PERFORMANCE WORK STATEMENT (PWS)

Monaco D21 Upgrade

VLSB 23-2034

Part 1

General Information

1. GENERAL: Project intent is to upgrade technology to existing systems and to maintain compliance with the Industrial Control System (ICS) cybersecurity requirements within the proprietary Monaco D-21 Fire Alarm Reporting System (FARS) located at Shaw AFB. This requirement includes but is not limited to preventative maintenance to be perform to the Monaco systems at B308, B1992, B825, B708.

1.1 Description of Services/Introduction: Perform PM on the existing Monaco D21 system to include upgrading to the latest version of Windows 10 along with all compatible drivers and video cards.

1.2 Background: The existing version of Windows 10-2018 needs to be updated to the latest version. With the upgrade, critical software/ drivers that controls the Monaco D21 will need to be upgraded to ensure the system maintains functionality.

1.3 Objectives: Perform the upgrades as needed and maintaining functionality of the Monaco D21 system.

0. Scope:

Due to the highly specialized and proprietary nature of the installed systems, all work is to be performed only by Monaco trained personnel.

The following items will be performed by trained Monaco personnel:

· Provide completed reports after completion of trip

· Provide any recommendations for upgrades/changes to the D-21 System

· Clean and verify operation of the internal and exterior components of the D-21 PCs

· Ensure all cards are seated and operating properly

· Check operational status of internal fans

· Clean filters as applicable

· Check and re-seat cables and connectors as necessary

· Defragment the hard drive and clean the hard drive carrier

· Perform printer service to include the following:

· Check ink/toner level if supported in the existing model

· Ensure correct drivers are installed on each D-21/EM desktop computer

· Print test page from each D-21/EM desktop computer

· Update the D-21 software to the most current site applicable version as determined by Monaco Enterprises, Inc.

· Perform Antivirus updates

· Requires GOV provided McAfee

· Update RMF Ready Software settings to meet new STIG’s

· Requires existing RMF Ready software

· RMF Ready software updates can only be provided on Windows 10 CPU’s

· Update D-21 MAP software/layers if applicable

· Create a complete database backup, archive database (if determined to be necessary by on-site technician) to improve system performance, and provide backup to the Base on removable media

· Clean and visually inspect all D-21 monitors, adjusting any settings as necessary; tighten cables/connectors and label if necessary

· Conduct extended system-wide poll from each RFM (primary and alternates), test the system’s performance and assist in the correction of any deficiencies in the database

· Check rack mounted UPS systems: If digital readout exists, note current load and battery charge percentages; perform either a self-test if applicable to the UPS model or a 15 minute load test and record results

· If no digital readout exists, perform a 15 minute load test and record results

· For all UPS systems, verify that only Fire Reporting systems are connected and report any issues to the representative of the AHJ

· Verify network connectivity between all D-21 network computers and devices

· Verify and test Monaco support connection to allow for continued 24-hour support from the Monaco D-21 help desk

· Ensure redundant D-21 database is synchronized with the primary D-21 database

· Perform redundant server takeover test

· Update media files if new files are available

· Check condition of all D-21 rack equipment if installed, ensure all connections are secure and all computers and units are operating as intended; note off-normal units on customer report

· Provide a copy of the D-21 software installation disk for archive purposes

· Provide electronic copies of new D-21 manuals if available

· Visually inspect and functionally test Tone Panels, GPIOs, Network Video Monitoring, Mobile Base Stations, and Remote Station Alerting equipment (if installed); clean equipment if accessible at ground level

· Clean the RFM(s), verify redundant RFM operation if in service

· Visually inspect the antenna network from ground level and measure and record forward and reflected power on each RFM-X, RFM-7000, and each RFM Repeater (accessibility must be provided by the site)

· Update the RFM firmware to the most current site applicable version if necessary

· For Radio network connected mobiles, perform a drive test in at least one Mobile Client equipped vehicle to verify mobile connectivity to each Mobile Base Station

· Inspect Monaco provided DVR equipment (if installed) and ensure lines are recording normally

· Inspect Monaco network video monitoring (NVM) systems and provide status reports for any non-functioning cameras (if installed)

· Update D-21 Hazmat and Technical manuals, if available

· Update the D-21 Map, if updates to the existing ESRI map files are provided within 30 days of PO/Contract award

· Validate the system performance after installation

· Provide up to 4 hours of D-21 operator training after system initialization while the installation technician is on-site

· At the conclusion of the project, provide forms, system drawings, and documentation to detail the work that has been completed

0. Period of Performance: 365 days after issuance of NTP.

1.6 General Information

1.6.2 Quality Assurance: The Government shall monitor and evaluate the Contractor’s performance to ensure services are received IAW requirements set forth in this PWS. The method of surveillance will be spelled out in the Governments’ Quality Assurance Surveillance Plan. The COR will periodically inspect by watching actual task performance, physically checking an attribute of the completed task, checking a management information report, investigating customer complaints, or otherwise inspecting the task or its result to determine whether or not the performance meets the standards contained in this PWS. The COR may also inspect tasks not specifically mentioned in the Services Summary. The COR will document the results of the surveillance and this documentation will become the official Air Force (AF) record of the Contractor’s performance. When a performance threshold has not been met or Contractor performance has not been accomplished, the COR will initiate and provide a report to the CO for action concerning the Contractor. The Contractor shall respond to the CO within ten (10) calendar days of receipt. The surveillance results shall be maintained as past performance information of the Contractor’s overall compliance with contract terms and conditions. The Government will neither supervise contractor employees nor control the method by which the contractor performs the required tasks. It shall be the responsibility of the contractor to manage its employees and to guard against any actions that are of the nature of personal services, or give the perception of personal services. If the contractor believes that any actions constitute, or are perceived to constitute personal services, it shall be the contractor's responsibility to notify the Contracting Officer immediately.

The COR will be identified by separate letter. The COR is authorized to perform the following functions: assure that the Contractor performs the technical requirements of the contract: perform inspections necessary in connection with contract performance: maintain written and oral communications with the Contractor concerning technical aspects of the contract: issue written interpretations of technical requirements, including Government drawings, designs, specifications: monitor Contractor's performance and notifies both the Contracting Officer and Contractor of any deficiencies; coordinate availability of government furnished property, and provide site entry of Contractor personnel. A letter of designation issued to the COR, a copy of which is sent to the Contractor, states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the resulting order.

1.6.3 Recognized Holidays: [Contractor is not required to work recognized holidays but may request to in advance.]

New Year’s DayLabor Day
Martin Luther King Jr.’s BirthdayColumbus Day
President’s DayVeteran’s Day
Memorial DayThanksgiving Day
Independence DayChristmas Day

1.6.4 Hours of Operation: The contractor is responsible for conducting business, between the hours of 0730 – 1630 hours, Monday thru Friday except Federal holidays or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. For other than firm fixed price contracts, the contractor will not be reimbursed when the government facility is closed for the above reasons. The Contractor must at all times maintain an adequate workforce for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce are essential.

1.6.5 Base Closure: The Government will notify the contractor of anticipated closure of the facility due to inclement weather or any other authorized closure. In the event of an unplanned closure of the facility the contractor will be notified using the contact information provided. The Contractor is not authorized to bill the Government for those hours unless the Contractor can perform productive duties from an alternate worksite. Work scheduled but not accomplished because of base closure, will be accomplished as soon as possible after reopening the base.

1.6.6 Place of Performance: The work to be performed under this contract will be performed at B308, B1992, B825, B708 Shaw AFB SC 29152.

1.6.7 Type of Contract: The government will award a FIXED FEE CONTRACT.

1.6.8 SECURITY REQUIREMENTS.

1.6.8.4. Listing of Employees. The contractor shall maintain a current listing of employees. The list shall include the employee's name, social security number and level of security clearance (if needed). The list shall be validated and signed by the company representative and provided to the Sponsoring Agency Security Manager. An updated listing shall be provided when an employee's status or information changes. Sending a “Visit Request” through the Joint Personnel Adjudicative System (JPAS) can also fulfill this requirement.

1.6.8.5. Physical Security: The contractor shall be responsible for safeguarding all government equipment, information and property provided for contractor use. At the close of each work period, government facilities, equipment, and materials shall be secured.

1.6.8.8. Security Training. The Contractor ensures all Contractor employees receive initial and recurring security education training from the sponsoring agency's security manager. The security manager shall provide employees with training required by DODM 5200.01, DoD Information Security Program, Volume 3, and AFI 16-1404, "Air Force Information Security Program". The Contractor will also provide initial and follow-on training to contractor personnel who work in Air Force controlled/restricted areas. Air Force restricted areas and controlled areas are explained in AFI 31-101, Integrated Defense.

1.6.8.6 Pass and Identification Items: The Contractor shall comply with all requirements and procedures in accordance with (IAW) Air Force Federal Acquisition Regulations System (AFFARS) 5352.242-9000, Contractor Access to Air Force Installations. The Contractor shall ensure the pass and identification items required for contract performance are obtained for employees. All contractor employees shall undergo a background check conducted by 20th Security Forces Squadron prior to issuance of base access credentials. Until 1 Oct 2020 Shaw AFB will accept identification cards or driver's licenses from all states and Territories except ones marked "NOT VALID FOR FEDERAL IDENTIFICATION or FERERAL LIMITS MAY APPLY or any other words to that effect." Effective 1 Oct 2020 only REAL ID identification cards or driver's licenses will be accepted. For a full list of REAL ID Act and compliant and non-complaint states, please visit https://www.dhs.gov/current-status-states-territories. Contact 20th Security Forces Squadron for alternative forms of acceptable identification to conduct background checks. All documentation shall be submitted for base passes or base identification per Base Security Requirements. Contractor personnel shall obtain and wear specific Contractor base passes. Contractor personnel who have personal Department of Defense (DoD) retiree or dependent identification cards (ID), shall not use those personal ID cards for base access when performing contract work. All Contractor personnel who operate a vehicle in performance of this contract shall possess a valid driver’s license, current registration and insurance. Failure to turn in a base credential when requested can result in a non-recommend from Security Forces for future base access. The Contractor is responsible for employee inability to obtain base access required for contract performance. The contractor will be responsible for ensuring their employees are added to the Security Forces Entry Authorization List (EAL) to facilitate their servicing within the flight line perimeter.

1.6.8.7 Background Checks. All Contractor employees shall submit to a criminal background check accomplished by Shaw Air Force Base Security Forces prior to the employee being issued base access credentials. Each Contractor personnel must submit their Social Security Number, Date of Birth, and Driver's License state and number (if applicable). Failure to submit required information can result in denial or delay of issuance of credentials. Background checks are only good for the company that requested them. Processing background checks takes, at a minimum, 7-10 days from time of submission.

1.6.8.8 Federal Investigations Requirements. Contractor employees requiring initial issuance of a Common Access Card (CAC), Access to Restricted Areas, Use of Government Automated Information Systems/Networks, Child Care positions, or designated Positions of Trust shall complete submission of a Tier 1 investigation to the Office of Personnel Management (OPM), or a DoD-determined equivalent investigation. When required, the Government (20 FW Information Protection Office) will submit Tier 1 investigations to OPM at no cost to the Contractor.

1.6.8.9 Retrieving Identification Media. The Contractor shall retrieve all identification media from employees who depart for any reason before the contract expires; e.g. terminated for cause, retirement, etc.

1.6.8.10 Traffic Laws. The Contractor and its employees shall comply with base traffic regulations.

1.6.8.11 Weapons, Firearms, and Ammunition. Contractor employees are prohibited from possessing weapons, firearms, or ammunition, on themselves or within their contractor-owned vehicle or privately-owned vehicle while on Shaw AFB SC.

1.6.8.12 For Official Use Only (FOUO). The Contractor shall comply with DoD 5400.7-R, Chapter 4, DoD Freedom of Information Act (FOIA) Program, requirements. This regulation sets policy and procedures for the disclosure of records to the public and for marking, handling, transmitting, and safeguarding FOUO material.

1.6.8.13 Reporting Requirements. Contractor personnel shall report to an appropriate authority any information or circumstances of which they are aware may pose a threat to the security of DoD personnel, Contractor personnel, resources, and classified or unclassified defense information. Contractor employees shall be briefed by their immediate supervisor upon initial on-base assignment.

1.6.8.14 Controlled/Restricted Areas. The Contractor shall implement local base procedures for entry to Air Force controlled/restricted areas where Contractor personnel will work. An AF Form 2586, Unescorted Entry Authorization Certificate, must be completed and signed by the sponsoring agencies Security Manager before a Restricted Area Badge will be issued. Contractor employees must have a completed Tier 1 investigation before receiving a Restricted Area Badge. Interim access can be granted IAW AFI 31-501, Personnel Security Program Management.

1.6.8.15. Photography Restrictions. No one is authorized to take any pictures or video recordings of Air Force operational aircraft or restricted areas without the approval of 20 FW/CVN regardless of location while on Shaw AFB. This includes, but is not limited to, photographs taken from personal electronic devices such as blackberries, iPADs, iPODs, cell phones, or any other devices with digital recording capabilities. Any Contractor requiring pictures or videotape of Shaw's restricted/controlled areas to support their contract must request and possess written authorization prior entering the area. Written authorization letters to photograph or video the flightline must be signed by one of the following: 20 Maintenance Group Commander or Deputy; Aircraft Maintenance Squadron Commander; a Fighter Squadron Top 3, Director of Operations, or Commander; 20 Operations Group Commander or Deputy; 20 Operations Support Squadron Commander or Director of Operations; or 20 FW/CVN. Written authorization letters to photograph or video MQ-9 operational areas must be signed by the 50 ATKS or 25 ATKG commander. Written authorization letters to photograph or video the Missile Defense Agency area must be signed by the 609 ACOMS commander.

1.6.9 Special Qualifications: All personnel are required to have a valid SCDHEC license for asbestos operations and a current fit test for the type of respirators in use.

1.6.10 Post Award Conference/Periodic Progress Meetings: The Contractor agrees to attend any post award conference convened by the contracting activity or contract administration office in accordance with Federal Acquisition Regulation Subpart 42.5. The contracting officer, Contracting Officers Representative (COR), and other Government personnel, as appropriate, may meet periodically with the contractor to review the contractor's performance. At these meetings the contracting officer will apprise the contractor of how the government views the contractor's performance and the contractor will apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the government. Other topics may include (as applicable): opportunities to improve the contract, any modifications required of the contract, unsatisfactory performance inspections results, and valid customer complaints against each performance objective observed, and the results of corrective and preventive action measures. The Contractor will also notify the CO in writing, of work being requested or performed, if any, that the Contractor considers over and above the requirements of the contract. Appropriate action shall be taken to resolve outstanding issues. The Government will provide the Base Environmental Plan at this meeting. The minutes of these meetings will be documented in writing, signed by the CO and any other signatures as deemed appropriate, and distributed to the COR functional area and the Contractor. Should the Contractor not concur with the minutes, the Contractor will set out in writing to the CO any areas of non-concurrence. These meetings shall be held as needed, but not less than bi-annually after the contract is awarded. There will also be an initial meeting to take place 30 days after the contract has been awarded.

1.6.11 Key Personnel: The follow personnel are considered key personnel by the government: Ms. Bobbi Randle-West. 803-895-9558. The contractor shall provide a contract manager who shall be responsible for the performance of the work. The name of this person and an alternate who shall act for the contractor when the manager is absent shall be designated in writing to the contracting officer. The contract manager or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The contract manager or alternate shall be available between 0730 – 1630 hours, Monday thru Friday except Federal holidays or when the government facility is closed for administrative reasons. Qualifications for all key personnel are listed below:

SCDHEC Supervisor License

1.6.12 Identification of Contractor Employees: All contract personnel attending meetings, answering Government telephones, and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression in the minds of members of the public that they are Government officials. Contractor personnel shall be easily recognizable while on the installation in conjunction with this contract. This shall be accomplished through the wear of distinctive clothing, overcoats, or hats, bearing the company name or logo. The coloring or design of the items selected should identify personnel easily and quickly for reasons of safety and personal protection. Contractor personnel shall display distinguishing badges or other visible identification. They must also ensure that all documents or reports produced by contractors are suitably marked as contractor products or that contractor participation is appropriately disclosed.

1.6.14 Organizational Conflict of Interest: Contractor and subcontractor personnel performing work under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent Organizational Conflict of Interests (OCI) as defined in FAR Subpart 9.5. The Contractor shall notify the Contracting Officer immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the Contracting Officer to avoid or mitigate any such OCI. The Contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the Contracting Officer and in the event the Contracting Officer unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the Contracting Officer may effect other remedies as he or she deems necessary, including prohibiting the Contractor from participation in subsequent contracted requirements which may be affected by the OCI.

1.6.16 STANDARDS: The Government is authorized to restrict employment under this contract of any Contractor personnel or prospective Contractor personnel, who is identified as a potential threat to the health, safety, security, general well-being, or the operational mission of the installation (to include annexes such as Poinsett and Wateree) and its population. A determination may also remove Contractor personnel for, but is not limited to, incidents involving most immediately identifiable types of misconduct or delinquency such as: disorderly conduct, use of abusive or offensive language, intimidation by words or actions, fighting, participation in disruptive activities which interferes with the normal operations or brings discredit to the Government, theft, vandalism, sexual harassment, or any criminal actions. This also includes selling, consuming, or being under the influence of intoxicants, drugs, or substances which produce similar effects while in or on Federally-controlled property. Contractor personnel shall only smoke and/or use tobacco products in designated and approved smoking/tobacco use areas. If the CO directs removal of Contractor personnel for violating the above provisions, the Contractor shall immediately remove the individual(s) at no cost to the Government. Removal of employees for misconduct does not alleviate the Contractor from providing services. Per Shaw AFB Plan 31- 101, the installation commander has authority to debar any individual from the installation who commits a crime or offense prejudicial to good order and discipline. All disputes to the CO’s decision must be filed within ten (10) days of the decision to the Base Operations Support Flight Chief. The removed Contractor personnel may not resume work unless/until a decision is made by the Government CO overturning the removal decision.

1.6.17 SUBCONTRACTOR COMPLIANCE: The Contractor shall be responsible for ensuring Subcontractors satisfy the requirements set forth in the contract. The Contractor shall include a provision in all subcontracts to require Subcontractor compliance with terms and conditions of this contract.

1.6.18 EMPLOYING GOVERNMENT PERSONNEL: The Contractor shall not employ any person who is an employee of the United States Government if the employment of that person would create a conflict of interest. Further, the Contractor shall not employ any person who is an employee of the Department of the Air Force, either military or civilian, unless such person seeks and receives approval in accordance with DODD 5500.7R, Joint Ethics Regulation. In addition, the Contractor shall not employ any person who is an employee of the Department of the Air Force if such employment would be contrary to the policies contained in AFI 64-106, Industrial Labor Relations Activities. All questions of “conflict of interest” shall be referred to the CO. The Contractor is cautioned that off duty active military personnel hired under this contract are always subject to Permanent Change of Station (PCS), change in duty hours or deployment. Military Reservists and National Guard members may be subject to recall to active duty. The abrupt absence of these personnel could adversely affect the Contractor's ability to perform. Their absence at any time shall not constitute an excuse for nonperformance under this contract.

1.6.19 COMPLIANCE WITH LABOR LAWS: The Contractor shall comply with all applicable laws pertaining to wages, worker’s compensation, equal opportunity, Service Contract Act, and so forth, as implemented by Air Force directives and required by law.

1.6.20 Continuation of Essential Contractor Services: This requirement is not considered mission essential, and services will be suspended during a declared emergency. Contractor personnel will not be required or expected to perform maintenance in such an event as a hurricane or when travel is deemed “unsafe” by local authorities. Inspections and/or maintenance actions due during this time will be completed as soon as the condition warranting the delay is lifted. This maintenance will not be withheld until the next service interval and contractor personnel are expected to perform the maintenance that was to be performed prior to the delay within 5 days.

1.6.21 Information Management: All records, files, documents, regardless of media (e.g., paper, electronic, etc.) as described in the PWS that are the responsibility of or generated by the Contractor, are the property of the Government, and shall remain so upon termination or completion of the contract. The Contractor shall keep these items current and maintain and dispose of them in accordance with the requirements established in Air Force Instruction (AFI) 33-322, Records Management Program, paragraph 10, Air Force Manual (AFMAN) 33-363, paragraph 6.4, AFI 33-364, paragraph 2.10, and the Air Force Records Disposition Schedule available on the Air Force Portal link. Records shall be turned over to the Government upon completion of the contract unless otherwise stated. All records are subject to the Freedom of Information and Privacy Act. The Shaw AFB Records Management Office (20 CS/SCOKR), 895-1630, will provide assistance and training to the Contractor to ensure compliance with Federal record keeping requirements.

1.6.21.2 Records: The Contractor shall be responsible for creating, maintaining, and disposing of only those Government required records that are specifically cited in this PWS. If requested by the Government, the Contractor shall provide the original record or a reproducible copy of any such record within five working days of receipt of the request.

1.6.22 Purchase of Recycled Products: The Contractor shall comply with the DoD Green Procurement Program for Recovered Materials.

1.6.23 Publications: The Contractor shall ensure compliance with all applicable publications, regulations, and operating instructions related to the tasks set forth in this PWS. The Contractor is required to acquire and abide by the latest version of all publications. See Part 6 for a list of applicable publications.

1.6.24 Safety Requirements: The Contractor shall perform work in a safe manner as required by OSHA Safety and Health Requirements and applicable Department of Labor, Department of Defense and Air Force safety standards. The Contractor shall provide a verbal report to the CO as soon as possible following an occurrence of damage to Government property or an accident resulting in death, injury, occupational disease, or adverse environmental impact. Provide a completed copy of the required Accident Investigation Report to the CO within five (5) calendar days of each occurrence. The Accident Investigation Report shall be prepared and submitted IAW AFI 91-204.

1.6.24.1 Mishaps: In the event of an accident/mishap, the Contractor shall take reasonable and prudent action to establish control of the accident/mishap scene, prevent further damage to persons or property, and preserve evidence until released by the accident/mishap investigative authority through the CO.

1.6.24.2 Investigations: If the Government elects to conduct an investigation of the accident/mishap, the Contractor shall cooperate fully and assist Government personnel in the conduct of investigation until the investigation is completed.

1.6.24.3 Lock Out Tag Out (LOTO): The Contractor will follow all LOTO procedures IAW OSHA regulation 1910.147 and AFI 91-203. The Contractor will also provide proof of an approved LOTO process to the COR upon contract approval.

1.7. Environmental Management System, Executive Summary For Contractors

1.7.1. Introduction. In accordance with Air Force Instruction 32-7001, Environmental Management, Shaw Air Force Base (SAFB) has implemented an ISO 14001 based Environmental Management System (EMS). The goal of the EMS is to improve the core business processes of SAFB, as they relate to the environment, seeking to improve and enhance performance in support of the overall mission. The EMS supports a transition from a compliance driven program to one that focuses pollution prevention efforts on managing both environmental and mission risks.

1.7.2. Environmental Policy. Central to the SAFB EMS is the base environmental policy set by Wing Leadership. The policy establishes fence-to-fence applicability to include all 20th Fighter Wing organizations, all tenants, and contractors conducting business on SAFB property. It further extends applicability to the areas under SAFB control at Wateree Recreational Area and the Poinsett Electronic Combat Range. As indicated in the policy, SAFB leadership is committed to continual improvement, pollution prevention, regulatory compliance, the conservation of natural resources, and the integration of environmental awareness into day-to-day operations. Through such commitments, SAFB is able to set environmental objectives and targets with focus on enhancing the mission through environmental management.

1.7.3. What is EMS? An EMS is that part of an overall management system that includes organizational structure, planning activities, responsibilities, practices, procedures, processes, and resources for developing, implementing, achieving, reviewing, and maintaining the environmental program and achieving environmental goals based on continual-improvement. The EMS is intended to help SAFB balance its mission with maintaining regulatory compliance and developing sustainability strategies to secure this base’s ability to support current and future mission requirements.

1.7.4. Significant Aspects. An aspect is any interaction with the environment caused by activities on SAFB. Through the EMS, these aspects have been systematically inventoried and evaluated based on the following ranking criteria.

· Relative financial cost

· Risk to the environment

· Risk of regulatory non-compliance

· Potential mission degradation

· Community Concerns These criteria are scored and weighted for each aspect as recommended by Wing Leadership to establish those environmental aspects deemed most critical to address.

1.7.5. What is My Role? As a contractor performing work on SAFB property you must understand that any activities that directly or indirectly impact the environment, especially the significant aspects listed above, must be communicated with the 20th Civil Engineer Squadron, and the greatest precaution should be taken to avoid negative impacts in these areas. Think of EMS the same way you think about safety. Just as you are aware of all safety hazards associated with your job, you must also be aware of all environmental impacts associated with your job and mitigate those to the extent possible.

To find out more about the SAFB EMS or to discuss potential impacts of contracted activities, contact the 20th Civil Engineer Squadron at 803.895.9987.

1.7.6. 20th Fighter Wing Commander Memorandum on Shaw AFB Commitment to Environmental Protection:

PART 2

DEFINITIONS & ACRONYMS

2. DEFINITIONS AND ACRONYMS:

2.1. DEFINITIONS

2.1.1. CONTRACTOR. A supplier or vendor awarded a contract to provide specific supplies or service to the government. The term used in this contract refers to the prime.

2.1.2. CONTRACTING OFFICER. A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note: The only individual who can legally bind the government.

2.1.3. CONTRACTING OFFICER'S REPRESENTATIVE (COR). An employee of the U.S. Government appointed by the contracting officer to administer the contract. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.

2.1.4. DEFECTIVE SERVICE. A service output that does not meet the standard of performance associated with the Performance Work Statement.

2.1.5. DELIVERABLE. Anything that can be physically delivered, but may include non-manufactured things such as meeting minutes or reports.

2.1.6. KEY PERSONNEL. Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.

2.1.7. PHYSICAL SECURITY. Actions that prevent the loss or damage of Government property.

2.1.8. QUALITY ASSURANCE. The government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.

2.1.9. QUALITY ASSURANCE Surveillance Plan (QASP). An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.

2.1.10. QUALITY CONTROL. All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.

2.1.11. SUBCONTRACTOR. One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.

2.1.12. WORK DAY. The number of hours per day the Contractor provides services in accordance with the contract.

2.1.12. WORK WEEK. Monday through Friday, unless specified otherwise.

2.2. ACRONYMS: [List all acronyms used in the PWS and what they represent. At a minimum, insert the acronyms provided below].

ACORAlternate Contracting Officer's Representative
AFFARSAir Force Federal Acquisition Regulation Supplement
AFIAir Force Instruction
CFRCode of Federal Regulations
CONUSContinental United States (excludes Alaska and Hawaii)
CORContracting Officer Representative
ACOTAlternate Contracting Officer's Representative
COTSCommercial-Off-the-Shelf
DD250Department of Defense Form 250 (Receiving Report)
DD254Department of Defense Contract Security Requirement List
DFARSDefense Federal Acquisition Regulation Supplement
DMDCDefense Manpower Data Center
DODDepartment of Defense
FARFederal Acquisition Regulation
HIPAAHealth Insurance Portability and Accountability Act of 1996
COContracting Officer
OCIOrganizational Conflict of Interest
OCONUSOutside Continental United States (includes Alaska and Hawaii)
ODCOther Direct Costs
PIPOPhase In/Phase Out
POCPoint of Contact
PRSPerformance Requirements Summary
PWSPerformance Work Statement
QAQuality Assurance
QAPQuality Assurance Program
QASPQuality Assurance Surveillance Plan
QCQuality Control
QCPQuality Control Plan
TETechnical Exhibit

PART 3

GOVERNMENT FURNISHED PROPERTY, EQUIPMENT, AND SERVICES

3. GOVERNMENT FURNISHED ITEMS AND SERVICES:

3.1. Services: N/A

3.2 Facilities: The Government will provide access to the system within buildings B308, B1992, B825, B708

3.3 Utilities: The Government will furnish sufficient quantities of electricity, water, sewage, that currently exists in the facility, if additional power is required the contractor shall provide generator power: The Contractor shall instruct employees in utilities conservation practices. The contractor shall be responsible for operating under conditions that preclude the waste of utilities, which include turning off the water faucets or valves after using the required amount to accomplish cleaning vehicles and equipment.

3.4 Equipment: N/A

3.5 Materials: N/A

Security Police: The Government will provide general on-base security police service. Use the following numbers as needed:

Security-Police and Fire Protection: Call phone number 911.

Security Police Crime Stop Numbers: Crime Stop Number is 803-895-3669/3670.

Emergency Medical Service: The Government will provide emergency medical treatment for Contractor personnel while they are performing duties associated with this contract. The Contractor shall reimburse the Government for the cost of medical treatment and patient transportation at the current inpatient or outpatient treatment rate as appropriate.

Forms and Publications: The Government will provide forms and publications to perform the work required by the contract. If network access is included in this contract, the Government will provide electronic access to required forms and publications. Publications can be accessed on-line at http://www.e-publishing.af.mil.

Base Civil Engineers: The Government will provide fire prevention inspections and maintenance of Government furnished fire systems.

Postal/Installation Distribution:. All commercial mail services are the responsibility of the Contractor.

Parking: Space is available for common vehicles at the parking lot adjacent to the facilities

PART 4

CONTRACTOR FURNISHED ITEMS AND SERVICES

(This section is used to identify the materials and equipment that the contractor must provide. Examples provided below.)

4. CONTRACTOR FURNISHED ITEMS AND RESPONSIBILITIES:

4.1 General): The Contractor shall furnish all supplies, equipment, facilities and services required to perform work under this contract that are not listed under Section 3 of this PWS.

4.3. Materials. The Contractor shall furnish materials, supplies, and equipment necessary to meet the requirements under this PWS.

4.4. Equipment. The Contractor shall furnish all equipment required to meet the requirements under this PWS.

PART 5

SPECIFIC TASKS

(This section is the heart of the PWS. All of the services to be performed under the contract should be described in sufficient detail here. This includes all general tasks required by the Government.)

5. Specific Tasks:

5.1. Basic Services. The contractor shall provide services for the completion of the task identified

5.3. CONTRACTOR MANAGEMENT REPORTING (CMR): The Contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract via secure data collection site. The contractor is required to complete all required data fields at the Air Force CMRA link http://www.ecmra.mil. Reporting inputs will be for the labor executed during the period of performance for each Government Fiscal Year (FY), which runs 1 October through 30 September. While inputs may be reported any time during the FY, all data shall be reported no later than 31 October of each calendar year. Contractors may direct questions to the CMRA help desk.

Uses and Safeguarding of Information: Information from the secure web site is considered to be proprietary in nature when the contract number and contractor identity are associated with the direct labor hours and direct labor dollars. At no time will any data be released to the public with the contractor name and contract number associated with the data.

PART 6

APPLICABLE PUBLICATIONS

6. APPLICABLE PUBLICATIONS (CURRENT EDITIONS)

6.1. The Contractor must abide by all applicable regulations, publications, manuals, and local policies and procedures. Regulation 61-86.1 SCDHEC Standards of Performance for Asbestos Projects

PART 7

ATTACHMENT/TECHNICAL EXHIBIT LISTING

1. Attachment/Technical Exhibit List:

0. Attachment 1/Technical Exhibit 1 – Services Summary

7.2. Attachment 2/Technical Exhibit 2 – Deliverables Schedule

0. Attachment 3/Technical Exhibit 3 – Estimated Workload Data

TECHNICAL EXHIBIT 1

Services Summary The contractor service requirements are summarized into performance objectives that relate directly to mission essential items. The performance threshold briefly describes the minimum acceptable levels of service required for each requirement. These thresholds are critical to mission success.

Performance Objective (The Service required—usually a shall statement)

Standard
Performance Threshold (This is the maximum error rate. It could possibly be “Zero deviation from standard”)

Method of Surveillance

SS # 1.

Provide completed reports to include any recommendations for upgrades/changes to the D-21 System

The contractor shall provide reports with detailed recommendations concerning upgrades or changes to the system.

Complete report

Evaluation of report at 100% completion

TECHNICAL EXHIBIT 2

DELIVERABLES SCHEDULE

Deliverable
Frequency
# of Copies
Medium/Format
Submit To
Trip Report
END OF PROJECT
1 Copy
EMAIL
roberta.west-randle@us.af.mil

Provide a complete database backup on removable media

One time during performance
2 copies
Identifiable CD
Roberta West-Randle
Provide results of UPS system testing
One time during performance
1 copy
Email

Provide D-21 software installation disk for archive purposes

One time during performance
2 copies
Identifiable CD
Roberta West-Randle

Provide electronic copies of new D-21 manuals if available

One time during performance
1 copy
Identifiable CD
Roberta West-Randle

Provide forms, system drawings, and documentation to detail the work that has been completed

END OF PROJECT

1 Copy
EMAIL
roberta.west-randle@us.af.mil

TECHNICAL EXHIBIT 3

ESTIMATED WORKLOAD DATA

ITEM

NAME

ESTIMATED QUANTITY

1
Prep work, pre-clean and poly containment area
________
36 hours
2
Abatement
________
36 hours
3
Clearance Sampling and tear down
________
36 hours