Performance Work Statement Summary
This Performance Work Statement details the repair of a 2006 International R-11 vehicle to restore it to original operational condition. The contractor must remove and replace the cambox, remove and replace the cambox door, service the over-the-wing nozzle, and perform prep and paint work. Key responsibilities include collecting the vehicle from JBER (Joint Base Elmendorf-Richardson) and returning it after repair completion, procuring all parts and accessories necessary for the repair, providing all labor for inspection, diagnosis and repair work, and performing operational checks to verify proper function and reliability. The period of performance is 60 days from receipt of the vehicle.
The contractor bears full responsibility for quality control, inspection, and testing in accordance with accepted industry standards and safety procedures. The contractor must provide all materials and products, manage transportation of the unit to and from JBER, assume liability for any damage caused by negligence, ensure proper personal protective equipment usage, and dispose of all hazardous waste according to local, state, and federal regulations. No hazardous waste is currently anticipated. The damage photographs indicate significant damage to the cargo box structure and door assembly that requires structural repair and repainting.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Performance Work Statement Repair 2006 International R-11 Reg Number Work Order
Date: 20 August 2026
I. Summary Repair 2006 International R-11 Reg Number, return this vehicle to original operational condition. Work must include:
Remove/replace cambox, remove/replace cambox door, over the wing nozzle, and prep & paint.
1. Base Access/Transportation: Must be able to Collect R-11 and Return after repair.
2. Procurement of all parts and accessories required to repair this 2006 International R-11.
3. Provide all labor required to inspect, diagnose and repair this vehicle. See sample damage photos below.
4. Perform operational checks to ensure proper function and reliability.
II. Submittals: N/A
III. Products:
All materials and products will be provided by the contractor in the performance of this contract.
IV. Quality Control:
The Contractor shall be responsible for all quality control and all inspection and test that are required unless otherwise specified.
1. The contractor shall perform all work according to accepted Industry Standards and Safety Procedures.
2. The contractor is responsible for any damage to the work area or adjacent areas due to negligence and will immediately repair at the contractor’s own expense.
3. Shop personnel will be required to transport the unit to and from JBER to the shop performing repairs.
V. Execution:
1. Period of Performance: Return 2006 International R-11 Reg Number within 60 days after receipt of the vehicle.
VI. Environmental & Safety:
1. The contractor shall perform all work according to accepted Industry Standards.
2. Ensure all workers are wearing the proper PPE for the assigned task.
3. The contractor will dispose of all hazardous waste per local, state, and federal regulations.
4. Known Encountered Waste Summary: none
VII. Testing: N/A