This is a Performance Work Statement for cleaning and haul away services at the United States Military Academy (USMA) at West Point. The Contractor shall provide comprehensive interior cleaning and debris removal for the 4th floor of Building 606, as well as perform identical work in other West Point buildings as occupants relocate from Building 606 to new locations.

The primary scope of work includes: emptying the building of all residual items such as equipment, rugs, furnishings, papers, books, and personal/business items; preserving and moving furniture to designated storage locations; relocating up to 20 additional desks from various building areas to 4th floor storage; providing all necessary dumpsters including delivery, removal, and replacement once filled; sweeping and vacuuming empty spaces to leave the building in move-ready condition; and performing equivalent work in other West Point buildings as needed. The Contractor will receive notification from USMA when building sections have been vacated and must complete all work within 2 weeks of notification. The work period extends from the date of award through September 30, 2026. An attached drawing detailing building locations and layout is referenced but not included in this document.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Performance Work Statement

The Contractor shall provide cleaning and haul away service for all interior sections of the 4th floor building 606.

The contractor shall empty the building of all residual items including but not limited to equipment, rugs and other furnishings, papers, books, and other personal and business items left behind after the move from the building is complete. The furniture in these rooms will be saved and moved to a specified location for storage. Additionally, up to 20 additional desks will be moved from various areas in the building to the same storage location on the 4th floor.

See attached drawing to detail the locations and layout.

The contractor shall sweep and/or vacuum the empty spaces and leave the building in good condition for the next occupants to move in.

The contractor shall provide all dumpsters needed to complete these tasks.

The contractor shall provide dumpsters, deliver them in place, fill them with the contents of the building and remove and replace them once they are filled and remove all dumpsters at the end of the work.

The contractor will be notified when a section of the building has been vacated and the section needs to be cleared of items and cleaned.

The contractor will arrange for work to be completed within 2 weeks of notification from USMA.

The contractor shall perform the same work in other buildings on West Point as requested as the occupants move from building 606 to their new location.

The contractor will be notified when area has been vacated, and the section needs to be cleared of items and cleaned. The contractor will arrange for work to be completed within 2 weeks of notification from USMA.

The work for this time frame will take place from date of award until the end of September 2026.