This document is application instructions for the Poly-Crete SLB-UV flooring system manufactured by Sherwin-Williams. The Poly-Crete SLB-UV is a 100% solids aromatic cementitious urethane system installed at 3/16" thickness with natural quartz aggregate broadcast finish. The system requires a concrete surface profile of CSP 3-4 and consists of three application steps: an optional primer (Poly-Crete TF), a basecoat (Poly-Crete SL Flintshot Quartz), and a grout coat (Resuflor Glaze pigmented). The primer provides 90 square feet of coverage per unit with 0.80 gallons per unit, while the basecoat covers 40-42 square feet per unit and requires 3.125 gallons per unit with 800 pounds of aggregate per 1,000 square feet. The grout coat has a 2:1 mix ratio and provides 100 square feet of coverage per gallon, available in 3, 15, or 150-gallon quantities. All components have zero grams per liter volatile organic compounds (VOC).
Installation must occur at temperatures between 60°F and 85°F. Storage requirements specify that Poly-Crete SL Aggregate and Hardener maintain a 6-month shelf life and must be kept dry to prevent lumping, while Poly-Crete SL Resin has a 12-month shelf life. Frozen hardener requires heating above 100°F to melt crystals. Large area applications require multiple mixers. Sherwin-Williams HPF maintains a technical service department available to answer questions and provide guidance prior to application.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
APPLICATION INSTRUCTIONS
DESIGNED TO PERFORM sherwin-williams.com/resin-flooring
IMPORTANT!
Read these instructions carefully several days prior to starting your work. Seek answers to any questions you may have before you begin. Sherwin-Williams HPF maintains a technical staff that will be glad to answer your questions and give you advice pertaining to your particular installation. Large areas will require two or more mixers.
Poly-Crete SLB is a 100% solids aromatic cementitious urethane system with a broadcast aggregate. This system is installed at 3/16" thick. Poly-Crete SLB uses a natural quartz aggregate. NOTE: Do not apply at a temperature below 60°F (15°C) or above 85°F (29°C).
STORAGE CONDITIONS
Poly-Crete SLB must be stored dry. Exposure of the aggregate to moisture for an extended period will cause lumps. Do not allow resins to freeze. Frozen (crystallized) hardener must be heated above 100°F to melt crystals. Both the Poly-Crete SL Aggregate and Hardener have a 6-month shelf life. Poly-Crete SL Resin has a 12-month shelf life.
POLY-CRETE® SLB - UV
The following information is to be used as a guideline for the installation of the Poly-Crete SLB-UV flooring system. Contact the Sherwin-Williams Technical Service Department for assistance prior to application.
APPLICATION INFORMATION — SURFACE PREP PROFILE CSP 3-4
OPTIONAL FINISHES
VOC MIXED APPLICATION STEP MATERIAL MIX RATIO
THEORETICAL COVERAGE
PER COAT
PACKAGING
POLY-CRETE SLB-UV
0 g/L Primer (optional) Poly-Crete TF A, B & C unit 90 sq. ft./unit 0.80 gal./unit
0 g/L
Basecoat
Poly-Crete SL Flintshot Quartz
A, B & C unit To Excess
40-42 sq. ft./unit 800 lbs./1000 sq. ft.
3.125 gal./unit 50 lbs
0 g/L Grout Coat Resuflor™ Glaze (pigmented) 2:1 100 sq. ft./gal. 3, 15 or 150 gal.
<100 g/L Topcoat Resutile™ AT Premeasured Units See coverage below 1.375-1.75 gal./unit
VOC MIXED APPLICATION STEP MATERIAL MIX RATIO
THEORETICAL COVERAGE
PER COAT
PACKAGING
POLY-CRETE SLB-UC
0 g/L Topcoat Poly-Crete TF A, B & C unit 80 sq. ft./unit 0.80 gal./unit
OR
0 g/L Topcoat Poly-Crete Color-Fast Small & Large units 100 sq. ft./Sm – 200 sq. ft./Lg Sm 1 gal.-Lg 2 gal.
POLY-CRETE SLB-HP
<50 g/L Topcoat Resuflor UVE 2:1 100 sq. ft./gal. 3, 15 or 150 gal.
POLY-CRETE SLB-PA
<100 g/L Topcoat Accelera™ 4850 2:1 100 sq. ft./gal. 3 or 15 gal.
OR
<50 g/L Topcoat Accelera EXT Premeasured Unit 65 sq. ft./unit ~0.75 gal./unit
POLY-CRETE SLB-CRN
<100 g/L Topcoat Resuflor 3741 2:1 100 sq. ft./gal. 3 or 15 gal.
For additional topcoat options, contact your Sherwin-Williams Representative.
Resutile AT Kit Spread Rates Gloss Pigmented (w/grit) Gloss Pigmented (no grit) Satin Pigmented (w/grit) Satin Pigmented (no grit)
Standard 700 square feet/kit 675 square feet/kit 850 square feet/kit 825 square feet/kit
LH
775 square feet/kit 750 square feet/kit N/A N/A
POLY-CRETE® SLB-UV
DESIGNED TO PERFORM sherwin-williams.com/resin-flooring
SURFACE PREPARATION
Surface should be profiled, clean, dry, oil free and sound; Shot Blasting is the preferred preparation method. Please refer to the master Surface Preparation Guide on our website for more information. Never feather edge Poly-Crete SLB, always terminate in keyway groove at doorways and exposed edges. Refer to architectural drawings for details. Do not apply at temperatures below 60°F or above 85°F.
NOTE: For each application of material and before mixing, mark your batches to ensure you achieve your spread rate targets. This is best accomplished by dividing your target spread rate by the width of the area being coated (or your planned wet edge). Example: If your spread rate is 100 square feet and your area is 20 feet wide, you would make a mark every 5 feet (100 divided by 20 = 5).
MIXING AREA
Select a convenient mix area as close as possible to the application area and protect the surface from spillage by covering with a layer of cardboard and/or a sheet of plastic. Be generous with the amount of space allocated for this function. Do not mix this product in direct sunlight or when temperatures exceed 80°F. Exposure to high temperatures will greatly reduce the working time of this product. DO NOT MIX UNTIL READY FOR IMMEDIATE USE.
JOINT GUIDELINES
Refer to the Joint Guidelines for complete details on our website.
PRIMER
Priming or sealing of the substrate is typically not required; however, substrate must be primed with Poly-Crete TF Plus when broadcasting F60 aggregate or if the substrate is very porous (allow to cure a minimum of 6 hours @ 70°F) to prevent resins from being absorbed prematurely by substrate.
APPLICATION METHOD
Poly-Crete SLB-UV is applied by 1/2" V-notched squeegee method, and is typically applied at a thickness of 1/8". With broadcast and topcoat, Poly-Crete SLB-UV has a nominal finished system thickness of 3/16". Lay out installation in sections to allow full width to be finished in 15 minutes (@ 70°F) or less to assure absence of placement lines.
A. Poly-Crete TF Plus is supplied in pre-measured units consisting of one pail of resin, one pail of hardener and one bag of aggregate (powder). Pour the Poly-Crete TF Plus resin into a 2-gallon pail; scrape bottom and sides with a mix stick to assure that all material is transferred to the mix bucket. Use the Poly-Crete pail to scrape the mix stick, never scrape mix the stick on the side of the mix pail. Measure 1/4 oz. of Poly-Crete HF Accelerator and add it to the mix bucket. Pour the entire Poly-Crete TF Plus hardener into the center of the mix bucket. Using a 1/2" 750 RPM drill with a 4" dispersion blade, mix the resin and hardener for 30 seconds. Slowly add the Poly-Crete TF Plus aggregate to the resin and hardener and mix at 750 RPM for 1 minute. PRODUCT MUST BE MIXED WITH A 4" DISPERSION BLADE AND A 1/2" VARIABLE SPEED 750 RPM DRILL. *DO NOT ADD HARDENER TO RESIN UNTIL BATCH IS READY FOR MIXING*. *FAILURE TO ADD ALL POLY-CRETE TF PLUS POWDER
WILL RESULT IN IMPROPER CURE OF MATERIAL*
B. Pour the entire batch in two 4"-6" ribbons along the starting point.
C. Using a 3" chip brush, cut in along edges, drains and doorways.
D. Roll the material with an 18" 3/8" nap roller at 40 to 60 square feet/kit depending on substrate texture and porosity.
E. Cross roll the material to remove any puddles and achieve a uniform thickness. Allow to cure for 4 hours @ 70°F before proceeding to the next application.
NOTE: Resuflor Aqua 3477 can be used as a primer in place of Poly-Crete TF. Please contact Technical Service for application instructions.
BASECOAT
A. Poly-Crete SLB-UV is supplied in pre-measured units consisting of one pail of resin, one pail of hardener and one bag of aggregate (powder). Pour resin into a
5-gallon pail; scrape bottom and sides to assure that all pigment is transferred. (If using Poly-Crete Natural SL with pigment, add the pigment to the resin and hardener.) The resin and hardener should be pre-blended for approximately 30 seconds. A 4" dispersion blade is recommended for this product together with a high-speed drill 750 RPM minimum to shear the cement-based aggregate into the system and avoid lumps. Gradually add aggregate until a homogeneous mix is attained (Approximately 1 minute). THOROUGH BLENDING IS MANDATORY. A properly mixed batch applies easier and has a uniform surface appearance.
Incomplete mixing will cause an inconsistent finish or possible blistering. Have three mixing buckets that are rotated to assure minimum time between mixes. To avoid irregular curing or blisters, regularly clean the mixing blade and pail to avoid combining fresh material with older batches. Material should be applied directly onto the wet edge immediately after mixing.
B. When applying on level surfaces or surfaces sloped up to 1/4"/foot, the product is used as supplied. For more steeply sloped surfaces such as ramps that are up to 3/4"/foot, adding 3 quarts of Q11 (QRok #3) to each mix will prevent sagging while still providing a uniform surface after loop rolling.
C. Pour the entire batch onto the floor and spread with an 18"x 1/2" V-notched squeegee. To avoid transition lines between mixes, it is very important that the material is poured directly onto the wet edge.
D. Trowel edges, drains and around equipment supports with an even pressure and a low-angle trowel in a sweeping motion to complete troweling. This ensures that new batches of material are blended together with no transition lines for continuity of finish.
E. Immediately roll and then cross roll with an 18" loop roller to eliminate lines and help release air.
POLY-CRETE® SLB-UV
F. Loop Rolling must be completed immediately after leveling of material to eliminate any residual roller marks in the finished surface (Within 12 minutes of mixing at 70° F).
G. The aggregate must be broadcast UP into the air while dispersing evenly and vertically at an approximate rate of 0.8 pounds per square foot into the wet surface (0.5 lbs. for F-60). Wait approximately 15 minutes before broadcasting into Poly-Crete SLB to ensure air has been released. Broadcasting too quickly will result in air entrapment. Do not loop roller areas that have been broadcast.
The time window at which SLB is broadcast is extremely critical:
• At 80°-90°F, you have 20 minutes in which to finish the broadcast.
• At 70°-80°F, you have 25 minutes in which to finish the broadcast.
• At 55°-65°F, you have 30 minutes in which to finish the broadcast.
• Too early and the surface may become uneven.
• Too late and the aggregate may not penetrate into the matrix surface.
• Allow to cure for a minimum of 8 hours (@ 70°F). Remove excess aggregate by brush (Do not sand).
PREPARATION OF PLYWOOD FOR APPLICATION OF POLY-CRETE SLB
A. Plywood should be new and free of contamination (clean and dry). Marine grade plywood is recommended.
B. Installations over existing concrete or substrates with a possible chance of moisture contamination transfer should be isolated using a polyethylene vapor barrier;
all joints should be taped according to manufacturer’s instructions. Raised platforms should have consideration for airbricks in outside walls to reduce the risk of excessive dampness.
C. It is recommended that 2 layers of plywood be installed offset at joints to reduce flexing between joists. Plywood should be at least 3/4" thick.
D. Plywood should be positively fastened with high-quality construction adhesive and recessed screws at 6" on center screw pattern.
E. Bandage joints using a mixture of Resuflor EOC 100% solids epoxy and No Sag #1, embedding a minimum of 8" of close weave fiberglass matting into the wet resin.
F. All key ways should be installed by using a Skil® type saw with a 1/4" wide blade set to 1/4" deep (Concrete diamond cutting blades will burn and not cut wood).
G. Any drain detail must be keyed a minimum 2" away from the drain edge with the outside exposed edge removed to a slope using a wood chisel. Doorway thresholds should be treated in a similar way to allow a smooth transition for the termination of the material.
H. Detail such as cold joints should also be cut using a Skil saw detail as per concrete CAD drawing detail.
I. Plywood should be thoroughly vacuumed prior to installation.
TOPCOAT INSTRUCTIONS
Poly-Crete Color-Fast, Poly-Crete TF Plus, Resuflor Glaze, Resuflor 3741, Accelera or Resuflor Glaze Shop Floor with Resutile AT is used to topcoat Poly-Crete SLB systems.
Refer to their respective Product Data Sheets and/or Application Instructions for application details.
CURE
Allow a minimum of 8 hours cure before light foot traffic at 70°F, and a minimum of 24 hours is required at 50°F. Additional time must be allowed for heavier loads or lower temperatures. Contact the Sherwin-Williams High Performance Flooring Technical Department for more information.
DESIGNED TO PERFORM sherwin-williams.com/resin-flooring
THE SHERWIN-WILLIAMS DIFFERENCE
Sherwin-Williams High Performance Flooring delivers world-class industry subject matter expertise, unparalleled technical and specification service, and unmatched regional commercial team support to our customers around the globe.
United States & Canada sherwin-williams.com/resin-flooring swflooring@sherwin.com
©2026 The Sherwin-Williams Company High Performance Flooring
HPF-1530952-08 3/26
POLY-CRETE® SLB-UV
APPLICATION INSTRUCTIONS
IMPORTANT!
Before using Sherwin-Williams High Performance Flooring products, read and understand their accompanying Safety Data Sheet.
STANDARD TERMS AND CONDITIONS OF SALE, INCLUDING STANDARD WARRANTY APPLY - VISIT industrial.sherwin-williams.com/na/us/en/resin-flooring FOR THE LATEST VERSION.
CAUTION! As with all chemical products, individuals may have different reactions to exposure to specific products. This is dependent upon many factors, including the individual’s personal characteristics, the size of the installation, the ventilation available, the intensity of the exposure or the length of the exposure. Individuals may experience discomfort during the installation process of one product, but not another.
In some cases this is experienced as a skin irritation and in others it is experienced as an inhalant irritation. Typically, it disappears once the exposure is eliminated. In some cases people can become “sensitized” to a product and experience the discomfort every time there is exposure without Personal Protective Equipment (“PPE”).
To protect yourself from various exposures or discomfort during the mixing and application of our products, we recommend covering exposed skin including using gloves, long sleeves, safety glasses and a respirator such as the 3M 8577 P95 Universal Disposable Carbon Respirator or a cartridge respirator.
Use only as directed. KEEP OUT OF REACH OF CHILDREN.
Do not reseal moisture-contaminated hardener. This will result in carbon dioxide generation or possible violent rupture of container.