This performance work statement outlines the scope of work for a paving indefinite delivery/indefinite quantity contract at Fort Stewart and Hunter Army Airfield in Georgia. The contractor will provide supervision, pavement repair and overlay work including pot hole and crack filling, milling, manhole and inlet construction and repair, utility road crossing repairs, installation of striping, signage and pavement markings, pipe installation, new construction of parking lots and roads, fencing work, concrete placement, erosion control, traffic signal work, sewer infrastructure work, water line replacements, and rubber and paint removal from airfield pavement. The related pre-solicitation notice is for solicitation number W9124M24B0002 to establish an IDIQ contract vehicle for these paving services to be awarded by the Department of the Army Mission and Installation Contracting Command.

View the file

Other files

File Type Posted
Drawings.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work

Paving IDIQ Ft. Stewart/HAAF

IJO NOS WG-303-2J & ED-303-2J

Work to be Done: The work covered by this contract consists of furnishing all plant, labor, materials and performing all operations required in connection with Paving IDIQ Ft. Stewart/HAAF, Fort Stewart and Hunter Army Airfield, Georgia, complete in strict accordance with specifications and drawings, subject to the terms and conditions of the contract. The work includes, but is not necessarily restricted to, the following items:

1. Proper, adequate and proficient supervision shall be provided by the contractor throughout all phases of work.

2. Unless otherwise approved, the Contractor shall be permitted to do the work between the hours of 7:30 a.m. to 4:00 p.m., Monday through Friday, exclusively. Prior to the contractor performing any work during hours other than those specified, the contractor shall submit a request to the COR for approval by the Contracting Officer. Requests shall be submitted no less than 24 hours prior to the time the contractor desires to work.

3. Repair and Overlay Pavement to include pot hole repair, crack repair, widening existing roads, and installing slurry seal treatments. This work may contain requirements for milling of pavement. Additional requirements for constructing, raising or repairing manholes/inlets and valves.

4. Constructing or replacing headwalls, sidewalks, curbs and gutters. Additional requirements for Utility road crossing repairs to include demolition and construction.

5. Installing reflective paint and thermoplastic paint striping, arrows, handicap markings and letters as shown. Additional requirements for removal and installing street signs and pavement markings, including airfield pavement markings. All work shall follow the requirements of MUTCD.

6. Installation of concrete and corrugated metal pipe to include excavation, backfilling and compaction.

7. Construct new parking lots, roadway and related drainage structures.

8. Remove and install fencing.

9. Placement of new concrete to include slabs, sidewalks and related items.

10. Establish grass and erosion control on job sites.

11. Modify existing traffic light signal system and install new traffic light signal system at intersections.

12. Sanitary sewer structure and sewer line replacement.

13. Water line replacements.

14. Rubber and paint removal from airfield pavement.