Plans-FINAL PLANS AO2023 14.pdf
PDF 11 MB Posted
- Solicitation number
- B27000820
- Issued by
- Hawaii
About this file
Document Summary
This file contains 100% construction documents for the UST and AST Closure project at Kawaihapai Airfield in Mokuleia, Oahu, Hawaii (Project No. AO2023-14), prepared for the State of Hawaii Department of Transportation Airports. The scope of work consists of demolishing and removing the existing 12,000-gallon underground storage tank (UST) system for aviation fuel (Avgas), associated above-ground storage tank (AST) infrastructure, underground piping, fuel dispensing equipment, control panels, flow meters, hose reels, electrical conduits, grounding systems, concrete pads and aprons, and all related appurtenances. The project includes backfilling excavation areas with appropriate fill materials, restoring pavements with asphalt concrete, stabilizing restored surfaces with topsoil and grass (El Toro Zoysia), and conducting verification soil sampling following tank removal in accordance with Hawaii Department of Health Technical Guidance Manual requirements. Construction activities are limited to 8:00 a.m. to 3:30 p.m., Monday through Friday, excluding holidays unless otherwise permitted by the State. The civil engineer is Toru R. Kumagai of Lokahi Environmental; mechanical and electrical engineering is provided by The Chong Group, LLC. The construction documents are dated July 24, 2026, with revision 16 showing 16 total sheets.
The contractor must comply with Hawaii Administrative Rules Chapter 11-280.1 regarding underground storage tank removal, obtain all necessary permits and notifications to the Hawaii Department of Health, prepare a comprehensive work plan including tank and piping cleaning and confirmation sampling, properly dispose of residual fuel and tank sludge per federal, state, and local regulations, conduct verification sampling of excavation areas using multi-increment sampling methodology, and submit a tank closure report with analytical results upon completion. Additional requirements include comprehensive erosion and sediment control measures with temporary and permanent stabilization, AOA traffic control procedures with continuous radio monitoring, storm water pollution prevention compliance including NPDES permitting for construction activities disturbing one or more acres, and archaeological monitoring protocols with immediate notification to authorities if human remains or artifacts are discovered. The contractor must provide full site safety responsibility, defend and indemnify the State and Engineer from liability, install all temporary erosion control measures prior to ground disturbance with AIR-EE inspection approval before commencing work, maintain weekly inspections throughout construction, and remove temporary controls only after permanent stabilization is established and approved.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Specifications-FINAL SPECIFICATIONS w NTB AO2023 14.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TITLE SHEET, PROJECT LOCATION,
AND AIRPORT VICINITY MAP
G-001
P:
\P
R O
JE
C
TS
\2
PR
O
JE
C
TS
\1
8-
H D
O T
AI
R
PO
R
TS
U
ST
C
LO
SU
R
E\
D
ES
IG
N
\A O
-1
H D
H \1
C O
N
ST
R U
C
TI
O N
D O
C U
M
EN
TS
R
EV
IS
O N
\P
LA
N
S\
-G
EN
ER
AL
\A O
-1 4_
1_
G
1.
D
W G
, 8 /2
5/
:3
PM
Hilo International Airport
Dillingham Airfield
Hilo International Airport
Dillingham Airfield
PROJECT TEAM
PROJECT LOCATION
PROJECT NO. AO2023-14
TORU R. KUMAGAI
CIVIL ENGINEER
CIVIL:
LOKAHI ENVIRONMENTAL
2024 NORTH KING STREET
SUITE 200
HONOLULU HI 96819
(808) 842-1133
UST AND AST CLOSURE
MECHANICAL:
THE CHONG GROUP, LLC
900 FORT STREET MALL
SUITE 1230
HONOLULU HI 96813
(808) 791-9855
ELECTRICAL:
THE CHONG GROUP, LLC
900 FORT STREET MALL
SUITE 1230
HONOLULU HI 96813
(808) 791-9855
MICHAEL A. CHONG
MECHANICAL ENGINEER
MICHAEL A. CHONG
ELECTRICAL ENGINEER
DSGN. DRWN. CHKD. APPD.
OF
NO. DATE REVISION
AO2023-14
SHEETS
04/30/2026
5/2/2025
DATE
100% CONSTRUCTION
DOCUMENTS
MAY 2, 2025
UST AND AST CLOSURE
AT
KAWAIHAPAI AIRFIELD
MOKULEIA, OAHU, HAWAII
This work was prepared by me or under my supervision.
Licensed Expiration Date
STATE OF HAWAII
DEPARTMENT OF TRANSPORTATION
AIRPORTS
PROJECT TITLE :
DATE : DWG. NO.
SHEET :
PROJECT NO.:
SHEET TITLE:
PROJECT LOCATION
STATE OF HAWAII
DEPARTMENT OF TRANSPORTATION
AIRPORTS
PLANS FOR
AT
KAWAIHAPAI AIRFIELD (HDH)
MOKULEIA, OAHU, HAWAII
AIRPORT VICINITY MAP
DEPARTMENT OF TRANSPORTATION
STATE OF HAWAII
APPROVED:
DATEFOR DIRECTOR OF TRANSPORTATION
HAWAII
MAUI
KAHOOLAWE
LANAI
MOLOKAI
OAHU
KAUAI
NIIHAU
Upolu Airport
Waimea-Kohala Airport
Hilo International Airport
Kalaupapa Airport Molokai Airport
Kahului Airport
Lanai Airport Hana Airport
Dillingham Airfield
Lihue Airport
Port Allen Airport
Kapalua Airport
Kalaeloa Airport
Daniel K. Inouye International Airport
Ellison Onizuka Kona International Airport At Keahole
P a c i f i c O c e a n
North
South
EastWest
NENW
SESW
NOT TO SCALE
P a c i f i c O c e a n
TK TK TK TK
SHEET INDEX, CONSTRUCTION
NOTES, AND ABBREVIATION LIST
G-002
P:
\P
R O
JE
C
TS
\2
PR
O
JE
C
TS
\1
8-
H D
O T
AI
R
PO
R
TS
U
ST
C
LO
SU
R
E\
D
ES
IG
N
\A O
-1
H D
H \1
R
EV
IS
IO
N
\P
LA
N S\
-G
EN
ER
AL
\A
O
-1
4_
2_ G
2.
D W
G , 7
/2 4/
:5
PM
SHEET DESCRIPTION
SHEET INDEX
DWG.
NO.
SHT.
NO.
T I T L E
1 G-001 TITLE SHEET, PROJECT LOCATION, AND AIRPORT VICINITY MAP
2 G-002 SHEET INDEX, CONSTRUCTION NOTES, AND ABBREVIATION LIST
C-001
C I V I L
GENERAL CIVIL NOTES 1
E L E C T R I C A L
C-002
C-101
4 GENERAL CIVIL NOTES 2
GENERAL SITE PLANC-102
EROSION AND SEDIMENT CONTROL PLANC-103
EXISTING CONDITIONS PLAN
15 ELECTRICAL SITE PLAN, SINGLE LINE DIAGRAM REMOVAL OF WORK, DETAIL
E-001
16 GROUNDING PLAN AND DETAILS, REMOVAL OF EXIST. ELECT. EQUIPMENT
E-002
E-003
M E C H A N I C A L
PAVEMENT SECTION DETAILS
M-001
M-002
SITE PLAN, MECHANICAL GENERAL NOTES, LEGEND AND ABBREVIATIONS
FUELING SYSTEM PLAN, EQUIPMENT SCHEDULE, PIPING SUMP DETAIL
ABBREVIATION LIST
A.C. ASPHALTIC CONCRETE
AOA AIRPORT OPERATIONS AREA
APPROX. APPROXIMATELY
ARCH. ARCHITECTURAL
ARFF AIRCRAFT RESCUE AND FIRE FIGHTING
ASTM AMERICAN SOCIETY FOR TESTING AND MATERIALS
BC BOTTOM OF CURB
BL BASE LINE
BRL BUILDING RESTRICTION LINE
BMP BEST MANAGEMENT PRACTICES
BOT. BOTTOM
BW BOTTOM OF WALL
C.L. CENTERLINE
CL. CLASS
CMU CONCRETE MASONRY UNITS
C.O. CLEAN OUT
CONC. CONCRETE
CONT. CONTINUED
D6 DRAIN LINE WITH SIZE
DET. DETAIL
DIAM. DIAMETER
D.L. DRAIN LINE
DOTA DEPARTMENT OF TRANSPORTATION AIRPORTS
DWG. DRAWING
E EAST
ELEV. ELEVATION
EP EDGE OF PAVEMENT
EXIST. EXISTING
GAL GALLONS
GALV GALVANIZED
G.I. GALVANIZED IRON
H/HOR. HORIZONTAL
HDOT HAWAII DEPARTMENT OF TRANSPORTATION
HDPE HIGH DENSITY POLYETHYLENE
INV. INVERT
LCJ LONGITUDINAL CONTRACTION JOINT
LONG. LONGITUDINAL
LT. LEFT
M MECHANICAL
MIL MILLIMETER
MIN. MINIMUM
MAX. MAXIMUM
N NORTH
NTS NOT TO SCALE
O.C. ON CENTER
O/S OFFSET
PARA. PARAGRAPH
P.C. PORTLAND CEMENT CONCRETE
PFAS PER- AND POLYFLUOROALKYL SUBSTANCES
R RADIUS
REF. REFERENCE
REINF. REINFORCED
ROFA RUNWAY OBJECT FREE AREA
RSA RUNWAY SAFETY AREA
RT. RIGHT
RWY RUNWAY
S SLOPE
SECT. SECTION
SCH./SCHED. SCHEDULE
SCHED. SHEET
ST STREET
STA STATION
SQ. SQUARE
TCJ TRANSVERSE CONTRACTION JOINT
TCSJ TRANSVERSE CONSTRUCTION JOINT
TWY TAXIWAY
TXL TAXILANE
TC TOP OF CURB
TW TOP OF WALL
TYP. TYPICAL
VERT. VERTICAL
WWF WELDED WIRE FABRIC
GENERAL CONSTRUCTION NOTES
1. ALL WORK SHALL BE DONE IN ACCORDANCE WITH THE STATE
OF HAWAII, "2005 STANDARD SPECIFICATIONS FOR ROAD AND
BRIDGE CONSTRUCTION" AND STATE OF HAWAII DOT
HIGHWAYS DIVISION "STANDARD PLANS" DATED 2008.
2. THE CONTRACTOR SHALL VERIFY THE LOCATION OF ALL
EXISTING UTILITIES, WHETHER SHOWN ON THE PLAN OR NOT,
AND SHALL BE RESPONSIBLE FOR THE REPAIR OR
REPLACEMENT OF SAME IN THE EVENT OF DAMAGES DUE TO
HIS CONSTRUCTION PRACTICES. THE CONTRACTOR SHALL
COORDINATE HIS WORK WITH THE RESPECTIVE UTILITY
COMPANIES.
3. THE CONTRACTOR SHALL NOTIFY THE STATE 48 HOURS
BEFORE THE COMMENCEMENT OF ANY UTILITY LINE WORK
TO SCHEDULE A FIELD REVIEW AND SECURE APPROVAL OF
THE PROPOSED UTILITY LINE LOCATION.
4. THE PROPOSED UTILITY LINE LOCATION SHALL BE LAID OUT
IN THE FIELD PRIOR TO THE CONDUCTING OF THE FIELD
REVIEW BY THE STATE.
5. FIELD ADJUSTMENTS SHALL BE MADE AS DIRECTED BY THE
STATE PRIOR TO THE COMMENCEMENT OF ANY UTILITY LINE
WORK.
6. THE EXISTING PAVEMENT SHALL BE SAW-CUT BEFORE
COMMENCEMENT OF GRADING OR TRENCHING WORK.
7. ANY PAVEMENT MARKINGS, STRUCTURES AND
APPURTENANCES (WITHIN OR OUTSIDE THE CONTRACT ZONE
LIMITS) DAMAGED AND/OR WORN AWAY AS A RESULT OF
CONSTRUCTION OPERATIONS SHALL BE RESTORED TO ITS
ORIGINAL CONDITION, OR BETTER, AS DIRECTED BY THE
STATE.
8. ANY PAVEMENT MARKINGS, STRUCTURES, AND
APPURTENANCES (WITHIN OR OUTSIDE OF THE CONTRACT
ZONE LIMITS) DAMAGED AND/OR WORN AWAY UNDER THE
PERMIT SHALL BE REPAINTED OR RECONSTRUCTED AS
DIRECTED BY THE STATE.
9. NO TRENCHING SHALL BE LEFT OPEN FOR MORE THAN FIVE
(5) WORKING DAYS.
10. DIMENSIONS TAKE PRECEDENCE OVER SCALE.
11. THE CONTRACTOR SHALL VERIFY AND CHECK ALL
DIMENSIONS AND DETAILS ON THE CONSTRUCTION
DRAWINGS AND SPECIFICATIONS FOR ANY DISCREPANCIES.
IF ANY DISCREPANCY OR CONFLICT OCCURS, THE
CONTRACTOR SHALL NOTIFY THE ENGINEER AND SHALL
WAIT FOR CLARIFICATION BEFORE RESUMING OR
COMMENCING WORK ON THE DISCREPANCY ITEM.
12. THE CONTRACTOR SHALL OBSERVE AND COMPLY WITH ALL
FEDERAL, STATE, AND LOCAL LAWS REQUIRED FOR THE
PROTECTION OF PUBLIC HEALTH, SAFETY, AND
ENVIRONMENTAL QUALITY.
13. WORK INCIDENTAL TO THE CONTRACT AND NECESSARY TO
COMPLETE THE PROJECT, ALTHOUGH NOT SPECIFICALLY
REFERRED TO ON THE CONTRACT DOCUMENTS, SHALL BE
FURNISHED AND PERFORMED BY THE CONTRACTOR.
14. THE CONTRACTOR AGREES THAT HE SHALL ASSUME SOLE
AND COMPLETE RESPONSIBILITY FOR THE JOB SITE AND
CONDITIONS DURING THE COURSE OF CONSTRUCTION OF
THIS PROJECT, INCLUDING THE SAFETY OF ALL PERSONS
AND PROPERTY: THAT THIS REQUIREMENT SHALL APPLY
CONTINUOUSLY AND NOT BE LIMITED TO NORMAL WORKING
HOURS: AND THAT THE CONTRACTOR SHALL DEFEND,
INDEMNIFY AND HOLD THE STATE AND ENGINEER HARMLESS
FROM ANY AND ALL LIABILITY, REAL OR ALLEGED, IN
CONNECTION WITH THE PERFORMANCE OF WORK ON THIS
PROJECT, EXCEPTING FOR LIABILITY ARISING FROM THE
SOLE NEGLIGENCE OF THE STATE OR THE ENGINEER.
15. ALL PERMITS SHALL BE OBTAINED BY THE CONTRACTOR.
16. CONSTRUCTION WORK WILL BE PERMITTED ONLY DURING
THE HOURS BETWEEN 8:00 A.M. AND 3:30 P.M. MONDAY
THROUGH FRIDAY EXCEPT HOLIDAYS UNLESS OTHERWISE
PERMITTED BY THE STATE.
17. SURVEY MONUMENT STAKEOUT SHALL BE MADE BY
REGISTERED SURVEYORS ENGAGED BY THE CONTRACTOR.
18. REGISTERED SURVEYORS ENGAGED BY THE CONTRACTOR
SHALL SUBMIT A LETTER TO THE STATE CERTIFYING THAT
THE MONUMENT STAKEOUT AND INSTALLATION IS CORRECT.
19. ALL CONSTRUCTION AND GRADING STAKEOUT SHALL BE
DONE BY A REGISTERED SURVEYOR TO BE ENGAGED BY THE
CONTRACTOR.
20. BENCHMARK INFORMATION LOCATED ON SHEET C002.
21. THE STATE RESERVES THE RIGHT TO MAKE CHANGES TO THE
DRAINAGE SYSTEM AS SUCH CHANGES ARE FOUND TO BE
NECESSARY AS THE LAND IS CLEARED AND EROSION
CONTROL CONSTRUCTION PROGRESSES.
22. THE CONTRACTOR SHALL PROVIDE TO THE STATE RECORD
DRAWINGS OF ALL UTILITIES AND STRUCTURES UPON
COMPLETION OF WORK. SPOT ELEVATIONS SHALL ALSO BE
PROVIDED TO VERIFY THE FINISHED GRADES.
23. THE CONTRACTOR SHALL MAKE ARRANGEMENTS FOR
UTILITIES SUCH AS ELECTRICITY, WATER, ETC., REQUIRED
FOR HIS OPERATIONS AND ALL COSTS SHALL BE BORNE BY
THE CONTRACTOR.
24. NO BLASTING SHALL BE PERMITTED ON THIS PROJECT.
25. THE CONTRACTOR SHALL COORDINATE THE STORAGE OF HIS
MATERIAL WITH THE STATE AND OWNER.
26. THE CONTRACTOR SHALL PROVIDE VEHICULAR ACCESS TO
ALL EXISTING STRUCTURES.
27. THE CONTRACTOR SHALL BE REQUIRED TO PROVIDE
ADEQUATE, SAFE, NONSKID BRIDGING MATERIAL OVER THE
TRENCH, INCLUDING SHORING WHEN TRENCHING IN
PAVEMENT AREAS TO HANDLE ALL TYPES OF VEHICULAR
TRAFFIC. NO TRENCH SHALL BE LEFT OPEN DURING
NON-WORKING HOURS, STRIKES, OR JOB SHUTDOWN.
AC ASPHALT CONCRETE
B BOTTOM
BC BOTTOM CURB
BW BOTTOM WALL
CONC. CONCRETE
DSP DRY STANDPIPE
EB ELECTRICAL BOX
EP EDGE OF PAVEMENT
FAA FEDERAL AVIATION ADMINISTRATION
G GROUND
GP GUARD POST
H HEIGHT
HH HANDHOLE
HT/HTC HAWAIIAN TELCOM
LP LIGHT POLE
MH MANHOLE
MW MONITORING WELL
STA STATION
T TOP
TC TOP CURB
TW WATER
TOPOGRAPHIC SURVEY ABBREVIATION LIST
12 M-004 SECTIONS
11 M-003 SECTIONS
GENERAL CONSTRUCTION NOTES CONTINUED
28. CONTRACTOR SHALL SUBMIT FAA FORM 7460-1, NOTICE TO
PROPOSED CONSTRUCTION OR ALTERATION AT LEAST 45
DAYS PRIOR TO THE START OF CONSTRUCTION OR THE DATE
AN APPLICATION OF A CONSTRUCTION PERMIT IS FILLED,
WHICHEVER IS EARLIEST. CONSTRUCTION EQUIPMENT AND
STAGING AREA HEIGHTS INCLUDING HEIGHTS OF
TEMPORARY CONSTRUCTION CRANES SHALL BE INCLUDED IN
THE SUBMITTAL. THE FORM AND CRITERIA FOR SUBMITTAL
CAN BE FOUND ONLINE AT:
HTTPS://OEAAA.FAA.GOV/OEAAA/EXTERNAL/CONTENT/FORMS.JSP
AOA TRAFFIC CONTROL NOTES
1. THE CONTRACTOR SHALL FURNISH ALL ESCORTS, FLAG
PEOPLE, AND COMMUNICATION DEVICES; AS WELL AS, ALL
AOA TRAFFIC CONTROL DEVICES SPECIFIED IN THE
TECHNICAL PROVISION SECTION 01800 - SPECIAL
REQUIREMENTS FOR CONTRACTORS ON THE AOA.
2. THE CONTRACTOR'S ESCORTS SHALL CONTINUOUSLY
MONITOR RADIO FREQUENCY, INDICATED IN THE TECHNICAL
PROVISION SECTION 01800, FOR ALL POTENTIAL AIRCRAFT
ACTIVITY THAT IS UNFORESEEN.
3. BEFORE STARTING ANY WORK AT EACH WORKDAY, THE
CONTRACTOR SHALL SET UP ALL AOA TRAFFIC CONTROL
DEVICES IN THE ORDER REQUIRED BY THE CONTRACT. AT
THE END OF EACH WORKDAY, THE CONTRACTOR SHALL TAKE
DOWN ALL AOA TRAFFIC CONTROL DEVICES IN THE REVERSE
ORDER.
4. THE CONTRACTOR SHALL NOT TAKE DOWN ANY AOA TRAFFIC
CONTROL DEVICES UNTIL WORK IS COMPLETED IN THE AOA.
5. THE CONTRACTOR SHALL NOT LEAVE THE AOA UNTIL ALL
AOA TRAFFIC CONTROL DEVICES HAVE BEEN TAKEN DOWN.
6. THE CONTRACTOR SHALL NOT LEAVE THE AIRPORT UNTIL
ALL STAGING AREAS ARE CLEARED ACCORDING TO
TECHNICAL PROVISION SECTION 01700 - MOBILIZATION AND
DEMOBILIZATION.
DSGN. DRWN. CHKD. APPD.
OF
NO. DATE REVISION
AO2023-14
SHEETS
04/30/2028
7/24/2026
DATE
100% CONSTRUCTION
DOCUMENTS
JULY 24, 2026
UST AND AST CLOSURE
AT
KAWAIHAPAI AIRFIELD
MOKULEIA, OAHU, HAWAII
This work was prepared by me or under my supervision.
Licensed Expiration Date
STATE OF HAWAII
DEPARTMENT OF TRANSPORTATION
AIRPORTS
PROJECT TITLE :
DATE : DWG. NO.
SHEET :
PROJECT NO.:
SHEET TITLE:
C-5018
14 ELECTRICAL SITE DISTRIBUTION PLAN, SYMBOLS
13 M-005 FUELING SYSTEM PIPING DIAGRAM
AutoCAD SHX Text
LICENSED
AutoCAD SHX Text
PROFESSIONAL
AutoCAD SHX Text W
AutoCAD SHX Text H
AutoCAD SHX Text A
AutoCAD SHX Text No. 17517-C
AutoCAD SHX Text U
AutoCAD SHX Text I
AutoCAD SHX Text I
AutoCAD SHX Text A
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text A
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text S
AutoCAD SHX Text
ENGINEER
DSGN. DRWN. CHKD. APPD.
OF
NO. DATE REVISION
AO2023-14
SHEETS
04/30/2028
7/24/2026
DATE
100% CONSTRUCTION
DOCUMENTS
JULY 24, 2026
UST AND AST CLOSURE
AT
KAWAIHAPAI AIRFIELD
MOKULEIA, OAHU, HAWAII
This work was prepared by me or under my supervision.
Licensed Expiration Date
STATE OF HAWAII
DEPARTMENT OF TRANSPORTATION
AIRPORTS
PROJECT TITLE :
DATE : DWG. NO.
SHEET :
PROJECT NO.:
SHEET TITLE:
CIVIL GENERAL NOTES 1
C-001
CONSTRUCTION NOTES:
1. ALL APPLICABLE CONSTRUCTION WORK SHALL BE DONE IN ACCORDANCE WITH THE
STANDARD SPECIFICATIONS FOR PUBLIC WORK CONSTRUCTION, SEPTEMBER 1984, AS
AMENDED, OF THE DEPARTMENT OF PUBLIC WORKS, CITY & COUNTY OF HONOLULU AND
THE COUNTIES OF KAUAI, MAUI, AND HAWAII.
2. VERIFY AND CHECK ALL DIMENSIONS AND DETAILS SHOWN ON THE DRAWINGS PRIOR TO
THE START OF CONSTRUCTION. ALL CONFLICTS SHALL BE IMMEDIATELY BROUGHT TO THE
ATTENTION OF THE CONTRACTING OFFICER.
3. THE UNDERGROUND PIPES, CABLES OR DUCTING LINES KNOWN TO EXIST BY THE ENGINEER
FROM HIS SEARCH OF RECORDS ARE INDICATED OF THE PLANS. THE CONTRACTOR SHALL
VERIFY THE LOCATIONS AND DEPTHS OF THE FACILITIES AND EXERCISE PROPER CARE IN
EXCAVATING IN THE AREA, WHEREVER CONNECTIONS OF NEW UTILITIES TO EXISTING
UTILITIES ARE SHOWN ON THE PLANS. THE CONTRACTOR SHALL EXPOSE THE EXISTING
LINES AT THE PROPOSED CONNECTIONS TO VERIFY THEIR LOCATIONS AND DEPTHS PRIOR
TO EXCAVATION FOR THE NEW LINES.
4. NO CONTRACTOR SHALL PERFORM ANY CONSTRUCTION OPERATION AS TO CAUSE FALLING
ROCKS, SOIL OR DEBRIS IN ANY FORM TO FALL, SLIDE OR FLOW INTO EXISTING CITY OR
STATE DRAINAGE SYSTEMS, OR ADJOINING PROPERTIES, STREETS OR NATURAL
WATERCOURSES. SHOULD SUCH VIOLATIONS OCCUR, THE CONTRACTOR MAY BE CITED
AND THE CONTRACTOR SHALL IMMEDIATELY MAKE ALL REMEDIAL ACTIONS NECESSARY.
5. THE CONTRACTOR SHALL BE RESPONSIBLE FOR CONFORMANCE WITH THE APPLICABLE
PROVISIONS OF THE WATER QUALITY AND WATER POLLUTION CONTROL STANDARDS
CONTAINED IN HAWAII ADMINISTRATIVE RULES, TITLE 11, CHAPTER 55, “WATER POLLUTION
CONTROL”, AS WELL AS CHAPTER 14 OF THE REVERSED ORDINANCES OF HONOLULU, AS
AMENDED, BEST MANAGEMENT PRACTICES SHALL BE EMPLOYED AT ALL TIMES DURING
CONSTRUCTION.
6. CONFINED SPACE
FOR ENTRY BY STATE PERSONNEL, INCLUDING INSPECTORS AND REPRESENTATIVES, INTO A
PERMIT REQUIRED CONFINED SPACE AS DEFINED IN 29 CFR PART 1910.146(B), THE
CONTRACTOR SHALL BE RESPONSIBLE FOR THE PROVIDING:
I. ALL SAFETY EQUIPMENT REQUIRED BY THE CONFINED SPACE REGULATIONS APPLICABLE
TO ALL PARTIES OTHER THAN THE CONSTRUCTION INDUSTRY, TO INCLUDE, BUT NOT
LIMITED TO, THE FOLLOWING:
a. FULL BODY HARNESSES FOR UP TO TWO PERSONNEL
b. LIFELINE AND ASSOCIATED CLIPS
c. INGRESS/EGRESS AND FULL PROTECTION EQUIPMENT
d. TWO-WAY RADIOS (WALKIE-TALKIES) IF OUT OF LINE-OF-SIGHT,
e. EMERGENCY (ESCAPE) RESPIRATOR (10 MINUTE DURATION).
f. CELLULAR TELEPHONE TO CALL FOR EMERGENCE ASSISTANCE.
g. CONTINUOUS GAS DETECTOR (CALIBRATED) TO MEASURE OXYGEN, HYDROGEN
SULFIDE, CARBON MONOXIDE AND FLAMMABLES (CAPABLE OF MONITORING AT A
DISTANCE AT LEAST 20 FEET AWAY).
h. PERSONAL MULTI-GAS DETECTOR TO BE CARRIED BY INSPECTOR.
II. CONTINUOUS FORCED AIR VENTILATION ADEQUATE TO PROVIDE SAFE ENTRY CONDITIONS.
III. ONE ATTENDANT/RESCUE PERSONNEL TOPSIDE (TWO, IF CONDITIONS WARRANT IT).
IV. ALL SAFETY EQUIPMENT SHALL COMPLY WITH THE STANDARDS OF THE OCCUPATIONAL
SAFETY AND HEALTH ADMINISTRATION AND ALL APPLICABLE FEDERAL, STATE, AND CITY
LAWS AND REGULATIONS RELATING TO SAFETY.
8. ALL EXISTING UTILITIES TO REMAIN IN USE, WHETHER OR NOT SHOWN ON THE PLANS BY
THE CONTRACTOR DURING CONSTRUCTION. ALL DAMAGES TO EXISTING UTILITIES SHALL BE
REPAIRED AND PAID FOR BY THE CONTRACTOR.
9. WHEN TRENCH EXCAVATION IS CLOSE TO OR UNDER EXISTING STRUCTURES OR FACILITIES, THE CONTRACTOR SHALL BE RESPONSIBLE FOR PROPERLY SHEETING, SHORING AND
BRACING THE EXCAVATION AND STABILIZING THE EXISTING GROUND TO RENDER IT SAFE
AND SECURE FROM POSSIBLE SLIDES, CAVE-INS AND SETTLEMENT AND FOR PROPERLY
SUPPORTING EXISTING STRUCTURES AND FACILITIES WITH BEAMS, STRUTS OR
UNDER-PINNING TO FULLY PROTECT THEM FROM DAMAGE.
10. THE CONTRACTOR SHALL RESTORE TO THEIR ORIGINAL CONDITION OR BETTER, ALL
IMPROVEMENTS DAMAGED AS A RESULT OF THE CONSTRUCTION, INCLUDING PAVEMENTS,
EMBANKMENTS, CURBS, SIGNS, LANDSCAPING, STRUCTURES, UTILITIES, WALLS, FENCES,
ETC. UNLESS PROVIDED FOR SPECIFICALLY IN THE PROPOSAL. DEMOLITION AND
RESTORATION OF EXISTING ITEMS SHALL BE INCIDENTAL AND INCLUDED WITHIN THE
AMOUNT PAID FOR UNCLASSIFIED TRENCH EXCAVATION.
11. ALL CONCRETE AND A.C. PAVEMENT TO BE TRENCHED OR RECONSTRUCTED SHALL BE
SAW-CUT TO THE REQUIRED WIDTH PRIOR TO THE CONSTRUCTION.
12. PURSUANT TO CHAPTER 6E, HRS, IN THE EVENT ANY ARTIFACTS OR HUMAN REMAINS ARE
UNCOVERED DURING CONSTRUCTION OPERATIONS, THE CONTRACTOR SHALL IMMEDIATELY
SUSPEND WORK AND NOTIFY THE HONOLULU POLICE DEPARTMENT AND THE STATE
DEPARTMENT OF LAND AND NATURAL RESOURCES-HISTORIC PRESERVATION DIVISION
(692-8015). IN ADDITION, FOR NON-CITY PROJECTS, THE CONTRACTOR SHALL INFORM THE
CITY DEPARTMENT OF PLANNING PERMITTING, CIVIL ENGINEERING BRANCH.
STOCKPILING NOTES:
1. ALL STOCKPILING WORK SHALL BE DONE IN ACCORDANCE WITH CHAPTER 18A, ARTICLES 1, 2, 3 AND 4, AS RELATED TO STOCKPILING, SOIL EROSION AND SEDIMENT CONTROL, OF THE
REVISED ORDINANCES OF HONOLULU, 2021, AS AMENDED.
2. NO CONTRACTOR SHALL PERFORM ANY STOCKPILING OPERATION SO AS TO CAUSE FALLING
ROCKS, SOIL OR DEBRIS IN ANY FORM TO FALL, SLIDE OR FLOW ONTO ADJOINING
PROPERTIES, STREETS OR NATURAL WATERCOURSES. SHOULD SUCH VIOLATIONS OCCUR,
THE CONTRACTOR MAY BE CITED AND THE CONTRACTOR SHALL IMMEDIATELY MAKE ALL
REMEDIAL ACTIONS NECESSARY.
3. THE CONTRACTOR, AT HIS OWN EXPENSE, SHALL KEEP THE PROJECT AREA AND
SURROUNDING AREA FREE FROM DUST NUISANCE. THE WORK SHALL BE IN CONFORMANCE
WITH THE AIR POLLUTION CONTROL STANDARDS CONTAINED IN THE HAWAII
ADMINISTRATIVE RULES, TITLE 11, CHAPTER 60.1, “AIR POLLUTION CONTROL”.
4. THE UNDERGROUND PIPES, CABLES OR DUCTLINES KNOWN TO EXIST BY THE ENGINEER
FROM HIS SEARCH OF RECORDS ARE INDICATED ON THE PLANS. THE CONTRACTOR SHALL
VERIFY THE LOCATIONS AND DEPTHS OF THE FACILITIES AND EXERCISE PROPER CARE IN
EXCAVATING IN THE AREA. WHEREVER CONNECTIONS OF NEW UTILITIES ARE SHOWN ON
THE PLANS, THE CONTRACTOR SHALL EXPOSE THE EXISTING LINES AT THE PROPOSED
CONNECTIONS TO VERIFY THEIR LOCATIONS AND DEPTHS PRIOR TO EXCAVATION FOR THE
NEW LINES.
5. ADEQUATE PROVISIONS SHALL BE MADE TO PREVENT SURFACE WATERS FROM DAMAGING
THE CUT FACE OF AN EXCAVATION OR THE SLOPED SURFACES OF A FILL. FURTHERMORE,
ADEQUATE PROVISIONS SHALL BE MADE TO PREVENT SEDIMENT-LADEN RUNOFF FROM
LEAVING THE SITE.
6. ALL SLOPES AND EXPOSED AREAS SHALL BE SODDED OR PLANTED AS SOON AS FINAL
GRADES HAVE BEEN ESTABLISHED. PLANTING SHALL NOT BE DELAYED UNTIL ALL
STOCKPILING WORK HAS BEEN COMPLETED. STOCKPILING TO FINAL GRADE SHALL BE
CONTINUOUS, AND ANY AREA WITHIN WHICH WORK HAS BEEN INTERRUPTED OR DELAYED
SHALL BE PLANTED.
7. FILLS ON SLOPES STEEPER THAN 5:1 SHALL BE KEYED.
8. THE CITY SHALL BE INFORMED OF THE LOCATION OF THE BORROW SITE FOR THE PROJECT
WHEN THE APPLICATION FOR A STOCKPILING PERMIT IS MADE. THE BORROW SITE MUST
ALSO FULFILL THE REQUIREMENTS OF THE GRADING ORDINANCE.
9. NO STOCKPILING WORK SHALL BE DONE ON SATURDAYS, SUNDAYS AND HOLIDAYS AT ANY
TIME WITHOUT PRIOR NOTICE TO DOT-AIR, PROVIDED SUCH STOCKPILING WORK IS ALSO IN
CONFORMANCE WITH THE COMMUNITY NOISE CONTROL STANDARDS CONTAINED IN THE
HAWAII ADMINISTRATIVE RULES, TITLE 11, CHAPTER 46, “COMMUNITY NOISE CONTROL”.
10. THE LIMITS OF THE AREA TO BE STOCKPILED SHALL BE FLAGGED BEFORE THE
COMMENCEMENT OF THE STOCKPILING WORK.
11. THE GENERAL CONTRACTOR/DEVELOPER/OWNER OF THE PROJECT SHALL BE RESPONSIBLE
FOR ALL STOCKPILING OPERATIONS TO BE PERFORMED IN CONFORMANCE WITH
APPLICABLE PROVISIONS OF THE HAWAII ADMINISTRATIVE RULES, TITLE 11, CHAPTER 54,
"WATER QUALITY STANDARDS," AND TITLE 11, CHAPTER 55, "WATER POLLUTION CONTROL",
AS WELL AS CHAPTER 14 OF THE REVISED ORDINANCES OF HONOLULU, AS AMENDED. BEST
MANAGEMENT PRACTICES SHALL BE EMPLOYED AT ALL TIMES DURING CONSTRUCTION.
THE GENERAL CONTRACTOR/DEVELOPER/OWNER OF THE PROJECT SHALL OBTAIN NATIONAL
POLLUTANT DISCHARGE ELIMINATION SYSTEM (NPDES) PERMIT COVERAGE(S) FOR THE
FOLLOWING:
1. STORM WATER DISCHARGES ASSOCIATED WITH CONSTRUCTION ACTIVITIES THAT DISTURB
ONE (1) ACRE OR MORE, AND
2. DISCHARGES OF HYDROTESTING EFFLUENT, DEWATERING EFFLUENT, AND WELL DRILLING
EFFLUENT TO STATE WATERS.
IN ACCORDANCE WITH STATE LAW, ALL DISCHARGES RELATED TO PROJECT CONSTRUCTION OR
OPERATIONS ARE REQUIRED TO COMPLY WITH STATE WATER QUALITY STANDARDS (HAWAII
ADMINISTRATIVE RULES, CHAPTER 11-54). BEST MANAGEMENT PRACTICES SHALL BE USED TO
MINIMIZE OR PREVENT THE DISCHARGE OF SEDIMENT, DEBRIS, AND OTHER POLLUTANTS TO
STATE WATERS. PERMIT COVERAGE IS AVAILABLE FROM THE DEPARTMENT OF HEALTH, CLEAN
WATER BRANCH AT HTTP://HEALTH.HAWAII.GOV/CWB. THE OWNER/DEVELOPER/CONTRACTOR IS
RESPONSIBLE FOR OBTAINING OTHER FEDERAL, STATE, OR LOCAL AUTHORIZATIONS AS
REQUIRED BY LAW.
12. WHERE APPLICABLE AND FEASIBLE THE MEASURES TO CONTROL EROSION AND OTHER
POLLUTANTS SHALL BE IN PLACE BEFORE ANY STOCKPILING WORK IS INITIATED.
13. TEMPORARY EROSION CONTROLS SHALL NOT BE REMOVED BEFORE PERMANENT EROSION
CONTROLS ARE IN-PLACE AND ESTABLISHED.
14. IF THE STOCKPILING WORK INVOLVES CONTAMINATED SOIL, THEN ALL STOCKPILING WORK
SHALL BE DONE IN CONFORMANCE WITH APPLICABLE STATE AND FEDERAL REQUIREMENTS.
15. ALL STOCKPILING AND CONSTRUCTION WORK SHALL IMPLEMENT MEASURES TO ENSURE
THAT THE DISCHARGE OF POLLUTANTS FROM THE CONSTRUCTION SITE WILL BE REDUCED
TO THE MAXIMUM EXTENT PRACTICABLE AND WILL NOT CAUSE OR CONTRIBUTE TO AN
EXCEEDANCE OF WATER QUALITY STANDARDS.
16. NON-COMPLIANCE TO ANY OF THE ABOVE REQUIREMENTS SHALL MEAN IMMEDIATE
SUSPENSION OF ALL WORK, AND REMEDIAL WORK SHALL COMMENCE IMMEDIATELY. ALL
COSTS INCURRED SHALL BE BILLED TO THE VIOLATOR. FURTHERMORE, VIOLATORS SHALL
BE SUBJECTED TO ADMINISTRATIVE, CIVIL AND/OR CRIMINAL PENALTIES.
17. FOR BENCH MARK, SEE SHEET C101.
18. LIFE OF THE STOCKPILE SHALL BE 30 DAYS.
EROSION PREVENTION/ SEDIMENT CONTROL NOTES:
1. THE CONTRACTOR SHALL FOLLOW THE GUIDELINES IN THE STATE OF HAWAII, DEPARTMENT
OF TRANSPORTATION - AIRPORTS (DOTA) CONSTRUCTION SITE RUNOFF/PBMP PROGRAM,
WHICH INCLUDES, BUT IS NOT LIMITED TO, THE DOTA CONSTRUCTION ACTIVITIES BMP
MANUAL AND ENVIRONMENTAL REQUIREMENTS FOR CONSTRUCTION PROJECTS STANDARD
OPERATING PROCEDURES.
2. PRIOR TO ANY EARTH DISTURBING ACTIVITIES, THE CONTRACTOR SHALL INSTALL
TEMPORARY EROSION CONTROL MEASURES. THE AREA OF SOIL DISTURBANCE SHALL BE
LIMITED TO THAT NECESSARY TO INSTALL THE THE TEMPORARY EROSION CONTROL
MEASURES. UPON COMPLETION OF THE TEMPORARY EROSION CONTROL INSTALLATION,
THE CONTRACTOR SHALL REQUEST AN INSPECTION CONDUCTED BY AIR-EE. THE SCHEDULE
OF THE INSPECTION IS SUBJECT TO THE AVAILABILITY OF THE AIR-EE INSPECTOR.
CONSTRUCTION ACTIVITIES CAN ONLY COMMENCE AFTER ALL DEFICIENCIES THAT ARE
OBSERVED DURING THE INSPECTION ARE PROPERLY ADDRESSED AND DOCUMENTED.
3. SLOPE PROTECTION IS REQUIRED ON AREAS WITH SLOPES GREATER THAN 15% AND ON
AREAS OF MODERATE SLOPE THAT ARE PRONE TO EROSION UNLESS THEY ARE BEING
ACTIVELY WORKED. USE DIVERSION UPSTREAM OF SLOPE (DIKES, SWALES, SLOPE DRAINS)
TO DIVERT WATER AROUND THE SLOPE. PROVIDE A 10-FT BUFFER ZONE AT THE TOE OF
SLOPE. ONLY 5 ACRES MAY BE DISTURBED AT ANYTIME ON SLOPES GREATER THAN 15%.
4. TEMPORARY STABILIZATION IS REQUIRED ON DISTURBED AREAS WHICH ARE AT FINAL
GRADE OR WHEN THE DISTURBED AREA WILL NOT BE WORKED FOR 14 CONSECUTIVE DAYS
OR MORE. STABILIZATION MUST COMMENCE IMMEDIATELY AND BE COMPLETED WITHIN THE
14 DAY PERIOD.
5. TEMPORARY EROSION CONTROLS SHALL NOT BE REMOVED PRIOR TO THE PERMANENT
STABILIZATION OF THE SITE. THE CONTRACTOR SHALL SUBMIT THEIR REQUEST FOR FINAL
BMP INSPECTION TO AIR-EE ONCE PERMANENT STABILIZATION IS ESTABLISHED. SCHEDULE
OF THE FINAL BMP INSPECTION IS SUBJECT TO THE AVAILABILITY OF THE AIR-EE
INSPECTOR. TEMPORARY EROSION CONTROL MEASURES CAN ONLY BE REMOVED AFTER
ALL DEFICIENCIES THAT ARE OBSERVED DURING THE FINAL BMP INSPECTION ARE
PROPERLY ADDRESSED AND DOCUMENTED.
6. MINIMIZE SOIL COMPACTION AREAS WHERE FINAL STABILIZATION OR INFILTRATION
PRACTICES WILL BE INSTALLED SHALL BE PROTECTED FROM EXCESSIVE COMPACTION
DURING CONSTRUCTION. VEHICLE AND EQUIPMENT USE SHALL BE RESTRICTED OR
TECHNIQUES TO CONDITION THE SOILS TO SUPPORT VEGETATION SHALL BE IMPLEMENTED
IN THE AREAS THAT HAVE BEEN COMPACTED AND ARE DESIGNATED TO REMAIN
VEGETATIVE OR POST-CONSTRUCTION INFILTRATION AREAS.CLEARLY MARK THE AREAS TO
BE AVOIDED WITH FLAGS OR TEMPORARY FENCING. WHERE TEMPORARY FENCING IS USED,
FENCING MUST BE ADEQUATELY SUPPORTED BY POSTS AND MAINTAINED IN AN UPRIGHT
POSITION.
7. PERIMETER CONTROLS ARE REQUIRED DOWN SLOPE OF ALL DISTURBED AREAS. MAINTAIN
DOWNSTREAM VEGETATED AREA.
8. INLET PROTECTION
A. ALL STORM DRAIN INLETS ONSITE AND THOSE OFFSITE WHICH MAY RECEIVE RUNOFF FROM
THE SITE SHALL USE AN INLET PROTECTION DEVICE UNLESS THEY ARE DIRECTED TO A
SEDIMENT BASIN.
B. SEDIMENT LEVELS MAY NOT EXCEED ONE THIRD OF THE HEIGHT OF A SEDIMENT BARRIER
OR INLET PROTECTION DEVICE AT ANY POINT ALONG THE LENGTH OF THE SEDIMENT
BARRIER OR THE INLET PROTECTION DEVICE.
C. SEDIMENT BARRIERS AND INLET PROTECTION DEVICES MUST BE UNCLOGGED AND
CLEANED WHEN PERFORMANCE IS COMPROMISED.
D. TORN, WEATHERED OR SAGGING SEDIMENT BARRIERS OR INLET PROTECTION DEVICES
MUST BE REPAIRED OR REPLACED IMMEDIATELY.
E. EACH INLET PROTECTION MUST BE INSPECTED AFTER EVERY RAINFALL EVENT, AND ANY
ACCUMULATED SEDIMENT AND DEBRIS MUST BE REMOVED.
10. TRACKING CONTROL
A. MINIMIZE SEDIMENT TRACK-OUT ONTO OFF-SITE STREETS, OTHER PAVED AREAS, AND
SIDEWALKS FROM VEHICLES EXITING THE CONSTRUCTION SITE BY RESTRICTING VEHICLE
TRAFFIC TO PROPERLY DESIGNATED AREAS AND USING ADDITIONAL CONTROLS TO
REMOVE SEDIMENT FROM VEHICLE TIRES PRIOR TO EXITING THE SITE.
B. VEHICULAR PARKING AND MOVEMENT ON PROJECT SITES MUST BE CONFINED TO PAVED
SURFACES OR PREDEFINED PARKING AREAS AND VEHICLE PATHS, WHICH SHALL BE
MARKED WITH FLAGS OR BOUNDARY FENCING.
C. ALL POLLUTANTS AND MATERIALS THAT ARE DROPPED, WASHED, TRACKED, SPILLED, OR
OTHERWISE DISCHARGED FROM A PROJECT SITE TO OFF-SITE STREETS, SIDEWALKS MUST
BE CLEANED USING DRY METHODS SUCH AS SWEEPING OR VACUUMING.
D. WASHING POLLUTANTS AND MATERIALS THAT ARE DISCHARGED FROM THE PROJECT SITE
TO THE MS4 INTO DRAIN INLETS OR CATCH BASINS IS PROHIBITED UNLESS THE MATERIAL IS
SEDIMENT AND THE INLETS ARE DIRECTED TO A SEDIMENT BASIN OR SEDIMENT TRAP.
PROJECT SEQUENCE
1. INSTALL TEMPORARY EROSION CONTROL MEASURES INCLUDING BUT NOT LIMITED TO,
STABILIZED CONSTRUCTION ENTRANCES, PERIMETER CONTROLS, AND INLET PROTECTION
FOR PROTECTED AREAS, CLEARING AND GRUBBING AS NECESSARY FOR THE INSTALLATION
OF THESE BMPS.
2. SCHEDULE AN INSPECTION OF THE TEMPORARY BMPS WITH AIR-EE. THE SCHEDULE OF THE
INSPECTION IS SUBJECT TO THE AVAILABILITY OF THE AIR-EE INSPECTOR. DOCUMENT AND
ADDRESS ANY DEFICIENCIES FOUND DURING THE INSPECTION.
3. RELOCATE, RECONSTRUCT AND MAINTAIN BMPS AS NEEDED TO KEEP THEM EFFECTIVE AT
ALL TIMES. INITIATE TEMPORARY STABILIZATION IMMEDIATELY ONCE GRADING IS
COMPLETED.
4. PROCEED WITH CONSTRUCTION WITH LEAST POSSIBLE DISTURBANCE OF VEGETATIVE
AREAS AND TEMPORARY STRUCTURES.
5. SCHEDULE FINAL BMP INSPECTION WITH AIR-EE (SCHEDULE SUBJECT TO THE AVAILABILITY
OF THE AIR-EE INSPECTOR). DOCUMENT AND ADDRESS ANY OBSERVED DEFICIENCIES
DURING THE FINAL BMP INSPECTION.
6. REMOVE OR DISMANTLE TEMPORARY EROSION CONTROL STRUCTURES AFTER FULL
ESTABLISHMENT OF PERMANENT VEGETATIVE COVER, PAVEMENT, OR PROPOSED FINISHED
SURFACE.
7. PRACTICE GOOD HOUSEKEEPING MEASURES THROUGHOUT THE DURATION OF
CONSTRUCTION.
8. INSPECTIONS SHALL BE PERFORMED WEEKLY.
RAIN RESPONSE PLAN
1. THE FOLLOWING WILL BE PERFORMED WHEN HEAVY RAINS, TROPICAL STORM OR
HURRICANE IS IMMINENT OR IS FORECASTED IN THE NEXT 48 HOURS:
A. TEMPORARY SUSPENSION OF ACTIVE GRADING, GRUBBING AND TRENCHING.
B. INSPECT ALL PERIMETER CONTROLS AND INLET PROTECTION DEVICES, AND MAINTAIN AS
NEEDED. INLET PROTECTION DEVICES ARE NOT ALLOWED TO BE REMOVED UNTIL DIRECTED
BY THE AIRPORT MANAGER OR WHEN THERE IS AN IMMEDIATE THREAT OCCURRING TO
PUBLIC SAFETY. THE AIRPORT MANAGER WILL JUDGE THE SEVERITY OF ANY APPROACHING
STORM AND ISSUE DIRECTIVES, AS NEEDED. ALL INLET PROTECTION DEVICES MUST BE
REINSTALLED IMMEDIATELY HAVE THE CESSATION OF THE SEVERE WEATHER AND THREAT
TO PUBLIC SAFETY.
C. RE-INSPECT AFTER THE APPROACHING HEAVY RAINS, TROPICAL STORM OR HURRICANE
AND REPLACE OR MAINTAIN BMPS AS NEEDED.
GOOD HOUSEKEEPING BMPS
1. STREET SWEEPING AND VACUUMING. ALL POLLUTANTS DISCHARGED FROM CONSTRUCTION
SITE TO OFF-SITE AREAS MUST BE SWEPT OR VACUUMED EACH DAY BEFORE LEAVING THE
JOB SITE.
2. MATERIALS DELIVERY, STORAGE AND USE MANAGEMENT. PREVENT, REDUCE, OR ELIMINATE
THE DISCHARGE OF POLLUTANTS FROM MATERIAL DELIVERY, STORAGE, AND USE TO THE
STORM WATER SYSTEM OR WATERCOURSED BY MINIMIZING THE STORAGE OF HAZARDOUS
MATERIALS ONSITE, STORING MATERIALS IN A DESIGNATED AREA, INSTALLING SECONDARY
CONTAINMENT. CONSTRUCTION MATERIALS, WASTE, TOXIC AND HAZARDOUS SUBSTANCES,
STOCKPILES AND OTHER SOURCES OF POLLUTION SHALL NOT BE STORED IN BUFFER
AREAS, NEAR AREAS OF CONCENTRATED FLOW, OR AREAS ABUTTING THE MS4, RECEIVING
WATERS, OR DRAINAGE IMPROVEMENTS THAT DISCHARGE OFF-SITE. PRIMARY AND
SECONDARY CONTAINMENT CONTROLS AND COVERS SHALL BE IMPLEMENTED TO THE MEP.
3. SPILL PREVENTION AND CONTROL. CREATE AND IMPLEMENT SPILL PREVENTION AND
RESPONSE PLANS TO ELIMINATE AND MINIMIZE THE DISCHARGE OF POLLUTANTS TO THE
MS4 AND RECEIVING WATERS FROM LEAKS AND SPILLS BY REDUCING THE CHANCE FOR
SPILLS, ABSORBING, CONTAINING, AND CLEANING UP SPILLS AND PROPERLY DISPOSING OF
SPILL MATERIALS. AT A MINIMUM, ALL PROJECTS SHALL CLEANUP ALL LEAKS AND SPILLS
IMMEDIATELY.
4. STOCKPILE MANAGEMENT. STOCKPILES SHALL NOT BE LOCATED IN DRAINAGE WAYS,
WITHIN 50 FEET FROM AREAS OF CONCENTRATED FLOWS, AND ARE NOT ALLOWED IN THE
STATE RIGHT-OF-WAY. SEDIMENT BARRIERS OR SILT FENCES SHALL BE USED AROUND THE
BASE OF ALL STOCKPILES. STOCKPILES SHALL NOT EXCEED 15 FEET IN HEIGHT.
STOCKPILES GREATER THAN 15 FEET IN HEIGHT SHALL REQUIRE 8 FOOT WIDE BENCHING.
STOCKPILES MUST BE COVERED WITH PLASTIC SHEETING OR A COMPARABLE MATERIAL
WHEN THEY ARE INACTIVE OR BY THE END OF THE WORK SHIFT, WHICHEVER IS SOONER.
5. HAZARDOUS MATERIALS. PREVENT OR REDUCE THE DISCHARGE OF POLLUTANTS TO
STORM WATER FROM HAZARDOUS WASTE THROUGH PROPER MATERIAL USE, MATERIAL
STORAGE, AND WASTE DISPOSAL. IN THE EVEN THAT HAZARDOUS MATERIALS ARE
DISCHARGED ONTO THE GROUND OR MS4, THE CONTRACTOR SHALL IMMEDIATELY NOTIFY
THE HAWAII DEPARTMENT OF HEAL TH (DOH) HAZARD EVALUATION AND EMERGENCY
RESPONSE (HEER) OFFICE, DOH CLEAN WATER BRANCH (CWB), THE AIRPORT MANAGER,
DOTA STATE PROJECT MANAGER, AND DOTA AIR-EE. A WRITTEN REPORT DESCRIBING THE
DATE AND TIME OF DISCHARGE, DESCRIPTION OF EVENTS, POLLUTANTS THAT WERE
DISCHARGED, THE REASONS OR CAUSE FOR THE DISCHARGE, SPILL RESPONSE, AND THE
MEASURES THAT HAVE BEEN TAKEN OR WILL BE TAKEN TO PREVENT A RECURRENCE OF
THE DISCHARGE SHALL BE SUBMITTED TO DOH HEER OFFICE AND DOTA AIR-EE WITHIN 30
DAYS OF THE DISCHARGE. A SPILL REPORTING FORM SHALL ALSO BE FILLED OUT AND
SUBMITTED TO AIR-EE WITHIN 30 DAYS OF THE DISCHARGE. THE CONTRACTOR SHALL
REFER TO THE HNL SPILL REPORTING FACT SHEET FOR THE SPILL REPORTING FORM AND
ADDITIONAL INFORMATION.
6. NONHAZARDOUS MATERIALS. IN THE EVENT THAT NONHAZARDOUS MATERIALS ARE
DISCHARGED TO THE MS4, THE CONTRACTOR SHALL IMMEDIATELY NOTIFY THE DOH HEER
OFFICE, DOH CWB, AIRPORT MANAGER, DOTA STATE PROJECT MANAGER, AND DOTA AIR-EE.
A WRITTEN REPORT DESCRIBING THE DATE AND TIME OF DISCHARGE, DESCRIPTION OF
EVENTS, POLLUTANTS THAT WERE DISCHARGED, THE REASONS OR CAUSE FOR THE
DISCHARGE, SPILL RESPONSE, AND THE MEASURES THAT HAVE BEEN TAKEN OR WILL BE
TAKEN TO PREVENT A RECURRENCE OF THE DISCHARGE SHALL BE SUBMITTED TO DOH
HEER OFFICE, DOH CWB, AND DOTA AIR-EE WITHIN 30 DAYS OF DISCHARGE. A SPILL
REPORTING FORM SHALL ALSO BE FILLED OUT AND SUBMITTED TO AIR-EE WITHIN 30 DAYS
OF THE DISCHARGE. THE CONTRACTOR SHALL REFER TO THE HNL SPILL REPORTING FACT
SHEET FOR THE SPILL REPORTING FORM AND ADDITIONAL INFORMATION.
7. VEHICLE AND EQUIPMENT CLEANING. ELIMINATE AND MINIMIZE THE DISCHARGE OF
POLLUTANTS TO STORM WATER FROM VEHICLE AND EQUIPMENT CLEANING OPERATIONS
BY USING OFF-SITE FACILITIES WHEN FEASIBLE, WASHING IN DESIGNATED, CONTAINED
AREAS ONLY, AND ELIMINATING DISCHARGES TO THE STORM DRAIN SYSTEM BY
EVAPORATING AND/OR TREATING WASH WATER, AS APPROPRIATE OR INFILTRATING WASH
WATER FOR EXTERIOR CLEANING ACTIVITIES THAT USE WATER ONLY.
8. VEHICLE AND EQUIPMENT FUELING. PREVENT FUEL SPILLS AND LEAKS BY USING OFF-SITE
FACILITIES, FUELING ONLY IN DESIGNATED AREAS, ENCLOSING OR COVERING STORED
FUEL, AND IMPLEMENTING SPILL CONTROLS SUCH AS SECONDARY CONTAINMENT AND
ACTIVE MEASURES USING SPILL RESPONSE KITS.
9. VEHICLE AND EQUIPMENT MAINTENANCE. ELIMINATE AND MINIMIZE THE DISCHARGE OF
POLLUTANTS TO STORM WATER FROM VEHICLE AND EQUIPMENT MAINTENANCE
OPERATIONS BY USING OFF-SITE FACILITIES WHEN FEASIBLE, PERFORMING WORK IN
DESIGNATED AREAS ONLY, USING SPILL PADS UNDER VEHICLES AND EQUIPMENT,
CHECKING FOR LEAKS AND SPILLS, AND CONTAINING AND CLEANING UP SPILLS
IMMEDIATELY.
10. SOLID WASTE MANAGEMENT. PREVENT OR REDUCE DISCHARGE OF POLLUTANTS TO THE
LAND, GROUNDWATER, AND IN STORM WATER FROM SOLID WASTE OR CONSTRUCTION AND
DEMOLITION WASTE BY PROVIDING DESIGNATED WASTE COLLECTION AREAS, COLLECT SITE
TRASH DAILY, AND ENSURING THAT CONSTRUCTION WASTE IS COLLECTED, REMOVED, AND
DISPOSED OF ONLY AT AUTHORIZED DISPOSAL AREAS. SOLID WASTE SHALL BE COVERED
OR PLACED UNDER COVER TO PREVENT CONTACT WITH STORM WATER. TRUCKS HAULING
SOLID WASTE, SOIL, OR AGGREGATE MUST BE COVERED WHEN USING THE HAUL
ROADS/ROUTES WITHIN THE AOA.
11. SANITARY/SEPTIC WASTE MANAGEMENT. TEMPORARY AND PORTABLE SANITARY AND
SEPTIC WASTE SYSTEMS SHALL BE MOUNTED OR STAKED IN, WELL-MAINTAINED AND
SCHEDULED FOR REGULAR WASTE DISPOSAL AND SERVICING. SOURCES OF SANITARY
AND/OR SEPTIC WASTE SHALL NOT BE SORTED NEAR THE MS4 OR RECEIVING WATERS.
12. LIQUID WASTE MANAGEMENT. LIQUID WASTE SHALL BE CONTAINED IN A CONTROLLED AREA
SUCH AS A ROLL-OFF BIN OR PORTABLE TANK OF SUFFICIENT VOLUME AND TO CONTAIN
THE LIQUID WASTES GENERATED. CONTAINMENT AREAS OR DEVICES MUST BE
IMPERMEABLE AND LEAK FREE AND SHOULD NOT BE LOCATED WHERE ACCIDENTAL
RELEASE OF THE CONTAINED LIQUID CAN DISCHARGE TO WATER BODIES, CHANNELS, OR
STORM DRAINS. THE LIQUID WASTE SHALL BE UNDER COVER, IN A COVERED CONTAINER OR
IN CONTAINER WITH A LID TO PREVENT CONTACT WITH STORM WATER. IF THE LIQUID
WASTE IS HAZARDOUS MATERIAL, IT MUST BE STORED WITH SECONDARY CONTAINMENT
AND COVERED OR UNDER COVER.
13. CONCRETE WASTE MANAGEMENT. PREVENT OR REDUCE THE DISCHARGE OF POLLUTANTS
TO STORM WATER FROM CONCRETE WASTE BY CONDUCTING WASHOUT OFFSITE OR
PERFORMING ONSITE WASHOUT IN A DESIGNATED AREA CONSTRUCTED AND MAINTAINED IN
SUFFICIENT QUANTITY AND SIZE TO CONTAIN ALL LIQUID AND CONCRETE WASTE
GENERATED BY WASHOUT OPERATIONS. PLASTIC LINING MATERIAL SHOULD BE A MINIMUM
OF 10 MILLIMETER POLYETHYLENE SHEETING AND SHOULD BE FREE OF HOLES, TEARS, OR
OTHER DEFECTS THAT COMPROMISE THE IMPERMEABILITY OF THE MATERIAL
CONTAINMENT AREAS OR DEVICES SHOULD NOT BE LOCATED WHERE ACCIDENTAL
RELEASE OF THE CONTAINED LIQUID CAN DISCHARGE TO WATER BODIES, CHANNELS, OR
STORM DRAINS. WASHOUT FACILITIES MUST BE CLEANED, OR NEW FACILITIES MUST BE
CONSTRUCTED AND READY FOR USE ONCE THE WASHOUT IS 75 PERCENT FULL. FOUR (4)
INCHES OF FREEBOARD MINIMUM MUST BE MAINTAINED. ONCE CONCRETE WASTES ARE
WASHED INTO THE DESIGNATED AREA AND ALLOWED TO HARDEN, THE CONCRETE SHOULD
BE BROKEN UP, REMOVED, AND DISPOSED OF AS SOLID WASTES.
14. FOR MANAGEMENT OF CONTAMINATED SOIL, IF ENCOUNTERED, THE PROJECT WILL NEED
TO FOLLOW THE DOTA PROGRAMMATIC EHE-EHMP
(https://hidot.hawaii.gov/airports/doing-business/engineering/env...rammatic-ehe-ehmp/).
15. MEASURES TO CONTROL EROSION AND OTHER POLLUTANTS AS REFLECTED ON PLANS
SHALL BE IN PLACE BEFORE ANY WORK IS INITIATED. THESE MEASURES SHALL BE
PROPERLY CONSTRUCTED AND MAINTAINED THROUGHOUT THE CONSTRUCTION PERIOD.
16. ALL CONTROL MEASURES SHALL BE CHECKED DAILY AND REPAIRED AS NECESSARY.
17. CONTRACTOR SHALL OBSERVE AND COMPLY WITH THE STATE DEPARTMENT OF HEALTH
REGULATIONS REGARDING STORM WATER DISCHARGE.
18. THE CONTRACTOR, AT HIS OWN EXPENSE, SHALL KEEP THE PROJECT AREAS AND
SURROUNDING AREAS FREE FROM DUST NUISANCE. THE WORK SHALL BE IN
CONFORMANCE WITH AIR POLLUTION CONTROL STANDARDS CONTAINED IN HAWAII
ADMINISTRATIVE RULES: CHAPTER 11-60, "AIR POLLUTION CONTROL".
19. THE CONTRACTOR SHALL ENSURE THAT ALL TIRES OF CONSTRUCTION VEHICLES ARE
SUFFICIENTLY CLEANED OFF SO THAT DIRT OR DEBRIS IS NOT TRACKED OFF THE
CONSTRUCTION SITE. WASHING OFF TIRES WITH WATER WILL NOT BE ACCEPTABLE UNLESS
THE RUNOFF IS CONTAINED AND DOES NOT ENTER THE STORM DRAIN SYSTEM.
20. COVER OR RELOCATE MATERIAL STOCKPILES AND LIQUID MATERIAL CONTAINERS TO AVOID
CONTACT WITH RAINWATER.
21. PLACE SPILL PANS OR OIL-ONLY SPILL PADS UNDER CONSTRUCTION VEHICLES TO PREVENT
RUNOFF FROM CONTACTING ANY SPILLED PETROLEUM PRODUCTS. PROPERLY DISPOSE OF
ANY ACCUMULATED OILY WATER AFTER THE RAIN EVENT.
ARCHAEOLOGICAL NOTES:
1. PURSUANT TO CHAPTER 6E, HRS, IN THE EVENT ANY ARTIFACTS OR HUMAN REMAINS ARE
UNCOVERED DURING CONSTRUCTION OPERATIONS, THE CONTRACTOR SHALL IMMEDIATELY
SUSPEND WORK AND NOTIFY THE HAWAII POLICE DEPARTMENT AND THE STATE
DEPARTMENT OF LAND AND NATURAL RESOURCES, HISTORIC PRESERVATION DIVISION
(692-8015).
2. THE CONTRACTOR MUST FOLLOW THE APPROVED AND MOST CURRENT ARCHAEOLOGICAL
MONITORING AND POST-REVIEW DISCOVERIES PLAN AND U.S. ARMY CULTURAL RESOURCE
INVESTIGATION PERMIT, AND NATIVE AMERICAN GRAVES PROTECTION AND REPATRIATION
ACT (NAGPRA) COMPREHENSIVE AGREEMENT (CA) .
3. THE CONTRACTOR MUST PROVIDE A U.S. ARMY CULTURAL RESOURCE INVESTIGATION
PERMIT PRIOR TO ANY EXCAVATION WORK.
4. THE CONTRACTOR MUST NOTIFY THE STATE ENGINEER PRIOR TO ANY EXCAVATION WORK.
PUBLIC HEALTH, SAFETY, AND CONVENIENCE NOTES:
1. CONTRACTOR SHALL OBSERVE AND COMPLY WITH ALL FEDERAL, STATE, AND LOCAL LAWS
REQUIRED FOR THE PROTECTION OF PUBLIC HEALTH, SAFETY AND ENVIRONMENTAL
QUALITY.
2. THE CONTRACTOR, AT HIS OWN EXPENSE, SHALL KEEP THE PROJECT AND ITS
SURROUNDING AREAS FREE FROM DUST NUISANCE. THE WORK SHALL BE IN
CONFORMANCE WITH THE AIR POLLUTION STANDARDS AND REGULATIONS OF THE STATE
DEPARTMENT OF HEALTH. THE COUNTY AND STATE SHALL REQUIRE SUPPLEMENTARY
MEASURES IF REQUIRED.
3. THE CONTRACTOR SHALL PROVIDE, INSTALL AND MAINTAIN ALL NECESSARY SIGNS, LIGHTS, FLARES, BARRICADES, MARKERS, CONES, AND OTHER PROTECTIVE FACILITIES AND SHALL
TAKE ALL NECESSARY PRECAUTIONS FOR THE PROTECTION, CONVENIENCE AND SAFETY
OF THE PUBLIC.
UST NOTES:
1. CONDUCT UST REMOVAL WORK IN ACCORDANCE WITH HAWAII ADMINISTRATIVE RULES (HAR)
CHAPTER 11-280.1 UNDERGROUND STORAGE TANKS.
2. PROVIDE/OBTAIN ALL NECESSARY NOTIFICATIONS AND PERMITS REQUIRED TO REMOVE THE
EXISTING UST AND INSTALL NEW AST.
3. PREPARE A WORK PLAN, WHICH INCLUDES NOTIFICATION TO THE HAWAII DEPARTMENT OF HEALTH
(HDOH), TANK AND PIPING CLEANING, REMOVAL, AND CONFIRMATION SAMPLING.
4. DISPOSED OF RESIDUAL FUEL, TANK SLUDGE, AND OTHER WASTE IN ACCORDANCE WITH
APPLICABLE FEDERAL, STATE, AND LOCAL REGULATIONS AND REQUIREMENTS.
5. UPON REMOVAL OF THE UST AND ASSOCIATED PIPING, CONDUCT VERIFICATION SOIL SAMPLING
USING A MULTI-INCREMENT SAMPLING METHOD IN ACCORDANCE WITH THE HDOH TECHNICAL
GUIDANCE MANUAL (TGM). COMPLY WITH THE APPLICABLE GUIDANCE IN THE DOH TGM, DOH
ENVIRONMENTAL ACTION LEVEL (EAL) GUIDANCE AND OTHER GUIDANCE DOCUMENTS ON THE HDOH
HAZARD EVALUATION AND EMERGENCY RESPONSE (HEER) WEBSITE. IF GROUNDWATER IS
ENCOUNTERED, COLLECT GROUNDWATER SAMPLES FOR ANALYSIS.
6. IF ANY SIGNS OF CONTAMINATION ARE OBSERVED DURING UST REMOVAL, INFORM THE FINDING
IMMEDIATELY TO THE CONTRACTING OFFICER. CONDUCT EXCAVATION AND REMOVAL OF
CONTAMINATED SOIL IF ENCOUNTERED AFTER OBTAINING APPROVALS FROM THE CONTRACTING
OFFICER.
prop
7. SUBMIT A TANK CLOSURE REPORT INCLUDING THE VERIFICATION SAMPLING AND ANALYTICAL
RESULTS.
TK TK TK TK
AutoCAD SHX Text
LICENSED
AutoCAD SHX Text
PROFESSIONAL
AutoCAD SHX Text W
AutoCAD SHX Text H
AutoCAD SHX Text A
AutoCAD SHX Text No. 17517-C
AutoCAD SHX Text U
AutoCAD SHX Text I
AutoCAD SHX Text I
AutoCAD SHX Text A
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text A
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text S
NO. DATE REVISION
AO2023-14
SHEETS
04/30/2028
7/24/2026
DATE
100% CONSTRUCTION
DOCUMENTS
JULY 24, 2026
UST AND AST CLOSURE
AT
KAWAIHAPAI AIRFIELD
MOKULEIA, OAHU, HAWAII
This work was prepared by me or under my supervision.
Licensed Expiration Date
STATE OF HAWAII
DEPARTMENT OF TRANSPORTATION
AIRPORTS
PROJECT TITLE :
DATE : DWG. NO.
SHEET :
PROJECT NO.:
SHEET TITLE:
CIVIL GENERAL NOTES 2
C-002
ABBREVIATIONS
AC ASPHALT CONCRETE
BC BOTTOM CURB
BFE BASE FLOOD ELEVATION
BLDG BUILDING
BOT. BOTTOM
BW BOTTOM WALL
C CENTERLINE
C.L. CHAIN-LINK
CONN CONNECT
COTG CLEANOUT TO GRADE
CONC. CONCRETE
D DIAMETER OR DRAIN
DET. DETAIL
DWG DRAWING
EA EACH
ELEV./EL. ELEVATION
EP EDGE OF PAVEMENT
ESCP EROSION AND SEDIMENT
CONTROL PLAN
EXIST. EXISTING
FF FINISH FLOOR
FH FIRE HYDRANT
FT FEET
FL FLANGE
GND. GROUND
G.P. GUARD POST/GUY POLE/GATE POST
GV GATE VALVE
HB HOSE BIBB
HDPE HIGH-DENSITY POLYETHYLENE
ICV IRRIGATION CONTROL VALVE
INV INVERT
L LENGTH
LF LINEAR FOOT
LP LIGHT/LAMP POLE
MAX. MAXIMUM
MECH MECHANICAL
MIN. MINIMUM
MH MANHOLE
MJ MECHANICAL JOINT
NOI NOTICE OF INTENT
NPDES NATIONAL POLLUTANT DISCHARGE
ELIMINATION SYSTEM
O/H OVERHEAD
O.C.A. ON CENTER
PAV'T PAVEMENT
P PROPERTY LINE
PVC POLYVINYL CHLORIDE
RD. ROAD
ROW RIGHT OF WAY
RPBP REDUCED PRESSURE
BACKFLOW PREVENTER
S SEWER OR SPREAD
S.L. STREET LIGHT
SMH SEWER MANHOLE
STD. STANDARD
STRUCT. STRUCTURAL
TC TOP OF CURB
TMK TAX MAP KEY
TP TOP PIPE OR TOP PAVEMENT
TS TOP STEM
TW TOP WALL
TYP. TYPICAL
U/G UNDERGROUND
UP UTILITY POLE
U.P./S.L UTILITY POLE W/ STREET LIGHT
W WATER / WIDTH
WL WATER LINE
WM WATER METER
WMH WATER MANHOLE
WV WATER VALVE BOX
L
L
24" MIN OVERLAP
(TYP)
12" DIA. BIOSOCK
COMPOST FILTER SOCK
OR APPROVED EQUAL
(TYP)
AC
P
AV
EM
EN
T
EDGE AC
PAVEMENT
AC PAVEMENT
12" DIA. BIOSOCK COMPOST
FILTER SOCK OR APPROVED
EQUAL (TYP)
PLAN
SECTION
24" MIN OVERLAP
(TYP)
8"X8"X16" CONC BL0CKS AT
10' MAX SPACING TO
STABILIZE SOCKS IN PAVED
AREAS (TYP)
8"X8"X16" CONC BL0CKS AT 10'
MAX SPACING TO STABILIZE
SOCKS IN PAVED AREAS (TYP)
RUNOFF
NOTES:
1. COMPOST SHALL NOT CONTAIN BIOSOLIDS AND SHOULD COMPLY WITH
UNITED STATES ENVIRONMENTAL PROTECTION AGENCY GUIDELINES IN
ACCORDANCE WITH THE CITY AND COUNTY OF HONOLULU STORM
WATER BEST MANAGEMENT PRACTICE MANUAL, NOVEMBER 2011.
2. STAKING IS NOT REQUIRED.
3. OVERLAP ENDS OF BIOSOCK COMPOST FILTER SOCKS MINIMUM
12-INCHES.
SECTION
PLAN
STORM SEWER GRATE
LIFT STRAPS USED
FOR EASY MOVEMENT
AND INSPECTION OF
UNIT
VELCRO CLOSURE
STORM SEWER GRATE DANDY BAGOR
APPROVED EQUAL
HI-FLOW DANDY BAG OR APPROVED EQUAL (SAFETY ORANGE)
MECHANICAL PROPERTIES TEST METHOD UNITS MARV
ASTM D 4632 1.62 (365) X 0.89 (200)
ASTM D 4632 24 X 10
ASTM D 4833 0.40 (90)
ASTM D 3786 3097 (450)
ASTM D 4533 0.51 (115) X 0.33 (75)
ASTM D 4355 90
ASTM D 4751 0.425 (40)
ASTM D 4491 5907 (145)
ASTM D 4491 Sec 2.1-1
*NOTE: ALL DANDY BAGS OR APPROVED EQUAL CAN BE
ORDERED WITH OPTIONAL OIL ABSORBENT PILLOWS
1/min/m (gal/min/ft ) Mm (US Std Sieve) kN (lbs) kPa (psi) kN (lbs) kN (lbs)
PERMITTIVITY
FLOW RATE
APPARENT OPENING SIZE
UV RESISTENCE
TRAPEZOID TEAR STRENGTH
MULLEN BURST STRENGTH
PUNCTURE STRENGTH
GRAB TENSILE ELONGATION
GRAB TENSILE STRENGTH
COMPOST FILTER SOCK DETAIL
SCALE:NTS
C-002
DRAIN INLET PROTECTION DETAIL
SCALE:NTS
C-002
OR EQUIVALENT
ACCESS (VELCRO)
AGGREGATE POUCH
AGGREGATE POUCH
"TRUE DAM" BY DANDY PRODUCTS, INC.
3" DIAMETER DAM
WOOVEN MONOFILAMENT
OVERFLOW GAP OF DAM
EXISTING CURB AND GUTTER
CURB DROP INLET
EXISTING 6" HIGH CURB
6" MINIMUM
SEDIMENT FILTER FOR CATCHBASIN DETAIL
SCALE:NTS
C-002
TK TK TK TK
STABILIZED CONSTRUCTION ENTRANCE
SCALE:NTS
C-002
EXISTING
GROUND
6" THICK, CRUSHED
ROCK NO.2
10' WIDE STABILIZED
INGRESS/EGRESS ACCESS WAY
SEE PLAN FOR LENGTH
6"
FINISH GRADE TO MATCH
EXISTING GRADE
AutoCAD SHX Text
LICENSED
AutoCAD SHX Text
PROFESSIONAL
AutoCAD SHX Text W
AutoCAD SHX Text H
AutoCAD SHX Text A
AutoCAD SHX Text No. 17517-C
AutoCAD SHX Text U
AutoCAD SHX Text I
AutoCAD SHX Text I
AutoCAD SHX Text A
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text A
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text S
EX. 2" VTR
EX. 2" FUEL SUPPLY
EX
. 1
-1 /4"
C F
DR
C
EX. GRD TERMINAL
EX. U/G #1/0
EX. GRD TERMINALEX. GRD ROD DSGN. DRWN. CHKD. APPD.
OF
NO. DATE REVISION
AO2023-14
SHEETS
04/30/2028
7/24/2026
DATE
100% CONSTRUCTION
DOCUMENTS
JULY 24, 2026
UST AND AST CLOSURE
AT
KAWAIHAPAI AIRFIELD
MOKULEIA, OAHU, HAWAII
This work was prepared by me or under my supervision.
Licensed Expiration Date
STATE OF HAWAII
DEPARTMENT OF TRANSPORTATION
AIRPORTS
PROJECT TITLE :
DATE : DWG. NO.
SHEET :
PROJECT NO.:
SHEET TITLE:
SITE PLAN
C-102
ASPHALT PAVEMENT
RESTORATION
LEGEND
LIMITS OF WORK
CENTER LINE
NORTH
0' 40'20'20' 10'
1" = 20'-0"
GENERAL SITE PLAN1
NOTES:
1. UNDERGROUND FACILITIES, STRUCTURES AND UTILITIES HAVE
BEEN PLOTTED FROM AVAILABLE SURVEYS AND RECORDS.
THEREFORE, THEIR LOCATION MUST BE CONSIDERED
APPROXIMATE ONLY. THERE MAY BE OTHERS, THE EXISTENCE
OF WHICH IS NOT PRESENTLY KNOWN. BEFORE STARTING ANY
WORK, LOCATE AND PROTECT ALL EXISTING BURIED UTILITY
LINES, WHETHER OR NOT SHOWN ON THESE DRAWINGS, DURING
THE COURSE OF CONSTRUCTION
2. CONTRACTOR SHALL VERIFY THE LOCATION OF MONITORING
WELL PRIOR TO ANY GROUND DISTURBING ACTIVITIES. IF
MONITORING WELLS ARE FOUND WITHIN THE PROJECT LIMITS,
THE CONTRACTOR SHALL NOTIFY THE STATE PROJECT
MANAGER AND ADEQUATELY PROTECT THE MONITORING WELLS
FROM DAMAGE DURING CONSTRUCTION.
3. CONTRACTOR TO FIELD VERIFY THE EXISTING WATER LINES,
ELECTRICAL, TELCOM LINES AND FUEL LINES.
4. CONTRACTOR SHALL NOTIFY THE STATE PROJECT MANAGER
AND COORDINATE WITH HDOTA HDH MAINTENANCE AND ANY
EXISTING TENANTS FOR ACCESS AND USE OF THE AREA NEAR
THE NORTH SHORE AVIATION HANGAR AND ADJACENT LOT.
5. CONTRACTOR SHALL RESTORE ALL EXISTING IMPROVEMENTS
DISTURBED DURING CONSTRUCTION TO MATCH OR EXCEED
EXISTING CONDITION AND QUALITY.
6. SEE MECHANICAL DRAWINGS FOR PIPING AND EQUIPMENT
REMOVAL.
7. COORDINATE ALL SITE DEMOLITION WITH PROPOSED SITE
IMPROVEMENTS.
8. SAWCUT PAVEMENTS AND CURBING TO FULL DEPTH PRIOR TO
REMOVAL OR REMOVE TO NEAREST JOINT.
9. THE CONTRACTOR SHALL CONTACT HAWAII ONE CALL CENTER
(811 OR (866) 423-7287 OR https://digsafelyhawaii.com/) AT LEAST
FIVE (5) WORKING DAYS, BUT NOT MORE THAN TWENTY-EIGHT
(28) CALENDAR DAYS, PRIOR TO BEGINNING PLANNED
EXCAVATION.
DEMOLISH AND REMOVE CONCRETE
PAD. PROVIDE AC PAVEMENT AND
SMOOTH CONNECTION TO EXISTING
GRADE, TYP.
DEMOLISH AND REMOVE CONCRETE
PAD. PROVIDE BACKFILL, STABILIZE
SURFACE WITH 6" THICK GRAVEL AND
SMOOTH CONNECTION TO EXISTING
GRADE.
EXISTING 12,000 GALLON
UNDERGROUND STORAGE TANK
FOR REMOVAL SPECIFICATIONS SEE
MECHANICAL AND ELECTRICAL
DRAWINGS. BACKFILL AS NECESSARY
AND STABILIZE WITH TOP SOIL AND
GRASS (EL TORO ZOYSIA), TYP.
EXISTING DISPENSER SYSTEM
FOR REMOVAL SPECIFICATIONS SEE
MECHANICAL AND ELECTRICAL
DRAWINGS
EXISTING CONTROL PANEL
FOR REMOVAL SPECIFICATIONS
SEE ELECTRICAL DRAWINGS
LIMITS OF WORK AND
DISTURBANCE
AC PAVEMENT TRENCH
RESTORATION
PROVIDE AC
PAVEMENT TRENCH
RESTORATION, TYP.
AC PAVEMENT TRENCH
RESTORATION
EXISTING 2" VTR
FOR REMOVAL
SPECIFICATIONS SEE
MECHANICAL DRAWINGS.
PROVIDE BACKFILL,
STABILIZE SURFACE WITH
TOP SOIL, GRASS (EL
TORO ZOYSIA) AND
SMOOTH CONNECTION TO
EXISTING GRADE, TYP.
EXISTING ELECTRICAL
CONDUITS AND HANDHOLES.
FOR REMOVAL DETAILS SEE
ELECTRICAL DRAWINGS.
PROVIDE BACKFILL,
STABILIZE SURFACE WITH
GRASS AND SMOOTH
CONNECTION TO EXISTING
GRADE, TYP.
EXISTING POWER POLE
AND TRANSFORMER
(PROTECT)
FIELD VERIFY
EXISTING POWER POLE
(PROTECT)
FIELD VERIFY
LANDSCAPE
RESTORATION
EXISTING NORTH SHORE
AVIATION HANGAR
(PROTECT DURING
CONSTRUCTION)
EXISTING QUONSET HUT
(PROTECT DURING
CONSTRUCTION)
EXISTING ACCESS ROAD
DEMOLISH AND REMOVE CONCRETE
PAD. PROVIDE AC PAVEMENT AND
SMOOTH CONNECTION TO EXISTING
GRADE, TYP.
EXISTING GROUNDING SYSTEM
FOR REMOVAL SPECIFICATIONS SEE
MECHANICAL AND ELECTRICAL
DRAWINGS. PROVIDE AC PAVEMENT
RESTORATION AND SMOOTH
CONNECTION TO EXISTING GRADE,
TYP.
SCALE: 1" = 20'
TK TK TK TK
EXISTING DRAIN INLET
(PROTECT)
RESTORE CONCRETE CURB
SEE C&C OF HONOLULU STD DETAIL R-1
5 LF
AutoCAD SHX Text
TREES
AutoCAD SHX Text D=0.5
AutoCAD SHX Text H=10
AutoCAD SHX Text H=10
AutoCAD SHX Text D=0.5
AutoCAD SHX Text
TREES
AutoCAD SHX Text
TREES
AutoCAD SHX Text D=0.5
AutoCAD SHX Text H=15
AutoCAD SHX Text
TREES
AutoCAD SHX Text D=2
AutoCAD SHX Text H=25
AutoCAD SHX Text H=30
AutoCAD SHX Text D=1.5
AutoCAD SHX Text H=20
AutoCAD SHX Text D=0.5
AutoCAD SHX Text H=30
AutoCAD SHX Text D=1
AutoCAD SHX Text
TREES
AutoCAD SHX Text
SIGN
AutoCAD SHX Text
TOP SLOPE
AutoCAD SHX Text
BOTTOM SLOPE
AutoCAD SHX Text 12.89
AutoCAD SHX Text 12.89
AutoCAD SHX Text 12.96
AutoCAD SHX Text
ELEC BOX
AutoCAD SHX Text
ELEC BOX
AutoCAD SHX Text 13.23
AutoCAD SHX Text
DS
AutoCAD SHX Text
DS
AutoCAD SHX Text
TW 15.75
AutoCAD SHX Text
DS
AutoCAD SHX Text
DS
AutoCAD SHX Text 12.34
AutoCAD SHX Text 12.46
AutoCAD SHX Text
SIGN
AutoCAD SHX Text
DI
AutoCAD SHX Text
TOP=11.56
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AutoCAD SHX Text
AC 12.72
AutoCAD SHX Text
AC 11.02
AutoCAD SHX Text
AC 11.02
AutoCAD SHX Text
CC 12.17
AutoCAD SHX Text
CC 12.08
AutoCAD SHX Text
CC 12.01
AutoCAD SHX Text
CC 13.00
AutoCAD SHX Text
CC 12.95
AutoCAD SHX Text
AC 11.35
AutoCAD SHX Text
AC 11.22
AutoCAD SHX Text
AC 11.15
AutoCAD SHX Text
AC 11.07
AutoCAD SHX Text
CC 12.79
AutoCAD SHX Text 11.37
AutoCAD SHX Text 11.37
AutoCAD SHX Text 11.56
AutoCAD SHX Text 11.89
AutoCAD SHX Text 12.09
AutoCAD SHX Text 12.22
AutoCAD SHX Text 12.36
AutoCAD SHX Text 12.39
AutoCAD SHX Text 12.42
AutoCAD SHX Text 12.38
AutoCAD SHX Text 12.39
AutoCAD SHX Text 12.35
AutoCAD SHX Text 12.38
AutoCAD SHX Text 12.37
AutoCAD SHX Text 12.42
AutoCAD SHX Text 12.43
AutoCAD SHX Text 12.43
AutoCAD SHX Text 12.47
AutoCAD SHX Text 12.39
AutoCAD SHX Text 12.42
AutoCAD SHX Text 12.38
AutoCAD SHX Text 12.38
AutoCAD SHX Text 12.35
AutoCAD SHX Text 12.33
AutoCAD SHX Text 12.33
AutoCAD SHX Text 12.18
AutoCAD SHX Text 12.23
AutoCAD SHX Text 12.09
AutoCAD SHX Text 11.31
AutoCAD SHX Text 11.39
AutoCAD SHX Text 11.40
AutoCAD SHX Text 11.40
AutoCAD SHX Text 10.98
AutoCAD SHX Text 11.03
AutoCAD SHX Text 11.05
AutoCAD SHX Text 11.04
AutoCAD SHX Text 12.71
AutoCAD SHX Text 12.90
AutoCAD SHX Text 11.29
AutoCAD SHX Text 11.16
AutoCAD SHX Text 10.90
AutoCAD SHX Text 10.94
AutoCAD SHX Text 10.87
AutoCAD SHX Text 10.90
AutoCAD SHX Text 10.86
AutoCAD SHX Text 10.94
AutoCAD SHX Text 10.97
AutoCAD SHX Text 11.02
AutoCAD SHX Text 11.01
AutoCAD SHX Text 11.12
AutoCAD SHX Text 11.11
AutoCAD SHX Text 11.12
AutoCAD SHX Text 11.20
AutoCAD SHX Text 11.17
AutoCAD SHX Text 11.35
AutoCAD SHX Text 11.38
AutoCAD SHX Text 11.38
AutoCAD SHX Text 11.39
AutoCAD SHX Text 11.33
AutoCAD SHX Text 11.23
AutoCAD SHX Text 11.16
AutoCAD SHX Text 11.15
AutoCAD SHX Text 10.96
AutoCAD SHX Text 11.06
AutoCAD SHX Text 11.11
AutoCAD SHX Text
CC 12.97
AutoCAD SHX Text 12.95
AutoCAD SHX Text 12.89
AutoCAD SHX Text 12.89
AutoCAD SHX Text 12.84
AutoCAD SHX Text 12.75
AutoCAD SHX Text 12.79
AutoCAD SHX Text 12.80
AutoCAD SHX Text 12.84
AutoCAD SHX Text 12.84
AutoCAD SHX Text 12.89
AutoCAD SHX Text 12.94
AutoCAD SHX Text 12.87
AutoCAD SHX Text 12.76
AutoCAD SHX Text 12.74
AutoCAD SHX Text 12.73
AutoCAD SHX Text 12.75
AutoCAD SHX Text 12.72
AutoCAD SHX Text 12.75
AutoCAD SHX Text 12.67
AutoCAD SHX Text 12.48
AutoCAD SHX Text 12.48
AutoCAD SHX Text 12.51
AutoCAD SHX Text 12.05
AutoCAD SHX Text 12.06
AutoCAD SHX Text
CC 12.47
AutoCAD SHX Text
CC 12.36
AutoCAD SHX Text
CC 12.51
AutoCAD SHX…