The file's text, extracted by GovTribe without its formatting.
Appendix A: Self-Assessment Manual Facilitation with Site Study
| August 26, 2022 |
| Contract Price: $44,700 |
| Project Steps |
| Step Details |
| Step Timing |
| Step Responsibility |
| Step Billing |
| 1. Project Acceptance |
| · Finalized statement of work |
· Signed professional services agreement
· Construction of updated shared web site
| By Monday, September 2, 2024 |
| CPSE and |
Plant City Fire Rescue $3,725.00
| 2. Project Executive Orientation |
| · Discussion of final SOW and identification of resources need for each step |
· Overview of the shared web site
| By Friday, September 20, 2024 |
| CPSE |
| N/A |
| 3. Self-Assessment Writing Team Instruction |
| · Instruction of the CFAI Model competencies and writing requirements for agency Self-Assessment Manual |
| Tuesday, October 22, 2024 and Wednesday, October 23, 2024 |
| CPSE |
| $11,175.00 |
4. Upload of SAM Categories 1,3, and 4
· Agency upload of Category 1 Draft
· Agency upload of Category 3 Draft
· Agency upload of Category 4 Draft
| By Friday, December 6, 2024 |
| Plant City Fire Rescue |
| N/A |
| 5. Technical Review of Categories 1, 3, and 4 |
| · Technical Advisor review and comment on Categories 1, 3, and 4 |
| By Friday, December 13, 2024 |
| CPSE |
| N/A |
| 6. Upload of SAM Categories 9, 10, and 11 |
| · Agency upload of Category 9 Draft |
· Agency upload of Category 10 Draft
· Agency upload of Category 11 Draft
| By Friday, January 24, 2025 |
| Plant City Fire Rescue |
| N/A |
| 7. Technical Review of Categories 9, 10, and 11 |
| · Technical Advisor review and comment on Categories 9, 10 and 11 |
| By Friday, January 31, 2025 |
| CPSE |
| $7,450.00 |
| 8. Upload of SAM Categories 6, 7, and 8 |
| · Agency upload of Category 6 Draft |
· Agency upload of Category 7 Draft
· Agency upload of Category 8 Draft
| By Friday, February 28, 2025 |
| Plant City Fire Rescue |
| N/A |
| 9. Technical Review of Categories 6, 7, and 8 |
| · Technical Advisor review and comment on Categories 6, 7, and 8 |
| By Tuesday, March 12, 2024 |
| CPSE |
| N/A |
| 10. Upload of SAM Categories 2 and 5 |
| · Agency upload of Category 2 Draft |
· Agency upload of Category 5 Draft; Criteria A, B, C, D, E, F, G, H, I, (J, K, L, if applicable)
| By Friday, April 4, 2025 |
| Plant City Fire Rescue |
| N/A |
| 11. Technical Review of Categories 2 and 5 |
| · Technical Advisor review and comment on Category 2, and the Criteria of Category 5 |
| By Friday, April 11, 2025 |
| CPSE |
| $7,450.00 |
| 12. Final SAM Web Meeting (optional) |
| · Final technical advisor review and wrap up of SAM categories and criteria |
· CPSE & agency exhibit preparation and site study discussion
| By Friday, April 25, 2025 |
| CPSE and |
Plant City Fire Rescue N/A
| 13. Self-Assessment Site Study |
| · Site work activity by 3 technical advisors to evaluate the agency’s CFAI model work |
Monday, May 5, 2025 through Wednesday, May 7, 2025
| 14. Self-Assessment Site Study Report |
| · Technical advisor report and recommendations for agency to consider before becoming a CFAI candidate agency |
| By Friday, May 16, 2025 |
| CPSE |
| N/A |
Acceptance:
| City of Plant City, FL |
| Initials of Authorized Party: |
| Bill McDaniel, City Manager |
| Center for Public Safety Excellence (CPSE) |
| Initials of Authorized Party: |
| Debbie Sobotka, COO |
image1.gif