Playground Specifications.pdf
PDF 684 KB Posted
- Attached to
- Playground Equip with installation
- Solicitation number
- RFP GACS 200000000052 1
- Issued by
- Kalamazoo County, Forest Hills CDP, Michigan
About this file
This is a Project Manual for the Galesburg-Augusta Middle School Playground, prepared by Tower Pinkster Titus Associates, Inc. for Galesburg-Augusta Community Schools located in Galesburg, Michigan. The project (No. 14-182.22) encompasses the design and construction of a comprehensive playground facility including freestanding and composite structure playground equipment, site clearing and earth moving operations, concrete paving for walkways, playground protective surfacing, chain-link fencing, site furnishings (benches and picnic tables), and turf establishment. The specifications detail requirements for a swing unit, spinner unit, and play structure from approved manufacturers including GameTime, Creative Recreational Systems, Inc., Play Environments Inc., BCI Burke Company, Landscape Structures Inc., and Miracle Midwest. Additional work includes removal of existing site improvements, installation of engineered wood fiber protective surfacing with a critical height of 10 feet, construction of concrete walkways with specified compressive strength of 4,000 psi, installation of chain-link fencing with aluminum-coated or aluminum wire fabric, and seeding of turf areas. The project manual was dated December 7, 2016, with a 2019 revision.
The specifications require compliance with multiple safety and construction standards including ASTM F 1487, CPSC No. 325, ACI 301, and ASTM standards for concrete, reinforcement, and chain-link fencing. Playground equipment must be certified by IPEMA's third-party product certification service, and a five-year warranty is required from the manufacturer for equipment components. Field quality control includes engagement of a factory-authorized Certified Playground Inspector and testing by qualified independent agencies for concrete compressive strength, soil compaction, and turf establishment. Turf maintenance must be provided for a minimum of 60 days from planting completion until establishment. The project specifications allow for unit prices for supplemental excavation and engineered fill if unsatisfactory soil conditions are encountered. All materials, including topsoil with specific pH and organic matter requirements, grass seed mixes, and fertilizers, must meet specified standards or equivalent approved alternatives.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Playground Plans.pdf | ||
| GACS MS Playground RFP.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Tower Pinkster Titus Associates, Inc.
242 East Kalamazoo Avenue, Suite 200, Kalamazoo, MI 49007-5828
4 East Fulton Street, Suite 200, Grand Rapids, MI 49503
Galesburg-Augusta Middle
School Playground
PROJECT MANUAL
September 20, 2019
OWNER
GALESBURG-AUGUSTA COMMUNITY SCHOOLS
1076 North 37th Street
Galesburg, Michigan 49053
PROJECT NUMBER
14-182.22
SET NUMBER
PROJECT NO. 14-182.22
GALESBURG-AUGUSTA MIDDLE SCHOOL PLAYGROUND 0 - 1
GALESBURG-AUGUSTA COMMUNITY SCHOOLS 12/07/2016
© 2019 Tower Pinkster Titus Associates - All Rights Reserved
TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS (Not Applicable)
DIVISION 01 - GENERAL REQUIREMENTS (Not Applicable)
DIVISION 02 - EXISTING CONDITIONS (Not Applicable)
DIVISION 03 - CONCRETE (Not Applicable)
DIVISION 04 - MASONRY (Not Applicable)
DIVISION 05 - METALS (Not Applicable)
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES (Not Applicable)
DIVISION 07 - THERMAL AND MOISTURE PROTECTION (Not Applicable)
DIVISION 08 - OPENINGS (Not Applicable)
DIVISION 09 - FINISHES (Not Applicable)
DIVISION 10 - SPECIALTIES (Not Applicable)
DIVISION 11 - EQUIPMENT
11 6800 Playfield Equipment and Structures
DIVISION 12 – FURNISHINGS (Not Applicable)
DIVISION 13 - SPECIAL CONSTRUCTION (Not Applicable)
DIVISION 14 - CONVEYING EQUIPMENT (Not Applicable)
DIVISION 21 - FIRE SUPPRESSION (Not Applicable)
DIVISION 22 - PLUMBING (Not Applicable)
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC) (Not Applicable)
DIVISION 26 – ELECTRICAL (Not Applicable)
DIVISION 27 - COMMUNICATIONS (Not Applicable)
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY (Not Applicable)
DIVISION 31 - EARTHWORK
31 1000 Site Clearing 31 2000 Earth Moving
PROJECT NO. 14-182.22
GALESBURG-AUGUSTA MIDDLE SCHOOL PLAYGROUND 0 - 2
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 1313 Concrete Paving 32 1373 Concrete Paving Joint Sealants 32 1816.13 Playground Protective Surfacing 32 3113 Chain Link Fences 32 3900 Miscellaneous Site Specialties 32 9200 Turf and Grasses
DIVISION 33 - UTILITIES (Not Applicable)
END OF TABLE OF CONTENTS
PROJECT NO. 14-182.22 PLAYFIELD EQUIPMENT AND STRUCTURES
GALESBURG-AUGUSTA MIDDLE SCHOOL PLAYGROUND 116800 - 1
SECTION 11 6800 - PLAYFIELD EQUIPMENT AND STRUCTURES
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes freestanding and composite structure playground equipment.
B. Related Sections:
1. Section 32 1816.13 "Playground Protective Surfacing" for protective surfacing under and around playground equipment.
1.2 DEFINITIONS
A. Fall Height: According to ASTM F 1487, "the vertical distance between a designated play surface and the protective surfacing beneath it."
B. Use Zone: According to ASTM F 1487, the "area beneath and immediately adjacent to a play structure or equipment that is designated for unrestricted circulation around the equipment and on whose surface it is predicted that a user would land when falling from or exiting the equipment."
1.3 ACTION SUBMITTALS
A. Product Data: For each type of product indicated.
B. Shop Drawings: For playground equipment and structures. Include plans, elevations, sections, details, and attachments to other work.
C. Samples for Initial Selection: For each type of playground equipment and structure indicated.
1. Manufacturer's color charts.
2. Include similar Samples of playground equipment and accessories involving color selection.
1.4 INFORMATIONAL SUBMITTALS
A. Qualification Data: For qualified Installer and manufacturer.
B. Product Certificates: For each type of playground equipment, from manufacturer.
C. Warranty: Sample of special warranty.
D. Any proposed play equipment substitutions to be reviewed with owner and approved by owner in writing
GALESBURG-AUGUSTA MIDDLE SCHOOL PLAYGROUND 116800 - 2
1.5 CLOSEOUT SUBMITTALS
A. Maintenance data.
1.6 QUALITY ASSURANCE
A. Manufacturer Qualifications: A firm whose playground equipment components have been certified by IPEMA's third-party product certification service.
B. Installer Qualifications: An employer of workers approved by manufacturer.
C. Safety Standards: Provide playground equipment complying with or exceeding requirements in ASTM F 1487 CPSC No. 325.
1.7 WARRANTY
A. Special Warranty: Manufacturer's standard form in which manufacturer agrees to repair or replace components of playground equipment that fail in materials or workmanship within specified warranty period.
1. Warranty Period: Five years from date of Final Completion.
PART 2 - PRODUCTS
2.1 PLAYGROUND EQUIPMENT FABRICATION
A. General: Provide sizes, strengths, thicknesses, wall thickness, and weights of components as indicated but not less than required to comply with structural performance and other requirements in ASTM F 1487.
Factory drill components for field assembly. Unnecessary holes in components, not required for field assembly, are not permitted. Provide complete play structure, including supporting members and connections, means of access and egress, designated play surfaces, barriers, guardrails, handrails, handholds, and other components indicated or required to comply with referenced standards for equipment indicated.
1. Composite Play Structure: Provide complete play structure, designed to be modular, linked, and expandable, forming one integral unit for more than one play activity.
B. Metal Frame: Fabricate main-frame upright support posts from metal pipe or tubing with cross-section profile and dimensions as indicated. Unless otherwise indicated, provide each pipe or tubing main-frame member with manufacturer's standard drainable bottom plate or support flange. Fabricate secondary frame members, bracing, and connections from either steel or aluminum.
C. Composite Frame: Fabricate main-frame upright support posts from metal and plastic with profile and dimensions as indicated. Fabricate secondary frame members, bracing, and connections from either steel or aluminum.
D. Protective Barriers: Fabricated such that openings within the barrier and between the barrier and the play surface preclude passage of the torso probe according to ASTM F 1487, CPSC No. 325 the most
GALESBURG-AUGUSTA MIDDLE SCHOOL PLAYGROUND 116800 - 3
stringent requirements in ASTM F 1487 and CPSC No. 325. Provide barriers designed to minimize the possibility of climbing, free of hand- and footholds, and configured to completely surround the protected area except for access openings. Extend barriers above the protected elevated surface for use by age group indicated.
2.2 FREESTANDING PLAYGROUND EQUIPMENT AND STRUCTURES
A. Swing Unit
1. Basis-of-Design Product: Subject to compliance with requirements, provide Double Arch Swing by GameTime, www.gametime.com. Colors to be selected by Owner from Manufacture’s standard color selection, or approved comparable product.
B. Spinner Unit
1. Basis-of-Design Product: Subject to compliance with requirements, provide Sky Runner overhead spinner by GameTime. Colors to be selected by owner from Manufacture’s standard color selection, or approved comparable product.
C. Play Structure
1. Basis-of-Design Product: Subject to compliance with requirements, provide Commercial Playground Equipment, FreeStyle Xll by Creative Recreational Systems, Inc., (313)528-2836 www.creativesystems.com or approved comparable product.by one of the following;
2.
a. Play Enviroments, Inc. 800-685-6291, or 616-395-2565
b. BCI Burke Company, LLC 440-877-9133
c. GameTime; company 800-444-4954, or 616-392-741
d. Landscape Structures Inc. 888-778-7529 or 810-229-6245
e. Miracle Midwest 800-722-8546
3. Colors; To be selected by Owner from Manufacture’s standard color options.
2.3 CAST-IN-PLACE CONCRETE
A. Concrete Materials and Properties: Comply with requirements in Section 03 3000 "Cast-in-Place Concrete" ACI 301 ACI 301M to produce normal-weight concrete
PART 3 - EXECUTION
3.1 INSTALLATION
A. General: Comply with manufacturer's written installation instructions unless more stringent requirements are indicated. Anchor playground equipment securely, positioned at locations and elevations indicated.
1. Maximum Equipment Height: Coordinate installed heights of equipment and components with finished elevations of protective surfacing. Set equipment so fall heights and elevation
GALESBURG-AUGUSTA MIDDLE SCHOOL PLAYGROUND 116800 - 4
requirements for age group use and accessibility are within required limits. Verify that playground equipment elevations comply with requirements for each type and component of equipment.
3.2 FIELD QUALITY CONTROL
A. Perform tests and inspections.
1. Manufacturer's Field Service: Engage a factory-authorized Cerities Playground Inspector to inspect components, assemblies, and equipment installations, including connections, and to assist in testing.
B. Tests and Inspections: For playground and playground equipment and components at final completion and to certify compliance with ASTM F 1487 CPSC No. 325.
C. Prepare written test and inspection reports.
D. Notify Owner 48 hours in advance of date and time of final inspection.
END OF SECTION 11 6800
PROJECT NO. 14-182.22 SITE CLEARING
GALESBURG-AUGUSTA MIDDLE SCHOOL PLAYGROUND 311000 - 1
SECTION 31 1000 - SITE CLEARING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Protecting existing vegetation to remain.
2. Removing existing vegetation.
3. Strip and remove topsoil.
4. Removing above- and below-grade site improvements.
5. Disconnecting, capping or sealing site utilities.
6. Temporary erosion- and sedimentation-control measures.
B. Related Sections:
1. Section 01 7300 "Execution" for field engineering and surveying.
2. Section 02 4119 "Selective Structure Demolition" for partial demolition of buildings or structures.
1.2 DEFINITIONS
A. Subsoil: All soil beneath the topsoil layer of the soil profile, and typified by the lack of organic matter and soil organisms.
B. Surface Soil: Soil that is present at the top layer of the existing soil profile at the Project site. In undisturbed areas, the surface soil is typically topsoil; but in disturbed areas such as urban environments, the surface soil can be subsoil.
C. Topsoil: Top layer of the soil profile consisting of existing native surface topsoil or existing in-place surface soil and is the zone where plant roots grow. Its appearance is generally friable, pervious, and black or a darker shade of brown, gray, or red than underlying subsoil; reasonably free of subsoil, clay lumps, gravel, and other objects more than 2 inches (50 mm) in diameter; and free of subsoil and weeds, roots, toxic materials, or other nonsoil materials.
D. Plant-Protection Zone: Area surrounding individual trees, groups of trees, shrubs, or other vegetation to be protected during construction.
E. Tree-Protection Zone: Area surrounding individual trees or groups of trees equal to the tree’s root zone and branch spread..
F. Vegetation: Trees, shrubs, groundcovers, grass, and other plants.
1.3 MATERIAL OWNERSHIP
A. Except materials indicated to be stockpiled or otherwise remain Owner's property, cleared materials shall become Contractor's property and shall be removed from Project site.
GALESBURG-AUGUSTA MIDDLE SCHOOL PLAYGROUND 311000 - 2
1.4 PROJECT CONDITIONS
A. Traffic: Minimize interference with adjoining roads, streets, walks, and other adjacent occupied or used facilities during site-clearing operations.
1. Do not close or obstruct streets, walks, or other adjacent occupied or used facilities without permission from Owner and authorities having jurisdiction.
2. Provide alternate routes around closed or obstructed traffic ways if required by Owner or authorities having jurisdiction.
B. Salvable Improvements: Carefully remove items indicated to be salvaged and store on Owner's premises where indicated.
C. Utility Locator Service: Notify utility locator service for area where Project is located before site clearing.
D. Do not commence site clearing operations until temporary erosion- and sedimentation-control measures are in place.
E. The following practices are prohibited within root zones:
1. Storage of construction materials, debris, or excavated material.
2. Parking vehicles or equipment.
3. Erection of sheds or structures.
4. Impoundment of water.
5. Excavation or other digging unless otherwise indicated.
6. Attachment of signs to or wrapping materials around trees or plants unless otherwise indicated.
F. Soil Stripping, Handling, and Stockpiling: Perform only when the topsoil is dry or slightly moist.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Satisfactory Soil Material: Requirements for satisfactory soil material are specified in Section 31 2000 "Earth Moving."
PART 3 - EXECUTION
3.1 PREPARATION
A. Protect and maintain benchmarks and survey control points from disturbance during construction.
B. Locate and clearly identify trees, shrubs, and other vegetation to remain or to be relocated.
C. Protect existing site improvements to remain from damage during construction.
1. Restore damaged improvements to their original condition, as acceptable to Owner.
GALESBURG-AUGUSTA MIDDLE SCHOOL PLAYGROUND 311000 - 3
3.2 TEMPORARY EROSION AND SEDIMENTATION CONTROL
A. Provide temporary erosion- and sedimentation-control measures to prevent soil erosion and discharge of soil-bearing water runoff or airborne dust to adjacent properties and walkways, according to erosion- and sedimentation-control requirements of authorities having jurisdiction.
B. Verify that flows of water redirected from construction areas or generated by construction activity do not enter or cross protection zones.
C. Inspect, maintain, and repair erosion- and sedimentation-control measures during construction until permanent vegetation has been established.
D. Remove erosion and sedimentation controls and restore and stabilize areas disturbed during removal.
3.3 EXISTING UTILITIES
A. Locate, identify, disconnect, and seal or cap utilities indicated to be removed or abandoned in place.
1. Arrange with utility companies to shut off indicated utilities.
B. Interrupting Existing Utilities: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after arranging to provide temporary utility services according to requirements indicated:
1. Notify Architect not less than two days in advance of proposed utility interruptions.
2. Do not proceed with utility interruptions without Architect's written permission.
C. Excavate for and remove underground utilities indicated to be removed.
3.4 CLEARING AND GRUBBING
A. Remove obstructions, trees, shrubs, and other vegetation to permit installation of new construction.
3.5 TOPSOIL STRIPPING
A. Strip and remove topsoil to whatever depths are encountered in a manner to prevent intermingling with underlying subsoil or other waste materials.
3.6 SITE IMPROVEMENTS
A. Remove existing above- and below-grade improvements as indicated and necessary to facilitate new construction.
B. Remove slabs, paving, curbs, gutters, and aggregate base as indicated.
1. Unless existing full-depth joints coincide with line of demolition, neatly saw-cut along line of existing pavement to remain before removing adjacent existing pavement. Saw-cut faces vertically.
GALESBURG-AUGUSTA MIDDLE SCHOOL PLAYGROUND 311000 - 4
2. Paint cut ends of steel reinforcement in concrete to remain with two coats of antirust coating, following coating manufacturer's written instructions. Keep paint off surfaces that will remain exposed.
3.7 DISPOSAL OF SURPLUS AND WASTE MATERIALS
A. Remove surplus soil material, topsoil, obstructions, demolished materials, and waste materials including trash and debris, and legally dispose of them off Owner's property.
END OF SECTION 31 1000
PROJECT NO. 14-182.22 EARTH MOVING
GALESBURG-AUGUSTA MIDDLE SCHOOL PLAYGROUND 312000 - 1
SECTION 31 2000 - EARTH MOVING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Preparing subgrades for slabs-on-grade walks pavements and turf.
1. Section 31 1000 "Site Clearing" for site stripping, grubbing, stripping topsoil, and removal of above-and below-grade improvements and utilities.
2. Section 32 9200 "Turf and Grasses" for finish grading in turf and grass areas, including preparing and placing planting soil for turf areas.
1.2 UNIT PRICES
A. Work of this Section is affected by unit prices for earth moving specified in Section 01 2200 "Unit Prices."
1. Unit Price 1: Supplemental Excavation, Satisfactory Soil Fill: Unit price for unforeseen excavation due to unsatisfactory soil conditions and replacement with satisfactory soil. Unit of measurement shall be cubic yard.
2. Unit Price 2: Supplemental Excavation, Engineered Fill: Unit price for unforeseen excavation due to unsatisfactory soil conditions and replacement with engineered fill. Unit of measurement shall be cubic yard.
1.3 DEFINITIONS
A. Backfill: Soil material used to fill an excavation.
B. Borrow Soil: Satisfactory soil imported from off-site for use as fill or backfill.
C. Drainage Course: Aggregate layer supporting the slab-on-grade that also minimizes upward capillary flow of pore water.
D. Excavation: Removal of material encountered above subgrade elevations and to lines and dimensions indicated.
1. Authorized Additional Excavation: Excavation below subgrade elevations or beyond indicated lines and dimensions as directed by Architect. Authorized additional excavation and replacement material will be paid for according to Contract provisions for changes in the Work.
2. Unauthorized Excavation: Excavation below subgrade elevations or beyond indicated lines and dimensions without direction by Architect. Unauthorized excavation, as well as remedial work directed by Architect, shall be without additional compensation.
E. Fill: Soil materials used to raise existing grades.
GALESBURG-AUGUSTA MIDDLE SCHOOL PLAYGROUND 312000 - 2
F. Structures: Buildings, footings, foundations, retaining walls, slabs, tanks, curbs, mechanical and electrical appurtenances, or other man-made stationary features constructed above or below the ground surface.
G. Subbase Course: Aggregate layer placed between the subgrade and base course for hot-mix asphalt pavement, or aggregate layer placed between the subgrade and a concrete slab-on-grade, cement concrete pavement, or a cement concrete or hot-mix asphalt walk.
H. Subgrade: Uppermost surface of an excavation or the top surface of a fill or backfill immediately below subbase, drainage fill, drainage course, or topsoil materials.
I. Utilities: On-site underground pipes, conduits, ducts, and cables, as well as underground services within buildings.
1.4 PROJECT CONDITIONS
A. Utility Locator Service: Notify utility locator service for area where Project is located before beginning earth moving operations.
B. Do not commence earth moving operations until temporary erosion- and sedimentation-control measures, specified in Section 31 1000 "Site Clearing," are in place.
PART 2 - PRODUCTS
2.1 SOIL MATERIALS
A. General: Provide borrow soil materials when sufficient satisfactory soil materials are not available from excavations.
B. Satisfactory Soils: Soil Classification Groups GW, GP, GM, SW, SP, and SM according to ASTM D 2487, or a combination of these groups; free of rock or gravel larger than 3 inches (75 mm) in any dimension, debris, waste, frozen materials, vegetation, and other deleterious matter.
C. Unsatisfactory Soils: Soil Classification Groups GC, SC, CL, ML, OL, CH, MH, OH, and PT according to ASTM D 2487, or a combination of these groups.
1. Unsatisfactory soils also include satisfactory soils not maintained within 2 percent of optimum moisture content at time of compaction.
D. Subbase Material: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D 2940; with at least 90 percent passing a 1-1/2-inch (37.5-mm) sieve and not more than 12 percent passing a No. 200 (0.075-mm) sieve.
E. Base Course: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D 2940; with at least 95 percent passing a 1-1/2-inch (37.5-mm) sieve and not more than 8 percent passing a No. 200 (0.075-mm) sieve.
F. Engineered Fill: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D 2940; with at least 90 percent passing a 1-1/2-inch (37.5-mm) sieve and not more than 12 percent passing a No. 200 (0.075-mm) sieve.
GALESBURG-AUGUSTA MIDDLE SCHOOL PLAYGROUND 312000 - 3
G. Bedding Course: Naturally or artificially graded mixture of natural or crushed gravel, crushed stone, and natural or crushed sand; ASTM D 2940; except with 100 percent passing a 1-inch (25-mm) sieve and not more than 8 percent passing a No. 200 (0.075-mm) sieve.
H. Sand: ASTM C 33; fine aggregate.
PART 3 - EXECUTION
3.1 PREPARATION
A. Protect structures, utilities, sidewalks, pavements, and other facilities from damage caused by settlement, lateral movement, undermining, washout, and other hazards created by earth moving operations.
B. Protect and maintain erosion and sedimentation controls during earth moving operations.
C. Protect subgrades and foundation soils from freezing temperatures and frost. Remove temporary protection before placing subsequent materials.
3.2 DEWATERING
A. Prevent surface water and ground water from entering excavations, from ponding on prepared subgrades, and from flooding Project site and surrounding area.
B. Protect subgrades from softening, undermining, washout, and damage by rain or water accumulation.
1. Reroute surface water runoff away from excavated areas. Do not allow water to accumulate in excavations. Do not use excavated trenches as temporary drainage ditches.
3.3 EXPLOSIVES
A. Explosives: Do not use explosives.
3.4 EXCAVATION
A. Unclassified Excavation: Excavate to subgrade elevations regardless of the character of surface and subsurface conditions encountered. Unclassified excavated materials may include rock, soil materials, and obstructions. No changes in the Contract Sum or the Contract Time will be authorized for rock excavation or removal of obstructions.
1. If excavated materials intended for fill and backfill include unsatisfactory soil materials and rock, replace with satisfactory soil materials.
B. Excavation for Walks and Pavements: Excavate surfaces under walks and pavements to indicated lines, cross sections, elevations, and subgrades.
GALESBURG-AUGUSTA MIDDLE SCHOOL PLAYGROUND 312000 - 4
3.5 SUBGRADE INSPECTION
A. Reconstruct subgrades damaged by freezing temperatures, frost, rain, accumulated water, or construction activities, as directed by Architect, without additional compensation.
3.6 UNAUTHORIZED EXCAVATION
A. Fill unauthorized excavation under foundations or wall footings by extending bottom elevation of concrete foundation or footing to excavation bottom, without altering top elevation. Lean concrete fill, with 28-day compressive strength of 2500 psi (17.2 MPa), may be used when approved by Architect.
1. Fill unauthorized excavations under other construction, pipe, or conduit as directed by Architect.
3.7 STORAGE OF SOIL MATERIALS
A. Stockpile borrow soil materials and excavated satisfactory soil materials without intermixing. Place, grade, and shape stockpiles to drain surface water. Cover to prevent windblown dust.
1. Stockpile soil materials away from edge of excavations. Do not store within drip line of remaining trees.
3.8 BACKFILL
A. General: Place and compact backfill in excavations promptly, but not before completing the following:
1. Construction below finish grade including, where applicable, subdrainage, dampproofing, waterproofing, and perimeter insulation.
2. Removing concrete formwork.
3. Removing trash and debris.
4. Removing temporary shoring and bracing, and sheeting.
5. Place backfill on subgrades free of mud, frost, snow, or ice.
3.9 SOIL FILL
A. Place and compact fill material in layers to required elevations as follows:
1. Under grass and planted areas, use satisfactory soil material.
2. Under walks and pavements, use satisfactory soil material.
3.10 COMPACTION OF SOIL BACKFILLS AND FILLS
A. Place backfill and fill soil materials in layers not more than 8 inches (200 mm)in loose depth for material compacted by heavy compaction equipment, and not more than 4 inches (100 mm) in loose depth for material compacted by hand-operated tampers.
B. Place backfill and fill soil materials evenly on all sides of structures to required elevations, and uniformly along the full length of each structure.
GALESBURG-AUGUSTA MIDDLE SCHOOL PLAYGROUND 312000 - 5
C. Compact soil materials to not less than the following percentages of maximum dry unit weight according to
ASTM D 698 ASTM D 1557:
1. Under structures, building slabs, steps, and pavements, scarify and recompact top 12 inches (300
mm) of existing subgrade and each layer of backfill or fill soil material at 95 percent.
a. Under slabs on grade, place 4 inches(102 mm) compacted depth of sand
2. Under walkways, scarify and recompact top 6 inches (150 mm) below subgrade and compact each layer of backfill or fill soil material at 92 percent.
3. Under turf or unpaved areas, scarify and recompact top 6 inches (150 mm) below subgrade and compact each layer of backfill or fill soil material at 90 percent.
3.11 GRADING
A. General: Uniformly grade areas to a smooth surface, free of irregular surface changes. Comply with compaction requirements and grade to cross sections, lines, and elevations indicated.
B. Site Rough Grading: Slope grades to direct water away from buildings and to prevent ponding. Finish subgrades to required elevations within the following tolerances:
1. Turf or Unpaved Areas: Plus or minus 1 inch (25 mm).
2. Walks: Plus or minus 1 inch (25 mm).
3. Pavements: Plus or minus 1/2 inch (13 mm).
3.12 SUBBASE AND BASE COURSES UNDER PAVEMENTS AND WALKS
A. Place subbase course on subgrades free of mud, frost, snow, or ice.
B. On prepared subgrade, place subbase course under pavements and walks as follows:
1. Place base course material over subbase course under hot-mix asphalt pavement.
2. Shape subbase course to required crown elevations and cross-slope grades.
3. Place subbase course in compacted thickness in a single layer.
4. Compact subbase course at optimum moisture content to required grades, lines, cross sections, and thickness to not less than 95 percent of maximum dry unit weight according to ASTM D 698
ASTM D 1557.
3.13 FIELD QUALITY CONTROL
A. Testing Agency: Owner will engage a qualified geotechnical engineering testing agency to perform tests and inspections.
B. Allow testing agency to inspect and test subgrades and each fill or backfill layer. Proceed with subsequent earth moving only after test results for previously completed work comply with requirements.
C. Testing agency will test compaction of soils in place according to ASTM D 1556, ASTM D 2167, ASTM D 2922, and ASTM D 2937, as applicable. Tests will be performed at the following locations and frequencies:
GALESBURG-AUGUSTA MIDDLE SCHOOL PLAYGROUND 312000 - 6
1. Paved Areas: At subgrade and at each compacted fill and backfill layer, at least one test for every 2000 sq. ft. (186 sq. m) or less of paved area or building slab, but in no case fewer than three tests.
D. When testing agency reports that subgrades, fills, or backfills have not achieved degree of compaction specified, scarify and moisten or aerate, or remove and replace soil materials to depth required;
recompact and retest until specified compaction is obtained.
3.14 PROTECTION
A. Protecting Graded Areas: Protect newly graded areas from traffic, freezing, and erosion. Keep free of trash and debris.
B. Repair and reestablish grades to specified tolerances where completed or partially completed surfaces become eroded, rutted, settled, or where they lose compaction due to subsequent construction operations or weather conditions.
C. Where settling occurs before Project correction period elapses, remove finished surfacing, backfill with additional soil material, compact, and reconstruct surfacing.
1. Restore appearance, quality, and condition of finished surfacing to match adjacent work, and eliminate evidence of restoration to greatest extent possible.
3.15 DISPOSAL OF SURPLUS AND WASTE MATERIALS
A. Remove surplus satisfactory soil and waste materials, including unsatisfactory soil, trash, and debris, and legally dispose of them off Owner's property.
END OF SECTION 31 2000
PROJECT NO. 14-182.22 CONCRETE PAVING
GALESBURG-AUGUSTA MIDDLE SCHOOL PLAYGROUND 321313 - 1
SECTION 32 1313 - CONCRETE PAVING
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes exterior cement concrete pavement for the following:
1. Walkways.
B. Related Sections include the following:
1. Division 31 Section "Earth Moving" for subgrade preparation, grading, and subbase course.
2. Division 32 Section "Pavement Joint Sealants" for joint sealants of joints in concrete pavement and at isolation joints of concrete pavement with adjacent construction.
1.2 SUBMITTALS
A. Design Mixtures: For each concrete pavement mixture.
1.3 QUALITY ASSURANCE
A. Manufacturer Qualifications: Manufacturer of ready-mixed concrete products who complies with ASTM C 94/C 94M requirements for production facilities and equipment.
B. ACI Publications: Comply with ACI 301, "Specification for Structural Concrete," unless modified by requirements in the Contract Documents.
C. Concrete Testing Service: Engage a qualified independent testing agency to perform material evaluation tests and to design concrete mixtures.
1.4 PROJECT CONDITIONS
A. Traffic Control: Maintain access for vehicular and pedestrian traffic as required for other construction activities.
PART 2 - PRODUCTS
2.1 FORMS
A. Form Materials: Plywood, metal, metal-framed plywood, or other approved panel-type materials to provide full-depth, continuous, straight, smooth exposed surfaces.
1. Use flexible or curved forms for curves with a radius 100 feet(30.5 m) or less.
GALESBURG-AUGUSTA MIDDLE SCHOOL PLAYGROUND 321313 - 2
B. Form-Release Agent: Commercially formulated form-release agent that will not bond with, stain, or adversely affect concrete surfaces and will not impair subsequent treatments of concrete surfaces.
2.2 STEEL REINFORCEMENT
A. Plain-Steel Welded Wire Reinforcement: ASTM A 185, fabricated from as-drawn steel wire into flat sheets.
B. Reinforcing Bars: ASTM A 615/A 615M, Grade 60(Grade 420); deformed.
C. Joint Dowel Bars: Plain steel bars, ASTM A 615/A 615M, Grade 60(Grade 420). Cut bars true to length with ends square and free of burrs.
D. Tie Bars: ASTM A 615/A 615M, Grade 60(Grade 420), deformed.
E. Bar Supports: Bolsters, chairs, spacers, and other devices for spacing, supporting, and fastening reinforcing bars, welded wire reinforcement, and dowels in place. Manufacture bar supports according to CRSI's "Manual of Standard Practice."
2.3 CONCRETE MATERIALS
A. Cementitious Material: Use one of the following cementitious materials, of the same type, brand, and source throughout the Project:
1. Portland Cement: ASTM C 150, Type I/II, gray. Supplement with the following:
a. Fly Ash: ASTM C 618, Class C or F.
b. Ground Granulated Blast-Furnace Slag: ASTM C 989, Grade 100 or 120.
B. Normal-Weight Aggregates: ASTM C 33, Class 4S coarse aggregate, uniformly graded. Provide aggregates from a single source with documented service record data of at least 10 years' satisfactory service in similar pavement applications and service conditions using similar aggregates and cementitious materials.
1. Coarse Aggregate: MDOT 6A or MDOT 6AA.
2. Maximum Coarse-Aggregate Size: 1-1/2 inches(38 mm) nominal.
3. Fine Aggregate: MDOT 2NS.
4. Do not use fine or coarse aggregates containing substances that cause spalling.
C. Water: ASTM C 94/C 94M.
D. Air-Entraining Admixture: ASTM C 260.
E. Chemical Admixtures: ASTM C 494/C 494M, of type suitable for application, certified by manufacturer to be compatible with other admixtures and to contain not more than 0.1 percent water-soluble chloride ions by mass of cementitious material.
GALESBURG-AUGUSTA MIDDLE SCHOOL PLAYGROUND 321313 - 3
2.4 CURING MATERIALS
A. Absorptive Cover: AASHTO M 182, Class 2, burlap cloth.
B. Moisture-Retaining Cover: ASTM C 171, polyethylene film or white burlap-polyethylene sheet.
C. Water: Potable.
D. Evaporation Retarder: Waterborne, monomolecular film forming; manufactured for application to fresh concrete.
2.5 RELATED MATERIALS
A. Expansion- and Isolation-Joint-Filler Strips: ASTM D 1751, asphalt-saturated cellulosic fiber.
B. Bonding Agent: ASTM C 1059, Type II, non-redispersible, acrylic emulsion or styrene butadiene.
C. Penetrating Liquid Slab Treatment: Chemically reactive, waterborne solution of inorganic silicate or siliconate materials and proprietary components; odorless; colorless; that penetrates, hardens, and densifies concrete surfaces.
1. Products:
a. Chemisil Plus; ChemMasters.
b. Day-Chem Sure Hard; Dayton Superior Corporation.
c. Euco Diamond Hard; Euclid Chemical Co.
d. Seal Hard; L&M Construction Chemicals, Inc.
2.6 CONCRETE MIXTURES
A. Prepare design mixtures, proportioned according to ACI 301, with the following properties:
1. Compressive Strength (28 Days): 4000 psi(27.6 MPa).
2. Maximum Water-Cementitious Materials Ratio at Point of Placement: 0.45.
3. Slump Limit: 4 inches(100 mm), plus or minus 1 inch(25 mm).
4. Air Content: 5-1/2 percent plus or minus 1.5 percent.
2.7 CONCRETE MIXING
A. Ready-Mixed Concrete: Measure, batch, and mix concrete materials and concrete according to ASTM C 94/C 94M and ASTM C 1116. Furnish batch certificates for each batch discharged and used in the Work.
1. When air temperature is between 85 deg F(30 deg C) and 90 deg F(32 deg C), reduce mixing and delivery time from 1-1/2 hours to 75 minutes; when air temperature is above 90 deg F(32 deg C), reduce mixing and delivery time to 60 minutes.
GALESBURG-AUGUSTA MIDDLE SCHOOL PLAYGROUND 321313 - 4
PART 3 - EXECUTION
3.1 EXAMINATION
A. Proof-roll prepared subbase surface below concrete pavements with heavy pneumatic-tired equipment to identify soft pockets and areas of excess yielding.
1. Completely proof-roll subbase in one direction and repeat in perpendicular direction. Limit vehicle speed to 3 mph(5 km/h).
2. Subbase with soft spots and areas of pumping or rutting exceeding depth of 1/2 inch(13 mm) require correction according to requirements in Division 31 Section "Earth Moving."
3.2 INSTALLATION
A. Edge Forms and Screed Construction: Set, brace, and secure edge forms, bulkheads, and intermediate screed guides for pavement to required lines, grades, and elevations. Install forms to allow continuous progress of work and so forms can remain in place at least 24 hours after concrete placement.
1. Clean forms after each use and coat with form-release agent to ensure separation from concrete without damage.
B. Steel Reinforcement: Comply with CRSI's "Manual of Standard Practice" for fabricating, placing, and supporting reinforcement.
1. Clean reinforcement of loose rust and mill scale, earth, ice, or other bond-reducing materials.
2. Install welded wire reinforcement in lengths as long as practicable. Lap adjoining pieces at least one full mesh, and lace splices with wire. Offset laps of adjoining widths to prevent continuous laps in either direction.
C. Joints, General: Form construction, isolation, and contraction joints and tool edgings true to line with faces perpendicular to surface plane of concrete. Construct transverse joints at right angles to centerline, unless otherwise indicated.
D. Construction Joints: Set construction joints at side and end terminations of pavement and at locations where pavement operations are stopped for more than one-half hour unless pavement terminates at isolation joints.
1. Continue steel reinforcement across construction joints, unless otherwise indicated. Do not continue reinforcement through sides of pavement strips, unless otherwise indicated.
2. Provide tie bars at sides of pavement strips where indicated.
E. Isolation Joints: Form isolation joints of preformed joint-filler strips abutting concrete curbs, catch basins, manholes, inlets, structures, walks, other fixed objects, and where indicated.
1. Locate expansion joints at intervals of 50 feet(15.25 m), unless otherwise indicated.
2. Extend joint fillers full width and depth of joint.
3. Terminate joint filler not less than 1/2 inch(13 mm) or more than 1 inch(25 mm) below finished surface if joint sealant is indicated.
4. Place top of joint filler flush with finished concrete surface if joint sealant is not indicated.
GALESBURG-AUGUSTA MIDDLE SCHOOL PLAYGROUND 321313 - 5
5. Furnish joint fillers in one-piece lengths. Where more than one length is required, lace or clip joint-filler sections together.
6. Protect top edge of joint filler during concrete placement with metal, plastic, or other temporary preformed cap. Remove protective cap after concrete has been placed on both sides of joint.
F. Contraction Joints: Form weakened-plane contraction joints, sectioning concrete into areas as indicated.
Construct contraction joints for a depth equal to at least one-fourth of the concrete thickness.
1. No saw cut joints.
G. Edging: Tool edges of pavement, gutters, curbs, and joints in concrete after initial floating with an edging tool to a 1/4-inch(6-mm) radius. Repeat tooling of edges after applying surface finishes. Eliminate tool marks on concrete surfaces.
H. Concrete Placement: Comply with ACI 301 requirements for measuring, mixing, transporting, and placing concrete.
1. Moisten subbase to provide a uniform dampened condition at time concrete is placed.
2. Do not add water to fresh concrete after testing.
3. Deposit and spread concrete in a continuous operation between transverse joints. Do not push or drag concrete into place or use vibrators to move concrete into place.
4. Screed pavement surfaces with a straightedge and strike off.
5. Commence initial floating using bull floats or darbies to impart an open textured and uniform surface plane before excess moisture or bleed water appears on the surface. Do not further disturb concrete surfaces before beginning finishing operations or spreading surface treatments.
6. formed concrete. If results are not approved, remove and replace with formed concrete.
7. Slip-Form Pavers: When automatic machine placement is used for pavement, submit revised mix design and laboratory test results that meet or exceed requirements. Produce pavement to required thickness, lines, grades, finish, and jointing as required for formed pavement.
a. Compact subbase and prepare subgrade of sufficient width to prevent displacement of paver machine during operations.
8. When adjoining pavement lanes are placed in separate pours, do not operate equipment on concrete until pavement has attained 85 percent of its 28-day compressive strength.
9. Cold-Weather Placement: Comply with ACI 306.1. Protect concrete work from physical damage or reduced strength that could be caused by frost, freezing actions, or low temperatures.
10. Hot-Weather Placement: Comply with ACI 301 when hot-weather conditions exist.
3.3 FINISHING
A. General: Do not add water to concrete surfaces during finishing operations.
B. Float Finish: Begin the second floating operation when bleed-water sheen has disappeared and concrete surface has stiffened sufficiently to permit operations. Float surface with power-driven floats, or by hand floating if area is small or inaccessible to power units. Finish surfaces to true planes. Cut down high spots and fill low spots. Refloat surface immediately to uniform granular texture.
1. Textured Broom Finish: Draw a soft bristle broom across float-finished concrete surface perpendicular to line of traffic to provide a uniform, fine-line texture.
GALESBURG-AUGUSTA MIDDLE SCHOOL PLAYGROUND 321313 - 6
2. After final floating, apply a hand-trowel finish followed by a broom finish to concrete.
3. Cure concrete with curing compound recommended by dry-shake hardener manufacturer. Apply curing compound immediately after final finishing.
C. Penetrating Liquid Slab Treatment: Prepare, apply, and finish penetrating liquid slab treatment according to manufacturer's written instructions.
1. Remove curing compounds, sealers, oil, dirt, laitance, and other contaminants and complete surface repairs.
2. Do not apply to concrete that is less than seven days old.
3. Apply liquid until surface is saturated, scrubbing into surface until a gel forms; rewet; and repeat brooming or scrubbing. Rinse with water; remove excess material until surface is dry. Apply a second coat in a similar manner if surface is rough or porous.
3.4 CONCRETE PROTECTION AND CURING
A. General: Protect freshly placed concrete from premature drying and excessive cold or hot temperatures.
B. Comply with ACI 306.1 for cold-weather protection.
C. Evaporation Retarder: Apply evaporation retarder to concrete surfaces if hot, dry, or windy conditions cause moisture loss approaching 0.2 lb/sq. ft. x h(1 kg/sq. m x h) before and during finishing operations.
Apply according to manufacturer's written instructions after placing, screeding, and bull floating or darbying concrete, but before float finishing.
D. Begin curing after finishing concrete but not before free water has disappeared from concrete surface.
E. Curing Methods: Cure concrete by moisture curing, moisture-retaining-cover curing, or a combination of these methods.
3.5 PAVEMENT TOLERANCES
A. Comply with tolerances of ACI 117 and as follows:
1. Elevation: 1/4 inch(6 mm).
2. Thickness: Plus 3/8 inch(10 mm), minus 1/4 inch(6 mm).
3. Surface: Gap below 10-foot-(3-m-) long, unleveled straightedge not to exceed 1/4 inch(6 mm).
4. Joint Spacing: 3 inches(75 mm).
5. Contraction Joint Depth: Plus 1/4 inch(6 mm), no minus.
6. Joint Width: Plus 1/8 inch(3 mm), no minus.
3.6 FIELD QUALITY CONTROL
A. Testing Agency: Owner will engage a qualified independent testing and inspecting agency to perform field tests and inspections and prepare test reports.
B. Testing Services: Testing of composite samples of fresh concrete obtained according to ASTM C 172 shall be performed according to the following requirements:
GALESBURG-AUGUSTA MIDDLE SCHOOL PLAYGROUND 321313 - 7
1. Testing Frequency: Obtain at least 1 composite sample for each 100 cu. yd.(76 cu. m) or fraction thereof of each concrete mix placed each day.
a. When frequency of testing will provide fewer than five compressive-strength tests for each concrete mixture, testing shall be conducted from at least five randomly selected batches or from each batch if fewer than five are used.
2. Slump: ASTM C 143/C 143M; one test at point of placement for each composite sample, but not less than one test for each day's pour of each concrete mix. Perform additional tests when concrete consistency appears to change.
3. Air Content: ASTM C 231, pressure method; one test for each composite sample, but not less than one test for each day's pour of each concrete mix.
4. Concrete Temperature: ASTM C 1064; one test hourly when air temperature is 40 deg F(4.4 deg C) and below and when 80 deg F(27 deg C) and above, and one test for each composite sample.
5. Compression Test Specimens: ASTM C 31/C 31M; cast and laboratory cure one set of three standard cylinder specimens for each composite sample.
6. Compressive-Strength Tests: ASTM C 39/C 39M; test 1 specimen at 7 days and 2 specimens at 28 days.
a. A compressive-strength test shall be the average compressive strength from 2 specimens obtained from same composite sample and tested at 28 days.
C. Strength of each concrete mix will be satisfactory if average of any 3 consecutive compressive-strength tests equals or exceeds specified compressive strength and no compressive-strength test value falls below specified compressive strength by more than 500 psi(3.4 MPa).
D. Test results shall be reported in writing to Architect, concrete manufacturer, and Contractor within 48 hours of testing. Reports of compressive-strength tests shall contain Project identification name and number, date of concrete placement, name of concrete testing and inspecting agency, location of concrete batch in Work, design compressive strength at 28 days, concrete mixture proportions and materials, compressive breaking strength, and type of break for both 7- and 28-day tests.
E. Nondestructive Testing: Impact hammer, sonoscope, or other nondestructive device may be permitted by Architect but will not be used as sole basis for approval or rejection of concrete.
F. Additional Tests: Testing and inspecting agency shall make additional tests of concrete when test results indicate that slump, air entrainment, compressive strengths, or other requirements have not been met, as directed by Architect.
G. Remove and replace concrete pavement where test results indicate that it does not comply with specified requirements.
H. Additional testing and inspecting, at Contractor's expense, will be performed to determine compliance of replaced or additional work with specified requirements.
3.7 REPAIRS AND PROTECTION
A. Remove and replace concrete pavement that is broken, damaged, or defective or that does not comply with requirements in this Section.
GALESBURG-AUGUSTA MIDDLE SCHOOL PLAYGROUND 321313 - 8
B. Protect concrete from damage. Exclude traffic from pavement for at least 14 days after placement.
C. Maintain concrete pavement free of stains, discoloration, dirt, and other foreign material. Sweep concrete pavement not more than two days before date scheduled for Substantial Completion inspections.
END OF SECTION 32 1313
PROJECT NO. 14-182.22 CONCRETE PAVING JOINT SEALANTS
GALESBURG-AUGUSTA MIDDLE SCHOOL PLAYGROUND 321373 - 1
SECTION 32 1373 - CONCRETE PAVING JOINT SEALANTS
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Cold-applied joint sealants.
B. Related Sections:
1. Section 07 9200 "Joint Sealants" for sealing nontraffic and traffic joints in locations not specified in this Section.
2. Section 32 1313 "Concrete Paving" for constructing joints in concrete pavement.
1.2 ACTION SUBMITTALS
A. Product Data: For each joint-sealant product indicated.
1.3 QUALITY ASSURANCE
A. Installer Qualifications: Manufacturer's authorized representative who is trained and approved for installation of units required for this Project.
1.4 PROJECT CONDITIONS
A. Do not proceed with installation of joint sealants under the following conditions:
1. When ambient and substrate temperature conditions are outside limits permitted by joint-sealant manufacturer or are below 40 deg F (5 deg C).
2. When joint substrates are wet.
3. Where joint widths are less than those allowed by joint-sealant manufacturer for applications indicated.
4. Where contaminants capable of interfering with adhesion have not yet been removed from joint substrates.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Compatibility: Provide joint sealants, backing materials, and other related materials that are compatible with one another and with joint substrates under conditions of service and application, as demonstrated by joint-sealant manufacturer based on testing and field experience.
GALESBURG-AUGUSTA MIDDLE SCHOOL PLAYGROUND 321373 - 2
2.2 COLD-APPLIED JOINT SEALANTS
A. Single-Component, Self-Leveling, Silicone Joint Sealant for Concrete: ASTM D 5893, Type SL.
1. Products: Subject to compliance with requirements, provide one of the following:
a. Crafco Inc., an ERGON company; RoadSaver Silicone SL.
b. Dow Corning Corporation; 890-SL.
c. Pecora Corporation; 300 SL.
2.3 JOINT-SEALANT BACKER MATERIALS
A. Round Backer Rods for Cold- and Hot-Applied Joint Sealants: ASTM D 5249, Type 1, of diameter and density required to control sealant depth and prevent bottom-side adhesion of sealant.
2.4 PRIMERS
A. Primers: Product recommended by joint-sealant manufacturer where required for adhesion of sealant to joint substrates indicated, as determined from preconstruction joint-sealant-substrate tests and field tests.
PART 3 - EXECUTION
3.1 INSTALLATION
A. General: Comply with joint-sealant manufacturer's written installation instructions for products and applications indicated unless more stringent requirements apply.
B. Cleaning of Joints: Clean out joints immediately before installing joint sealants.
C. Joint Priming: Prime joint substrates where indicated or where recommended in writing by joint-sealant manufacturer, based on preconstruction joint-sealant-substrate tests or prior experience. Apply primer to comply with joint-sealant manufacturer's written instructions. Confine primers to areas of joint-sealant bond; do not allow spillage or migration onto adjoining surfaces.
D. Joint-Sealant Installation Standard: Comply with recommendations in ASTM C 1193 for use of joint sealants as applicable to materials, applications, and conditions indicated.
E. Install joint-sealant backings of kind indicated to support joint sealants during application and at position required to produce cross-sectional shapes and depths of installed sealants relative to joint widths that allow optimum sealant movement capability.
1. Do not leave gaps between ends of joint-sealant backings.
2. Do not stretch, twist, puncture, or tear joint-sealant backings.
3. Remove absorbent joint-sealant backings that have become wet before sealant application and replace them with dry materials.
F. Install joint sealants using proven techniques that comply with the following and at the same time backings are installed:
GALESBURG-AUGUSTA MIDDLE SCHOOL PLAYGROUND 321373 - 3
1. Place joint sealants so they directly contact and fully wet joint substrates.
2. Completely fill recesses in each joint configuration.
3. Produce uniform, cross-sectional shapes and depths relative to joint widths that allow optimum sealant movement capability.
G. Provide joint configuration to comply with joint-sealant manufacturer's written instructions unless otherwise indicated.
H. Clean off excess joint sealant or sealant smears adjacent to joints as the Work progresses, by methods and with cleaning materials approved in writing by manufacturers of joint sealants and of products in which joints occur.
END OF SECTION 32 1373
PROJECT NO. 14-182.22 PLAYGROUND PROTECTIVE SURFACING
GALESBURG-AUGUSTA MIDDLE SCHOOL PLAYGROUND 32181613 - 1
SECTION 32 1816.13 - PLAYGROUND PROTECTIVE SURFACING
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Organic loose-fill surface.
1. Section 31 2000 "Earth Moving"
1.2 DEFINITIONS
A. Critical Height: Standard measure of shock…
This is the start of the file's text. The full file is on GovTribe.