PLANS.pdf
PDF 473 KB Posted
- Solicitation number
- IFB-127085
- Issued by
- York County, Virginia
About this file
This is a structural repair plan document for Fire Station #3 in Williamsburg, Virginia, prepared by Terracon Professional Services for the Virginia Facilities jurisdiction. The project encompasses repairs to the apparatus bay main building, specifically addressing concrete slab deterioration and overhead door jamb damage at 1114 Hubbard Lane, Williamsburg, Virginia 23185. The scope of work includes demolition and replacement of an existing concrete slab (108 feet 4 inches in area), repair of overhead door jambs constructed of steel, replacement of concrete masonry units as required, and installation of reinforcing steel with specifications for epoxy embedment and extended bar placement into the slab. The design incorporates an axle load rating of 52 kips for the apparatus bay slab and adheres to the 2021 Virginia Construction Code with ultimate design wind speed of 129 miles per hour for Risk Category IV structures.
The project specifications require adherence to multiple industry standards including the American Institute of Steel Construction manual, American Concrete Institute specifications (ACI 301-R85, ACI 318-11, and ACI 308), American Welding Society codes, and ASTM standards for materials. Structural steel must be galvanized or coated for weather exposure, and all concrete work must achieve a minimum 28-day compressive strength of 4,000 PSI with air entrainment of 6 percent for weather exposure. Reinforcing steel shall conform to ASTM A615 Grade 60, with concrete cover requirements of 3 inches for foundations, 2 inches for beams and columns, and 1.5 inches for slabs. Special inspections are required in conformance with the Virginia Uniform Statewide Building Code Section 1704 and IBC 2021, with structural steel shop-fabrication requiring certification by approved fabricators. The coating system specified is Tnemec Hi-Build Epoxoline II Series N69 or approved equal, applied over zinc-rich compatible primer following SSPC-SP3 or greater surface preparation standards.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SOLICITATION DOCUMENT.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
APPARATUS BAY MAIN BUILDING
N
S1.01
AREA OF WORK
108'-4"
AREA OF CONCRETE SLAB TO BE REPAIRED
S1.01
35'-7" ±
OVERHEAD DOOR JAMB REPAIR,
SEE DETAIL
S1.01
4 BASE OF STEEL DOOR JAMB TO BE
EXAMINED UPON CONCRETE DEMOLITION
/5 S1.01
2.5" DEEP SAWN JOINT
TO ALIGN W/ EXISTING
14'-0" ± 14'-0" ±
DEMOLISH EXIST. CONC. & REPLACE
6'-0"
#5 BAR @ 12" O.C. EACH WAY
EXISTING FOOTING
1/2" BOND BREAKER
(2) SS L2.5x2.5x3/8 W/ 5"
LONG HEADED STUDS @
32" O.C. @ VEHICLE
DOORS ONLY
OVERHEAD DOOR JAMB
EXISTING
CONCRETE SLAB
ENSURE ADEQUATE
GRANULAR FILL &
COMPACTION OF SUBGRADE#5 BENT BAR @ 12" O.C.
EMBED 6" SIMPSON
SET-3G EPOXY AND
EXTEND 2' INTO SLAB
6"
PROVIDE #5 BENT BAR @ 12"
O.C., EXTEND 2' INTO SLAB
CONT. #5 BAR
ALIGN W/ DOORS AS NEEDED,
MATCH EXISTING LOCATION & DEPTH
OVERHEAD DOOR TRACK
DOOR JAMB
CMU JAMB TO BE REMOVED &
REPLACED AS REQUIRED. NEW
CMU TO BE GROUTED SOLID
S1.01
BASE OF STEEL OVERHEAD
DOOR JAMB TO BE REMOVED &
REPLACED, SEE DETAIL /5 S1.01
8" ±
R E
M O
V E
E X
IS
T
S
T E
E L J
A M
B
REMOVE & REPLACE BASE OF OVERHEAD
DOOR JAMB WITH 12ga BENT PLATE TO
MATCH EXISTING JAMB PROFILE, NEW
JAMB MATERIAL TO BE WEEPED AT BASE.
NEW JAMB MATERIAL TO BE PREPARED,
COATED W/ ZINC RICH PRIMER & PAINTED
W/ HIGH-PERFORMANCE COATING TO
MATCH EXISTING JAMB
CONCRETE SLAB TO
BE REPAIRED
1/16
AT INTERIOR OF JAMB, (2) 3"x3"x14ga x 4" LONG
BENT PLATE CLIP WELDED TO NEW JAMB
BASE, FASTEN TO NEW SLAB W/ 1/2" Ø SS
TITEN HD W/ 4" EMBED.
2" 2"
AT INTERIOR OF JAMB, (2) 3"x3"x14ga PLATE
WELDED FROM NEW JAMB TO EXISTING
CONCRETE MASONRY AT INTERIOR OF
JAMB TO BE REMOVED & REPLACED AS
REQUIRED, GROUT MASONRY AFTER
REPLACEMENT. SHORE ADJACENT DOOR
HEADER PRIOR TO DEMOLITION
www.TERRACON.com
SHEET NUMBER:
DESIGNED BY:
APPROVED BY:
DRAWN BY:
TERRACON PROJECT NUMBER:
ISSUE DATE:
SHEET TITLE:
/8
/2
:1 :1
P
M
A P
P A
R A
T U
S B
A Y
R E P
A I R
S
Y O
R K T
O W
N F
IR
E S
T A T
IO
N
H
U B B A R
D L
A N
E W
IL
L
IA
M S B U
R G
V
IR
G
IN
IA
VIRGINIA FACILITIES
4350 NEW TOWN AVE, SUITE 201
WILLIAMSBURG, VIRGINIA 23188
(757) 564-4434
MB266099
05/08/2026
REPAIR PLAN &
DETAILS
S1.01
ERW
MJL
ERW
1" = 10'-0"S1.01
1 STATION SITE PLAN
1/4" = 1'-0"S1.01
2 AREA OF WORK - PLAN
1" = 1'-0"S1.01
3 APPARATUS BAY CONCRETE SLAB REPAIR
3" = 1'-0"S1.01
4 OVERHEAD DOOR JAMB - PLAN
1 1/2" = 1'-0"S1.01
5 OVERHEAD DOOR JAMB - SECTION
STRUCTURAL STEEL:
1. ALL STRUCTURAL STEEL WORK SHALL CONFORM TO THE CURRENT EDITION OF THE
"MANUAL OF STEEL CONSTRUCTION" OF THE "AMERICAN INSTITUTE OF STEEL
CONSTRUCTION".
2. ALL WELDED CONNECTIONS SHALL BE IN ACCORDANCE WITH THE LATEST EDITION OF
THE "MANUAL OF STEEL CONSTRUCTION" OF THE "AMERICAN INSTITUTE OF STEEL
CONSTRUCTION" AND THE LATEST EDITION OF THE "CODE FOR WELDING IN BUILDING
CONSTRUCTION" OF THE AMERICAN WELDING SOCIETY. USE E70XX LOW HYDROGEN
ELECTRODES.
3. ALL STRUCTURAL STEEL AND CONNECTIONS EXPOSED TO THE WEATHER SHALL
GALVANIZED OR COATED AS REQUIRED.
2021 VIRGINIA CONSTRUCTION CODE (VCC) DESIGN LOADS:
USE/LOCATION:
APPARATUS BAY SLAB, AXLE LOAD = 52 KIPS
SNOW LOAD
• NOT APPLICABLE
WIND LOAD
• ULTIMATE DESIGN WIND SPEED = 129 MPH
• WIND RISK CATEGORY IV
• WIND EXPOSURE B
• INTERNAL PRESSURE COEFFICIENT = +/- 0.18
• COMPONENTS AND CLADDING (LRFD, 10 SQFT):
- ROOF: ZONE 1: + 16 / - 44.7 PSF
ZONE 1': + 16 / - 25.7 PSF
ZONE 2: + 16 / - 59.0 PSF
ZONE 3: + 16 / - 80.3 PSF
- WALLS: ZONE 4: + 25.7 / - 27.8 PSF
ZONE 5: + 25.7 / - 34.2 PSF
EARTHQUAKE DESIGN DATA
• NOT APPLICABLE
CONCRETE:
1. ALL CONCRETE WORK SHALL CONFORM TO ALL THE PROVISIONS OF THE
"SPECIFICATIONS FOR STRUCTURAL CONCRETE FOR BUILDINGS" (ACI 301-R85) AND TO
THE "BUILDING CODE REQUIREMENTS FOR REINFORCED CONCRETE" (ACI 318-11).
2. ALL STRUCTURAL CONCRETE SHALL HAVE A MINIMUM 28 DAY COMPRESSIVE STRENGTH
OF 4,000 PSI UNLESS NOTED OTHERWISE. THE MAXIMUM SLUMP OF ALL CONCRETE
SHALL BE 4". ALL CONCRETE EXPOSED TO THE WEATHER SHALL HAVE AN AIR
ENTRAINMENT OF 6%±1%
3. NO ADMIXTURES CONTAINING CALCIUM CHLORIDE SHALL BE PERMITTED.
4. THE CONTRACTOR SHALL COMPLY WITH ALL THE PROVISIONS OF "RECOMMENDED
PRACTICE FOR HOT WEATHER CONCRETING" (ACI 305-R10) AND "RECOMMENDED
PRACTICE FOR COLD WEATHER CONCRETING" (ACI 306-R10). THE CONTRACTOR SHALL
SUBMIT COLD/HOT WEATHER PROCEDURES FOR APPROVAL.
5. ALL FORMWORK SHALL BE IN ACCORDANCE WITH THE AMERICAN CONCRETE INSTITUTE
"FORMWORK FOR CONCRETE" SPECIAL PUBLICATION NO. 4 AND ACI'S "STANDARD
RECOMMENDED PRACTICE FOR CONCRETE FORMWORK" (ACI 347-LATEST EDITION).
6. PROVIDE SAWN JOINTS OR CONSTRUCTION JOINTS IN SLABS AT ALL COLUMN
CENTERLINES AND AS SHOWN ON THE PLANS. SAWN JOINTS SHALL BE PROVIDED SO
THAT NO SLAB PANEL EXCEEDS 30 TIMES THE SLAB THICKNESS PER ACI
RECOMMENDATIONS. SAWN JOINTS SHALL BE CUT AS SOON AS POSSIBLE PER ACI
RECOMMENDATIONS.
7. FLOOR SLABS SHALL BE FINISHED TO A MINIMUM FLATNESS F-NUMBER, FF = 25 AND A
MINIMUM LEVELNESS F-NUMBER, FL = 20 IN ANY DIRECTION.
8. CONCRETE STRUCTURES MAY NOT SUPPORT THEIR DESIGN LIVE LOAD UNTIL THE
SPECIFIED COMPRESSIVE STRENGTH HAS BEEN ACHIEVED. LOADS GREATER THAN
THE DESIGN LIVE LOADS SHALL NOT BE PLACED ON THE STRUCTURE. THE
CONTRACTOR SHALL SUPPORT ADJACENT STRUCTURES, UTILITIES, AND EXCAVATIONS
AS REQUIRED FOR COMPLETION OF WORK.
9. ONE SET OF COMPRESSIVE TEST CYLINDERS FOR EACH 100 CUBIC YARDS POURED,
BUT NOT LESS THAN ONE SET FOR EACH DAY'S PLACEMENT AND EACH CLASS OF
CONCRETE, ALONG WITH SLUMP TESTS SHALL BE PERFORMED BY A TESTING
LABORATORY APPROVED BY THE STRUCTURAL ENGINEER.
10. ALL CONCRETE SHALL BE CURED IN ACCORDANCE WITH THE LATEST EDITION OF ACI
308, STANDARD SPECIFICATION FOR CURING CONCRETE. LIQUID CURING COMPOUNDS
SHALL BE COMPATIBLE WITH FLOORING ADHESIVES AND OTHER SURFACE
TREATMENTS AND SHALL BE APPROVED BY THE ARCHITECT PRIOR TO USE.
MASONRY:
1. ALL MASONRY AND GROUTING PROCEDURES SHALL BE IN COMPLIANCE WITH THE LATEST
EDITION OF THE BUILDING CODE FOR MASONRY STRUCTURES, ACI 530.
2. HOLLOW MASONRY UNITS SHALL BE GRADE N1 CONFORMING TO ASTM C90. SOLID
MASONRY SHALL BE GRADE N1 IN ACCORDANCE WITH ASTM C145 AND MAY BE 75% SOLID
UNLESS OTHERWISE NOTED.
3. MASONRY UNITS SHALL HAVE A MINIMUM COMPRESSIVE STRENGTH OF 2,000 PSI BASED
ON THE NET CROSS SECTIONAL AREA OF THE INDIVIDUAL BLOCK UNITS.
4. ALL MORTAR SHALL BE TYPE "S" MORTAR CEMENT CONFORMING TO ASTM C270 WITH
MINIMUM COMPRESSIVE STRENGTH OF 2,000 PSI AT 28 DAYS. ALL MORTAR JOINTS IN
MASONRY WALLS (HORIZONTAL AND VERTICAL) SHALL BE FILLED 100% WITH MORTAR.
5. ALL GROUT FOR VERTICAL REINFORCING AND BOND BEAMS SHALL BE 2,000 PSI MINIMUM
CONCRETE WITH SLUMP BETWEEN 8” AND 10”.
6. ALL CELLS CONTAINING REINFORCEMENT SHALL BE FILLED SOLIDLY WITH GROUT. GROUT
SHALL BE PLACED IN LIFTS OF 4’ MAXIMUM HEIGHT, UNLESS THE CONTRACTOR REQUESTS
AND OBTAINS APPROVAL TO PERFORM HIGH LIFT GROUTING. ALL GROUT SHALL BE
CONSOLIDATED APPROXIMATELY 5-10 MINUTES AFTER POURING AND BEFORE PLASTICITY
IS LOST BY VIBRATING. WHEN GROUTING IS STOPPED FOR ONE HOUR OR LONGER,
HORIZONTAL CONSTRUCTION JOINTS SHALL BE FORMED BY STOPPING THE POUR OF
GROUT NOT LESS THAN ½” BELOW THE TOP OF THE UPPER-MOST UNIT GROUTED.
HORIZONTAL STEEL SHALL BE FULLY EMBEDDED IN AN UNITERRUPTED POUR.
INSPECTION:
1. SPECIAL INSPECTIONS ARE REQUIRED FOR THE PROJECT IN CONFORMANCE WITH THE
VIRGINIA UNIFORM STATEWIDE BUILDING CODE (VUSBC) SECTION 1704 AND IBC 2021.
2. THE OWNER SHALL EMPLOY ONE OR MORE SPECIAL INSPECTORS TO PROVIDE INSPECTIONS
DURING CONSTRUCTION ON THE ITEMS LISTED IN THE STATEMENT OF SPECIAL INSPECTIONS
AND SCHEDULE FOR SPECIAL INSPECTIONS PREPARED FOR THIS PROJECT.
3. SPECIAL INSPECTION DOES NOT TAKE THE PLACE OF NORMAL INSPECTIONS REQUIRED BY
CODE OFFICIALS. ALL NORMAL INSPECTIONS BY LOCAL CODE OFFICIALS ARE STILL REQUIRED.
4. THE STRUCTURAL ENGINEER OF RECORD MAY VISIT THE SITE PERIODICALLY TO ASCERTAIN
GENERAL CONFORMANCE TO CONTRACT DOCUMENTS. THESE VISITS DO NOT SUBSTITUTE
FOR SPECIAL INSPECTIONS, NOR DO THEY IMPLY ACCEPTANCE OF THE WORK. THEY SHOULD
NOT BE CONSTRUED TO RELIEVE THE CONTRACTOR IN ANY WAY FROM OBLIGATIONS AND
RESPONSIBILITIES UNDER THE CONSTRUCTION CONTRACT.
5. THE FOLLOWING ITEMS SHALL BE SHOP-FABRICATED BY A CERTIFIED FABRICATOR WITH A
QUALITY ASSURANCE PROGRAM APPROVED BY THE LOCAL BUILDING CODE OFFICIAL TO
ALLOW FABRICATION WITHOUT IN-SHOP SPECIAL INSPECTIONS:
a. STRUCTURAL STEEL FRAMING
IF THE FABRICATOR CANNOT SUBSTANTIATE AN ACCEPTABLE QUALITY ASSURANCE PROGRAM
FOR THE COUNTY, THE FABRICATOR'S WORK SHALL BE INSPECTED BY AN APPROVED,
QUALIFIED AGENCY DURING FABRICATION AT NO ADDITIONAL COST TO THE OWNER.
AT THE CONCLUSION OF THE PROJECT, THE FABRICATOR SHALL PROVIDE A CERTIFICATE OF
COMPLIANCE TO THE BUILDING OFFICIAL STATING THAT THE WORK WAS COMPLETED IN
ACCORDANCE WITH THE APPROVED CONSTRUCTION DOCUMENTS.
DESIGN WITHOUT CONSTRUCTION REVIEW:
IT IS AGREED THAT IF TERRACON PROFESSIONAL SERVICES DO NOT EXTEND TO OR
INCLUDE THE REVIEW OR SITE OBSERVATION OF THE CONTRACTOR'S WORK OR
PERFORMANCE, THEN THE OWNER WILL DEFEND, INDEMNIFY AND HOLD HARMLESS
TERRACON, FROM ANY CLAIM OR SUIT WHATSOEVER, INCLUDING BUT NOT LIMITED TO ALL
PAYMENTS, EXPENSES OR COSTS INVOLVED, ARISING FROM OR ALLEGED TO HAVE
ARISEN FROM THE CONTRACTOR'S PERFORMANCE OR THE FAILURE OF THE
CONTRACTOR'S WORK TO CONFORM TO THE DESIGN INTENT AND THE CONTRACT
DOCUMENTS. TERRACON AGREES TO BE RESPONSIBLE FOR ITS OWN OR IT'S
EMPLOYEES' NEGLIGENT ACTS, ERRORS OR OMISSIONS.
OWNERSHIP OF DOCUMENTS:
THE CONTRACTOR ACKNOWLEDGES THESE PLANS AND SPECIFICATIONS PREPARED BY
TAM CONSULTANTS, INC., AS INSTRUMENTS OF PROFESSIONAL SERVICE.
NEVERTHELESS, THE PLANS AND SPECIFICATIONS PREPARED UNDER THIS AGREEMENT
SHALL REMAIN THE PROPERTY OF TAM CONSULTANTS, INC. UPON COMPLETION OF THE
WORK. THE CONTRACTOR AGREES TO HOLD HARMLESS AND INDEMNIFY TAM
CONSULTANTS INC., AGAINST ALL DAMAGES, CLAIMS AND LOSSES, INCLUDING DEFENSE
COSTS, ARISING OUT OF ANY REUSE OF THE PLANS AND SPECIFICATIONS WITHOUT THE
WRITTEN AUTHORIZATION OF TAM CONSULTANTS, INC.
REINFORCING STEEL:
1. REINFORCING STEEL SHALL BE DEFORMED BARS IN ACCORDANCE WITH ASTM A615,
GRADE 60.
2. BENDS SHALL BE FABRICATED AS PER DETAILS.
3. PLACE MAIN REINFORCING STEEL SO AS TO PROVIDE 3" MINIMUM COVER FOR
FOUNDATIONS POURED ON EARTH, 2” MINIMUM COVER FOR BEAMS AND COLUMNS, ¾”
MINIMUM COVER FOR SLABS AND 1½” FOR ALL REBAR IN EXPOSED CONCRETE (EXCEPT
AS OTHERWISE DETAILED).
4. PROVIDE ACCESSORIES AND BAR SUPPORTS IN ACCORDANCE WITH THE MANUAL OF
STANDARD PRACTICE FOR DETAILING REINFORCED CONCRETE STRUCTURES (ACI
315-80).
5. UNLESS NOTED OTHERWISE, REINFORCING STEEL BAR LAPS SHALL BE AS FOLLOWS
A. CONCRETE:
#3 - 1'-9” #4 - 2'-4” #5 - 2'-11” #6 - 3'-6” #7 - 4'-1” #8 - 4'-11”
R E V
IS
IO
N
S
N O
D
A T E
D E S C R
IP
T
IO
N
STRUCTURAL STEEL PAINT/COATING:
1. SURFACE PREPARATION OF SSPC-SP3 OR GREATER. VISIBLE DEPOSITS OF OIL, GREASE,
OR OTHER MATERIAL THAT INTERFERE WITH COATING ADHESION SHALL BE REMOVED
FROM THE STEEL SURFACE.
2. USE ZINC-RICH COMPATIBLE PRIMER PRIOR TO APPLICATION OF COATING SYSTEM.
3. THE COATING SYSTEM USED SHALL BE THE FOLLOWING, OR APPROVED EQUAL:
TNEMEC: HI-BUILD EPOXOLINE II SERIES N69
File details come from the government source that posted it. Updated .