This Addendum No. 3, issued November 17, 2026, modifies the contract documents for the ADA Upgrades Davis Academic Building project (Project No. 2026-049M25) at Pueblo Community College in Pueblo, Colorado. The addendum addresses clarifications and modifications to the scope of work, specifications, and contract procedures. Key dates include the anticipated final addendum issuance of November 19, 2026, qualifications due November 24, 2026, bids due December 3, 2026 at 2:00 p.m. MST, and public bid opening on December 3, 2026 at 2:15 p.m. MST. The project involves extensive ADA accessibility upgrades including stair repairs/replacement, new and renovated restrooms, HVAC modifications, electrical system updates including fire alarm notifications, plumbing modifications, and related mechanical and electrical work. The addendum clarifies thirty-three questions and answers addressing technical specifications, material selections, coordination requirements, fire alarm delegated design responsibilities, mechanical system modifications in an occupied building, electrical panel modifications, and various other construction details. Work is scheduled to begin in January 2027 during the heating season in an occupied academic building, requiring careful coordination of outages and occupied-area maintenance.

No liquidated damages are specified for this project. The contract is subject to Colorado prevailing wage requirements, with applicable wage rates provided in the addendum. PCC is exempt from City of Pueblo taxes but is not exempt from Pueblo County taxes. The contract requires a bid bond of not less than 5 percent of the bid price, performance and labor/material payment bonds, and specific insurance coverage. An asbestos inspection report dated December 12, 2016, is provided for reference. The project uses Colorado State Buildings Program standard forms including the Design/Bid/Build Contractor's Agreement (SC-6.21), General Conditions (SC-6.23), and supplementary forms. The bidding process follows Competitive Sealed Best Value methodology with qualifications weighted at 40 percent and bid price at 60 percent. Fire alarm work, including delegated design and system modifications, is included in the construction contract with the general contractor responsible for providing a qualified fire alarm subcontractor. The state prevailing wage statute applies, and the contractor must comply with Colorado labor requirements including the 80 percent Colorado labor requirement for public works projects.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pueblo Community College Addendum No. 3 ADA Upgrades Davis Academic Building Page 1 of 8

1935 Dominion Way, Suite 202

Colorado Springs, CO 80918

Office: 719.277.7300

ADDENDUM NUMBER 3

PROJECT: Pueblo Community College DATE: November 17, 2026 ADA Upgrades Davis Academic Building Project No.: 2026-049M25

OWNER: Pueblo Community College 900 W. Orman Ave.

Pueblo, Colorado 81004

The Drawings, Specifications and Contract Documents on the subject project are modified, corrected, supplemented and/or superseded as hereinafter described.

The following additions, deletions, changes and information shall become a part of and modify all work shown or described in the Drawings and Project Manual.

All bidders shall make necessary adjustments in their bid on account of this addendum.

Each and every bidder, subcontractor, and material supplier shall be responsible for reading each item in this addendum to ascertain to what extent and in what manner it affects the work in which they are interested. Each Bidder shall indicate on the Bid Form their acknowledgment of receipt of this addendum document by addendum number and addendum date.

GENERAL

1. Advertisement for Bids: The published Due Date for Final Addendum Issue

(anticipated) on the Advertisement for Bids has been moved to November 19, 2026.

See item #3 for updated schedule reminders.

2. Advertisement for Bids: Add Advertisement for Bids AFB Exhibits. See attachments.

3. BID SCHEDULE REMINDERS:

Final Addendum Issued (anticipated) November 19, 2026

Qualifications Due November 24, 2026, 2:00 p.m. (MST) Bids Due December 3, 2026, 2:00 p.m. (MST)

Public Bid Opening December 3, 2026, 2:15 p.m. (MST)

QUESTIONS

4. Q: The AFB describes AA#2 as “stair repairs,“ while 01 23 00 and G0.00 describe it as

“Replace Exterior NW Concrete Stairs.” A2.51 shows four handrails removed and two

ADA Upgrades Davis Academic Building Page 2 of 8 new handrails provided. The A2.51 title block reads “ADD ALT #4.” Work would start in January.

Please confirm the AA#2 scope (repair vs. full replacement) and the extent of the sawcut. Please confirm whether handrails are required on both sides of each stair, and the railing finish (galvanized and painted?). Please advise whether AA#2 can be scheduled in spring to avoid cold-weather concrete.

A: AA#2 is an extensive repair of the stairs, as it involves replacement of the stairs.

Additional information will be provided in future addendum.

5. Q: Please provide wage determination sheet for this project.

A. The Wage Determination sheet is part of the attached AFB Exhibits list.

6. Q: Please confirm if there are liquidated damages? If so, please specify the amount to be stated in section 7.7 of the SC6.21 Contractors Agreement.

A: There are no liquidated damages for this project.

7. Q: General Conditions section 9.3.1 and 9.3.2 states that all federal and state taxes are to be excluded. Please confirm whether bidders are to include or exclude city and/or county taxes.

A: PCC is exempt from City of Pueblo taxes. PCC is not exempt from Pueblo County taxes.

8. Q: Is there an asbestos or hazardous materials report available for the areas being disturbed? Who will handle abatement if anything is found?

A: A report was prepared by All-Phase Environmental Consultants, Inc., dated December 12, 2016 describing asbestos inspections performed on November 22, 2016 and December 2, 2016 at the Davis Academic Building, and the findings from these inspections. See attached report.

9. Q: Addendum 1 references revised sheet A2.40, but the attachment list says A4.00.

Which is correct?

A: A2.40 is the correct sheet. A4.00 was incorrectly transcribed; there is no sheet

A4.00.

10. Q: Section 10 14 67 makes tactile signage Owner-furnished/Contractor-installed

(OF/CI), and A7.00 agrees. As.20-A2.22 Note 5 says provide room signage to match existing,” and the AFB lists “updating signage” as base scope. Several toilet accessories are OFCI per 10 28 00 (TA06, TA07, TA11, TA15).

Please confirm that all signage is OFCI, and give the quantity and locations of signs to be installed (new restrooms and doors only, or building-wide). Please confirm the complete list of OFCI toilet accessories.

ADA Upgrades Davis Academic Building Page 3 of 8

A: Signage for this project will be furnished and installed by Owner’s signage vendor.

Specifications and Drawings will be updated to reflect this, with additional information on signage and Toilet Accessories provided in a future addendum.

11. Q: Please provide a Door schedule for this project.

A: A Door Schedule is provided on Sheet A6.00. Sheet A6.00 will be updated in a future addendum.

12. Q: Please provide a Glazing Schedule for this project.

A: Window types with designations and glazing callouts are provided in Sheet A6.00.

Sheet A6.00 will be updated in a future addendum.

13. Q: L1A-15 serves “Recepts Restrooms & Door Operator.” NEC 210.11(C)(3) limits a bathroom receptacle circuit to bathroom receptacles unless it serves a single bathroom. Confirm whether the door operator may remain on this circuit.

A: NEC 210.11(C)(3) applies to dwelling units and does not require a dedicated bathroom receptacle circuit in this academic building. Retain the existing circuit reuse indicated for the door operator. Maintain required GFCI protection for restroom receptacles.

14. Q: The submittal table references Section 28 31 05, but no Division 28 section is in the project manual. Confirm that visible notification appliances are required in new restrooms 036, 144A, 250E and Sensory Room 015A (Alt 1). Also confirm the existing FA panel manufacturer/vendor and whether the Pueblo FD requires a shop drawing submittal.

A: Section 28 31 05 is included in the Addendum 1 electrical specifications, issued 11/10/2026. Include fire alarm notification modifications for Restrooms 036, 144A, and 250E, and for Sensory Room 015A under Add Alternate 1. The GC shall provide a qualified fire alarm subcontractor for the delegated design, permits, installation, programming, testing, and acceptance. Submit fire alarm shop drawings and calculations to the AHJ as required by Section 28 31 05, 1.4. Final device types, quantities, locations, and circuiting are by the qualified fire alarm designer.

15. Q: The specification requires a factory-authorized technician for pre-install meeting, commissioning, programming and training. For stand-alone occupancy sensors in three restrooms, please confirm this can be waived.

A: Use Section 26 51 13 as revised in Addendum 1 issued 11/10/2026. The former factory-authorized controls commissioning paragraph is not retained; current paragraph 3.3 is Cleaning. A separate factory-authorized technician is not required by this section for the stand-alone restroom controls. Include control setup and functional verification of the sequences shown on the plans, required equipment startup, and Owner operating instructions.

16. Q: E0.02 calls for commercial grade, white devices with nylon plates. The specification calls for Federal Spec / heavy-duty devices with the color bracketed “[brown][ivory][gray]” and stainless steel or plastic plates. Which governs?

ADA Upgrades Davis Academic Building Page 4 of 8

A: Provide white, 20 A, specification-grade switches and receptacles of the configurations indicated. Provide satin-finish stainless steel plates in renovated restrooms. Elsewhere, match adjacent existing wall plates unless specifically indicated otherwise. Apply the installation-environment requirements of Section 26 05 34.

17. Q: E0.02 lists receptacle heights of “18 in. or 6 in.” and “48 in.” without saying where each applies. 26 05 33 lists 20 in. standard. Please clarify.

A: Unless a location is specifically dimensioned otherwise, mount standard receptacles at 20 inches AFF, measured to the top of the device, in accordance with Section 26 05 33, 3.5.D. Use the application-specific heights in that paragraph for utilitarian rooms and counter locations. Architectural elevations and applicable accessible reach limits govern where they differ. The ambiguous 18-inch/6-inch and general 48-inch notes on E0.02 are to be replaced accordingly.

18. Q: The project manual contains two versions of 26 00 10. One applies to Divs

26/27/28 and requires the contractor to pay permanent and temporary service charges. Its submittal table includes a generator, ATS, SPDs, structured cabling and housekeeping pads. Which version governs?

A: Use Section 26 00 10, General Electrical, identified as Addendum 1, issued

11/10/2026, as the replacement for the prior versions of that section. Its submittal table applies to this project. Superseded submittal-table references do not add generator, ATS, SPD, structured-cabling, or housekeeping-pad work to the indicated project scope.

19. Q: 01 50 00 says Owner power is available at no charge. 26 00 10 3.7 says the contractor pays connection and energy charges. Confirm.

A: Provide temporary electrical distribution, connections, extensions, protection, and disconnection required for the Work under Section 26 00 10, 3.5. For temporary-power use charges, refer to Section 01 50 00, 1.4.C.

20. Q: Confirm the ECUH-1 location (assumed Restroom 144A), whether it has an integral disconnect and built-in thermostat, and whether a remote line-voltage thermostat is required (23 03 00 says line-voltage controls are wired by Electrical).

Confirm that C2C Sec 1 has two spaces and the breaker type.

A: ECUH-1 is specified as a recessed ceiling heater in Restroom 144A with an aintegral disconnect and thermostat. Connect to C2C-40/42, as shown on E4.02 and E6.03, using the new 30 A, two-pole breaker scheduled on E6.03. Provide a breaker listed for the existing panel and meeting the indicated interrupting rating.

21. Q: Must panel shutdowns, fire alarm impairments and work in occupied restrooms/corridors be done after hours or on weekends? Are there restricted periods such as finals or events?

A: Maintain electrical and fire alarm service to occupied areas except during approved interruptions. Obtain Owner approval before outages and coordinate affected areas, ADA Upgrades Davis Academic Building Page 5 of 8 temporary measures, duration, and restoration. G0.00 note 12 requires at least 72 hours' coordination; Section 01 10 00, 1.9.B.6 requires at least three days' advance coordination. These notice requirements do not establish permitted daily work hours.

22. Q: Are the existing fixtures in Storage 036, Maintenance 144A, Office 250E and Dress

A 015A fluorescent? Are PCB ballasts expected?

A: Handle and dispose of removed lamps, ballasts, batteries, and other regulated electrical materials under Section 26 00 10, 3.10 and Section 26 05 05, 1.11. Report suspected hazardous materials that are not identified in the Contract Documents before proceeding with the affected work.

23. Q: New horn/strobe and strobe devices are to be connected to the existing system after verifying compatibility, capacity, addressing and programming. Section 26 00 10 references Division 28 (28 31 05), but Division 28 is not included in the Project Manual. New combination fire/smoke dampers at each floor are shown, but no smoke detection or FA control modules are indicated.

Please identify the existing fire alarm panel make/model and the Owner's FA service vendor (if proprietary). Please issue Section 28 31 05, confirm who prepares FA shop drawings and the permit submittal to Pueblo Fire, and confirm whether the fire/smoke dampers require duct smoke detectors and/or FA control relays. Please also confirm the actuator voltage of the combination fire/smoke dampers (no damper specification is included), and that duct detectors, FA relay/monitor modules, control wiring and damper testing with the FA system are by [text cut off in source PDF]

A: Refer to Addendum 1, issued 11/10/2026 for Section 28 31 05 for fire alarm delegated design, shop drawings, AHJ submittal, programming, and testing. Section 23 03 00, 2.6 identifies Mechanical furnishing/setting the combination fire/smoke dampers and Electrical power/control wiring; the GC shall integrate this work with the qualified fire alarm subcontractor under Section 28 31 05. Include testing of affected damper/fire alarm interfaces required by the completed design.

24. Q: P1.01 KN 6: “Waste and vent up to main level. Extend as shown and drop in plumbing wall to below slab. Continue to existing 4" building main.” The location and invert of the main and the extent of underslab work in the Lower Level are not shown.

P0.02 requires waste/vent piping to match the existing material.

Please confirm whether trenching the Lower Level slab is required for the Restroom 036 waste connection, and provide the location and invert of the existing 4" building main. Please confirm the existing waste/vent pipe material (cast iron?).

A: Trenching of lower slab will be required. Original approximate invert elevation was

99.0 with a USGS=4757.5. Original pipe material is cast iron. Information was obtained from Owner’s as-built drawings.

25. Q: The WC-1A description calls for a battery-operated flush valve, and the accessory listed is the Sloan Royal 111 with EBV-500-A.

Please confirm the intended flush valve configuration for WC-1A (battery-operated sensor vs. manual).

ADA Upgrades Davis Academic Building Page 6 of 8

A: WC-1A requires battery-operated sensor flushing. Provide the scheduled Sloan Royal flushometer with EBV-500-A battery-powered sensor operator, configured for the scheduled 1.28 GPF water closet. A manual-only flush valve does not meet the fixture schedule. This combination matches the exiting fixtures installed within the building

26. Q: MD1.02 removes hydronic baseboard and caps the piping in the wall, and M1.03 modifies the 2-1/2" HWS/HWR serving AHU-1. Work starts January 4, during the heating season, in an occupied building. The documents do not say whether the system contains glycol.

Please confirm the allowed heating hot water shutdown windows and durations, whether the system contains glycol (type and concentration), and whether the Contractor or the Owner drains, refills, treats and vents the system.

A: The mechanical work includes removal and capping of the affected hydronic baseboard branch shown on MD1.02. Maintain heating service to occupied areas except during Owner-approved isolation/outage periods. Restore affected system operation after the indicated modifications. Original documents show a 15% glycol percent. Contractor is responsible for drain, refill, and venting.

27. Q: M0.02 states “Provide MERV 8 filters for all new and existing equipment.”

Please confirm that this applies only to equipment within the scope of work, not to all existing air-handling equipment in the building.

A: Confirmed. Not all existing equipment will require new MERV8 Filters. Only equipment that is being touched as part of the scope of work.

28. Q: The maximum overcurrent protection for ECUH-1 (208V, 1-phase, 4 kW, 19.2 FLA) is blank on both M5.01 and E6.04. New loads connect to existing panels C2C, C2A, L3B and L3C.

Please confirm the breaker size for ECUH-1 on C2C-40/42, and confirm that the spare breakers/spaces shown for new loads in panels C2C, C2A, L3B and L3C have been field verified.

A: E6.03 schedules ECUH-1 on C2C-40/42 with a new 30 A, two-pole breaker. E6.04 specifies two #10 copper conductors and a #10 equipment grounding conductor in 3/4-inch conduit. Match the new breaker to the existing panel's listing and indicated interrupting rating. Existing circuits and available positions shall be verified before modification under E0.02 and Section 26 05 05.

29. Q: M1.01 shows HVAC work in Sensory Room 015A (new ductwork and grilles), but unlike the electrical sheet (E4.01, tagged AA1), the mechanical sheet does not mark this work as Add Alternate #1.

Please confirm that the Sensory Room 015A HVAC work on M1.01 is included only in

Add Alternate #1 and not in the base bid.

ADA Upgrades Davis Academic Building Page 7 of 8

A: Confirmed. Clarification is included in Addendum 1, issued 11/10/2026.

30. Q: Please confirm Division 27 and Division 28 will be By Owner.

A: Division 28 fire alarm modifications are included in the construction contract under Section 28 31 05. The GC shall provide the qualified fire alarm subcontractor; Division 26 provides the indicated electrical interfaces, raceways, and boxes. The data-device/rough-in work shown on E4.03 also remains included.

31. Q: Please confirm if there are attic style accessible ceiling spaces between the first and second floor, as well as above the second floor. Electrical subcontractors will need to get into those spaces in order to install any new electrical devices or equipment with the least demolition possible.

A: Do not assume a continuous accessible attic or interstitial space. Use the documented ceiling construction and available access for routing. Maintain access to electrical junction boxes, drivers, and controls. Exposed raceways in finished areas require the approval specified in Section 26 05 33; the new restroom gypsum-board ceilings do not constitute removable ceiling access.

32. Q: For the fire alarm work, what should we carry if the existing panel does not have enough capacity or needs upgrades? We would like everyone bidding the same scope.

A: Section 28 31 05 includes compatible equipment and circuit modifications needed for the renovation, including required modules, circuits, or power supplies. Existing conditions unrelated to the renovation are to be reported to the Owner and do not establish a wholesale system replacement requirement.

33. Q: Will fire alarm testing need to be done after hours? Should we include fire watch or testing of the entire building?

A: Regarding scheduling of Fire Alarm testing: Fire Alarm testing should be scheduled outside of regular business hours.

Regarding scheduling Fire Watch: Fire Watch will only be required if the fire alarm is disabled for a prolonged period of time and/or as required by AHJ.

Regarding extent of fire alarm testing: Include contractor pretesting, acceptance/reacceptance testing of modified components, and testing of affected existing system functions under Section 28 31 05, 2.7. The scope is not limited to testing new devices. The necessary extent of existing-system testing follows the actual modifications, NFPA 72, and AHJ requirements. Maintain the system except during approved impairments and restore affected functions.

SPECIFICATIONS

ADA Upgrades Davis Academic Building Page 8 of 8

34. Reissued “TABLE OF CONTENTS” – Added Section 00 31 26 EXISTING

HAZARDOUS MATERIAL INFORMATION.

35. Added Section 00 31 26 EXISTING HAZARDOUS MATERIAL INFORMATION.

DRAWINGS

END OF ADDENDUM NUMBER 3

Attachments: Advertisement for Bids Exhibits:

AFB-CSBV-App-A, Exhibit A1: Evaluation of Qualifications Form AFB-CSBV-App-A, Exhibit A2: Qualifications and Bid Ranking Matrix SBP-6.12, Information for Bidders SBP-6.13, Bid Form SBP-6.131, Bid Alternates SBP-6.14, Bid Bond State Form SBP-6.18, Direct Labor Burden Calculation Wage Determination SC-6.21, Contractor’s Agreement D/B/B SC-6.23, The General Conditions of the Contractor’s D/B/B Agreement

Revised Project Manual Table of Contents

Added Information Section 00 31 26 Report, All-Phase Environmental Consultants, Inc., dated December 12, 2016

AFB-CSBV-App-A

STATE OF COLORADO

OFFICE OF THE STATE ARCHITECT

STATE BUILDINGS PROGRAM

EXHIBIT A1: EVALUATION OF QUALIFICATIONS

FORM: COMPETITIVE SEALED BEST VALUE BIDDING

Name of Firm: Pueblo Community College (PCC) Name of Project: ADA Upgrades – Davis Academic Building Evaluator No:_______________________________________ Date:______________________________________________

AFB REFERENCE MINIMUM REQUIREMENTS Y ____ N ____

If the minimum requirements (including letter from surety) have not been met, specify the reason(s):

INSTRUCTIONS:

1. Weights are to be assigned prior to evaluation and are to be consistent on all evaluation forms.

2. Use only whole numbers.

3. Rating: 0 = not provided, 1 = Unacceptable, 2 = Poor, 3 = Fair, 4 = Good, 5 = Excellent

4. Total score includes the sum total of all criteria.

5. A passing score (as a percentage of the total points available) is to be established by the state prior to evaluation.

1. TECHNICAL APPROACH TO PROJECT Weight X Rating = Score ◻ Provide a strategic project approach summary discussing how your firm will provide successful Construction Contracting Services for this project. Include specific examples (1-2 page excerpts) of actual products (estimates, progress reports, schedules, constructability reviews, value engineering studies, forms, etc.). x =

◻ Provide a detailed description of how your firm will select qualified sub-contractors and manage them effectively on this project.

Weight

X

Rating

Score

2. EXPERIENCE, PAST PERFORMANCE AND EXPERTISE Weight X Rating = Score ◻ Provide a description of successful prior construction contracts, including performance in the areas of cost, quality control, schedule, compliance with plans and specifications and adherence to applicable laws and regulations as performed by your firm and by your subcontractors. x =

3. PROJECT MANAGEMENT APPROACH Weight X Rating = Score ◻ Provide a description of the composition and management structure of your firm. Identify the firm’s roles and responsibilities and relevant technical expertise and experience of the key management personnel that will be used on this project. Provide a description and separate

NickPalaski Text Box

NickPalaski Text Box

NickPalaski Text Box graphic organizational chart complete with working titles identifying the lines of authority, responsibility and coordination between your firm and your subcontractors and, ◻ Describe the proposed project schedule, quality control program, financial resources, equipment to be used on this project and its current location, and any other information or resources that demonstrates your firm’s competency to perform this work. A large component of this will be your phasing plan and schedule in this occupied building.

Weight

X

Rating

Score

4. STAFFING PLAN Weight X Rating = Score ◻ Provide a detailed staffing plan of key management personnel to be assigned to this project from your firm and your subcontractors and identify the time commitments and all current office locations. x =

5. SAFETY PLAN AND SAFETY RECORD Weight X Rating = Score ◻ Describe your firm’s safety program and provide your firms’ safety record over the last ten years. x =

6. JOB STANDARDS Weight X Rating = Score ◻ Demonstrate on past projects examples how a high quality of workmanship was achieved and industry standards of care were achieved and, X =

◻ Describe the firm’s method of personnel procurement, employment of Colorado workers, work force development and long-term career opportunities of workers and, Weight

X

Rating

Score

◻ Describe the firm’s availability of training programs, including apprenticeships approved by the United States Department of Labor and, Weight

X

Rating

Score

◻ Describe the benefits provided to workers, including healthcare and defined benefit or defined contribution retirement benefits, and whether the firm pays industry-standard wages.

Weight

X

Rating

Score

7. AVAILABILITY AND USE OF DOMESTICALLY PRODUCED GOODS Weight X Rating = Score ◻ Describe how your firm intends to use domestically produced iron, steel, and related manufactured goods in this project.

x

Weight X Rating = Score

Total Score: _________

NickPalaski Text Box

NickPalaski Text Box

NickPalaski Text Box

NickPalaski Text Box

NickPalaski Text Box

NickPalaski Text Box

NickPalaski Text Box

NickPalaski Text Box

NickPalaski Text Box

EXHIBIT A2: QUALIFICATIONS AND BID RANKING

MATRIX: COMPETITIVE SEALED BEST VALUE

BIDDING

INSTRUCTIONS/EXAMPLE:

1. QUALIFICATIONS 40% / BID 60%

2. Insert total score from each evaluator's SUBMITTAL review.

3. Add all evaluators’ total scores and divide by the number of evaluators to determine the average score for each firm’s qualifications.

4. The maximum score for qualifications on the evaluation form is equivalent to 40 points and is equivalent to the maximum points available for qualifications. Therefore, each firm’s score is determined as a percentage of the maximum points available. To score each average qualification score, use the example formula.

5. Assume the highest score is 600.

SCORING OF QUALIFICATIONS

FIRM B: 600 X 40 points = 40 points

FIRM C: 500 X 40 points = 33.33 points

FIRM A: 400 X40 points = 26.66 points

6. Determine score for each firm’s sealed Bid with the lowest fee being equivalent to a maximum score of 60 points. To score each Bid, use the example formula.

7. Assume the lowest Bid was $100,000.

SCORING OF BIDS

FIRM A: $100,000 X 60 points = 60 points $100,000

FIRM B: $100,000 X 60 points = 48 points $125,000

FIRM C: $100,000 X 60 points = 39.99 points $150,000

8. Add the average qualification score to the Bid score to determine cumulative qualifications and fee score.

9. Numerically rank all firms with the highest scoring firm being the most qualified and advantageous to the state.

FIRM

QUALIFICATIONS

AVE.

QUALS

SCORE

BID

& BID

RANK

EVAL

#1

EVA

L #2

EVA

L #3

EVA

L #4

EVA

L #5

EVA

L #6

SBP-6.12

Rev 7/2025

STATE OF COLORADO

OFFICE OF THE STATE ARCHITECT

STATE BUILDINGS PROGRAM

INFORMATION FOR BIDDERS

Institution or Agency:

Project No./Project Name:

1. BID FORM: Bidders are required to use the Bid form attached to the solicitation.

Each bidder is required to bid on all alternates and indicate the time from the date of the Notice to Proceed to Substantial Completion in calendar days. In addition, the bidder is required to indicate the period of time to finally complete the project from Substantial Completion to Final Acceptance, in calendar days.

Bids indicating times for Substantial Completion and Final Acceptance in excess of the number of days indicated in the Advertisement for Bids for completion of the entire Project may be found non-responsive and may be rejected. The bid shall not be modified or conditioned in any manner. Bids and applicable bid security shall be submitted according to the following instructions:

2. INCONSISTENCIES AND OMISSIONS: Bidders may request clarification of any seeming inconsistencies, or matters seeming to require explanation, in the bidding documents at least three (3) business days prior to the time set for the opening of Bids. Decisions of major importance on such matters will be issued in the form of addendum.

3. APPLICABLE LAWS AND REGULATIONS: All work under this Contract shall comply with the provisions of all state and local laws, approved state building codes, ordinances and regulations which might in any manner affect the work to be done or those to be employed in or about the work. Labor for work shall be governed by the provisions of Colorado law which are hereinafter set forth in Articles 27 and 52 of the General Conditions. This includes the requirements for apprenticeship and prevailing wage on Public Projects. The bidder should be aware that reporting of embodied carbon emissions of eligible materials shall be governed by the provisions of Colorado State Law. This includes the requirements for Environmental Product Declarations (EPDs) that meet the maximum acceptable Global Warming Potential (GWP) limits as established by the Office of the State Architect.

4. BID SECURITY: A bid security of not less than 5% of the bid price is required when the price is estimated to be $50,000 or more. The security shall be a bond by a surety company, the equivalent in cash, or otherwise supplied in a form

SBP-6.12

satisfactory for the State. Noncompliance requires the bid to be rejected as nonresponsive.

5. TAXES: The Bid submitted shall exclude all applicable federal excise or manufacturers’ taxes and all state sales and use taxes as hereinafter set forth in Article 9.3 of the GENERAL CONDITIONS.

6. OR EQUAL: The words “OR EQUAL” are applicable to all specifications and drawings relating to materials or equipment specified. Any material or equipment that will fully perform the duties specified, will be considered “equal”, provided the bid submits proof that such material or equipment is of equivalent substance and function and is approved, in writing. Requests for the approval of “or equal” shall be made in writing at least five (5) business days prior to bid opening. During the bidding period, all approvals shall be issued by the Architect/Engineer in the form of addenda at least two (2) business days prior to the bid opening date.

7. ADDENDA: Owner/architect initiated addenda shall not be issued later than two

(2) business days prior to bid opening date. All addenda shall become part of the Contract Documents and receipt must be acknowledged on the Bid form.

8. METHOD OF AWARD - LOWEST RESPONSIBLE BIDDER: If the bidding documents for this project require alternate prices, additive and/or deductible alternates shall be listed on the alternates bid form provided by the Principal Representative.

Bidders should note the Method of Award is applicable to this Bid as stated below.

A. DEDUCTIBLE ALTERNATES: The lowest responsible Bid, taking into account the Colorado resident bidder preference provision of Colorado law, will be determined by, and the contract will be awarded on the base bid combined with deductible alternates, accepted in numerical order as listed in the Bid Alternates Form provided by the Principal Representative. The subtraction of alternates shall result in a sum total within available funds. If this bid exceeds such amount, the right is reserved to reject all bids. An equal number of alternates shall be subtracted from the base bid of each bidder within funds available for purposes of determining the lowest responsible bidder.

B. ADDITIVE ALTERNATES: The lowest responsible Bid, taking into account the Colorado resident bidder preference provision of Colorado law, will be determined by and the contract will be awarded on the base bid combined with additive alternates in numerical order in as listed in the Bid Alternates Form provided by the Principal Representative. The addition of alternates shall result in a sum total within available funds. If this bid exceeds such amount, the right is reserved to reject all bids. An equal number of alternates shall be added to the base bid of each bidder within funds available for purposes of determining the lowest responsible bidder.

C. DEDUCTIBLE AND ADDITIVE ALTERNATES: Additive alternates will not be used if deductible alternates are used and deductible alternates will not be used if additive alternates are used.

9. NOTICE OF CONTRACTOR’S SETTLEMENT – Agencies/institutions must indicate in the initial Solicitation where settlement will be advertised in electronic media.

SBP-6.13

STATE OF COLORADO

OFFICE OF THE STATE ARCHITECT

STATE BUILDINGS PROGRAM

BID FORM

Institution or Agency:

Project No./Project Name:

Bidder Acknowledges Receipt of Addenda Numbers: _______________________________

(See 3a below for the next 3 items)

Bidder Anticipates Services outside the United States or Colorado:* No Yes

Bidder will comply with 80% Colorado Labor on project above $500,000 No Yes

Bidder is a Service-Disabled Veteran Owned Small Business:* No Yes

Base Bid $________________________

Bidder’s Time of Completion

Time Period from Notice to Proceed to Substantial Completion: ____________________________

Time Period from Substantial Completion to Final Acceptance: ____________________________

Total Time of Completion of Entire Project (a + b): _________________________

1. BID: Pursuant to the advertisement by the State of Colorado dated ______________ the undersigned bidder hereby proposes to furnish all the labor and materials and to perform all the work required for the complete and prompt execution of everything described or shown in or reasonably implied from the Bidding Documents, including the Drawings and Specifications, for the work and for the base bid indicated above. Bidders should include all taxes that are applicable.

2. EXAMINATION OF DOCUMENTS AND SITE: The bidder has carefully examined the Bidding Documents, including the Drawings and Specifications, and has examined the site of the Work, so as to make certain of the conditions at the site and to gain a clear understanding of the work to be done.

3. PARTIES INTERESTED IN BID: The bidder hereby certifies that the only persons or parties interested in this Bid are those named herein, and that no other bidder or prospective bidder has given any information concerning this Bid.

a. If the bidder anticipates services under the contract or any subcontracts will be performed outside the United States or Colorado, the bidder shall provide in a written statement which must include, but need not be limited to the type of services that will be performed at a location outside the United States or Colorado and the reason why it is necessary or advantageous to go outside the United States or Colorado to perform such services. (Does not apply to any project that receives federal moneys) *

b. For State Public Works projects per C.R.S. 8-17-101, Colorado labor shall be employed to perform at least 80% of the work. Colorado Labor means any person who is a resident of the state of Colorado at the time of the Public Works project.

Bidders indicating that their bid proposal will not comply with the 80% Colorado Labor requirement are required to submit written justification along with the bid submission. (Does not apply to any project that receives federal moneys) *

c. A Service-Disabled Veteran Owned Small Business (SDVOSB) per C.R.S. 24-103-211, means a business that is incorporated or organized in Colorado or maintains a place of business or has an office in Colorado and is officially registered and verified by the Center for Veteran Enterprise within the U.S. Department of Veteran Affairs.

Attach proof of certification along with the bid submission. *

d. Projects estimated to be $1 million or more that do not receive federal funds are required to comply with the State Apprenticeship Utilization requirements C.R.S.

24-92-115

e. Projects estimated to be $500,000 or more that do not receive federal funds are required to comply with the State Prevailing Wage requirements C.R.S. 24-92-201 through 210.

4. BID GUARANTEE: This Bid is accompanied by the required Bid Guarantee. Per C.R.S. §24- 105-201 If the construction value is $50,000 or greater a Bid Bond and Power of Attorney or Proposal Guaranty is required in an amount not less than 5% of the total Bid. You are authorized to hold said Bid Guarantee for a period of not more than thirty (30) days after the opening of the Bids for the work above indicated, unless the undersigned bidder is awarded the Contract, within said period, in which event the Office of the State Architect, may retain said Bid Guarantee, until the undersigned bidder has executed the required Agreement and furnished the required Performance Bond, Labor and Material Payment Bond, and Insurance Policy.

5. TIME OF COMPLETION: The bidder agrees to achieve Substantial Completion of the Project from the date of the Notice to Proceed within the number of calendar days entered above, and in addition, further agrees that the period between Substantial Completion and Final Acceptance of the Project will not exceed the number of calendar days noted above. If awarded the Work, the bidder agrees to begin performance within ten (10) days from the date of the Notice to Proceed subject to Article 46, Time of Completion and Liquidated Damages of the General Conditions of the Contract, and agrees to prosecute the Work with due diligence to completion. The bidder represents that Article 7D of the Contractor’s Agreement (SC-6.21) has been reviewed to determine the type and amount of any liquidated damages that may be specified for this contract.

6. EXECUTION OF DOCUMENTS: The bidder understands that if this Bid is accepted, bidder must execute the required Agreement and furnish the required Performance Bond, Labor and Material Payment Bond, Insurance Policy and Certificates of Insurance within ten (10) days from the date of the Notice of Award, and that the bidder will be required to sign to acknowledge and accept the Contract Documents, including the Drawings and Specifications.

7. ALTERNATES: Refer to the Information for Bidders (SC-6.12) for Method of Award for Alternates and use State Form SBP-6.13.1 Bid Alternates form to be submitted with this bid form if alternates are requested by the institution/agency in the solicitation documents.

8. Submit wage rates (direct labor costs) for prime contractor and subcontractor as requested by the institution/agency in the solicitation documents.

9. The right is reserved to waive informalities and to reject any and all Bids.

*Does not apply to projects for Institutions of Higher Education that have opted out of the State Procurement Code.

SIGNATURES: If the Bid is being submitted by a Corporation, the Bid shall be signed by an officer, i.e., President or Vice-President. If a sole proprietorship or a partnership is submitting the Bid, the Bid shall so indicate and be properly signed.

Dated this ________ Day of _______________________ , 20______

THE BIDDER:

By ________________________________________ _________________________________________________ Company Name Address

Phone Number ______________________________ _________________________________________________ City, State Zip Code

By ________________________________________ _________________________________________________ Name (Print) and Title Signature

SBP-6.131

Rev 7/2025 R1

STATE OF COLORADO

OFFICE OF THE STATE ARCHITECT

STATE BUILDINGS PROGRAM

BID ALTERNATES

Institution or Agency:

Project No./Project Name:

INSTRUCTIONS:

1. Refer to Item #8 in the Instructions to Bidders (SBP-6.12) for additional alternate information.

2. Additive alternates will not be used if deductible alternates are used. Deductible alternates will not be used if additive alternates are used.

3. Refer to the contract documents for thorough description(s) of the alternates.

4. If alternates are accepted, the base bid will be modified by the amount entered below.

ADDITIVE ALTERNATES

Alt. # Description of Additive Alternate Spec. Section Pricing

A.A.1 $

A.A.2 $

A.A.3 $

A.A.4 $

A.A.5 $

A.A.6 $

A.A.7 $

A.A.8 $

A.A.9 $

A.A.10 $ lanexxTX Line lanexxTX Line

SBP-6.131

Rev 7/2025 R1

DEDUCTIVE ALTERNATES

Alt. # Description of Deductive Alternate Spec. Section Pricing

D.A.1

D.A.2 $

D.A.3 $

D.A.4 $

D.A.5 $

D.A.6 $

D.A.7 $

D.A.8 $

D.A.9 $

D.A.10 $

THE BIDDER

BY_________________________________________________________________

Company Name

BY__________________________________________________________________

Signature Date

SBP-6.14

STATE OF COLORADO

BID BOND

Institution or Agency: Pueblo Community College

Project No./Project Name: ADA Upgrades Davis Academic Building / #2026-049M25

KNOW ALL MEN BY THESE PRESENTS:

WHEREAS, hereinafter called the “PRINCIPAL”, is submitting a PROPOSAL for the above described project, to the STATE OF COLORADO, hereinafter called the “OBLIGEE”.

WHEREAS, the Advertisement for Bids has required as a condition of receiving the Proposals that the Principal submit with the PROPOSAL GUARANTY in an amount not less than five per cent (5%) of the Proposal, which sum it is specifically agreed is to be forfeited as Liquidated Damages in the event that the Principal defaults in his obligation as hereinafter specified, and, in pursuance of which Requirement, this Bid is made, executed and delivered.

NOW THEREFORE, the Principal and a corporation of the State of , duly authorized to transact business in Colorado, as Surety, are held and firmly bound unto the Obligee, in the sum of five per cent (5%) of the Principal’s total bid price, lawful money of the United States for the payment of which sum, well and truly to be made to the Obligee, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.

FURTHER THAT, a condition of the obligation that the Principal shall maintain his Proposal in full force and effect for thirty (30) days after the opening of the proposals for the project, or, if the Principal’s Proposal is accepted, the Principal shall, within the prescribed time, execute the required Agreement, furnish the required Performance Bond, Labor and Material Payment Bond, Insurance Policy, Certificates of Insurance and Certification and Affidavit Regarding Illegal Aliens, then this obligation shall be null and void, otherwise it shall remain in full force and effect, and subject to forfeiture upon demand as Liquidated Damages.

IN WITNESS WHEREOF said Principal and Surety have executed this Bond, this ____ day of ________________________, A.D., 20 .

(Corporate Seal) THE PRINCIPAL

Company Name

ATTEST _________________________________________________

Address

City, State Zip Code

By ________________________________________ _________________________________________________

Name (Print) Signature

Name (Print) and Title

SBP-6.14

If the “Principal” is doing business as a Corporation, the Bid Bond shall be signed by an officer, i.e., President or Vice President. The signature of the officer shall be attested to by the Secretary and properly sealed.

If the “Principal” is an individual or a partnership, the Bid Bond shall so indicate and be properly signed.

(Corporate Seal) THE SURETY

____________________________________________ By_________________________________________________

Secretary Attorney-in-Fact

THIS BOND MUST BE ACCOMPANIED BY POWER OF ATTORNEY, EFFECTIVELY DATED.

FAILURE TO PROVIDE A PROPERLY EXECUTED BID BOND WITH A PROPERLY EXECUTED POWER

OF ATTORNEY WILL RESULT IN THE BIDDER’S PROPOSAL BEING DEEMED NON-RESPONSIVE.

State Form SBP–6.18 Issued 8/2023

STATE BUILDINGS PROGRAM

DIRECT LABOR BURDEN CALCULATION

Institution/Agency: Pueblo Comminuty College (PCC)

Project No./Name: 2026-049M25 / ADA Upgrades - Davis Academic Building

This form is required to be submitted for review prior to execution of a construction agreement.

List items below by the percentage of what makes up the total labor overhead; Items include benefits that a contractor pays to employees on their payroll. Examples include taxes, pension cost, health and dental insurance etc. The Labor Burden percentage must be agreed to by both the contractor and Principal Representative and will be included in the contract as part of Exhibit A and will be used in the calculation of any future Change Order Proposals (SC-6.312) Line 2.

Major sub-contractors defined as electricians, plumbers, mechanical contractors, excavators, millwork, concrete, block layers etc. Please provide one (1) Labor Burden Calculation Sheet per contractor and for each sub-contractor. These labor burdens shall be used in the calculation of any future Change Order Proposals (SC-6.312) Line 10.

State reserves the right to require back-up confirmation of all information included in this calculation.

Contractor/Subcontractor Name:

Percent of

Salary Paid

Payroll Taxes

Pension Costs

Health Insurance

Dental Insurance

Life Insurance

Other (Specify) Description: _________________________

Other (Specify) Description: _________________________

Total Labor Burden Percentage: 0%

"General Decision Number: CO20260027 05/18/2026

State: Colorado

Construction Types: Building

Counties: Colorado Counties of Pueblo

Modification Number Publication Date 0 01/02/2026 1 05/18/2026

ASBE0028-002 07/01/2025

Rates Fringes

ASBESTOS WORKER/HEAT & FROST INSULATOR - MECHANICAL

(DUCT, PIPE & MECHANICAL SYSTEM INSULATION).........$ 36.98 16.82

ELEC0012-005 09/01/2025

Rates Fringes

ELECTRICIAN.........................................$ 35.40 16.06

ENGI0009-017 05/01/2024

Rates Fringes

POWER EQUIPMENT OPERATOR: CRANE (91 TO 140 TONS)....$ 37.34 15.20

POWER EQUIPMENT OPERATOR: CRANE (51 TO 90 TONS).....$ 36.09 15.20

POWER EQUIPMENT OPERATOR: CRANE (50 TONS AND UNDER).$ 35.78 15.20

POWER EQUIPMENT OPERATOR: CRANE (141 TONS AND OVER).$ 39.80 15.20

IRON0024-009 11/01/2024

Rates Fringes

IRONWORKER: ORNAMENTAL..............................$ 39.21 12.50

IRON0024-010 11/01/2024

Rates Fringes

IRONWORKER, STRUCTURAL..............................$ 39.21 12.50

PAIN0079-009 08/01/2024

Rates Fringes

PAINTER (SPRAY).....................................$ 27.41 11.56

PLAS0577-002 05/01/2025

Rates Fringes

CEMENT MASON/CONCRETE FINISHER......................$ 34.73 15.15

PLUM0058-005 07/01/2025

Rates Fringes

6/26/26, 7:14 AM SAM.gov https://sam.gov/wage-determination/CO20260027/1 1/5

PIPEFITTER, EXCLUDES HVAC DUCT AND PIPE

INSTALLATION........................................$ 47.60 18.10

PLUM0058-006 07/01/2025

Rates Fringes

PLUMBER (EXCLUDES HVAC DUCT AND PIPE INSTALLATION)..$ 47.60 18.10

SHEE0009-008 07/01/2025

Rates Fringes

SHEET METAL WORKER (INCLUDES HVAC DUCT AND PIPE

INSTALLATION).......................................$ 43.05 22.65

SUCO2013-013 07/31/2015

Rates Fringes

TRUCK DRIVER: DUMP TRUCK...........................$ 17.34 0.00

ROOFER..............................................$ 16.71 0.00

PAINTER (BRUSH AND ROLLER)..........................$ 17.20 0.00

OPERATOR: GRADER/BLADE.............................$ 21.50 0.00

OPERATOR: BOBCAT/SKID STEER/SKID LOADER............$ 18.58 2.42

OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE...............$ 20.26 8.62

LABORER: PIPELAYER.................................$ 16.96 3.68

LABORER: MASON TENDER - CEMENT/CONCRETE............$ 16.00 0.00

LABORER: MASON TENDER - BRICK......................$ 15.99 0.00

LABORER: COMMON OR GENERAL.........................$ 13.67 1.36

CARPENTER...........................................$ 20.64 0.00

BRICKLAYER..........................................$ 21.96 0.00

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.

Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded. If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. The applicable Executive Order minimum wage rate will be adjusted annually.

Additional information on contractor requirements and worker https://sam.gov/wage-determination/CO20260027/1 2/5 protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (iii)).

The body of each wage determination lists the classifications and wage rates that have been found to be prevailing for the type(s) of construction and geographic area covered by the wage determination. The classifications are listed in alphabetical order under rate identifiers indicating whether the particular rate is a union rate (current union negotiated rate), a survey rate, a weighted union average rate, a state adopted rate, or a supplemental classification rate.

Union Rate Identifiers

A four-letter identifier beginning with characters other than �SU�, �UAVG�, �SA�, or �SC� denotes that a union rate was prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2024. PLUM is an identifier of the union whose collectively bargained rate prevailed in the survey for this classification, which in this example would be Plumbers.

0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. The date, 07/01/2024 in the example, is the effective date of the most current negotiated rate.

Union prevailing wage rates are updated to reflect all changes over time that are reported to WHD in the rates in the collective bargaining agreement (CBA) governing the classification.

Union Average Rate Identifiers

The UAVG identifier indicates that no single rate prevailed for those classifications, but that 100% of the data reported for the classifications reflected union rates. EXAMPLE:

UAVG-OH-0010 01/01/2024. UAVG indicates that the rate is a weighted union average rate. OH indicates the State of Ohio.

The next number, 0010 in the example, is an internal number used in producing the wage determination. The date, 01/01/2024 in the example, indicates the date the wage determination was updated to reflect the most current union average rate.

A UAVG rate will be updated once a year, usually in January, to reflect a weighted average of the current rates in the collective bargaining agreements on which the rate is based.

Survey Rate Identifiers

The �SU� identifier indicates that either a single non-union rate prevailed (as defined in 29 CFR 1.2) for this classification in the survey or that the rate was derived by computing a weighted average rate based on all the rates reported in the survey for that…