, including pH chemical analysis and chlorine levels. Maintain the carbon dioxide (CO2) for both bodies of water to include the purchase and delivery of the CO2. The settings on the controller will determine how much CO2 is pulled to support the system. The Contractor shall ensure the tank containing the C02 does not run empty before the next fill. Check and calibrate the water quality in the main pool, wader pool and hot tub to maintain the chemical levels no less than once per month. Time on site ranges from 2 to 6 hours depending on the maintenance needing to be performed. If a federal holiday falls on a service day, routine maintenance will take place the next business day. IAW AFMAN 48-114, Table 4.1 and Colorado 5 CCR 1003-5, Section 4.7 Table 1, confirm chlorination system is functioning, or proper coordination with facility staff has been made regarding any issues or concerns prior to leaving the facility.
1.1.2.1 Pulsar Chlorine Feeders. Contractor shall clean all chlorine feeders no less than once a month. The chlorine feeders shall be replaced as needed or at least every six months. Remove excess chemical residue on the internal and external components and tubing. Notify COR if replacement parts are needed. Use ONLY manufacturer-approved liquid chlorine in the chlorinators. The Briquettes are required to use only Plus Briquettes in the chlorinators. The Contractor shall ensure sufficient chorine and briquettes are available to the pools via the chlorine feeders between Contractor scheduled visits.
1.1.2.2 Service Calls. When a service call is required, the COR will provide a call number and identify if the call is routine or emergency. For each service call the Contractors limit of liability will be $500 for parts and/or materials per call out. The Contractor shall obtain approval from the COR prior to purchase and installation. The Contractor shall not consolidate requirements or parts lists from multiple service calls in an effort to exceed the threshold. Request for approval shall include the manufacture, part number, and purpose or required part(s), and only the contractor’s Shipping and Handling Fee shall be applied to the cost of the parts. The Contractor shall not proceed with ordering or installing parts without approval from the Contracting Officer. If approval is granted, the Contracting Officer will provide authorization and a task order, modification or Government Wide Purchase Card with funding for the additional parts.
1.1.2.3 Routine Service Calls. In the case of a malfunction of chlorination system during normal duty hours, listed in paragraph 5.1.1, report to the Aquatic Center within four (4) hours. Troubleshoot and correct the malfunction. Keep downtime within the prescribed limits listed in Section 2, Service Summary. Confirm chlorination system is functioning correctly before leaving the facility. See appendix 1 for further details.
1.1.2.4 Emergency Service Calls. The Aquatics Center operates during other than normal duty hours on weekends. Respond to emergency service calls within two (2) hours. In the event of a suspected or confirmed outbreak of infectious disease, the Contractor shall be notified to super chlorinate or shock treat the pools. See Appendix 3, Definitions for “shock treatment,” “routine shock," and "intervention shock.” See appendix 1 for further details.
1.2 CHEMICAL TESTING. Test the pools and hot tub for free chlorine residual, combined chlorine, and pH levels standards listed in AFMAN 48-114, Table 4.1, and Colorado 5 CCR 1003-5, Section 4.7 Table 1 at a minimum of once a month. The Contractor is responsible for testing while on site. The pool staff is responsible for testing the pools every 2 hours and the hot tub every hour. Maintain free available chlorine levels at 1 – 4 parts-per-million (ppm) for pools and 3 – 5 ppm for the in-ground hot tub. Maintain the pH between 7.2 – 7.8 for all bodies of water. Test total alkalinity in pools monthly and in hot tub each routine maintenance visit; total dissolved solids every month; and calcium hardness every month IAW AFMAN 48-114, Table 4.1 during regular routine maintenance service. Provide a hard copy of Chemical Usage List and Work Log (see Appendix 6 for sample) documenting test results for each service to the Aquatic Center at time of testing. A copy of the completed Chemical Usage List and Work Log shall be left at the pool office after every visit.
1.2.1 CHEMICALS. The contractor shall provide all chemicals for the performance and maintenance of the main pool, wader pool and in-ground hot tub for the Aquatics Center, building 404 to meet the requirements of this PWS.
1.3 MAINTAIN HEALTHY WATER BALANCE. Disinfect and oxidize all bodies of water to ensure sanitary water conditions to include water clarity (see definitions in Appendix 3). Backwash filters and clean hair catcher as required at each visit. Backwash, super chlorinate, dilute and/or replace water as needed for the in-ground hot tub. Drain and fill the hot tub as needed or at a minimum once per month. Backwash the main pool as needed in regard to diminishing flow rate estimated twelve (12) times per year. If issues occur when performing backwash on the main pool, the Contractor shall contact CE Water and Fuels Systems Maintenance Shop at 719-556-1489 so a plumber can be present during backwashing. If there is no answer, contact CE customer service at 719-556-4030 so that they can notify the shop. Coordinate with COR for super chlorination, dilution, and water replacement in the main pool if the total dissolved solids make the water too aggressive (see definitions in Appendix 3). Balance the water IAW AFMAN 48-114.
1.4 MATERIALS AND REPAIRS. Provide all materials and parts required for the maintenance and repair of the three pool chlorination systems to include pumps, pump controllers, and all filtration system components. Contractor shall maintain equipment IAW the manufacturer’s recommended procedures. Maintenance or repair in of this system shall be IAW normal commercial practices using parts specified by the manufacturer or items of equal to or better quality. The Contractor shall maintain a bench stock of commonly required materials for equipment to reduce pool downtime. These items may include BECS Chemical Controller Sensors, circuit boards, Pulsar Chlorination discharge valves, emergency overflow valves, solenoids, booster pumps, CO2 feeder solenoid valves, flow selectors, etc. These items shall be stored at the Contractor’s office/warehouse/ service vehicles. The Contractor shall stock necessary chemicals at all times. In the event any delay is encountered on delivery of any materials, the COR shall be notified immediately. The Contractor shall provide warranty on materials and labor.
1.5 SHUTDOWN/STARTUP. The Contractor shall, at the request of the CE COR, drain the wader pool, and/or the hot tub (see Appendix 1, Estimated Workload); however, if the swimming pool needs to be drained it will be accomplished by 21 CES personnel. Routine maintenance will not be required for a period of time (usually a week to ten days) and will be coordinated with COR in advance. Contractor shall be contacted by the COR when the body of water (swimming pool, wader pool, or the hot tub) is refilled to adjust the chlorination system IAW AFMAN 48-114.
1.6 CHEMICAL RECORDS. Document and maintain a monthly HAZMAT Chemical Usage Report, (see Appendix 7) indicating the chemical usage sorted by Material Stock Number (MSN) for the previous month, due within 5 days of end of month. Provide an electronic copy of the report to the installation HAZMART in Building 652. Please see deliverable section for further information.
1.7 Deliverables. The Government will provide a binder for the contractor to maintain all appropriate deliverables in accordance with Appendix 8. The documents that are included in the binder will be AF Form 3952 and Appendices 6 and 7.
2. SERVICES SUMMARY (SS): The contract service requirements are summarized in Performance Objectives that relate directly to mission essential items. The performance threshold represents the minimum acceptable level of performance. Performance Objectives, Performance Thresholds and other PWS requirements will be assessed regularly by a COR, unless otherwise specified. The Contractor is responsible for the satisfactory completion of all tasks required by this Performance Work Statement, whether listed in the Service Summary or not. All Service Summary items are evaluated monthly unless otherwise stated.
| PERFORMANCE OBJECTIVE |
| PWS PARA |
| PERFORMANCE THRESHOLD |
| 1. Operational Requirements. |
| Para 1.1. |
| Main pool must be operational 95% of the Aquatic Center operation time and the wader pool/ in-ground hot tub must be operational 90% of the Aquatic Center operation time. (See Appendix 3 for definition and calculations). |
| 2. Perform Routine Maintenance |
| Para 1.1.1, |
1.1.2.
No more than 2 validated customer complaints per month.
| 3. Respond to Routine Service Calls and Emergency Service Calls |
| Para 1.1.3.1; |
1.1.3.2 Respond within 4 hours for routine calls and 2 hours for emergency calls, 98% of the time.
| 4. Deliverables |
| Para 1.7 |
| Reports need to be kept updated and have no more than one document outdated per month. |
3. GOVERNMENT-FURNISHED PROPERTY AND EQUIPMENT. N/A
4. GENERAL INFORMATION
5. HOURS OF OPERATION.
5.1.1 Normal Duty Hours. The Contractor shall perform routine maintenance and routine service calls (para 1.1.3.1) required under this contract during the normal duty hours. The current hours are listed below but hours are subject to change. The contractor will be notified if hours are changed to adjust the routine visits.
Monday, Wednesday, and Friday: 0600-1300 Tuesday and Thursday: 1100-1800 Saturday: 1000-1600 Sunday: Closed
5.1.2 Holidays. Routine maintenance, routine service calls, will not be required on any Federal holidays. With proper coordination with the COR the Contractor can elect to still conduct regular service on the holiday or the next business day.
| New Year's Day |
| Labor Day |
| Martin Luther King Day |
| Columbus Day |
| President's Day |
| Veterans' Day |
| Memorial Day |
| Thanksgiving Day |
| Juneteenth |
| Christmas Day |
Independence Day
6. ENVIRONMENTAL AND HAZARDOUS MATERIAL (HAZMAT) HANDLING.
6.1 Hazardous Material. Maintain Manufacturer’s Safety Data Sheets (SDS), see paragraph 6.2 below, on all hazardous materials used in the performance of this contract and make them available to the Government for review upon request. Dispose of all chemicals IAW Environmental laws and regulations listed in Appendix 5. If any of the materials used by the Contractor in the performance of this contract are considered hazardous, follow all local, state, and federal laws listed in Appendix 5, concerning hazardous materials and hazardous waste and pay all costs associated with the proper management and disposal of any hazardous waste. If required by law, licenses for employees in the use of hazardous materials shall be the responsibility of and at the Contractor’s expense. All chemicals used in the performance of this contract and transported to and on Peterson SFB, will comply with IAW DOT 49 CFR Parts 100-185. No chemicals will be stored on Peterson SFB. Report any instances of spills, leaks, and inadvertent release of hazardous materials to the fire department and the COR as soon as the event occurs.
6.2 Hazardous Materials Pharmacy (HAZMART) Requirement. Obtain, prepare, and provide an AF Form 3952, Chemical/Hazardous Material Request Authorization and Manufacturer’s SDS, to the base HAZMART, Building 652, for all hazardous materials to be used on Peterson SFB two weeks prior to bringing the new materials or supplies on base for use under this contract. No chemicals will be used on Peterson SFB prior to obtaining this approval. The Installation Hazardous Material Management Team will pre-approve/authorize all hazardous materials and chemicals brought and used on the installation by the Contractor per AFI 32-7086, Section 2.4.2. The Contractor will report the hazmat chemical usage monthly as stated in Section 1.6.
6.3 Hazardous Waste Management. Immediately contact the Peterson SFB 21 CES Environmental at (719) 556-6266 upon generating any waste that is regulated as hazardous. Per Section 6.1, Contractor shall be aware of requirements associated with Hazardous Waste. The Contractor is responsible for proper management. Any unusable product that the Contractor deems to be hazardous waste must be manifested off base. The Contractor is responsible to ensure that their personnel are trained by 21 CES Environmental per Section 6.7.
6.4 Green Procurement. In order to comply with the green procurement requirements of Section 6002 of Resource Conservation and Recovery Act of 1976 and Executive Order 13834, the Government requires the use of recycled and recovered materials, bio-based products, energy and water savings products, and environmentally preferable products. Recycled and recovered materials are identified by the EPA’s Comprehensive Procurement Guidelines, information available at https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program. Bio-Based products are identified by United States Department of Agriculture under Bio-Based products, information is available at http://www.biopreferred.gov. Environmentally preferable products are products that are less hazardous to the environment. Some products are certified by the Green Seal organization and information is available at http://www.greenseal.org/. These materials and products must meet the requirements of the PWS, must not delay the progress of the work, must be available from more than one source, and must not be cost prohibitive. Material and product submittals for all recycled-content items shall list the recycled and recovered materials used and the percentage content. Appendix 9 lists some environmentally preferable products with the percentage content that may apply to this. Track the purchase, quantities, and the percent of recyclable content for these materials throughout the life of the contract. At the end of the contract, consolidate and provide information as required by Federal Acquisition Regulation (FAR) 52.223-9 and send to the COR and Environmental Office.
6.5 Water Quality. Comply with the requirements of the Authorization for wastewater service, change in wastewater service or disconnection of wastewater service under CONTRACT NO. GS-00P-16-BSD-1216. Only discharge water/products into the sanitary sewer system. Prior to discharge, contact Waste Water Program Manager, 21 CES Environmental at (719) 556-7707.
6.6 Air Quality. Comply with all requirements of the Peterson SFB Air Permit located at http://www.cdphe.state.co.us/ap/downop/ep147p04.pdf. Contract shall coordinate a review of Air Permit requirements with the installation Air Quality Program Manager, 21 CES Environmental at (719) 554-2750 prior to performing any maintenance (routine or otherwise).
6.7 General Environmental Training Compliance. Within 1 month of contract start, the Contractor shall, at no cost to the Contractor, schedule environmental training with Peterson SFB environmental management staff at (719) 556-6266. Specifically training for: air permit compliance, Environmental Compliance and Management Program, Environmental Management System, Hazardous Materials Management (all training is required to be obtained by each employee who works on the contract. Each person is only required to obtain the training once during life of contract. If personnel change, all new employees must obtain training within 1 month of starting work on this contract) and RCRA Awareness Training and storm water pollution prevention training (annually). Should the Government suspect non- compliance (by audits, ECAMP findings, surveillances), a refresher course by Peterson SFB environmental management staff shall be given to the Contractor on an as-needed basis.
7 CONTRACTOR PERSONNEL.
7.2 Contractor Employees. Contractor shall not employ persons for work on this contract if such employee is identified to the Contractor as a potential threat to the health, safety, security, or operational mission of the installation and its population.
7.2.1 All employees shall present a neat appearance and be easily recognized as Contractor employees. Identification of all employees shall be accomplished by wearing badges or by Contractor-provided distinctive clothing bearing the name of the Contractor.
8 Permits, Licenses and Certifications.
8.2 Unless otherwise specified in this contract, obtain necessary permits, licenses, and certifications; give all required notices; and comply with applicable Federal, State, County, and local laws, codes, and regulations in performance of the requirements of this contract.
8.3 Certified Pool/Spa Operator (CPO) or Aquatic Facility Operator (AFO). Contractor employee(s) performing work on this contract must hold and maintain a current certification as a CPO or AFO throughout the life of the contract to work on the pools and hot tub chlorination systems.
8.3.1 Contractor employee must be familiar with the Pulsar Chlorinators and CO2 Feeders. The Contractor is responsible for ensuring all applicable service technicians are familiar with the equipment and operations of PSFB pools.
8.4 BECS Technology. All technicians who preform work on BECS Chemical Controller systems must acquire BECS certification and be familiar with and able to apply software updates to BECS Technology upon contract award.
8.5 Provide Copies. The Contractor shall provide a copy of all necessary licenses and certifications to the COR(s) at the time of award and within 10 calendar days of any new employee hire date. The Contractor shall maintain sufficient records of all necessary licenses and certifications and make these records available to the Government upon request within two (2) business days.
9 QUALITY CONTROL. The Contractor shall develop and maintain a quality program to ensure services are performed IAW commonly accepted commercial practices. Contractor shall develop and implement procedures to identify and prevent defective services from recurring. As a minimum, the Contractor shall develop quality control procedures that address the areas as identified in Section II, Service Summary submitted quarterly to the COR.
9.2 The Contractor shall provide a digital copy of their field report for each visit to be emailed to the COR or other CE personnel, upon request. The Contractor shall make general annotations and suggestions about equipment to the COR upon observation.
10 BASE REGULATIONS.
10.2 SECURITY REQUIREMENTS. IAW Department of Defense Instruction (DoDI) 2000.16V1 AFI 10-245 0 AFGM 2019 01, Antiterrorism (AT) Program Implementation, Para 3.20.7.A, Air Force Antiterrorism Standards, the Contractor will submit to a Colorado Crime Information Center (CCIC) and National Crime Information Center (NCIC) check prior to being granted access to the installation. Refusal to submit to the CCIC/NCIC check or a report of adverse information will result in denial of access to the Contractor. In addition, IAW Installation Security Instruction (ISI) 31-101, Para 6.2.8, the Contractor will obtain all necessary cards, passes, decals or other items required for access on Peterson SFB, including access for those employees who drive to work. Upon completion or termination of the contract, or termination of a Contractor employee, the Contractor will surrender any identification badges and vehicle identification to the Security Police at the Visitor’s Control Center. Final contract payment will not be made until all badges have been returned to the COR.
10.2.1 The Contractor will send a letter to the contracting office on company stationery, including its address, telephone number and contract number, listing the following for each employee requiring access to Peterson Space Force Base (PSFB): full names of employee(s), date of birth, driver’s license number, state the drivers licenses was issued, , After approval, the letter will be on file with the Security Police at the Visitor’s Control Center, where the employees may apply for a Contractor’s Identification Badge.
10.2.2 Physical Security. Safeguard all Government property at all times. At the end of each work period, the Contractor will secure all Government facilities, equipment, and materials.
10.2.3 Key Control. Ensure that all keys issued to the Contractor by the Government are not lost or misplaced and are not used by unauthorized persons. No keys issued to the Contractor by the Government will be duplicated. The Contractor will prohibit the use of keys issued by the Government by any persons other than the Contractor’s employees.
10.1.4 Report the occurrences of a lost key to the COR. The Government may, at its option, require the Contractor to replace, re-key, or reimburse the Government for replacement of locks or re-keying as a result of Contractor losing keys. In the event a master key is lost, stolen, or duplicated, the Government will replace all locks and keys for that system and the Contractor shall be responsible for all costs as appropriate.
11 PERFORMANCE OF SERVICES DURING CRISIS DECLARED BY THE NATIONAL COMMAND AUTHORITY. IAW Department of Defense Instruction (DODI) 3020.37, paragraph E2.1.1, a crisis situation is defined as: Any emergency so declared by the National Command Authority or the overseas Combatant Commander, whether or not U.S. Armed Forces are involved, minimally encompassing civil unrest or insurrection, civil war, civil disorder, terrorism, hostilities buildup, wartime conditions, disasters, or international conflict presenting a serious threat to DOD interests. The Contractor is not required to perform services during a crisis unless otherwise directed by an authorized Government representative.
11.2 The Contractor shall report all Contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the 21st Contracting Squadron, PSFB, CO 80914 via a secure data collection site. The Contractor is required to completely fill in all required data fields at http://www.ecmra.mil. Reporting inputs will be for the labor executed during the period of performance for each Government fiscal year (FY), which runs 1 October through 30 September. While inputs may be reported any time during the FY, all data shall be reported no later than 31 October of each calendar year. Contractors may direct questions to the CMRA help desk.
12 Contract Modification. In the event a repair is in excess of $500 the contract will be modified to include all cost over the $500. The vendor will contact CES COR to report the repairs needed or inoperable parts needed to replace. The vendor will provide a quote to the COR and the CO providing the required parts and material for the repair.
13 The Government has an estimation of 15 repairs under the liability threshold annually. As stated above all repairs need to be documented with the COR to allow for an annual evaluation and for historical purposes. These are estimation it is up to the Contractor to keep track of all call outs and repairs to be considered for a Request for Equitable Adjustment after the annual evaluation.
12.2 If any body of water is inoperable for at least 28 days or longer in the month the vendor will not invoice for the or those body(s) of water. Depending on the required service or chemicals to prevent excessive cleaning the vendor may be able to invoice for all or some of the CLIN.
10 APPENDICES.
APPENDIX 1 -- WORKLOAD ESTIMATES.
1. Routine Maintenance. The Government estimates twelve (12) routine maintenance visits, with an average of seventy-two (72) hours per contract year.
2. Routine Service Calls. The Government estimates seventy-two (72) hours for routine calls per contract year.
3. Emergency Service Calls. The Government estimates sixteen (16) hours for emergency calls per contract year.
4. Aquatic Center. Operational time average is one hundred sixty-four (164) hours per month.
5. Backwash Pool(s). Approximately twelve (12) times per year. Backwash will be performed during routine maintenance hours.
6. Hot Tub. The Government estimates two (2) hours per drain and approximately 12 times a year.
7. Wader Pool. The Government estimates four (4) hours per drain.
APPENDIX 2 – SYSTEMS TO BE MAINTAINED
1. Main pool 241,133 gallons/4,979 cu ft., wader pool 1,620 gallons/400 cu. ft. and in-ground hot tub is 900 gallons.
2. Three (3) BECS System 5 Technology
3. Two (2) Pulsar I Hypo-chlorite Feed System (Wader Pool), Model #SF4W
4. Two (2) Stingl (Safety Vacuum Relief System) Model #SR500
5. Four (4) Whisper Flow Pumps. Model #WFE-4
6. One (1) Pentair Clean and Clear Cartridge Filter System
7. National Line CO2 Feeder, Model #NCS-CF-CO2-0030
8. Spa Control, Model #AS-TD-COMBO-95
9. Aquatic Control Technology CO2 Feeder, Model #12965
10. Bulk CO2 System Tank, Max 750 gallons
11. Levelor Electric Water Fill System, Model #K1100
12. EPD Automatic High-Rate Sand Filtration System, Model #2-0014-009
13. Facility and Mechanical Room Key, return to COR at end of contract. Do not duplicate keys.
14. Bulk Chlorine Storage Tank, 165 gallons
15. Two (2) Adjustable speed Stenner pumps, Model #45MP2 & 85M5
APPENDIX 3 -- DEFINITIONS
Aggressive Water: Water with corrosive properties due to low pH, calcium hardness, and/or total alkalinity. If the pH is lower than the standard stated used, then that is too aggressive.
Aquatic Facility Operator: An individual who has satisfied the 18-hour course designed to provide information and training for both supervisory and operations personnel responsible for operating clean, safe, and efficient facilities in public, hotel, condo, semi-public and municipal pool, or water park facilities. Certification is valid for 3 years.
Bio-Based Products: means a product determined by the Secretary of Agriculture to be a commercial or industrial product (other than food or feed) that is composed, in whole or in significant part, of biological products or renewable domestic agricultural materials (including plant, animal, and marine materials) or forestry materials OR an intermediate feedstock.
Calcium Hardness: The calcium portion of the total hardness. The level of calcium determines whether water is overly “soft” (too little) or “hard” (too much). Excessively high hardness levels (over 600 ppm) may cause cloudy water and scale. Excessively low levels (under 150 ppm) may harm the pools.
Carbon Dioxide (CO2) Gas: This gas is used to lower the pH level in water.
Certified Pool & Spa Operator: Individual who has satisfied the class work requirements and demonstrated knowledge of course material by passing the examination administered by National Swimming Pool Foundation certified instructors. Certification is valid for 5 years.
Clarity: The degree of transparency of pool water. Determined by the ability to see the deep end pool drain when standing at the shallow end of pool or by use of a turbidity meter.
Combined Chlorine: The chemical species that forms when chlorine chemically bonds to nitrogen- containing compounds like urine, perspiration, dead algae, etc. Combined chlorine can cause eye and skin irritation and has a strong chlorine-like order.
Dilution or Water replacement: Replacing all or some of the water is primarily because over time, salt from perspiration and other non-organic contaminants--the Total Dissolved Solids (TDS) will increase to levels causing cloudiness or other problems. Although organics are destroyed by your sanitizer system, TDS levels continue to increase over time. It is commonly recommended that the TDS should not exceed 1500 ppm (mg/L) higher than the TDS when the pool or spa was started up.
Disinfection: The process of destroying micro-organisms that might cause disease.
Down Time: Non-operational time. Main pool downtime is calculated by the Aquatic Center total operational hours divided by 5%. For example, 262 monthly hours / 5% = 13 hours monthly downtime. The wader pool and in-ground hot tub down time is calculated by Aquatic Center total operational hours divided by 10%. For example, 262 monthly hours / 10% = 26 hours monthly downtime. Monthly operational hours are subject to change and down time calculations will be adjusted accordingly.
Downtime calculations for the purpose of performance thresholds will only be inclusive outages that are a direct result of contractor action or negligence. Downtime that is a result of equipment failure will not be included in performance threshold calculations. Downtime is exclusively related to a failure of the Contractor to properly operate the system. Because it is a Contractor related failure, the Contractor’s response time will be included in the overall downtime calculation. For example: the Contractor performs his routine maintenance Wednesday morning at 8:00am, and then the pool goes down at 10:00am because the chemical levels were not properly adjusted. If it takes the Contractor 2 hours to respond to the pool and another hour to fix his mistake the overall downtime will be calculated to be 3 hours.
Emergency Service Call: When a problem exists within all bodies of water, causing a pool to be nonoperational.
Free Chlorine Residual: The portion of total chlorine that is not combined chlorine and is available as disinfectant. The portion of total chlorine that reacts with Diethyl-p-phenylenediamine (DPD).
Green Seal Organization: Green Seal is a non-profit organization that uses science-based programs to empower consumers, purchasers, and companies to create a more sustainable world.
Materials: On a Time and Material Contract chemicals and parts are considered materials.
Oxidation: The process of changing the chemical structure of water contaminants by increasing the number of oxygen atoms or reducing the number of electrons in the contaminant.
Oxidation Reduction Potential (a.k.a. ORP): A method of measuring the potential, which often relates to the concentration of an oxidizer in the water. ORP probes send signals to electrical controllers that can open valves on chemical feeders to dissolve and release disinfectants into the water.
pH: The negative logarithm of the hydrogen-ion concentration of a water solution. A measure of the degree of acidity or alkalinity of a solution. A pH below 7.0 is considered acid. A pH above 7.0 is considered alkaline.
Sanitary Water Condition: Achieved by proper use of a disinfectant and is free of almost all pathogens as specified in chapter 5 of the National Swimming Pool Foundation Pool and Spa Operator Handbook.
Routine Maintenance: Maintenance scheduled in advance during normal duty hours to ensure systems remain operational. Maintenance is preventative in nature and not the response to a system failure.
Routine Service Call: In the case of a malfunction of a chlorination system during normal duty hours the Contractor will be required to respond within four (4) hours to troubleshoot and correct the malfunction.
Scale: Calcium carbonate deposits that can be found deposited in the filter, heater, or on the pool tile or wall. Generally caused by high calcium hardness, total alkalinity, temperature, and/or pH.
Shock treatment: The addition of an immediately available oxidizing disinfectant, routinely or as an intervention. A shock chemical must be effective against a wide variety of pathogens and nuisance microorganisms with a reasonable CT factor. The CT factor is the product of the residual disinfectant concentration [C] in mg/L and time [T] in minutes that the disinfectant is in contact with the water. In addition, a shock chemical should be capable of destroying organic contaminants and nitrogen compounds with a reasonable reaction time.
· Routine shock involves raising free-chlorine levels to a minimum of 10 mg/L for one to four hours weekly for pools and daily for spas.
· Intervention shock, for a water quality problem (e.g., accidental fecal release, algae, clarity, eye irritation), involves raising the free-chlorine residual to 20 mg/L for an eight-hour period when bathers are not present.
Super chlorination: The practice of adding large quantities of a chlorinating chemical to kill algae and microorganisms, eliminate slime, destroy odors, or improve the ability to maintain a disinfectant residual.
Total Alkalinity: A measure of the ability of the water to maintain a desirable pH when acid is added to the water. This value is usually expressed as the equivalent amount of calcium carbonate in either mg/L or ppm.
Total Dissolved Solids: The amount of residue that would remain if all the water evaporated or was removed. Expressed as the mass of solid per the total initial volume of water (ppm or mg/L). Typically measure by electrical conductance.
Turbidity: A measure of the amount of solid particles that are suspended in water and that caused light rays shining through the water to scatter and appear cloudy. In pool/spa water testing a standard reagent is added to a known sample of water. The reagent reacts with the unknown concentration of the sample causing the sample to turn cloudy in proportion to the concentration. The cloudiness or turbidity is then measured by use of a calibrated cell. Clarity and turbidity have a reverse relationship: the more turbidity, the less clarity.
WAWF-RA: Wide Area Workflow-Receipt and Acceptance. Electronic submission of payment request.
APPENDIX 4 – ACRONYMS AND ABBREVIATIONS
AFI: Air Force Instruction AFMAN: Air Force Manual AFO: Aquatic Facility Operator CES: Civil Engineer Squadron COR: Contracting Officer Representative
CPO: Certified Pool Operator
DODI: Department of Defense Instruction
EPA: Environmental Protection Agency
HAZCOM: Hazard Communication Regulatory Requirement HAZMART: Hazardous Materials Pharmacy Requirement IAW: In Accordance With Mg/L: Milligrams Per Liter
MSN: Material Stock Number
OSHA: Occupational Safety and Health Administration
ORP: Oxidation Reduction Potential
PPM: Parts-Per-Million
PWS: Performance Work Statement
RCRA: Resource Conservation and Recovery Act
SDS: Safety Data Sheets
SFB: Space Force Base
TDS: Total Dissolved Solids
WAWF-RA: Wide Area Workflow-Receipt and Acceptance
APPENDIX 5 - APPLICABLE PUBLICATIONS, FORMS, AND WEBSITES
5.1 Applicable Publications and Forms. The Contractor shall accomplish the tasks IAW this PWS and the references as set forth. In the event of a conflict between the PWS and any other document, this PWS shall take precedence for operation. Most current forms and publications can be access via the Internet at the following web site http://www.e-publishing.af.mil/. Supplements or amendments to listed publications from any organizational level may be issued during the life of the contract.
| PUBLICATIONS AND FORMS |
| TITLE AND APPLICABLE PARAGRAPH(S) |
| PWS |
PARA
Dept. of Public Health & Environment, Colorado 5 CCR 1003-5
| State Board of Health Regulations Pertaining to Swimming Pools & Mineral Baths (last amended 3/18/98, effective 4/30/98) |
| 1 |
| DOT 49 CFR Parts 107, 171-172, 177 |
| Part 107 Hazardous materials program procedures; Part 171 General information, regulations, and definitions; Part 172 Hazardous materials table, special provisions, hazardous materials information, and training requirements; Part 177 Carriage by public highway |
| 4.2.1 |
| Air Force Instruction (AFI) 32-7086 |
| Hazardous Materials Management (dated 4 Feb 2015) |
| 4.2.2 |
Air Force Manual
(AFMAN) 48-114
| Recreational Waters and Mission Training Pool, Chapter 4, Table 4.1., Chapter 5, paragraph 5.3.3. |
| 1 |
| Air Force (AF) Form 3952 |
| Chemical/Hazardous Material Request Authorization Safety Data Sheets (SDS) |
| 4.2.2 |
| Contact 21 CES Environmental at (719) 556-6266 |
| National Pollutant Discharge Elimination System Permit Waste Water Memorandum of Agreement with Colorado Springs Utilities |
| 4.2.6 |
| 45 CFR 74.16 |
| Resource Conservation and Recovery Act (RCRA) standards, Section 6002 |
| 4.2.4 |
| National Swimming Pool Foundation Pool and Spa Operator Handbook |
| Chapter 5 - Disinfection |
| Appendix 2 |
5.1.1 Forms:
AF Form 3952 - Chemical / Hazardous Material Request Authorization, Contact 21 CES Environmental at (719) 556-6266
5.2 Websites:
Green Procurement PWS Paragraph 4.2.4 https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program http://www.biopreferred.gov http://www.greenseal.org/.
Section 6002 of Resource Conservation and Recovery Act of 1976 PWS Paragraph 4.2.4 https://www.epa.gov/enforcement/resource-conservation-and-recovery-act-rcra-and-federal-facilities
Executive Order 13834 – Efficient Federal Operations PWS Paragraph 4.2.4 https://www.epa.gov/greeningepa/executive-order-13834-efficient-federal-operations
Colorado Department of Public Health and Environment PAFB Air Quality OPERATING PERMIT PWS Paragraph 4.2.6 http://www.cdphe.state.co.us/ap/downop/ep147p04.pdf.
APPENDIX 6 - SAMPLE DAILY CHEMICAL USAGE LIST & WORK LOG-SWIMMING POOL BLDG 404
Technician: ____________________ Date: __________ Time In: __________ Time Out: __________ Routine Service / Emergency Call-In Wader Pool
| Temp (F) |
| Alkalinity (ppm) |
| pH |
| Hard Calcium |
(ppm) Total Chlorine (ppm)
| Free Chlorine (ppm) |
| Combined Chlorine (ppm) |
| ORP (mv) |
| Flow Rate (gpm) |
| Influent Pressure |
| Effluent Pressure |
| index |
| 78-86 |
| 60-180 |
| 7.2-7.8 |
| 200-400 |
| 1-5 |
| 1-4 |
| 0-0.4 |
(-0.5- 0.5)
Main Pool
| Temp (F) |
| Alkalinity (ppm) |
| pH |
| Hard Calcium |
(ppm) Total Chlorine (ppm)
| Free Chlorine (ppm) |
| Combined Chlorine (ppm) |
| ORP (mv) |
| Flow Rate (gpm) |
| Influent Pressure |
| Effluent Pressure |
| index |
| 78-82 |
| 60-180 |
| 7.2-7.8 |
| 200-400 |
| 1-5 |
| 1-4 |
| 0-0.4 |
(-0.5- 0.5)
Hot Tub
| Temp (F) |
| Alkalinity (ppm) |
| pH |
| Hard Calcium |
(ppm) Total Chlorine (ppm)
| Free Chlorine (ppm) |
| Combined Chlorine (ppm) |
| ORP (mv) |
| Flow Rate (gpm) |
| Influent Pressure |
| Effluent Pressure |
| index |
| 100-104 |
| 60-180 |
| 7.2-7.8 |
| 200-400 |
| 1-5 |
| 3-5 |
| 0-0.4 |
(-0.5- 0.5)
| Parts Used |
| Quantity |
| Location |
| Chemicals Used |
| Quantity |
| Location |
| Chemicals Delivered |
| Quantity |
Comments:
APPENDIX 7 - Sample of HAZMAT Chemical Usage Report
Month/ Year: ____________________
| SDS Number |
| Chemical |
| Quantity |
Chlorine
C02- Bulk
Sodium Carbonate
Sodium Bicarbonate
Sodium Bisulfate
Algaecide
Sodium Thiosulfate
Enzyme
Other-
Other-
Other-
APPENDIX 8 - CONTRACTOR REPORTS
| Report Number |
| PWS |
Paragraph
| Name |
| Recipient |
| Report or Cost Estimate Due |
| 1 |
| 1.2. |
| Chemical Usage List and Work Log. Provide a hard copy of Chemical Usage List and Work documenting test results for each service to the Aquatic Center at time of testing. |
| Applicable COR |
| A copy of the completed Chemical Usage List and Work Log shall be left at the pool office after every visit. |
| 2 |
| 1.6 |
| Chemical Records. Document and maintain a HAZMAT Chemical Usage Report, indicating the chemical usage sorted by Material Stock Number (MSN) for the previous month. |
| Applicable COR |
| Provide an electronic copy of the report to the installation HAZMART in Building 652 and to the COR, for monthly review prior to invoicing in Wide Area Workflow (WAWF). |
| 3 |
| 4.2.2 |
| Hazardous Materials Pharmacy (HAZMART) Requirement. Obtain, prepare, and provide an AF Form 3952, Chemical/Hazardous Material Request Authorization and Manufacturer’s MSDS, to the base HAZMART, Building 652, for all hazardous materials to be used on Peterson SFB two weeks prior to bringing the new materials or supplies on base for use under this contract. |
| Base HAZMART |
| The Contractor will report the hazmat chemical usage monthly as stated in Section 1.6. |
APPENDIX 9 - ENVIRONMENTALLY PREFERRED PRODUCTS (Not all inclusive)
1. Penetrating lubricants – 68% bio based content
2. Hydraulic fluids-stationary equipment – 44% minimum bio based content
3. Engine lubricating oils – 25% re-refined oil in the base stock
4. Gear lubricants – 25% re-refined oil in the base stock or 58% minimum bio based content
5. Greases – general, 49% minimum bio based content
6. Greases – multipurpose, 72% minimum bio based content
7. Penetrating lubricants, 68% minimum bio based content
8. Corrosion preventatives, 54% minimum bio based content
9. Industrial cleaners, 41% minimum bio based content
10. Industrial drums; steel drums-25-30% recovered steel, including 16% postconsumer content; Plastic drums-30-100% recovered high density polyethylene, including 30-100% postconsumer content
APPENDIX 10 – Chemical Usage
| Main Pool |
| 241,133 gallons/ 4,979 cu. ft. |
| Wader Pool |
| 1,620 gallons/400 cu. ft. |
| In-Ground Hot Tub |
| 900 gallons |
The information below is for historical refence use only. There have been some outages and equipment changes that have left certain information gaps. The first table provides the pool sizes.
| 1st Quarter |
| 2nd Quarter |
| 3rd Quarter |
| 4th Quarter |
| Total Quarter |
| 300 lbs Chlorine |
1600 lbs CO2 250 lbs Chlorine 1600 lbs CO2 400 lbs Chlorine 1650 lbs CO2 450 lbs Chlorine 1650 lbs CO2
The next table is from previous years when the pool ran solely on briquettes.
As of last year, the main pool and hot tub changed from briquettes to liquid chlorine. The system still uses the same amount of CO2 as previously stated. The hot tub and wader pool has no historical data due to the system being out of service. The wader pool was not changed to liquid chlorine, so it uses briquettes and is on a separate system from main pool and in-ground hot tub. Currently the main pool is using 200 gallons per month of liquid chlorine.