This document is an infographic detailing the end-to-end Progressive Design-Build (PDB) procurement process for Military Construction (MILCON) projects using Other Transaction (OT) authority under 10 U.S.C. § 2808a.

The process comprises three main phases: Pre-Agreement (Planning, Solicitation, and Award), Agreement Phase 1 (Design and Preconstruction Services using MILCON Design Funds), and Agreement Phase 2 (Final Design and Construction using MILCON Construction Funds). The Pre-Agreement phase includes eight steps: Project Requirements definition, Request for Qualifications (RFQ) publication, Statement of Qualifications (SOQs) submission and evaluation, down-selection of qualified firms, pitch presentations, Qualifications-Based Selection (QBS), negotiation of Phase 1 OT services, and award of the Phase 1 OT Agreement. Agreement Phase 1 encompasses Kickoff and Alignment, Schematic Design, Budget Lock, Design Development, Preconstruction Readiness, and a Decision Gateway to Phase 2, with an off-ramp decision point providing exit protection for the Government. Agreement Phase 2 includes authorization of construction upon cost, scope, schedule, and risk acceptance; overlapping Final Design and Construction Documents; overlapping Construction execution in work packages; Red Zone/Beneficial Occupancy activities; and Turnover/Construction Completion. The PDB with OT approach emphasizes early alignment between Government and industry, open-book collaboration and transparency, iterative and flexible strategy evolution, off-ramp protection at key milestones, overlapped execution optimizing design and construction, and tailored governance and oversight to deliver facilities with improved cost and schedule confidence.

View the file

Other files

File Type Posted
Playbook - Executing PDB with OTA.pdf PDF
Placemat Design Build to Budget.pptx PPTX presentation

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROGRESSIVE DESIGN-BUILD (PDB) WITH OT

End-to-End Process for MILCON Projects

Right Authority.

Right Collaboration.

Right Outcome.

OT STATUTORY

AUTHORITY:

10 U.S.C. § 2808a, Facility Construction or Repair:

Transactions Other Than Contracts and

Grants

AGREEMENT PHASE 1 – DESIGN & PRECONSTRUCTION SERVICES (OT Agreement using MILCON Design Funds)

EARLY ALIGNMENT

Aligns Government & Industry Goals Early

OPEN BOOK COLLABORATION

Transparency in estimating drives informed decisions

ITERATIVE & FLEXIBLE

Evolves Strategy & Solves Challenges Early

OFF RAMP PROTECTION

Exit points protect Government at key milestones

OVERLAPPED EXECUTION

Design and Construction Optimized

BETTER OUTCOMES

Deliver facilities with more cost and schedule confidence

AGREEMENT PHASE 2 – FINAL DESIGN & CONSTRUCTION (OT Agreement using MILCON Construction Funds)

KICKOFF & ALIGNMENT SCHEMATIC DESIGN BUDGET LOCK DESIGN DEVELOPMENT DECISION GATEWAY TO

PHASE 2

PRECONSTRUCTION

READINESS

Outcome: Government Authorizes Phase 2 Construction when Cost, Scope, Schedule and Risk are Acceptable

Risk Informed Project Alignment Meeting

• Goals & Objectives

• Risk Workshop

• Success Metrics

• Communication Plan

Concept Solutions

• Further Alternates

• Innovation Opportunities

• Risk Reduction

Schematic Design Development

• Develop Design

Concepts

• Evaluate Systems

• Confirm Approach

Budget Estimate Submission

• Level 3 Cost Estimate

• Cost Confidence Package

• Scope/Schedule Validation

Advance Design (Technical Development)

• Tailored Design

• Engineer Analysis

• Constructability Reviews

Integrated Schedule Development

• Long Lead Item Identification

• Resource Planning

Execution-Ready Integrated Solution

• Coordinate Estimate

• Constructability

• Risk Mitigation

Government Decision

• Scope Confirmed

• Cost Validated

• Risk Accepted

• Negotiate Phase 2:

Construction

Pre-Construction Work

• BCOES

• Permitting

• Early Submittals

• Site Readiness

Open Book Estimate / Price Schedule Open Book Estimate / Price Schedule

Switch to Firm-Fixed Price

1. Project Requirements

• Mission Need

• Performance Objectives

• Industry Outreach /

Market Intelligence

• SCO OTA Approval

AUTHORIZE PHASE

2 CONSTRUCTION

FINAL DESIGN / CONSTRUCTION DOCUMENTS

(OVERLAPPING)

CONSTRUCTION (OVERLAPPING w/ DESIGN) REDZONE / BENEFICIAL OCCUPANCY TURNOVER /

CONSTRUCTION

COMPLETE

LONG LEAD / EARLY

WORK

• Early Site

Acquisition

• Site Access

• Site Preparation

• Early Package

• Execute Construction in Work Packages

• Foundations / Structure

• Building / Systems

• Interior / Exterior

• Site Utilities

• Continuous Quality & Safety Reviews

• Punchlist

• Red Zone Commissioning

• Joint Occupancy (if needed)

• Beneficial Occupancy

• Base Certification

• Turnover / Construction Complete

• Close Out

• Mission Complete!

• Complete Construction Documents

• Permitting & Submittals

• Ongoing Design Development

• Submittals & Coordination

• Continued BCOES Reviews

• Receive MILCON Construction Funding

• Issue Modification to Agreement

• Obligate Funding

• Decision Milestones

• Green Light Long Lead Item Procurement Construction Continues

2. Request for Qualifications

(RFQ)

3. Statement of Qualifications

(SOQs)

• Industry Submits SOQs

• Government Evaluation

4. Down-Select •Government

Selects Best Qualified Offers

•Invite Firms to Pitch Presentations

5. Pitch Presentations

6. Qualifications Based Selection

(QBS)

• Government Selects

Best Qualified Offeror

7. Negotiate OT (Phase 1) Services

• Scope of Ph 1 Design/ Preconstruction Services

• Performance Metrics

8. Award OT (Phase 1)

Agreement

• Award Other

Transaction Agreement

GOVERNANCE

& OVERSIGHT

• Tailored Oversight

• Periodic Reporting

• Cost, Schedule, Performance Reviews

• Risk Management

Why PDB with

OT?

PRE-AGREEMENT: PLANNING, SOLICITATION, & AWARD

OFF RAMP

DECISION POINT

OFF RAMP

DECISION POINT

• Finalize Requirements Package

• Industry Day / Notice

• Publish Solicitation

• Offeror Presentations / Meetings / Interviews

• Q&A

• Site Visit, if applicable