The survey consists of 14 primary questions and supporting data collection requirements. Questions 1-3 address existing PLA usage in the local area, skilled labor shortages for required trades, and time-sensitive scheduling issues, with requests for supporting documentation. Questions 4-6 solicit opinions on whether a PLA would advance the Federal Government's interest in economy and efficiency in procurement, as well as any additional considerations. Questions 7-8 address bidding intentions under both PLA and non-PLA scenarios and request detailed cost impact analysis. Questions 9-14 focus on subcontractor availability and impact, including effects on the pool of available subcontractors, preferred subcontractor relationships, anticipated refusals by key subcontractors by trade, and expected price increases or decreases as a percentage. The survey also requires respondents to provide historical project data from the last 2-5 years including project name and location, detailed description, initial cost estimates versus actual final costs, on-time completion status, number of craft trades involved, PLA usage, and challenges experienced. This template is intended to inform the Government's decision-making process regarding PLA requirements for a specific federal construction project.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PLA SURVEY QUESTIONS

1) Do you have knowledge that a PLA has been used in the local area on projects of this kind? If so, please provide supporting documentation.

2) Are you aware of skilled labor shortages in the area for those crafts that will be needed to complete the referenced project? If so, please elaborate and provide supporting documentation where possible.

3) Are you aware of time sensitive issues/scheduling requirements that would affect the rate at which the referenced project should be completed? If so, please elaborate and provide supporting documentation where possible.

4) Identify specific reasons why or how you believe a PLA would advance the

Federal Government’s interest in achieving economy and efficiency in Federal procurement.

5) Identify specific reasons why you do not believe a PLA would advance the

Federal Government’s interest in achieving economy and efficiency in Federal procurement.

6) Identify any additional information you believe the Government should take into consideration regarding the use of a PLA on the referenced project.

7) Does your company intend to bid/propose on this project if a PLA requirement is included in the solicitation? Does your company intend to bid/propose on this project if a PLA requirement is not included in the solicitation?

8) What are the likely cost impacts, if any, to your bid/proposal price if a PLA requirement is included in the solicitation? Please provide as much detail as possible regarding any anticipated cost impacts (positive or negative) of the inclusion of a PLA requirement, including any information you can provide about the magnitude of the anticipated impact.

The information gathered in this exercise should include the following information on projects completed in the last 2-5 years (or other timeframe, as appropriate):

a. Project Name and Location

b. Detailed Project Description

c. Initial Cost Estimate vs. Actual Final Cost

d. Was the project completed on time?

e. Number of craft trades present on the project

f. Was a PLA used?

g. Were there any challenges experienced during the project?

9) Are other projects in the vicinity going to limit the pool of skill labor available for your project? If so, which projects?

10) Has your firm previously declined to bid on a project because of a PLA requirement? If so, please specify the project(s).

11) How will a PLA impact the pool of available subcontractors for this project?

12) How would a PLA on this project impact your ability to use your company’s preferred subcontractors?

13) Do you anticipate that some of your key subcontractors would refuse to work on this project if a PLA is required? If yes, for which trades?

14) If possible, provide an estimate of the expected increase or decrease in your total price if a PLA is required for this specific project and location in terms of a percentage?