This is a Sources Sought Notice from the US Army Corps of Engineers, Wilmington District seeking feedback from the construction community regarding the potential use of Project Labor Agreements (PLA) for the construction of a Special Operations Forces (SOF) Mission Command Center at Fort Liberty, North Carolina. The project, identified as PN 92107, exceeds $35 million and involves constructing a multi-story facility for approximately 290 personnel, built to ICD/ICS 705 standards and connected to Building 3-2147.
The facility will include specialized features such as fire alarm/mass notification systems, classified communications networks, intrusion detection, surveillance systems, electronic access control, a hardened protected distribution system, an automated parachute storage system, and cyber security measures. The scope includes site preparation, utilities, parking, access drives, and other site improvements. Interested parties must submit responses by 2:00 PM EST on January 13, 2025, to nicolette.l.campbell@usace.army.mil and john.t.hill@usace.army.mil. Respondents are asked to provide details about past projects and answer specific questions regarding construction categories, labor availability, market conditions, and potential PLA benefits or challenges. This notice is not a Request for Proposal but will be used to inform future acquisition decisions.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOURCES SOUGHT NOTICE FOR PROJECT LABOR AGGREEMENTS (PLAs) TO
CONSTRUCT PN 92107 SOF Mission Command Center, Fort Liberty, North Carolina
The US Army Corps of Engineers, Wilmington District, is soliciting comments from the construction community addressing the potential use of Project Labor Agreements (PLA) for a large-scale construction project (exceeding $35 million) within the Ft Liberty, North Carolina area. This procurement is for project PN 92107, to construct a Special Operations Forces (SOF) Mission Command Center, Fort Liberty, North Carolina
The project scope of work consists of construction of a SOF Mission Command Center (MCC) at the Joint Special Operations Command (JSOC) Main Compound, Fort Liberty, NC, for approximately 290 personnel. The building space requirements are similar to Category Code 14190, Echelons Above Brigade (EAB) Command & Control Facility (C2F), however the facility will not follow the standard design due to the unique needs of the JSOC mission and security requirements. The building will be multi-story, permanent construction built to the Technical Specifications for Construction and Management of Sensitive Compartmented Information Facilities – ICD/ICS 705 (ICD/ICS 705) standards and connected to the existing Building 3-2147. Built-in building systems will include fire alarm/mass notification, fire suppression, energy management control, telephone and advanced unclassified and classified communications networks, cable TV, intrusion detection, closed circuit surveillance, and electronic access control systems, a hardened protected distribution system, a built-in automated parachute storage and retrieval system, and cyber security measures. Department of Defense principles for high performance and sustainable building requirements will be included in the design and construction of the project in accordance with federal laws and Executive Orders.
Low Impact Development features will be included in the design and construction of this project as appropriate. Supporting facilities include site preparation, utilities (electrical, water, gas, sanitary sewer, chilled water, and information systems distribution), lighting, vehicle parking, access drives, curb and gutter, sidewalks, storm drainage, landscaping, roads, and other site improvements. Appropriate cybersecurity measures will be applied to the facility-related control systems in accordance with current Department of Defense criteria. Access for persons with disabilities will be provided. Comprehensive interior design and audio-visual services are included.
A PLA is defined as a pre-hire collective bargaining agreement with one or more labor organizations that establishes the terms and conditions of employment for a specific construction project and is an agreement described in 29 U.S.C 158(f). Federal Acquisition Regulation (FAR) Policy: (a) Project Labor Agreement (PLA) is a tool that agencies may use to promote economy and efficiency in Federal procurement. Pursuant to Executive Order 14063, agencies are encouraged to consider requiring the use of project labor agreements in connection with large-scale construction projects. (b) An agency may, if appropriate, require that every contractor and subcontractor engaged in construction on the project agree, for that project, to negotiate or become a party to a project labor agreement with one or more labor organizations if the agency decides that the use of project labor agreements will (1) Advance the Federal Government's interest in achieving economy and efficiency in Federal procurement, producing labor-management stability, and ensuring compliance with laws and regulations governing safety and health, equal employment opportunity, labor and employment standards, and other matters; and
(2) Be consistent with law. Reference: Provision: 52.222-33 Notice of Requirement for Project Labor Agreement and Clause 52.222-34 Project Labor Agreement.
Please provide the below requested information on projects completed in the last 5 years:
Project Name / Location
Detailed Project Description
Initial Cost Est. / Actual final cost
Was the project completed on-time?
Number of craft trades present on the project
PLA
(Y/N)
Were there any challenges experienced during project? (delays, investigations, health and safety issues, labor shortages, management/organizational issues, etc)
1)
2)
3)
Requested are responses to the following:
(1) Category of Construction (residential, commercial, highway, heavy industrial)
(2) Estimated cost, duration, deadline and complexity
(3) Which trades are expected to be employed on the projects?
a. Are you likely to need some union skilled trades for at least part of this project?
(4) What market share does union labor have in the geographic area for this project or type of construction?
(5) Does the local market contain the sufficient number of available skilled workers for this project?
a. Are the other projects in the vicinity going to limit the pool of skill labor available for your project?
(6) Has a project like this been done before in the local market?
(7) What investments have been made to support registered apprenticeship programs?
(8) Will the completion of the project require an extended period of time or have sensitive deadlines?
(9) Have PLAs been used on comparable projects undertaken by the public or private sector in this geographic region? Have PLAs been used on this type of project in other regions?
(10) Which CBAs are likely to expire during the course of the project under consideration that might cause delays? (local building trades and contractors can provide information)
(11) How do prevailing wage rates in the local market compare to Davis Bacon rates?
a. What impact does unionization in the local market have on wages?
(12) Could a PLA contribute to cost savings in any of the following ways?
a. Harmonization of shifts and holidays between the trades to cut labor costs?
b. Minimizing disruptions that may arise due expiration of CBA?
c. Availability of trained, registered apprentices, efficient for highly skilled workforce?
d. Allowing for changes in apprentice to journeyman ratio.
e. Serving as a management tool that ensures highly skilled workers from multiple trades are coordinated in the most efficient way?
f. Other?
(13) Could a PLA minimize risk and contribute to greater efficiency in any of the following ways?
a. Mechanisms to avoid delays
b. Complying with labor standards, safety rules and EEO laws.
c. Ensuring a steady supply of skilled labor in markets with low supply or high competition for workers.
(14) Are there ways in which a PLA might increase costs on this particular project?
Responses shall be submitted via email to Nicolette Campbell at nicolette.l.campbell@usace.army.mil and John Hill at john.t.hill@usace.army.mil no later than 2:00 PM EST on Monday, January 13, 2025.
This is NOT a Request for Proposal and does not constitute any commitment by the Government.
Responses to this labor market survey will be used by the Government to make appropriate acquisition decisions. All interested sources must respond to future solicitation announcements separately from responses to this survey.