PLan OR Lake 4-12(1) signoff.pdf
PDF 4 MB Posted
- Attached to
- OR LAKE 4-12(1), East Bay Road Rehabilitation
- Solicitation number
- 69056720B000003
About this file
This document package includes plans and specifications for the OR LAKE 4-12(1), East Bay Road Rehabilitation federal construction project. The project involves asphalt concrete pavement overlay work along 5.7 miles of East Bay Road within the Fremont National Forest in Oregon. The project is solicited by the Department of Transportation Federal Highway Administration under solicitation number 69056720B000003. Work includes mobilization, surveying and staking, quality control, contractor testing, schedule development, and 1/2-inch nominal maximum size asphalt concrete pavement. Bidding documents include vicinity and location maps, typical sections, temporary traffic control plans, quantities tabulation, and specifications.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| QA_04-27-2020.pdf | ||
| Plan Request form.pdf | ||
| IFB_East Bay Road.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Lake
Summer
Reservoir
Thompson
SCALE IN MILES
INDEX TO SHEETS
PROJECT MANAGER
R
E N
O R
A I
N
N
ST F
R
I
D
D E P A
T
NTOFT A SP
T T
O
U
TE
ATESO
AM
E R
IC
A
M
P A
C F
I C
I O
E C
A N
COLUMBIA R
IV
ER
S N
A K E
R
IV
E R
Lake
Malheur Lake
Harney
Lake
Summer
D
ES
C H
U T
E S
R I V
E R
Lake
Klamath
Upper
Abert
Lake
WASHINGTON
I D
A H
O
CALIFORNIA
OREGON KEY MAP
CRATER
LAKE N.P.
MALHEUR
NATIONAL
WILDLIFE
REFUGE
HART MT.
NATIONAL
ANTELOPE
RANGE
Grants Pass
MEDFORD
Ashland
Roseburg
EUGENE
Bend
Corvallis
Newport
SALEM
PORTLAND
Astoria
Pendleton
La Grande
Ontario
Burns
Falls
Klamath
Bend
North
City
Baker
Dalles
The
395101
395197
20 20
NEVADA
T29S
T28S
R14E
H. OPPENHEIMER
D. TEMPORARY TRAFFIC CONTROL PLAN
C. TYPICAL SECTION
B. SUMMARIES
A. GENERAL INFORMATION
D.3-6
D.2
D.1
C.2
C.1
B.1
A.3
A.2
A.1
A.1
STATE PROJECT
NUMBER
SHEET
I n t_ ft
D c p w w o r k d o r a a a .d g n
OR LAKE 4-12(1)
A
M
D e c e m b e r
C h e c k e d b y
D e s ig n e d b y T
P h a n
STANDARD DRAWINGS
ADVANCED TEMPORARY TRAFFIC SIGNING PLAN
TRAFFIC CONTROL QUANTITIES
TABULATION OF TEMPORARY
LINE GRAPH
TYPICAL SECTION
SUMMARY OF QUANTITIES
VICINITY MAP
PLAN SYMBOLS AND ABBREVIATIONS
TITLE SHEET
FEDERAL HIGHWAY ADMINISTRATION
U. S. DEPARTMENT OF TRANSPORTATION
Project Location
APPROVED:
DATE
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
TYPE OF CONSTRUCTION:
DESIGN DESIGNATION:
SPECIFICATION:
VANCOUVER, WASHINGTON
WESTERN FEDERAL LANDS HIGHWAY DIVISION
PLANS PREPARED BY
PLANS FOR PROPOSED PROJECT
OR LAKE 4-12(1)
Western Federal Lands Highway Division
Chief of Engineering, EAST BAY ROAD REHABILITATION
OREGON
LAKE COUNTY
FREMONT NATIONAL FOREST
0 10 20 30 4010
F R E M O N T
N A T I O N A L
F O R E S T
N A T I O N A L
F O R E S T
W I N E M A
C R A T E R
L A K E
N A T I O N A L
P A R K
R O G U E
R I V E R
N A T I O N A L
F O R E S T
Valley
Christmas Lake
W I N E M A
N A T I O N A L
F O R E S T
PROJECT LOCATION
See Vicinity Map Sheet A.3 on Federal Highway Projects, FP-14
Construction of Roads and Bridges
Standard Specifications for
LENGTH 5.700 MILES
e (max)
V
ADT 2039
ADT 2019
n/a
30 MPH
Asphalt pavement overlay
Lake
Silver for
CP GPS
JH
BH
TP
36 31
6 1
36 31
6 1
SEC.
SEC.
EL. 1234.56
N
E
RIP
G G
W W
DI
T
WESTERN FEDERAL LANDS HIGHWAY DIVISION
DETAIL APPROVED FOR USE 11/2001
REVISED: 9/2005 1/2007 10/2009 10/2014
W101-1
AND ABBREVIATIONS
PLAN SYMBOLS
D e c e m b e r
U
C p w w o r k d o r a a b .d g n
FEDERAL HIGHWAY ADMINISTRATION
U.S. DEPARTMENT OF TRANSPORTATION
DETAIL
U.S. CUSTOMARY DETAIL
STATE PROJECT
NUMBER
SHEET
A.2 LAKE 4-12(1) OR
DI
T
NO SCALE
- no symbol -wall face
N
W west drwg(s).
dist.
diaph.
diag.
dia.
DHV
D exp. jt.
exc.
EW
ER
EQ or eq.
EP
emb.
elev.
El. 94.16 ft e
E expansion joint excavation edge of water edge of road equation edge of pavement embankment elevation elevation with number superelevation rate east drawing(s) distance diaphragm diagonal diameter design hourly volume diameter galv.
ga.
galvanized gage (gauge)
HW
hex.
hdwl.
high water hexagon headwall ftg.
ft3 ft2 flg.
fin.
footing cubic foot (feet) square foot flange finish jt.
ID
joint inside diameter
LW
lt. or LT
Ls
LPSM
long.
LNFT
lat.
lam.
L low water left length of spiral lump sum longitudinal linear foot (feet) latitude lamination length of curve
NC
N normal crown north
OG
OD
o. to o.
o. c.
original ground outside diameter out to out on center pvmt.
PT
PST
PSC
PS
POT
POS
POC
pl.
PI
PCS
PCC
PC
pavement point of tangent point of spiral to tangent point of spiral to curve point of tangent to spiral point on tangent point on spiral point on curve plate point of intersection point of curve to spiral point of compound curve point of curve rte.
rt. or RT reqd.
reinf.
rdwy.
R/W
R.
R route right required reinforcement roadway right-of-way range radius typ.
Ts
TS
thd.
TBM
T.
T typical tangent distance (spiraled curve) point of tangent to spiral thread temporary bench mark township tangent distance
VPI
vph
V vertical point of intersection vehicles per hour design speed yd3 yd2 cubic yard(s) square yard sym.
STS
struc.
stiff.
stgr.
std.
STA, Sta.
ST
SS
SRS
SQYD
SQFT
spa.
SLRY
shldr.
sec.
SC
SADT
S symmetrical point of spiral to tangent spiral structural stiffener stringer standard station point of spiral to tangent point of spiral to spiral (no curve) point of spiral to reverse spiral square yard square foot spacing, spaces or spaced slurry unit shoulder section point of spiral to curve seasonal average daily traffic south
CUYD
culv.
CUFT
cubic yard(s) culvert cubic foot (feet) mon.
min.
MGAL
max.
matl.
monument minimum thousand gallon maximum material
NOTE:
on the appropriate plan sheet.
Other symbols used in the plans will be shown in a legend 1.
Property Line w/Found Property Corner
Section Corner (Found, Projected)16
Section Line16
Section Corner (Found, Projected)4
Section Line4
Parcel Number
National Park Boundary
National Forest Boundary
National Wildlife Refuge Boundary
Trail
Lake, Pond or Reservoir; Marshland
Spring or Seep
Material Source; Bore Hole; Test Pit
Section Line
Indian Reservation Boundary
Existing Roadway (Road, Paved, Gravel)
Section Corner (Found, Projected)
Large Creek or River
Spot Elevation; Coordinate Grid Tick
Above Ground Tank; Underground Tank
Treeline; Individual Trees
Boulder; Well; Satellite Dish; Grave
Cooking Grate; Garbage Can; Picnic Table
Flagpole; Fire Hydrant
Gas & Water Meter; Gas & Water Valve
Silt Fence
National Boundary
State Boundary
County Boundary
City Boundary
Township or Range Line
BLM Lands Boundary
Railroad
Intermittent Drainage or Small Creek
Control Point (Terrestrial and GPS); Jump Hub θs Ø
∆c spiral central angle diameter curve central angle total central angle approach ahead average daily traffic abutment appr.
AH
ADT
abut.
bearing bridge balance point bench mark back brg.
br.
BP
BM
BK
ctrs.
CS
cont.
constr. jt.
conn.
conc.
col.
CMP
clr.
cc or c. to c.
centers point of curve to spiral continuous construction joint connection concrete column corrugated metal pipe clear centerline center to center mile post main line
M.P.
M.L.
STEAM = steam, T = telephone, TV = CATV, W = water
P = power, SA = sanitary sewer, SD = storm drain, SS = storm sewer, FM = force main, FO = fiber optic, G = gas, IRR = irrigation, O = oil, UP = transformer or junction box, WF = water fountain
EM = electric meter, T = telephone pedestal, TV = CATV pedestal, Light, Support w/Anchor)
Poles (Power, Telephone, Joint Use, EXISTING PROPOSED
Transition
Toe of Fill
Top of Cut
CL
North Arrow
Fence
Gate with Fence
Cattleguard
Guardrail
Retaining Wall
Pipe Culvert (arrow shows flow)
Pipe Culvert with End Section
Pipe Culvert with Headwall
Underdrain
Concrete Barrier
Slope Stake Limits
Pipe Culvert with Drop Inlet
Box Culvert
Delineators
Underground Utilities
Overhead/Above Ground Utilities
Signs (single, double post; portable)
Miscellaneous Utility Features
Building
Right-of-Way Line with Monument
Permanent Easement
Construction Easement
Riprap
Fiber Roll or Wattle
VICINITY MAP
N
A.3
STATE PROJECT
NUMBER
SHEET
I n t_ ft p w w o r k d o r a a c .d g n
OR LAKE 4-12(1)
D e c e m b e r
C h e c k e d b y
D e s ig n e d b y T
P h a n
SCALE IN MILES
1 2 3 41
FOREST BOUNDARY
LAKE
SILVER
Strip
Landing
Strip
Landing Is la n d
Br an ch
Bu ny ard Creek
B ri d g e
C re e k
Spring
Freeman
Willow Spring
Spring
Flager
Spring
Chase
Spring
McBroom
Lake
LaBrie
Lake
Cottonwood
Dun can
C re e k
Reservoir
Duncan
Murdock
C r e e k
D ry
C re e k
BEGIN PROJECT
END PROJECT
OR LAKE 4-12(1)
OR LAKE 4-12(1)
FREMONT NATIONAL FOREST
m ile s
T o L a P in e
(MP 0.0)
10+00.00
(MP 5.7)
310+96
40 miles
To Pailsley
Sheet and Description
SECTION C SECTION D -
TYPICAL
SECTIONS
TEMPORARY
TRAFFIC
CONTROL
ALLOWANCE Bid Schedule
A0020 15101-0000 MOBILIZATION LPSM ALL
A0040 15214-0000 SURVEY AND STAKING, MISCELLANEOUS LPSM ALL
A0060 15301-0010 CONTRACTOR QUALITY CONTROL AND ASSURANCE LPSM ALL
A0080 15401-0000 CONTRACTOR TESTING LPSM ALL
A0100 15501-0000 CONSTRUCTION SCHEDULE LPSM ALL
A0120 40101-0600 ASPHALT CONCRETE PAVEMENT, GYRATORY MIX, 1/2-INCH NOMINAL MAXIMUM SIZE AGGREGATE, 0.3 TO <3 MILLION
ESAL TON 17,737 1,800 19,537
A0160 40105-3000 ANTISTRIP ADDITIVE, TYPE 3 TON 178 18 196
A0200 41201-0000 TACK COAT TON 67 4 71
A0220 62201-0350 BACKHOE HOUR 24
A0240 62201-2050 ROLLER HOUR 24
A0260 62201-2750 MOTOR GRADER HOUR 32
A0280 62301-0000 GENERAL LABOR HOUR 20
A0300 63502-0600 TEMPORARY TRAFFIC CONTROL, BARRICADE TYPE 3 EACH 4 4
A0320 63502-1250 TEMPORARY TRAFFIC CONTROL, TUBULAR MARKER, TYPE 42-INCH EACH 123 123
A0340 63502-1300 TEMPORARY TRAFFIC CONTROL, DRUM EACH 20 20
A0360 63504-1000 TEMPORARY TRAFFIC CONTROL, CONSTRUCTION SIGN SQFT 221 49 270
A0380 63506-0500 TEMPORARY TRAFFIC CONTROL, FLAGGER HOUR 320 320
A0400 63506-0600 TEMPORARY TRAFFIC CONTROL, PILOT CAR HOUR 80 80
MileStone: 100% Date Completed: In Progress Report Date: 12/18/19
A M E N D
Line Item No.
Pay Item Number
SUMMARY OF QUANTITIES - Schedule A
-D ec -2
1:
P M
Remarks and/or Determination of Estimated
Quantity Pay Item Description Unit
Estimated Quantities c:
\p w -w or k\ d0 su m m ar y.
xl sm
]S he et
STATE PROJECT
B.1LAKE 4-12(1)OR
SHEET
NUMBER
TYPICAL SECTION
10+00 to 310+96
C.1
STATE PROJECT
NUMBER
SHEET
I n t_ ft p w w o r k d la k e c a a .d g n
OR LAKE 4-12(1)
D e c e m b e r
T
P h
C h e c k e d b y
D e s ig n e d b y
Existing ground
LC
VariesVar ies
SAFETY EDGE DETAIL
Second lift of asphalt
First lift of asphalt
EAST BAY ROAD
C o n s tr u c ti o n l im it
C o n s tr u c ti o n l im it
12'12'[1]Varies [1]Varies
FOOTNOTE:
Profile grade
Safety edge Safety edge
Placed in two equal lifts
0.3 to <3 million ESAL, Type III roughness
" nominal maximum aggregate size,4 3" or 2
4" Asphalt concrete pavement, gyratory mix, Place tack coat between lifts
(done by others) Top of recycled base
DETAIL
PAVEMENT CONNECTION
Placed in two equal lifts
0.3 to <3 million ESAL, Type III roughness
" nominal maximum aggregate size,4 3" or 2
4" Asphalt concrete pavement, gyratory mix, road elevation
Match to existing
(Work will be done by others) shoulder finishing Roadway aggregate, (Work will be done by others) shoulder finishing Roadway aggregate, by others before paving
Remove compacted material placed
10'-20'
VariesVaries
Roadway aggregate, Shoulder finishing
(Work will be done by others)
(work will be done by others)
Recycled base
[2]
[1]
Quantities includes assumed approach road quantities of 20 TON
Shoulder varies, 4-foot average.
done by others)
(work will be
Saw cut vertical joint
Apply tack coat
QUANTITIES
TEMPORARY TRAFFIC CONTROL
TABULATION OF
D.1
STATE PROJECT
NUMBER
SHEET
I n t_ ft p w w o r k d la k e n b .d g n
OR LAKE 4-12(1)
D e c e m b e r
C h e c k e d b y
D e s ig n e d b y T
P h
N
D.2
STATE PROJECT
NUMBER
SHEET
I n t_ ft p w w o r k d o r a n c .d g n
OR LAKE 4-12(1)
P
N o v e m b e r
C h e c k e d b y
D e s ig n e d b y T
P h a n
TRAFFIC SIGNING PLAN
ADVANCED TEMPORARY 0
SCALE IN MILES
1 2 31
S il v e r
C re e k
S ilv e r
C re e k
W e s t
F o rk
LAKE
SILVER
E A
T
B
Y
O
A
DC
o u ty o a d
Begin Work
End Work
Optional Detour Route
60"
3.75" 3.75"52.5"
3.75'
3.75"
5.00"
3.75"
5.00"
3.75"
5.00"
Ref-1
NOTE:
1. Coordinate with the CO for exact Ref-1 sign location.
Ref-1
Ref-1
NO SCALE
SIGN SPACING TABLE
ROAD TYPE
DISTANCE BETWEEN
A B C
ROAD WORK
END
WORK
ROAD
AHEAD
ROAD WORK
END
ROAD WORK
END
ROAD WORK
END
WORK
ROAD
AHEAD
WORK
ROAD
AHEAD
Expressway / Freeway
ROAD NAME
ROAD NAME
ROAD WORK
NEXT xx MILES
WORK
ROAD
xxxxxxx
WORK
ROAD
xxxxx
WORK
ROAD
xxxxxxx
WORK
ROAD
xxxxxxx
ROAD WORK
NEXT xx MILES
W13-1P
(optional)
W13-1P
(optional) xx
MPH
xx
MPH
STANDARD APPROVED FOR USE 6/2005
DRAFT: 6/2014
REVISED:
Rural greater than 50 MPH
Urban and Rural 35 MPH to 50 MPH
Urban and Rural 30 MPH and less
SIGNS IN FEET
635-1
ADVANCE SIGNING
TEMPORARY TRAFFIC CONTROL
STATE PROJECT
NUMBER
SHEET
D.3
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
LAKE 4-12(1) OR
U S
C c p w w o r k d S td
.d g n
S e p te m b e r
FEDERAL LANDS HIGHWAY
U.S. CUSTOMARY STANDARD
STANDARD
G20-2
G20-2
G20-2
G20-1
See Note 11
G20-1
See Note 11
M in o r R o a d
M a jo r R o a d
W20-1
See Note 10
W20-1
See Note 10
W20-1 over
W16-8P
See Note 9
W20-1 over
W16-8P
See Note 9
W20-1
Ro ad N am e
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
W20-1
See Note 10
W20-1
See Note 10
G20-2
Erect all project advance warning signs before starting construction work.
Not all details shown on the temporary traffic control sheets may be applicable to this project. The Contractor may add or delete information and details in this traffic control plan as necessary to accommodate actual operations.
Where advance warning signs, placed as shown, interfere with permanent signs, locate the warning signs as determined by the CO for best results. Vary messages as required.
Additional or different message signs may be required to fit the actual construction conditions.
Install advisory speed plates under the W20 series warning signs as needed to indicate a maximum recommended speed through the construction area.
Ensure all sign supports exposed to impact by traffic meet the requirements of
NCHRP-350 or MASH for crashworthiness.
Maintain two-way traffic during all non-work hours except as approved by the CO.
Do not store traffic control devices along the roadway when not in use. Cover post-mounted signs when not applicable.
If W20-1 is placed on a roadway other than that on which the actual construction work occurs, include a supplementary plaque indicating the name of the road on which the construction does occur (applies to major roads only).
The message on the W20-1 signs may be "ROAD WORK AHEAD" or may specify the distance to the work area in feet or in miles. Install an additional W20-1 each end of the project. Show the distance on the G20-1 sign to the nearest whole mile.
If signing on a roadway under a jurisdiction other than the client agency, verify that an encroachment permit has been obtained.
State standards may be used as an alternative if approved by the CO.
Refer to the Section 635 of the Special Contract Requirements for allowable retroreflective sheeting types.
A
B
C
(S ee S ig n
Sp ac in g
Ta bl e)
ADVANCE
W
ARNI
NG
AREA
C
B as d et er m in ed b y th e
CO
W or k zo ne A re a of In flu en ce
Pr oj ec t L im its
A
A
(S ee S ig n
Sp ac in g
Ta bl e)
ADVANCE
W
ARNI
NG
AREA
A
A
For work zones that are 2 miles or more in length, install G20-1 signs at signs "B" feet apart according to the Sign Spacing Table.
sign when approach speeds exceed 50 MPH. When used place the two W20-1
NOTE:
LENGTH AND SPACING TABLE
APPROACH
SPEED*
SIGN SPACING TABLE
ROAD TYPE
DISTANCE BETWEEN
A B C
* Approach speed based on the regulatory posted speed, not the advisory speed.
BUFFER SPACE
LENGTH
Expressway / Freeway
WORK
ROAD
AHEAD
BE
PREPARED
TO STOP
ROAD WORK
END
xxx
FEET
635-5
STANDARD APPROVED FOR USE 6/2005
DRAFT: 8/2013
REVISED:
MPH
FEET
Rural greater than 50 MPH
Urban and Rural 35 MPH to 50 MPH
Urban and Rural 30 MPH and less
SIGNS IN FEET
(WITH FLAGGERS)
ROAD CLOSURE LAYOUT
TEMPORARY TRAFFIC CONTROL
STATE PROJECT
NUMBER
SHEET
D.4
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
LAKE 4-12(1) OR
U S
C c p w w o r k d S td
.d g n
A u g u s t
FEDERAL LANDS HIGHWAY
U.S. CUSTOMARY STANDARD
STANDARD
Traffic flow
Traffic flow
Signs are shown for one direction of travel only. Place devices similar to those depicted for the opposite direction of travel.
Final location and spacing of signs and devices may be changed to fit field conditions as approved by the CO.
For pilot car operation, mount the "PILOT CAR FOLLOW ME" (G20-4) sign at a conspicuous location on the rear of vehicle. Prominently display the name of the Contractor on the pilot car.
If closure is completely within the project limits, eliminate the "ROAD
WORK AHEAD" (W20-1) and "END ROAD WORK" (G20-2) signs.
For night time flagging operation, provide floodlighting at flagger stations.
Do not allow equipment, materials, or vehicles to be parked or stored in the buffer space.
(See Length and
Spacing Table)
1.
2.
3.
4.
5.
6.
(See Length and
Spacing Table)
WORK SPACE
G20-2
See Note 4
W20-1
See Note 4
W3-4
W16-2P
(optional)
W20-7
BUFFER SPACE
NOTE:
ADVANCE WARNING AREA (See Sign Spacing Table)
TERMINATION AREAVARIABLEBUFFER SPACEABC
(optional)
A
Flagger location
Flagger location
LENGTH AND SPACING TABLE
SPEED*
APPROACH
AREA
TAPER
SPACE
BUFFER
SPACE
WORK
CHANNELIZING DEVICE
not the advisory speed.
Approach speed based on the regulatory posted speed, *
SIGN SPACING TABLE
ROAD TYPE
DISTANCE BETWEEN
A B C
LENGTH
BUFFER SPACE
Expressway / Freeway
WORK
ROAD
AHEAD
ONE LANE
ROAD
AHEAD
xx
MPH
xxx
FEET
ROAD WORK
END
635-6
STANDARD APPROVED FOR USE 6/2005
DRAFT: 8/2013
REVISED:
MPH FEET
Rural greater than 50 MPH
Urban and Rural 35 MPH to 50 MPH
Urban and Rural 30 MPH and less
SIGNS IN FEET
(WITH FLAGGERS)
SINGLE LANE CLOSURE LAYOUT
TEMPORARY TRAFFIC CONTROL
SPACING IN FEET
STATE PROJECT
NUMBER
SHEET
D.5
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
LAKE 4-12(1) OR
U S
C c p w w o r k d S td
.d g n
A u g u s t
FEDERAL LANDS HIGHWAY
U.S. CUSTOMARY STANDARD
STANDARD
Traffic flow
Traffic flow
See Note 4
W20-1 W20-7W20-4
See Note 4
G20-2
Spacing Table)
(See Length and
(optional)
WORK SPACE (optional)(optional)
(optional)
W13-1P
(optional)
W16-2P
7.
6.
5.
4.
3.
2.
1.
the buffer space.
Do not allow equipment, materials, or vehicles to be parked or stored in
Requirements, Section 156.
For project specific minimum width, refer to the Special Contract
For night time flagging operation, provide floodlighting at flagger stations.
WORK AHEAD" (W20-1) and "END ROAD WORK" (G20-2) signs.
If closure is completely within the project limits, eliminate the "ROAD name of the contractor on the pilot car.
a conspicuous location on the rear of vehicle. Prominently display the
For pilot car operation, mount the PILOT CAR FOLLOW ME (G20-4) sign at conditions as approved by the CO.
Final location and spacing of signs and devices may be changed to fit field those depicted for the opposite direction of travel.
Signs are shown for one direction of travel only. Place devices similar to
NOTE:
ATAPER AREABUFFER SPACEVARIABLEBUFFER SPACETAPER AREAABC
(See Length and Spacing Table)ADVANCE WARNING AREA (See Sign Spacing Table) TERMINATION AREA
Device spacing
BUFFER SPACE
Channelizing devices
Flagger location
Flagger location
50' - 100' 50' - 100' (optional)
See Note 6
10' min.
WIDTH
"X"
AREA
NUMBER
OF POSTS
POST SIZE D HOLE SIZE
WOOD POST SELECTION TABLE
NO SCALE
635-14
STANDARD APPROVED FOR USE 6/2005
DRAFT: 10/2017
REVISED:
Diamond ≤ 48"
> 30'
> 17'
12' - 16'
> 13'
< 10
65 - 95
65 - 95
50 - 65
50 - 65
20 - 50
10 - 20
10 - 20
6 x 6
4 x 6
4 x 6
6 x 6
4 x 6
4 x 4
6 x 6
4 x 6
4 x 4
(INCH) (INCH)
(INCH)(SQFT)
Other Shapes ≤ 48" Diamond ≤ 36"
Other Shapes ≤ 12' Diamond ≤ 48"
WOOD POSTS
SIGN INSTALLATION
TEMPORARY TRAFFIC CONTROL
1.5
1.5
1.5
1.5
STATE PROJECT
NUMBER
SHEET
D.6
U.S. DEPARTMENT OF TRANSPORTATION
FEDERAL HIGHWAY ADMINISTRATION
LAKE 4-12(1) OR
U S
C c p w w o r k d S td
.d g n e p te m b e r
FEDERAL LANDS HIGHWAY
U.S. CUSTOMARY STANDARD
STANDARD
SINGLE POST SIGN TWO POST SIGN
SIGN INSTALLATION ANGLE
POST DETAIL
S e e N o te
S e e N o te
See Note 4 E d g e o f tr a v e le d w a y
E d g e o f p a v e d s h o u ld e r
CL Post
Local tangent
Bottom of sign panel
X
H
H
D
H
0.75X
X
X
H
Y D
H
0.2X
0.6X
0.2X
D
See post detail (typ.)
Break-away holes.
Long side of post
D
90°
93°
6" x 6" or larger.
Use 7' minimum spacing between posts for sign posts and 6' minimum mounting height for secondary sign.
use 7' minimum mounting height for main sign a minimum lateral distance of 1' behind the face of lateral offset of 2' may be used. In areas with curbs, 200' m in m in
6' - 12'
" dia. bolts 4 1Attach sign panels with a minimum of 2 - 1.
2.
3.
4.
5.
6.
7. State standards may be used as an alternative if approved by the CO.
per post.
H1 and H2 = Overall post length.
Select post lengths to fit field conditions.
D = Post embedment depth for average soil conditions.
In areas where lateral distance is limited, a minimum the curb may be used.
In pedestrian locations, or in areas with obstructed views, NOTE:
See table for hole size parallel to sign face.
Field drill holes through post
| 2020-03-10T14:20:57-0700 | |
| BRENT L COE |
File details come from the government source that posted it. Updated .