PCB27-07 CRA CEI Services RFQ Package.pdf

PDF 808 KB Posted

Attached to
Construction Engineering and Inspection for CRA Front Beach Road Segment 4.1 Design-Build
Solicitation number
PCB27-07-1-2027/CJ
Issued by
Bay County, Florida

About this file

This is a Request for Qualifications (RFQ) issued by the City of Panama City Beach, Florida, for Construction Engineering and Inspection (CEI) Services for the CRA Front Beach Road Segment 4.1 Design-Build project. The project encompasses the roadway reconstruction from the end of Segment 3 west of the Lullwater Drive intersection to west of Hills Road. The City seeks qualified firms to provide comprehensive CEI services including contract administration, construction inspection, materials sampling and testing, documentation, and project coordination throughout the construction phase. A mandatory Pre-Proposal Meeting is scheduled for November 3, 2026, at 1:00 PM at Panama City Beach Council Chambers. Written proposals are due by November 30, 2026, at 9:00 AM, with public opening immediately following. The Evaluation Committee will conduct initial review and rankings on December 9, 2026, with potential interviews scheduled for December 2026. The estimated contract execution and final award is targeted for January 28, 2027. The contract term extends for the duration of the Design-Build construction project, anticipated to begin upon City notification to proceed, with up to 30 calendar days allowed for preliminary administrative services prior to contractor notice to proceed and 30 calendar days for demobilization following final acceptance.

Pricing terms and compensation methodology will be negotiated with the selected firm following City Council approval of the top-ranked proposer; the City will be the sole arbiter of the compensation method used. The RFQ specifies that firms must be prequalified by the Florida Department of Transportation (FDOT) in Work Class 10.1, Roadway Construction Engineering Inspection, at the time of proposal submission. No set-asides are identified in the solicitation. The selected firm must provide proof of insurance meeting the City's Risk Management Requirements prior to contract award. The consultant is responsible for furnishing all personnel, equipment, vehicles, technology infrastructure, and services necessary to complete the scope of work, with detailed personnel qualification requirements established for multiple positions including Senior Project Engineer, Project Administrator, inspectors, surveyors, and specialized roles such as Resident Compliance Specialist and Geotechnical Engineers. The scope includes extensive documentation and reporting requirements, quality assurance reviews, and compliance monitoring with FDOT procedures and City standards. No incumbent is identified, and federal funding compliance requirements, including Davis-Bacon Act and federal labor standards, may apply if the project receives federal funding.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PCB27-07 - RFQ – CEI SERVICES FOR CRA FRONT BEACH ROAD

SEGMENT 4.1 DESIGN BUILD

REQUEST FOR QUALIFICATIONS

PCB27-07 RFQ –

CONSTRUCTION ENGINEERING AND INSPECTION

FOR CRA FRONT BEACH ROAD SEGMENT 4.1 DESIGN BUILD

CITY OF PANAMA CITY BEACH

17007 PANAMA CITY BEACH PARKWAY

PANAMA CITY BEACH, FLORIDA 32413

Date of Issue: October 27, 2026 Responses Due: November 30, 2026

TABLE OF CONTENTS

BIDDING AND CONTRACT DOCUMENT SECTIONS SECTION PAGES

Notice to Proposers 1 – 3

Scope of Services 1 – 24

Submittal Requirements 1 – 3

Evaluation Process 1 – 2

REQUIRED FORMS SECTION PAGES

Affidavit regarding Coercion for Labor and Compliance with Foreign Countries of Concern 1

Proposers Certification 1

Litigation Disclosure Form 1 – 4

W9 1 – 6

Insurance Requirements 1 – 4

REFERENCE DOCUMENTS

Standard Terms and Conditions 1 – 15

Notice to Proposers Page 1 of 3

NOTICE TO PROPOSERS

The City of Panama City Beach (“the City”), under the provisions of Section 287.055, Florida Statutes (the Consultant’s Competitive Negotiation Act), hereby gives notice that a Request for Statements of Qualifications from qualified firms are being accepted for Construction Engineering and Inspection (CEI) Services for the CRA Front Beach Road Segment 4.1 Design Build project from the end of the Segment 3 reconstruction west of Lullwater Drive intersection to west of Hills Road.

A mandatory Pre-Proposal Meeting will be held on the date and at the time identified in the Solicitation Timeline. The meeting will be held in the Panama City Beach Council Chambers, 17007 Panama City Beach Parkway, Panama City Beach, Florida 32413. Virtual attendance is available. Interested parties must contact the Purchasing Manager at least twenty-four (24) hours in advance to request virtual meeting access.

Proposals will be received by the Purchasing Manager at 17007 Panama City Beach Parkway, Panama City Beach, Florida 32413 until the date and time specified in the Solicitation Timeline.

Paper and electronic submittals will be publicly opened and receipt acknowledged immediately thereafter. The qualifications and other information should be submitted in strict compliance with the directives provided in the RFQ. The City is under no obligation, either express or implied, to reimburse responding firms for any expenses associated with preparation and submittal of the RFQ in response to this request.

Solicitation documents will be available beginning on the date identified in the Solicitation Timeline and can be downloaded online at www.demandstar.com and on the City’s website at www.pcbfl.gov/bids.aspx.

Electronic Bids will only be accepted when submitted through DemandStar’s bid portal. Emailed submissions will not be accepted.

Alternatively, one original, along with a USB flash drive containing the complete proposal and required documents is to be delivered to the City Hall Office at the address below. Any sealed bid submitted on paper must identify and clearly mark the bid # PCB27-07 CEI FOR CRA FRONT BEACH ROAD SEGMENT 4.1 DESIGN BUILD on the package. Receipt of a bid by any Panama City Beach Office, or personnel other than the City Hall’s front desk does not constitute “receipt” as required by this solicitation. The City Hall’s time stamp shall be conclusive as to the timeliness of receipt.

All paper submittals shall be sealed and delivered or mailed to:

City of Panama City Beach City Hall ATTN: Purchasing Manager

17007 Panama City Beach Parkway Panama City Beach, FL 32413

The City reserves the right to accept or reject any or all Submittals (in whole or in part) with or without cause and to waive technicalities, irregularities, or informalities, to obtain new Submittals, or to postpone the opening of Submittals, or if unable to negotiate a satisfactory contract, to terminate all negotiations under the RFQ and proceed by whatever means it may elect.

Embedded links within proposals are not permitted.

The City’s Standard Terms and Conditions are included with this solicitation and provisions applicable to the bidding process and selection to apply to this solicitation. However, a satisfactory agreement will be negotiated with the winning Firm(s) after ranking and recommendation to the http://www.demandstar.com/ https://www.pcbfl.gov/bids.aspx

Notice to Proposers Page 2 of 3

City Council and therefore any provisions regarding the substantive performance and/or contract terms are subject to future negotiation between the City and winning Firm(s).

The City shall enter into a Professional Services Agreement deemed to be in the best interest of the City. Each RFQ shall be valid for a period of ninety (90) days after opening. The City shall retain all RFQs and may use any ideas in an RFQ regardless of whether that Firm is selected.

PROPOSERS shall submit all questions, if any, in writing no later than the date and time specified in the Solicitation Timeline. If necessary, responses to questions will be issued in the form of Addenda to the Contract Documents and posted on the City's website. It is the sole responsibility of each Proposer to determine whether any Addenda has been issued and to acknowledge receipt of all Addenda in its Proposal.

All questions regarding the solicitation documents shall be directed to the City of Panama City Beach Purchasing Manager: Carrie Jagers via email: purchasing@pcbfl.gov. Contact with any other City official or City employees for the purpose of inquiries regarding this solicitation or the meaning or interpretation of these specifications shall be grounds for disqualification.

SOLICITATION TIMELINE:

Listed below are specific and estimated dates and times of actions related to this RFQ. The milestones with specific dates must be completed as indicated unless otherwise changed. If it is necessary to change any of the specific dates and times, an addendum to this RFQ will be issued.

EVENT TIME (LOCAL) DATE

Solicitation Release Date XXX October 27, 2026

Mandatory Pre-Proposal Meeting 1:00 PM November 3, 2026

Questions from proposers to warrant a response/addendum 12:00 PM November 18, 2026

Final Addendum Release By COB November 20, 2026

Proposals – Deadline and Opening 9:00 AM November 30, 2026

Review Committee Initial Review and Rankings – Public Meeting 9:00 AM December 9, 2026

Potential Interviews with Select Firms and Final Ranking, if applicable – Public Meeting

TBD December 2026

Estimated Ranking Recommendation to City Council and Approval to Commence Contract Negotiations

TBD January 14, 2027

Contract Negotiations TBD January 2027

Estimated Execution of Contract and Final Award TBD January 28, 2027

The City of Panama City Beach adheres to the Americans with Disabilities Act and will make reasonable accommodations for access to the bid opening by an individual with a disability upon notice 48 hours prior to the meeting. Please call City Clerk, Mindy Lawyer, at 850-233-5100 or email at CityClerk@pcbfl.gov to make a request.

In the event of any conflict between this RFQ and the City’s Standard Terms and Conditions, this RFQ shall prevail.

mailto:purchasing@pcbfl.gov mailto:CityClerk@pcbfl.gov

Notice to Proposers Page 3 of 3

For more information on the City’s purchasing policies and procedures, or to review the City’s Procurement Manual, please visit the City’s website at www.pcbfl.gov.

The City utilizes NextRequest for the processing of Public Records Requests. To make a public record request for prior bid documents, bid tabulations, contracts, etc., please visit https://pcbfl.nextrequest.com/ and click on Make Request. Complete the online form and choose the Bids/Procurement Department.

The City of Panama City Beach is an Equal Opportunity Employer.

http://www.pcbfl.gov/ https://pcbfl.nextrequest.com/

Scope of Services Page 1 of 24

SCOPE OF SERVICES

1.0 PURPOSE:

This scope of services describes and defines the Construction Engineering and Inspection (CEI) services which are required for contract administration, inspection, and materials sampling and testing for the construction projects listed below.

2.0 DEFINITIONS:

a) Agreement: The Professional Services Agreement between the City and the Consultant setting forth the obligations of the parties thereto, including but not limited to, the performance of the work, furnishing of services, and the basis of payment.

b) Contractor: The individual, firm, or company contracting with the City for performance of work or furnishing of materials.

c) Construction Contract: The written agreement between the City and the Contractor setting forth the obligations of the parties thereto, including, but not limited to, the performance of the work, furnishing of labor and materials, and the basis of payment.

d) Construction Project Manager: The city employee and/or city designated consultant assigned to manage the Construction Engineering and Inspection Contract and represent the City during the performance of the services covered under this Agreement.

e) Construction Training/Qualification Program (CTQP): The FDOT (Department) program for training and qualifying technicians in Aggregates, Asphalt, Concrete, Earthwork, and Final Estimates Administration. Program information is available at CTQP website.

f) Consultant: The Consulting firm under contract to the City for administration of CEI services.

g) CEI Project Administrator/Project Engineer: The employee assigned by the Consultant to be in charge of providing Construction Contract administration services for one (1) or more Construction Projects.

h) CEI Resident Compliance Specialist: The employee assigned by the Consultant to oversee project specific compliance functions.

i) CEI Senior Project Engineer: The Engineer assigned by the Consultant to be in charge of providing Construction Contract administration for one (1) or more Construction Projects.

This person may supervise other Consultant employees and act as the lead Engineer for the Consultant.

3.0 SCOPE:

Consultant shall provide services as defined in this Scope of Services, the referenced City/FDOT manuals, and procedures. The projects for which the services are required are:

CRA Front Beach Road Segment 4.1 Design Build from the end of the reconstruction of Segment 3 west of Lullwater Drive Intersection to west of Hills Road Intersection.

Consultant shall serve as the City’s representative on the project and faithfully represent the City’s interest in all matters, with special emphasis given to issues involving public safety, quality, timely completion of the work, and financial responsibility. Consultant shall exercise independent professional judgment in performing obligations and responsibilities under this Agreement.

Services provided by the Consultant shall comply with City and FDOT manuals, procedures, and memorandums found at the FDOT State Construction Office’s website. On a single Construction Contract, it is a conflict of interest for the Consultant to receive compensation from both the City and the Contractor either directly or indirectly. Other projects developing within the geographical area of the City may be added at the City’s discretion. The Consultant must perform to the satisfaction of the City’s representatives for consideration of additional CEI services.

Scope of Services Page 2 of 24

4.0 LENGTH OF SERVICE:

The services for each Construction Contract shall begin upon written notification to proceed by the City. In no event shall services begin before issuance of a valid notice to proceed by the City.

Consultant should track the execution of the Construction Contract such that the Consultant is ready for authorization to begin work. While no personnel shall be assigned until written notification by the City has been issued, the Consultant shall be ready to assign personnel within 14 calendar days of notification to the Contractor. For the duration of the project, Consultant shall coordinate closely with the City and Contractor to minimize rescheduling of Consultant activities due to construction delays or changes in scheduling of Contractor activities. For estimating purposes, the Consultant will be allowed an accumulation of 30 calendar days to perform preliminary administrative services prior to the issuance of the Contractor's notice to proceed on the first project and 30 calendar days to demobilize after Final Acceptance of the last Construction Contract. The anticipated letting schedules and construction times for the project are subject to the Design-Build obtaining confirmation from the City that the plans are “Released for Construction”.

5.0 ITEMS TO BE FURNISHED BY THE CITY TO THE CONSULTANT:

The City, on an as-needed basis, will furnish the following Construction Contract documents for each project. These documents may be provided in either paper or electronic format:

a) Construction Plans

b) Specifications Package

c) Computer Aided Drafting and Design (CADD) Files

d) Copy of the Executed Construction Contract

e) Utility Agency’s Approved Material List (if applicable)

6.0 ITEMS FURNISHED BY THE CONSULTANT:

The following items shall be furnished by the Consultant at a sufficient level to complete performance of the Agreement. The Consultant shall retain responsibility for risk of loss or damage to equipment or other items supplied during performance of this Agreement. All equipment, supplies or other items necessary to the compete the services shall be maintained in good condition and remain operational at all times.

6.1 City Documents:

All applicable City documents referenced herein shall be a condition of this Agreement. The City will utilize documents, directives, procedures, and standard forms that are available through the FDOT Website.

6.2 Office Automation:

a) Provide all software and hardware necessary to efficiently and effectively carry out the responsibilities under this Agreement.

b) Provide each inspection staff with a laptop computer (or tablet). All computer coding shall be input by Consultant personnel using equipment furnished by them.

c) All informational, contractual and other business required for this project will be through a system of paperless electronic means. When the specifications require a written submission of documentation, such documents must be submitted electronically.

d) All documents requiring a signature must be executed electronically by both parties in accordance with Chapter 668, Florida Statutes, which have the same force and effect as a written signature.

Scope of Services Page 3 of 24

e) Ownership and possession of computer equipment and related software provided by the Consultant shall remain with the Consultant at all times.

6.3 Vehicles:

Provide vehicles with appropriate safety equipment to effectively carry out the requirements of the Agreement. Vehicles shall have the Consultant’s name and phone number visibly displayed on both sides of the vehicle.

6.4 Field Equipment:

a) Supply survey, inspection, and testing equipment essential to perform services under this Agreement; such equipment includes non-consumable and non-expendable items.

b) Hard hats and safety vests shall have the Consultant’s name visibly displayed.

c) Equipment described herein and expendable materials under this Agreement will remain the property of the Consultant and shall be removed at completion of the work.

d) Handling of nuclear density gauges shall be in compliance with license requirements.

6.5 Licensing for Equipment Operations:

Obtain proper licenses for equipment and personnel operating equipment when licenses are required. The license and supporting documents shall be available for verification by the City, upon request. Radioactive Materials License for use of Surface Moisture Density Gauges shall be obtained through the State of Florida Department of Health.

7.0 LIAISON RESPONSIBILITY OF THE CONSULTANT:

For the duration of the Agreement, Consultant shall keep the City’s Construction Project Manager informed of all significant activities, decisions, correspondence, reports, and other communications related to its responsibilities under this Agreement. Consultant shall facilitate communications between all parties (i.e. architectural, mechanical, materials, landscaping, local agencies, etc.), ensuring responses and resolutions are provided in a timely manner, and maintain accurate records to document the communication process. Consultant shall inform the designated City project personnel of any design defects reported by the Contractor or observed by the Consultant. Consultant shall submit all administrative items relating to Invoice Approval, Personnel Approval, Time Extensions, and Supplemental Amendments to the Construction Project Manager for review and approval.

8.0 PERFORMANCE OF THE CONSULTANT:

During the term of this Agreement and all Supplemental Amendments thereof, the City will review various phases of the Consultant’s operations, such as construction inspection, materials sampling and testing, and administrative activities, to determine compliance with the Agreement.

Consultant shall cooperate and assist City representatives in conducting the reviews. If deficiencies are indicated, Consultant shall immediately implement remedial action, and document the City’s recommendations and the Consultant’s responses/actions. No additional compensation shall be allowed for remedial action taken by the Consultant to correct deficiencies.

Remedial actions and required response times may include, but are not limited to, the following:

a) Further subdivide assigned inspection responsibilities, reassign inspection personnel, or assign additional inspection personnel, within seven (7) calendar days of notification.

b) Immediately replace personnel whose performance has been determined by the Consultant and/or the City to be inadequate.

c) Immediately increase the frequency of monitoring and inspection activities in phases of work that are the Consultant's responsibility.

Scope of Services Page 4 of 24

d) Increase the scope and frequency of training of the Consultant personnel.

9.0 REQUIREMENTS OF THE CONSULTANT:

9.1 General:

a) Administer, monitor, and inspect the Construction Contract such that the project is constructed in conformance with the plans, specifications, and special provisions for the Construction Contract.

b) Observe the Contractor's work to determine the progress and quality of work. Identify discrepancies, report significant discrepancies to the City, and direct the Contractor to correct such observed discrepancies.

c) Review, evaluate, and negotiate Supplemental Agreements within the thresholds established in the CPAM. The Consultant shall seek input from the Construction Project Manager regarding all Supplemental Agreement requests and shall verify that all recommended Supplemental Agreements are consistent with applicable law and the requirements of the Contract Documents.

d) For all Supplemental Agreements, prepare and submit a written recommendation to the City for review and consideration. The Consultant shall have no authority to approve Supplemental Agreements, authorize additional contract time, authorize additional compensation, obligate City funds, modify the Construction Contract, or otherwise commit the City to any expenditure. The Consultant shall not direct the Contractor to perform work that would increase the Contract Price or Contract Time without prior written authorization from the City. All Supplemental Agreements shall be subject to review and approval by the City in accordance with the City's delegated authority, purchasing policies, and applicable approval requirements, including approval by the City Manager and/or City Council, as applicable.

e) Consult with the Construction Project Manager as necessary and promptly elevate all issues exceeding delegated authority to the Construction Project Manager for City direction and action.

f) Inform the designated City project personnel of any significant omissions, substitutions, defects, and deficiencies noted in the Contractor's work and the corrective action that has been directed to be performed by the Contractor.

9.2 Independent Engineering Judgment:

Consultant shall exercise independent engineering judgment in pursuit of the project. Personnel are expected to gather information from project inspection personnel and make informed, technically sound decisions to promote timely, successful completion of the project without sacrificing quality. For technical issues which require coordination with the City, all levels of CEI Senior Project Engineer shall be expected to present options for consideration along with a preferred option. Engineering experience and expertise are considerations for the selection of Consultant staff. It is the City’s expectation that this experience and expertise will be employed by Consultant staff to make sound engineering judgments and recommendations throughout the project.

9.3 Public Safety:

Public safety is paramount throughout the project. If the Consultant determines that any activity of the Contractor poses an imminent hazard to the public, the Consultant shall direct the Contractor to immediately cease the activity and to close the affected lanes of traffic until the deficiency is addressed. Consultant shall provide prompt notice to the designated City

Scope of Services Page 5 of 24 representative and documentation of the condition, action taken, and conditions for resuming work.

9.4 Timely Resolution:

Consultant shall prioritize the City’s goal of the timely and successful completion of the project, and actively work to develop solutions to issues encountered on the project in an expedient manner to ensure that issues do not persist for long periods without resolution.

9.5 Survey Control:

a) Check or establish the survey control baseline(s) along with sufficient baseline control points and bench marks at appropriate intervals along the project in order to: (1) make and record measurements necessary to calculate and document quantities for pay items,

(2) make and record pre-construction and final cross section surveys of the project site in those areas where earthwork (i.e., embankment, excavation, subsoil excavation, etc.) is part of the construction project, and (3) perform incidental engineering surveys.

b) Provide survey data in LandXML format.

c) Any questions or requests for “Waiver of Survey” should be directed to the City

Construction Project Manager.

9.6 On-site Inspection:

a) Monitor the Contractor's on-site construction activities and inspect materials in accordance with the Contract Documents for the Construction Contract to determine that the projects are constructed in reasonable conformity with such documents. Maintain detailed accurate records of the Contractor's daily operations and of significant events that affect the work.

Monitor off-site activities and fabrication unless otherwise stipulated by this Agreement.

b) Monitor and inspect Contractor’s Temporary Traffic Control Plan and review modifications to the Temporary Traffic Control Plan, including Alternate Traffic Control Plan, in accordance with the FDOT’s procedures. Consultant employees performing such services shall be qualified in accordance with the FDOT’s procedures.

9.7 Sampling and Testing:

a) Perform sampling and testing of component materials and completed work in accordance with the Contract Documents. The minimum sampling frequencies set out in the FDOT’s Materials Sampling, Testing and Reporting Guide shall be met. In complying with the aforementioned guide, provide daily surveillance of the Contractor's Quality Control activities and perform the sampling and testing of materials and completed work items for verification and acceptance.

b) Perform inspection and sampling of materials and components at locations remote from the project site.

c) Determine the acceptability of all materials and completed work items on the basis of either test results or verification of a certification, certified mill analysis, DOT label, DOT stamp, etc.

d) Prepare and submit sampling and testing documentation reports to the City the same week that the construction work is performed.

e) Transport samples to be tested to an FDOT approved laboratory within 24 hours after the initial cure. The Project Administrator will provide the VT Laboratory ID number for sample delivery. Transmittal card must accompany the sample. A chain of custody (if provided by the VT firm) must be signed by the Consultant Construction Engineering and Inspection (CCEI) and VT representatives for sample tracking purposes and maintained by both the CCEI and VT firms.

Scope of Services Page 6 of 24

The City will monitor the effectiveness of the Consultant’s testing procedures through observations. Sampling, testing and laboratory methods shall comply with the Contract Documents.

9.8 Engineering Services:

Consultant shall coordinate the Construction Contract administration activities of all parties other than the Contractor involved in completing the construction project. Notwithstanding the above, the Consultant is not liable to the City for failure of such parties to follow written direction issued by the Consultant. Services include maintaining the required level of surveillance of Contractor activities and interpreting the Contract Documents for the Construction Contract. Consultant shall maintain complete, accurate records of all activities and events relating to the project and properly document all project changes. The following services shall be performed:

a) Attend a pre-service meeting for the Agreement in accordance with CPAM. Provide appropriate staff to attend and participate in the pre-service meeting.

b) Schedule and coordinate a meeting with the City prior to the Pre-construction conference and another meeting prior to project Final Acceptance. The purpose of these meetings is to discuss the required documentation, including as-builts, necessary for permit(s) compliance.

c) Coordinate with the City and applicable funding agencies regarding grant-funded project requirements. Assist the City in maintaining compliance with applicable grant agreements, funding conditions, reimbursement requests, reporting requirements, audit requests, and recordkeeping obligations. Maintain project records necessary to support grant reimbursement and audit activities. Assist the City with project closeout activities, including final acceptance documentation, as-built records, permit closeout documentation, warranties, certifications, operation and maintenance manuals, and funding agency grant closeout requirements.

d) Verify that the Contractor is conducting inspections, preparing reports and monitoring all storm water pollution prevention measures associated with the project. For each project that requires the use of the NPDES General Permit, provide at least one (1) inspector who has successfully completed the "Florida Stormwater, Erosion, and Sedimentation Control Training and Certification Program for Inspectors and Contractors.”. The Consultant’s inspector shall be familiar with the requirements set forth in the FEDERAL REGISTER, Vol. 57, No. 187, Friday, September 5, 1992, pages 4412 to 4435 "Final NPDES General Permits for Storm Water Discharges from Construction Sites" and the FDOT’s guidelines.

e) Analyze the Contractor’s schedule(s) (i.e. baseline(s), revised baseline(s), updates, as-built, etc.) for compliance with the Contract Documents. Elements including, but not limited to, completeness, logic, durations, activity, flow, milestone dates, concurrency, resource allotment, and delays will be reviewed. Verify the schedule conforms with the construction phasing and MOT sequences, including all contract modifications. Provide a written review of the schedule identifying significant omissions, improbable or unreasonable activity durations, errors in logic, and any other concerns as detailed in

CPAM.

f) Analyze problems that arise on a project and proposals submitted by the Contractor, work to resolve such issues, and process the necessary documentation.

g) Monitor, inspect, and document utility relocation self-performed by the Contractor for conformance with Utility Agency’s Standards and the Utility Agency’s Approved Materials List. Document utility construction progress to be performed by Utility Agencies. Facilitate coordination and communication between Utility Agency’s representatives, City’s staff and

Scope of Services Page 7 of 24

Contractors executing the work. Identify potential utility conflicts and assist in the resolution of utility issues.

h) Identify, review, and track progress of Utility Work by Highway Contractor Agreements (UWHCA), Joint Project Agreements, and/or other City and utility agreements. Address work progress, track reimbursement activities, and address betterment and salvage determination. Prepare all necessary documentation to support reimbursement activities and betterment and salvage determination.

i) Produce reports, verify quantity calculations, and field measure for payment purposes as needed to prevent delays in Contractor operations and to facilitate prompt processing of such information in order for the City to make timely payment to the Contractor.

j) Monitor each Contractor’s and Subcontractor’s compliance with specifications and special provisions of the Construction Contract regarding payment of predetermined wage rates in accordance with standard procedures.

k) If the Project receives federal funding that requires compliance with the Davis-Bacon Act and associated federal labor standards, provide a Resident Compliance Specialist (RCS) for surveillance of the Contractor's compliance with Construction Contract requirements.

The Resident Compliance Specialist is responsible for reviewing, monitoring, evaluating, and acting upon documentation required for Construction Contract compliance, and maintaining the appropriate files thereof. Typical areas of compliance responsibility include EEO Affirmative Actions for the prime contractor and subcontractor, DBE Affirmative Action, Contractor Formal Training, Payroll, and Subcontracts. The Resident Compliance Specialist must keep all related documents and correspondence accurate and up to date, attend all compliance reviews and furnish the complete project files for review, and assist the District Contract Compliance Manager as requested.

l) The City will provide Community Outreach Services. The Consultant will need to be proactive in keeping the City’s Public Information Officer (PIO) aware of the status and traffic impacts of the referenced project. The Consultant will provide the City PIO with information, graphics, and necessary documentation to disseminate information to the public, elected officials, and the media of any upcoming events, which will affect traffic flow. Coordinate with the City’s PIO and assist with all publications (letters, flyers, brochures, and news releases) required for this contract. Provide timely, professional responses to project inquiries including emails, telephone calls, etc. Attend public information meetings, open houses, community meetings as directed by the City’s representatives.

m) Prepare and submit to the Construction Project Manager a monthly status report, in a format to be approved by the City.

n) Provide a digital video recording of the pre-construction conditions throughout the project limits. Provide a digital photo log or video of project activities, with heavy emphasis on potential claim items/issues and on areas of real/potential public controversy.

o) Provide a digital camera for photographic documentation of pre-construction state and of noteworthy incidents or events during construction. These photographs will be filed and maintained on the Consultant’s computer using a digital photo management system.

Photographs shall be taken the day prior to the start of construction and continue as needed throughout the project. Photographs shall be taken the days of Conditional, Partial and Final Acceptance. Provide visual documentation of the Project through the periodic collection of a set of panoramic digital photographs at predetermined stations throughout the project. Photographic locations should be located at intervals such that the digital photographs collectively portray the majority of the visible surfaces on the Project. The digital photographs should be taken with a frequency designed to reveal changes in the progress of the Project, which can be compared to other project data including daily

Scope of Services Page 8 of 24 reports of construction and scheduling updates. Photographic data files comprising each digital photograph are to be supplied together with an HTML (web page) based access and display system for viewing the photographs. Original photographic data files are to be supplied for archival purposes and comprise photographic data identical in form and content to that produced by the digital camera used to capture the image. Working photographic data files are to be supplied for everyday reference purposes and comprise copies of each original photographic data file, which have been processed to a reduced pixel and color resolution (size and clarity) for electronic distribution. The access and display system should be comprised of a series of HTML files (web pages) which allow a user to view each photographic data file individually, and in a sequence which simulates the visual experience of a viewer moving through the actual Project from one photographic station to the next. The original photographic data files, working photographic data files and access and display system are to be distributed on digital media. The working photographic data files and the access and display system should also be maintained on a server accessible via the Internet.

p) Review design-build plan submittals at each design phase, including but not limited to preliminary, 60%, 90%, final, and Released for Construction (RFC) documents, to evaluate constructability, sequencing, maintenance of traffic, utility coordination, drainage, permitting, public access, and overall compliance with the Contract Documents. The CEI Consultant shall identify potential conflicts, omissions, ambiguities, field constructability concerns, coordination issues, and conditions that may result in delays, change orders, claims, rework, or increased construction costs. The CEI Consultant shall provide written review comments and recommendations to the City and Design-Build Firm and shall participate in review meetings, workshops, and coordination meetings as requested by the City. The CEI Consultant's review shall be advisory in nature and shall not relieve the Design-Build Firm, Engineer of Record, or Contractor of their responsibility for design accuracy, completeness, or compliance with the Contract Documents

9.9 Geotechnical Engineering:

The prime Consultant may engage the services of a geotechnical subconsultant to perform some of the services indicated in this section. However, the prime Consultant will be responsible to the City for the satisfactory performance and timeliness of these services. The following is required:

a) Be familiar with the existing site conditions and the Contract Documents.

b) Observe and record the progress and quality of foundation work to determine that the foundations are constructed at the correct locations and elevations, identify discrepancies, and direct the Contractor to correct such observed discrepancies.

c) Attend the Preconstruction Conference and/or special geotechnical meeting for the Construction Contract. All services under this section will be performed in accordance with FDOT Specification Section 455.

d) Inspect and verify that the Contractor has performed the foundation work in accordance with applicable FDOT Specification Section 455 and other Contract Documents.

e) Provide qualified Geotechnical Engineers and CTQP qualified inspectors in Drilled Shaft inspection, relevant to the foundation type(s) required in the plans.

f) Schedule and coordinate meetings and facilitate communications between the Contractor and any Specialty Contractors, the CEI, and the City as needed.

g) Observe and verify that all work is performed in accordance with the Contract Documents.

h) Assure that any specialty work is completed as necessary to accomplish its intent.

Scope of Services Page 9 of 24

Mandatory geotechnical engineering services include:

1) Drilled Shafts:

• Review and accept or reject the Contractor’s Drilled Shaft Installation Plan for conformance with the Contract Documents of the project and the Release for Construction (RFC) plans. Incorporate the comments and recommendations provided by the City Construction Project Manager. Ensure that comments and rejection or acceptance letters are sent to the Contractor within the deadlines required by the Contract Documents.

• Schedule and coordinate a pre-drilled shaft installation meeting to go over the drilled shaft installation procedures. Make sure the Contractor’s field superintendent(s), CEI field representative(s), CTQP drilled shaft inspector(s) of the Geotechnical Foundation Designer of Record (GFDOR), and the City are invited. Prepare and distribute meeting minutes to the attendees within three (3) working days after the meeting.

• Observe construction of test holes, load test shafts, and production shafts. This includes review or verification testing of drilling slurry, core drilling and core logs, pilot hole drilling, and other procedures as required. Ensure that they are constructed in accordance with the RFC plans, applicable specifications, and other Contract Documents. Report to the city any problems and construction quality issues observed during the installation of drilled shafts within one (1) working day of completion of drilled shaft construction.

• Forward to the city the recommended production drilled shaft tip elevations and minimum rock socket lengths. Coordinate with the city to make sure the review is performed within the deadlines required by the Contract Documents.

• Review the recommended production drilled shaft tip elevations and minimum rock socket lengths and provide comments to the city office for its concurrence.

• Observe and ensure that the shaft bottom is at the required elevation and is properly inspected for cleanliness using manual soundings or shaft inspection device as required in the contract documents.

• Review drilled shaft excavation logs and concrete placement records to identify possible shaft integrity problems and possible causes.

• Verify the requirements on the RFC plans, applicable specifications, and other Contract Documents are followed throughout drilled shaft construction.

• Forward all drilled shaft inspection forms to the city without delay to allow selection of CSL testing.

• Observe the performance of any load tests and verify that the details are implemented as planned.

• Verify the quality control processes of the Drilled Shaft Installation Plans are followed during construction.

• Evaluate problems encountered during construction and coordinate with the City and the Contractor to resolve such problems, including possible verification testing and withdrawing the Design-Build (DB) Firm’s Drilled Shaft Installation Plan.

• Forward the Foundation Certification Packages to the City. Ensure these submittals are forwarded to the City timely so that their review can be performed within the deadlines required by the Contract Documents.

• Review certification packages submitted by the Contractor and coordinate with the City to submit rejection comments or verification testing requests on the certification packages to the DB Firm. Coordinate with the City to select appropriate shaft(s) for verification testing.

Ensure the deadlines required by the Contract Documents for review are met

Scope of Services Page 10 of 24

• Coordinate verification activities. Make sure the deadlines required by the Contract Documents are met.

• Perform verification testing (including integrity testing) following the process and time frame outlined in the Contract Documents.

• Ensure that deficiencies found by the verification program are resolved.

2) Spread Footings:

• Observe construction of spread footing foundations and verify that they are founded at the required elevation and on the proper soil/rock material.

• Verify that the requirements of the RFC plans, applicable specifications, and other Contract Documents are followed throughout the spread footing construction.

• Forward certification packages submitted by the Contractor to city.

• Evaluate problems encountered during construction and coordinate with the city and the

Contractor to resolve such problems.

• Review certification packages submitted by the Contractor and coordinate with the city to determine the acceptability of the spread footing foundations within the deadlines required by the Contract Documents.

9.10 Schedule Development and Review:

The Consultant may be required to develop a CPM schedule and pay-out curve. Consultant must provide a qualified CEI Scheduler experienced in Primavera scheduling software. The CEI Scheduler shall:

a) Prepare all necessary information for this assignment, including confidential engineering estimates.

b) Preserve any confidential information provided to them.

c) Analyze Contractor’s schedule(s) (i.e. baseline(s), revised baselines(s), updates, as-built, etc.) for compliance with contract documents. Elements including, but not limited to, completeness, logic, durations, activity, flow, milestone dates, concurrency, resource allotment, and delays will be reviewed.

d) Verify the schedule conforms with the construction phasing and MOT sequences, including all contract modifications.

e) Provide a written review of the schedule identifying significant omissions, improbable or unreasonable activity durations, errors in logic, and any other concern as detailed in

CPAM.

9.11 Asphalt Plant Services:

Consultant shall provide Asphalt Plant Inspection services for Verification and:

a) Ensure that all Bituminous Verification requirements are met.

b) Provide recommendations regarding the disposition of substandard materials.

c) Generate the Random Numbers and notify the Quality Control (QC) technician after the mixture is produced and instruct when the QC technician shall take the sample.

d) Perform testing and inspection within the allotted timeframe, as defined in the contract documents. Perform daily inspections of the Producer’s Facility to ensure that the Producer is complying with their QC Plan and the contract documents. Document all inspections in daily journal.

e) Keep a daily journal documenting the arrival and departure time, failures, QC, Process Control (P.C.), and Independent Verification (IV) samples taken (time and load numbers), time that IV technicians arrived and departed, all verification inspections performed, any production related problems, and any other pertinent information that the City directs to

Scope of Services Page 11 of 24 be documented. Electronically submit the daily journal to the City at the completion of production for the day.

f) Observe the QC testing for accuracy (on a random yet consistent basis) to ensure that the QC staff is accurately documenting the weights and calculations of the test results performed. Submit the copy of handwritten data to City, as requested. Be familiar with the Producer’s QC Plan for the facility and ensure that QC staff is following the Plan.

g) Notify the City immediately when recurring problems are encountered or serious lapses occur with the QC staff following their Producer QC Plan or the contract documents.

h) Be knowledgeable of the contract documents pertaining to Asphalt Production and testing at the Producer facilities.

i) Document all material sample failures and all specification violations in the daily journal and notify the City Office immediately.

j) Perform a daily review of the QC worksheets and records for accuracy and completeness.

Notify the City if the QC staff fails to complete the testing and pertinent paperwork within 24 hours. Make every effort to verify lots within the 24 hour timeframe, and on days the plant is producing.

k) Provide the following additional plant inspection and testing related services, as requested:

o Label and sign V and R sample boxes.

o Inspect the asphalt plant, review, and analyze both QC and V test results and verify

QC technician reports are accurate.

o Collect roadway cores for each IV sample collected.

o Update the daily production spreadsheet.

o Recommend to stop or restrict asphalt plant production.

o Approve, monitor, revise, transfer, and terminate Asphalt Mix Designs, as applicable.

10.0 PERSONNEL:

10.1 General Requirements:

Consultant shall provide prequalified personnel necessary to carry out its responsibilities efficiently and effectively under this Agreement. Unless otherwise agreed to by the City, the City will not compensate straight overtime or premium overtime for the positions of Senior Project Engineer, Project Administrator/Project Engineer, Contract Support Specialist and Assistant or Associate to any of these positions.

10.2 Personnel Qualifications:

Consultant shall provide competent personnel qualified by experience and education, and submit to the City Construction Project Manager the names of personnel proposed for assignment to the project, including a detailed resume for each containing at a minimum: certifications, TIN number, education, and experience.

Personnel identified in the Consultant technical proposal are to be assigned as proposed and are committed to performing services under this Agreement. Personnel changes will require written approval from the City. Staff that has been removed shall be replaced by the Consultant within seven (7) calendar days of City notification.

MINIMUM QUALIFICATIONS FOR THE CONSULTANT PERSONNEL ARE SET FORTH ON

THE FOLLOWING PAGES. Exceptions to these minimum qualifications will be considered on an individual basis. For CTQP certifications which require training specifically developed for FDOT specifications, the Consultant may propose project staff possessing an equivalent certification

Scope of Services Page 12 of 24 from a national or other state DOT accreditation program. These exceptions may be granted under the stipulation that the appropriate CTQP certification be obtained prior to the corresponding work activity or such other time as approved by the City.

Except as noted herein, before the project begins, all project staff shall have a working knowledge of the current CPAM and must possess all the necessary qualifications/certifications for fulfilling the duties of the position they hold. Cross training of the Consultant’s project staff is highly recommended to achieve a knowledgeable and versatile project inspection team but shall not be at any additional cost to the City and should occur as workload permits.

CEI SENIOR PROJECT ENGINEER -

LICENSURE:

• Professional Engineer (PE) registered in the State of Florida o Ability to obtain endorsement in the State of Florida within six months of Project

NTP if registered in another state

EXPERIENCE:

• Six (6) years of engineering experience

• Two (2) of those years involved in relevant transportation projects

• Exception: Five (5) years for Complex Category 2 (CC2) and PTS bridge structures

• A Master's Degree in Engineering may be substituted for one (1) year engineering experience.

QUALIFICATIONS/ CERTIFICATIONS:

• FDOT Advanced MOT

• CTQP Quality Control Manager (Attend and pass the examination) o To be achieved by Project NTP, if CEI Project Administrator/ Project Engineer holds qualification at time of proposal

ABILITIES/ RESPONSIBILITIES:

• Ability to: Communicate effectively in English (verbally and in writing)

• Responsible for: Directing a highly complex and specialized construction engineering administration and inspection program;

• Responsible for: Planning and organizing the work of subordinate and staff members;

• Responsible for: Developing and/or reviewing policies, methods, practices, and procedures;

• Responsible for: Reviewing programs for conformance with City/FDOT standards.

CEI PROJECT ADMINISTRATOR/PROJECT ENGINEER -

EDUCATION:

• High School Diploma or Equivalent

LICENSURE (FOR CEI PROJECT ENGINEER):

• Professional Engineer (PE) registered in the State of Florida o Must obtain endorsement in the State of Florida within six (6) months of Project

NTP if registered in another state

EXPERIENCE:

For personnel with Engineering, Engineering Technology or Construction Management degrees:

• Two (2) years of engineering experience in relevant transportation projects.

• A Master’s Degree in Engineering, Engineering Technology, or Construction Management may be substituted for one (1) year of engineering experience For personnel without Engineering, Engineering Technology or Construction Management degrees:

Scope of Services Page 13 of 24

• Eight (8) years of CEI or roadway or bridge construction experience,

• Two (2) of those years involved in relevant transportation projects.

QUALIFICATIONS/ CERTIFICATIONS:

Qualifications/certifications for this position may be obtained within six (6) months from the date of hire provided that this position works under the supervision and direction of a Senior Project Engineer, all other requirements for the position are met, and a training plan is submitted detailing when the qualifications/certifications will be obtained.

• FDOT Advanced MOT

• CTQP Final Estimates Level II

• CTQP Quality Control Manager (Attend and pass the examination)

ABILITIES/ RESPONSIBILITIES:

• Ability to: Communicate effectively in English (verbally and in writing)

• Responsible for: Receiving general instructions regarding assignments and exercising initiative and independent judgment in the solution of work problems.

• Responsible for: Directing and assigning specific tasks to administrative and field staff and assisting in all phases of the construction project.

• Responsible for: Progress estimates and final estimates throughout the construction project duration.

CEI ASSISTANT PROJECT ADMINISTRATOR/PROJECT ENGINEER –

EDUCATION:

• High School Diploma or Equivalent

LICENSURE (FOR CEI ASSISTANT PROJECT ENGINEER):

• Professional Engineer (PE) registered in…

This is the start of the file's text. The full file is on GovTribe.