Powering Affordable Reliable Technology (PART) Energy Program - Letters of Interest Guide

This is a Letters of Interest (LOI) guide for the Rural Utilities Service (RUS) Electric Program under the Powering Affordable Reliable Technology (PART) Energy Program, published September 8, 2026. The PART Program, authorized under Section 22001 of the Inflation Reduction Act, makes approximately $410 million in budget authority available (translating to approximately $1.1 billion in loans) for eligible entities to finance renewable energy generation and energy storage projects. Eligible applicants include for-profit organizations, state and local governments, Indian tribes, Alaska Native Corporations, nonprofits, and electric cooperatives. Projects must generate electricity from hydro, geothermal, or biomass sources, or provide energy storage systems charged by eligible renewable sources, with power delivered to both rural and nonrural residents in eligible service areas (minimum 50 percent rural, unless waived). Maximum individual award amounts are limited to $100 million, and combined awards under Section 22001 cannot exceed $100 million per entity. Loans will bear interest at municipal rates per Section 317(c) of the Rural Electrification Act, with eligible projects receiving loan forgiveness up to 40 percent upon meeting all award conditions.

LOIs must be submitted electronically through Grants.gov between September 8, 2026, and October 9, 2026, at 11:59 a.m. Eastern Time. Applicants must complete Standard Form 424 and attach the PART LOI form, service area and project location shapefiles, and financial statements (balance sheets and income statements for the shorter of three years or the years in operation). RUS will review LOIs on a rolling basis, considering applicant and project eligibility, geographic diversity, substantially underserved trust area (SUTA) status, and applicant financial status. Selected applicants will receive an Invitation to Proceed and have 60 calendar days to submit a complete loan application. RUS will evaluate applications based on financial coverage ratios, equity requirements (25 percent minimum for Project Loans; System Loans secured by senior liens on all assets), loan forgiveness ratepayer benefits, technical feasibility using commercially available technology, and financial feasibility. Construction must begin after the NOFO publication date and after environmental clearance is received. All funds must be advanced by September 30, 2031, with anticipated award dates from September 2026 to December 2027. Applicants must register with System for Award Management (SAM) and obtain a Unique Entity Identifier (UEI) before submission. Build America, Buy America Act requirements apply to all domestic materials and products used in projects.

PART LOI Guide

View the file

Other files

File Type Posted
PKG00294139.pdf PDF
PART_Form_SF_424_Questions-FINAL.pdf PDF
Letter_of_Interest_PART_Submission_-_FINAL.pdf PDF
PART_2026_NOFO_v2.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Powering Affordable Reliable Technology

(PART) Energy Program

Letters of Interest Guide

Rural Utilities Service Electric Program

September 8, 2026 i

A copy of this Guide and copies of supporting documents and information are available at https://www.rd.usda.gov/programs-services/electric-programs/powering-affordable-reliable-technology-program. If you require alternative means of communication for program information (e.g., Braille, large print, audiotape) please contact USDA’s TARGET Center at

(202) 720-2600 (voice and TDD) or the 711 Relay Service.

https://www.rd.usda.gov/programs-services/electric-programs/powering-affordable-reliable-technology-program https://www.rd.usda.gov/programs-services/electric-programs/powering-affordable-reliable-technology-program ii

Table of Contents

Contents

Executive Summary

Section I: Program Summary

A. Notice of Funding Opportunity (NOFO)

B. Introduction to the PART Program

C. The Rural Utilities Service (RUS)

D. Eligibility Requirements

E. Available Funding and Types of Loans

F. Key Dates and Timelines

G. How to Submit an LOI

H. Definitions and Acronyms

I. Additional Information and Resources

Section II: Program Requirements and Restrictions

A. Funding Restrictions

B. Eligibility Information

1. Eligible LOI Submitters and Applicants

2. Eligible Service Areas

3. Eligible Projects

4. Eligible Project Costs

C. Types of Loans

1. System Loans

2. Project Loans

D. Loan Forgiveness

E. Federal Requirements

1. Statutory and Regulatory Authority

2. Environmental and Historic Preservation Requirements iii

3. Build America, Buy America Requirements

4. Additional Federal Requirements

Section III: The Letter of Interest (LOI)

A. Submission through Grants.gov

B. Submission Dates and Times

C. Prerequisites to Submitting an LOI

D. Other Submission Requirements and Limitations

E. Information Required in an LOI

F. Instructions and Specifications for Submitting Shapefile(s)

G. Criteria for Evaluating LOIs

H. Invitation to Proceed

Section IV: Submitting an LOI

A. PART Submission through Grants.gov

B. Instruction for LOI Submission on Grants.gov

Appendices

Appendix A – Definitions

Appendix B – Acronyms

Please Note: The formatting of this document does not take into consideration accessibility concerns if the document were to be printed and viewed in a hard copy format.

1 | P a g e

Executive Summary

The Rural Utilities Service (RUS or the Agency), a Rural Development (RD) Agency of the United States Department of Agriculture (USDA), is soliciting Letters of Interest (LOI) for loan Applications, announcing the Application process for those loans, and providing deadlines for Applications from eligible entities under the Powering Affordable Reliable Technology (PART) Energy Program. These loan funds will be made to qualified PART Applicants to finance power generation Projects for Renewable Energy Resource (RER) systems or Energy Storage Systems (ESS) that support RER Projects. The PART Program is making approximately $410 million in appropriated budget authority (BA) funding available under the Inflation Reduction Act of 2022 (IRA). That BA will translate into approximately $1.1 billion.

This Guide describes the PART Program requirements and provides Applicants with the guidance and instructions necessary to prepare and submit a Letter of Interest (LOI) via Grants.gov. RUS will expand this guide in the future to include additional details on the submission of Applications and the post-application process requirements under PART.

This Guide is specific only to the PART Program and only provided as guidance. The NOFO is the formal guidance of the PART Program and any information contained within the NOFO takes precedence over this Guide. All PART requirements may be found in the NOFO in Grants.gov.

2 | P a g e

Section I: Program Summary A. Notice of Funding Opportunity (NOFO)

A Notice of Funding Opportunity (NOFO) for the Powering Affordable Reliable Technology (PART) Energy Program was published in Grants.gov on August 3, 2026, to support affordable energy growth across America. The NOFO specifies that the Rural Utilities Service (RUS), a Rural Development (RD) agency of the United States Department of Agriculture (USDA), is soliciting LOIs for loan applications, announcing the application process for those loans, and providing deadlines for Applications from eligible entities under the PART Program.

B. Introduction to the PART Program

PART is authorized under Section 22001 of the Inflation Reduction Act, (IRA) Public Law 117- 169 (IRA). Other Federal statutes and regulations that apply to this Notice are: Section 317 of the Rural Electrification Act of 1936, 7 U.S.C. 940g (RE ACT), 7 U.S.C. 8103, 7 CFR parts 1700- 1730, 1767, 1773, and 1787, and 7 CFR part 1b.

The PART Program is to be carried out by the RUS pursuant to Section 22001 of the IRA. Section 22001 of the IRA amends Section 9003 of the Farm Security and Rural Investment Act of 2002 by adding new subsection (h). Section 22001 of the IRA provides RUS with appropriated funds “for the cost of loans under Section 317 of the RE Act.” Additionally, Section 22001 of the IRA provides that PART funds may be utilized to finance Projects that store electricity generated from eligible energy sources listed under Section 317 of the RE Act. These Project Loans or System Loans will be forgiven up to forty percent (40%), provided the Awardee and the Project otherwise meet the terms and conditions of the loan forgiveness. Approximately $410 million in budget authority, or approximately $1.1 billion million in loans, is being made available under this Notice. The Administrator reserves the right to increase this funding level should additional funds become available or reduce funding in the event an insufficient number of high-quality projects are submitted for consideration.

Pursuant to Section 317(b) of the RE Act, loans shall be made for the purpose of constructing electric generation from renewable energy sources. Section 22001 of the IRA also provides that loan funds may be utilized for Projects that store electricity for such generation facilities.

Further, Section 317(b) requires that the power generated from the eligible renewable energy source be for resale to rural and nonrural residents. Lastly, Section 317(c) requires that the rate of a loan shall be equal to the average tax-exempt municipal rate of similar maturities.

This funding round will only provide awards for the construction of hydro, geothermal, or biomass energy generation, and/or storage systems charged with any energy source eligible under section 317 of the Rural Electrification Act.

https://grants.gov/ https://www.congress.gov/117/plaws/publ169/PLAW-117publ169.pdf https://www.congress.gov/117/plaws/publ169/PLAW-117publ169.pdf https://www.govinfo.gov/content/pkg/COMPS-10315/pdf/COMPS-10315.pdf https://www.govinfo.gov/content/pkg/COMPS-10315/pdf/COMPS-10315.pdf https://www.govinfo.gov/content/pkg/USCODE-2024-title7/pdf/USCODE-2024-title7-chap31-subchapIII-sec940g.pdf https://www.govinfo.gov/content/pkg/USCODE-2024-title7/pdf/USCODE-2024-title7-chap107-sec8103.pdf https://www.govinfo.gov/content/pkg/CFR-2025-title7-vol11/pdf/CFR-2025-title7-vol11-part1700.pdf https://www.govinfo.gov/content/pkg/CFR-2025-title7-vol11/pdf/CFR-2025-title7-vol11-part1700.pdf https://www.ecfr.gov/current/title-7/subtitle-B/chapter-XVII/part-1767 https://www.ecfr.gov/current/title-7/subtitle-B/chapter-XVII/part-1773 https://www.ecfr.gov/current/title-7/subtitle-B/chapter-XVII/part-1787 https://www.ecfr.gov/current/title-7/subtitle-A/part-1b https://www.govinfo.gov/content/pkg/COMPS-10315/pdf/COMPS-10315.pdf

3 | P a g e

C. The Rural Utilities Service (RUS)

RUS is a Rural Development (RD) agency of the United States Department of Agriculture (USDA).

RUS administers Federal programs that support the development and improvement of necessary infrastructure in rural areas. To further RD’s mission of expanding economic opportunities and improving the quality of life for rural residents, RUS invests across a broad range of sectors. RUS investment areas include water and wastewater treatment, electric power, and telecommunications services.

The RUS Electric Program, which provides capital and leadership to maintain, upgrade, and modernize America’s vast rural electric infrastructure, will implement the PART Program. Under the authority of the RE Act, the Electric Program makes direct loans and loan guarantees, as well as grants, available to eligible borrowers to finance the construction of new electric distribution, transmission, and generation facilities or to finance system improvements and replacements of existing electric facilities. The Electric Program also provides funding to support demand-side management, energy efficiency (EE) and conservation programs, and on-grid and off-grid renewable energy (RE) systems.

The RUS Electric Program is well known for providing financing to rural electric cooperatives.

RUS Electric Program financing is and has long been made available to corporations, tribal utilities, states, territories, and subdivisions and agencies thereof, municipalities, utility districts and non-profit organizations that serve consumers in rural areas. In general, to be an eligible borrower the entity must provide or propose to provide: i) the electric service needs of rural areas, or ii) the power supply needs of distribution borrowers under the terms of power supply arrangements satisfactory to RUS.

D. Eligibility Requirements

PART applicant(s) and the respective project(s) for which funding is being requested under the PART Program must meet eligibility requirements, including:

• Eligible Applicants: Eligible Applicants are identified in the NOFO and include, but are not limited to, electric service providers such as municipal utilities, cooperatives, private-sector developers, and investor-owned or Tribal utilities.

• Eligible Service Areas: Electricity generated or discharged from facilities shall be provided to both “rural and nonrural residents” located in service areas determined to be eligible under PART.

• Eligible Projects: The types of projects eligible to be financed with PART loan funds include the following Renewable Energy Resource (RER) systems that generate electricity or Energy Storage Systems (ESS) that support RER Projects. Only hydro, geothermal, or biomass energy generation, and/or storage systems charged with any energy source eligible under section

4 | P a g e

317 of the Rural Electrification Act are eligible under this funding Notice.

• Eligible Project Costs: Reasonable project costs that are capitalized may be eligible to be financed with PART loan funds, but limitations on the amount of funds to be awarded will depend on the type of loan, the amount of loan funds requested, loan security, and other factors.

E. Available Funding and Types of Loans

Available Funds: Approximately $410 million in budget authority through September 30, 2031.

However, based on projected subsidy rates, RUS expects to have approximately $815 million available to lend for the PART Program.

RUS may, at its discretion, increase the total level of funding available in this funding round from any available source provided the Awards meet the requirements of the statute which made the funding available to the Agency. The Agency may also choose to obligate fewer funds if in the sole judgement of the agency there are not a sufficient number of high-quality applications.

Type of Awards: The type of awards to be provided under PART are Project Loans or System Loans with loan forgiveness up to forty percent (40%), provided the Awardee and the Project otherwise meet the terms and conditions of the loan forgiveness.

Award Amounts: The maximum loan amount, inclusive of the forgivable portion, of any individual Award is limited to $100 million. Additionally, the combined total of any prior Powering Affordable Clean Energy (PACE) Award, PART Award or any other award made under Section 22001 of the Inflation Reduction Act may not exceed $100 million.

Loan Types: RUS will offer both Project Loans and System Loans to finance eligible PART projects. Project Loans and System Loans are also detailed in Section II of this Program Guide.

Municipal Rate Loans: Loans made under the PART Program will bear interest equal to the municipal rate as provided in Section 317(c) of the RE Act, and as further described in the first sentence of 7 CFR 1714.4(a) and 7 CFR 1714.5(a)-(c). Municipal rates can be found at https://www.rd.usda.gov/page/rural-utilities-loan-interest-rates. Note that because there is no interest rate cap for the PART Program, the third sentence of 7 CFR 1714.4(a) and 7 CFR 1714.5(d) shall not apply. Interest rates are announced by the Agency on a periodic basis and will be set for a particular loan at the time funds are drawn. The published rates described above are the rates that a borrower would pay if the borrower had drawn funds on the day the rates were in effect. The actual rates an applicant will pay when funds are drawn would likely be different than the rates offered today.

https://www.rd.usda.gov/page/rural-utilities-loan-interest-rates

5 | P a g e

F. Key Dates and Timelines

Date IRA Signed into Law: August 16, 2022.

NOFO Publish Date: August 3, 2026.

Submittal of Letters of Interest: Letters of Interest (LOIs) may be submitted beginning at 11:59 a.m. Eastern Time (ET) on September 8, 2026. LOIs will be accepted until 11:59 a.m. ET October 9, 2026. Submitters are advised that PART LOIs will be reviewed on a rolling basis as they are received and ranked accordingly reserving for the Administrator the right to take geographic diversity and substantially underserved trust area eligibility into account when ranking LOIs for further consideration and award.

Submittal of Application: An applicant that is invited by RUS to proceed to the next level of review through the submission of a full loan Application will have 60 calendar days from the date that the Invitation to Proceed is emailed to the PART Applicant or at a time agreeable in writing to the Agency. If the deadline to submit the completed Application falls on Saturday, Sunday, and/or a Federal holiday, the Application is due the next business day. RUS reserves the right, in its sole discretion, to extend the deadline for the submittal of a full Application upon a written request of the applicant if the applicant demonstrates to the satisfaction of the Administrator that exceptional circumstances exist to warrant the extension, and the agency grants the extension in writing.

Dates Funds Are Available: PART funds will be made available in the fiscal year 2026 and will only be available through September 30, 2031. Award agreements will contain a provision that requires the advance of all loan funds on or before September 30, 2031. All undisbursed funds as of close of business on September 30, 2031, will automatically be rescinded. Applicants are advised that the Agency will set a last day for advance in Award agreements well in advance of the statutory limit.

Anticipated Award Date: From September 2026 to December 2027.

Performance Period: Five (5) years from the date of environmental clearance, but no later than September 30, 2031.

6 | P a g e

Eligible Construction Start Date: Only those projects where construction begins after the date of publication of the PART Notice are eligible for funding under PART. Furthermore, construction cannot commence until after the submitter has received a written environmental clearance message from RUS. Any applicant that starts construction prior to the agreement on loan terms assume all risks and responsibilities for incurred expenses should the agency and applicant not come to agreement on loan terms.

RUS Environmental Approval: Projects must receive RUS environmental clearance prior to the start of construction to remain eligible to receive PART loan funds or RUS financing. A project in the pre-construction planning stage before the date of publication may be eligible for IRA financing provided construction has not commenced prior to completion of the environmental review and prior to the date of publication of the PART Notice.

G. How to Submit an LOI

Letters of Interest (LOI): Each applicant must submit an LOI to RUS electronically through Grants.gov. A detailed description of the items that should be included in an LOI and the specific requirements and instructions for submitting the LOI through Grants.gov are provided in Sections III and IV of this Guide, as well as the NOFO. Applicants are required to read the requirements of Grants.gov before submitting an application on that platform.

H. Definitions and Acronyms

Refer to the Appendices A and B.

I. Additional Information and Resources

Additional information and resources regarding PART including a copy of this PART Program Guide are available at https://www.rd.usda.gov/programs-services/electric-programs/powering-affordable-reliable-technology-program

If you require alternative means of communication for program information (e.g., Braille, large print, audiotape) please contact USDA’s TARGET Center at (202) 720-2600 (voice and TDD) or the 711 Relay Service.

Questions regarding the PART Program can be emailed to:

SM.RD.RUS.PART-Questions@usda.gov https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.rd.usda.gov%2Fprograms-services%2Felectric-programs%2Fpowering-affordable-reliable-technology-program&data=05%7C02%7Camy.mcwilliams%40usda.gov%7Cd0b0d2f5fc1a43e3f59808dedcde477d%7Ced5b36e701ee4ebc867ee03cfa0d4697%7C1%7C0%7C639191044402970616%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=%2B6L8GW7xeIG4TbdjUKcMvjkTckDDjpsi%2BIwvhqQI7mc%3D&reserved=0 https://gcc02.safelinks.protection.outlook.com/?url=https%3A%2F%2Fwww.rd.usda.gov%2Fprograms-services%2Felectric-programs%2Fpowering-affordable-reliable-technology-program&data=05%7C02%7Camy.mcwilliams%40usda.gov%7Cd0b0d2f5fc1a43e3f59808dedcde477d%7Ced5b36e701ee4ebc867ee03cfa0d4697%7C1%7C0%7C639191044402970616%7CUnknown%7CTWFpbGZsb3d8eyJFbXB0eU1hcGkiOnRydWUsIlYiOiIwLjAuMDAwMCIsIlAiOiJXaW4zMiIsIkFOIjoiTWFpbCIsIldUIjoyfQ%3D%3D%7C0%7C%7C%7C&sdata=%2B6L8GW7xeIG4TbdjUKcMvjkTckDDjpsi%2BIwvhqQI7mc%3D&reserved=0 mailto:SM.RD.RUS.PART-Questions@usda.gov

7 | P a g e

Section II: Program Requirements and Restrictions A. Funding Restrictions

The key PART Program funding restrictions are listed below:

(a) Entities that been approved for an award under the RUS Powering Affordable Clean

Energy (PACE) Program or the RUS Empowering Rural America (New ERA) Program may not apply for the same Project under the PART Program. Failure to follow this limitation could result in the PART Applicant being disqualified from the PART program.

(b) Only Projects where construction begins after the date of publication of this Notice will be eligible for funding under the PART Program.

(c) Funding will not be provided for merchant power Projects; Projects where a non-utility entity is generating power for its own use or behind the meter projects owned by the consumer.

(d) Funding will not be provided for the purchase of any existing RER or ESS.

(e) There are no Application or origination fees for loans under the PART Program.

(f) RUS will only finance Projects that utilize Commercially Available Technology under this

Notice.

PART Applicants may, with RUS approval request reimbursement for interconnection costs and other costs associated with being able to deliver the RER and/or the ESS to Off-Takers.

B. Eligibility Information

PART LOI submitters and the projects for which they are requesting funding must meet certain eligibility requirements. These include sufficient information to determine:

• Whether an applicant is eligible to submit an LOI and application under PART;

• Whether the areas proposed to be served by the projects financed under PART are eligible; and

• The types of proposed projects and whether proposed project costs are allowed to be financed with PART loan funds.

1. Eligible LOI Submitters and Applicants

RUS will accept LOIs and Applications from Operating Utilities that are determined to be

8 | P a g e

Eligible to participate in the PART Energy Program. Eligible Operating Utilities include:

(a) For-profit organizations;

(b) State or local governments;

(c) Indian tribes defined by the Federally Recognized Indian Tribe List Act of 1994

(Public Law 103-454; 108 Stat. 4791, 4792), including their wholly arms and instrumentalities;

(d) Alaska Native Corporations, regional or village corporations as defined under or established pursuant to the Alaska Native Claims Settlement Act (Public Law 104- 42; 85 State. 688);

(e) Nonprofits;

(f) Distribution electric cooperatives, and generation and transmission electric cooperatives; and

(g) Certified Electric Utilities.

LOIs and Applications otherwise eligible from any entity in the above categories will be evaluated for funding.

2. Eligible Service Areas

PART funds shall be used to finance an eligible RER or an eligible ESS where electricity generated or discharged is provided to “rural and nonrural residents” in Eligible Service Areas. Service areas are determined to be eligible based on those communities that receive and consume the electricity generated or discharged from a Project and not by the location of the Project.

Eligible Service Areas must meet the minimum rural percentage of at least 50 percent, unless waived by the Administrator based upon a showing A waiver would provide substantial benefits to rural consumers to avoid or mitigate the costs of excessive energy burdens, or severe economic conditions. The service areas of a former RUS or REA borrower may be considered 100 percent rural for the purposes of their applications as described further below.

The Eligible Service Areas will need to be determined for each Project and, in those cases where there are multiple owners (i.e., co-owners) of a Project, the Eligible Service Areas may need to be determined separately for each co-owner. A co-owner of a Project that is an Eligible Entity may in turn have more than one Off-Taker that receives the output from the Project. In such a case, the Service Areas of all the Off-Takers are combined to determine rural eligibility.

There may be cases where multiple Projects provide electrical power that is delivered to and consumed within the same Eligible Service Areas. If a Project does not provide service to an area that meets the minimum rural percentage of at least 50 percent or the Applicant has secured a written waiver from the Administrator, then the Applicant

9 | P a g e will not be eligible to receive PART Program loan funds for the Project.

An Applicant will need to upload digital Shapefiles that reflect the applicable service areas associated with each Project and demonstrate that the service areas meet the minimum rural percentage of at least 50 percent.

The following are important definitions and steps used to determine Eligible Service Areas:

Rural area: A “rural area” for PART means:

(a) Any area other than a city, town, or unincorporated area that has a population of greater than 20,000 inhabitants, or

(b) The service areas of current RUS borrowers or a former RUS or Rural Electrification Act (REA) borrowers for the purpose of that entity’s application.

The service areas of a former RUS or REA borrower would be considered rural only in those cases where 1) the PART Applicant is a former borrower and 2) the Project being financed with PART loan funds is providing electricity to the service areas of the former borrower.

Rural Determination: The service of current and former Rural Electrification Act Borrowers are deemed to be rural for those borrowers.

If the PART Applicant is not a current RUS borrower nor a former RUS or REA borrower, a rural determination will be conducted by RUS to:

(a) Identify the service territory where electricity from the facilities to be financed by PART loan funds would be delivered and consumed; and

(b) Further identify those areas within the service territory that are rural versus those areas that are non-rural.

Rural Percentage: If the PART Applicant is not a current RUS borrower nor a former RUS or REA borrower, the rural determination will calculate the rural percentage of the service territory. The rural percentage will be calculated by choosing one of the following 2 methods that provides the best results:

(a) The population located in the Rural Areas of a service territory versus the total population of the entire service territory; or

(b) Meters served in the Rural Areas of a service territory versus meters served in the entire service territory - assuming the data and information to conduct this calculation is made available to RUS.

10 | P a g e

3. Eligible Projects

A Project that is eligible to be financed with PART loan funds includes the construction of a new RER that generates electricity from Hydro, Geothermal and/or Biomass technologies and/or the construction of a new ESS used to store electricity in support of the technologies In Section 317 of the Rural Electrification Act.

Each RER and ESS that is to be financed with PART loan funds must be installed to provide electrical capacity and/or energy, as well as any ancillary services should they be included, for resale to rural and non-rural residents located in eligible service areas.

A project must be based on “commercially available technology” in which all equipment, devices, applications, or systems have a proven, reliable performance, and replicable operating history specific to the proposed application. The equipment, device, application, or system is based on established patented design or has been certified by an industry-recognized organization and subject to installation, operating, and maintenance procedures generally accepted by industry practices and standards.

Service and replacement parts for the equipment, device, application, or system must be readily available in the marketplace with established warranty applicable to parts, labor, and performance.

New facilities must be constructed after the publication date of this Notice and after the applicant receives environmental clearance from RUS in writing as well as be compliant with all other applicable requirements of the NOFO to remain eligible for financing with PART loan funds.

A project must have received RUS environmental clearance prior to the start of construction to remain eligible for financing under the PART Program.

The following elements and associated reasonable costs may be included in a PART LOI submission:

• New facilities that generate electricity from an RER under this Notice, including facilities that store electricity that support such assets (ESS) from technologies listed in Section 317 of the Rural Electrification Act. RUS will not approve facilities that violate the terms of an Applicant’s existing wholesale power contract.

• New linear facilities, including microgrids and distributed renewable energy, and equipment that are necessary to operate the Project including, but not limited to, transmission or distribution facilities that are needed to export, transmit, and deliver power from the generating facility to the Off-Taker.

• The upgrading of existing linear facilities and equipment that are necessary to operate the Project including, but not limited to, transmission or distribution facilities that are needed to export, transmit, and deliver power from the generating facility to the Off-Taker(s).

11 | P a g e

• The Project may include one or more RERs eligible under this NOFO and/or ESSs eligible under this Notice.

• Facilities may be co-located to operate interconnectedly or independently or constructed at separate sites.

• RERs and ESSs must be installed so that the eligible RER can provide energy and any ancillary services for resale to rural and non-rural residents located in Eligible Service Areas.

• Applicants may request interconnection and other costs associated with being able to deliver the RER and/or the ESS eligible under this Notice to Off-Takers, including related microgrid investments. Successful applicants may also recover a portion of their capitalizable pre-application costs pursuant to 7 CFR part 1767 and this Notice.

4. Eligible Project Costs

PART loan funds shall be used to finance Eligible Projects listed above and where applicable the costs for such facilities described in 7 CFR 1710.106, including interest during construction (IDC) pursuant to 7 CFR 1710.106(a)(4). Costs must be reasonable, allocable, and necessary for the Project. All eligible costs shall be those that are capitalized and are recorded as an asset on the Applicant’s balance sheet.

Capital costs may include, but not be limited to, land purchases, planning, design and engineering, feasibility studies, project management, equipment purchases and leases, materials and supplies, labor, construction contingencies, permitting, licensing and legal fees, insurance, startup and commissioning, taxes, and interest. Basically, any costs incurred during development and construction that are directly attributable to placing the Project into service should be capitalized. The Applicant must provide an estimated total cost of the Project along with a detailed description of and cost breakdown of the Project.

PART loan funds may be used to pay off or replace an interim construction loan used to finance an Eligible Project that has cleared environmental review, but PART loan funds cannot be used to refinance other outstanding debt. Also, PART loan funds cannot be used to finance any operating or maintenance expenses nor any other costs that are expensed.

PART Funds may be used to acquire or improve an operating facility using a technology or technologies eligible under this Notice, provided the action facilitates an increase in power supply to the Applicant after the date of publication of this Notice.

An Applicant may include in its loan Application the costs specified in 7 CFR 1710.106, including interest during construction (IDC) pursuant to 7 CFR 1710.106(a)(4).

Note that the PART Program does not require Applicants to pay any fees to submit an LOI or an Application for a loan, nor to have RUS process a loan application.

12 | P a g e

C. Types of Loans

RUS will offer both Project Loans and System Loans to finance a project as described below.

1. System Loans

A System Loan is provided where the PART Award is secured through a senior security interest in all assets of the PART Applicant. System Loans are only available to currently operating electric utilities.

To receive a System Loan, the PART Applicant will provide, if it has not already been provided, RUS with a perfected senior lien (or shared perfected senior lien on a Pari Pasu basis) on all its existing assets, both real and personal, including intangible personal property, as well as after-acquired property. At the Administrator’s discretion, a PART Applicant may be permitted to secure a System Loan through an indenture, if RUS is granted a perfected senior security interest in all its assets by the trustee.

A System Loan may be used to finance 100 percent of the Project costs included in an Application. At the discretion of the Administrator, System Loan funds can be released to finance Projects for costs incurred during construction of the facilities. This would be accomplished by the submittal to and approval by RUS of selected executed procurement and construction contracts where the total price of the contracts has been encumbered and then allowing the Applicant to drawdown the encumbered loan funds based on the cost incurred to date. However, loan forgiveness will not occur until the Project has been completed and RUS has confirmed that the Awardee has satisfied all other conditions specified in the Award. The Agency reserves the right to claw back funds advanced for projects that do not meet their loan commitments.

2. Project Loans

A Project Loan is provided to Applicants that are not eligible for, or have decided not to pursue, a System Loan.

A Project Loan is used to finance an eligible Project where the PART Award is secured through a senior security interest on the Project’s assets and the revenues generated from the Project’s assets, rather than by a security interest of all the assets of the PART Applicant’s electric utility system.

With a Project Loan, the Applicant would own and operate the eligible RER and/or ESS that are financed with the PART loan funds and ensure that the electrical output of these

13 | P a g e facilities is delivered to an Off-Taker(s) who has/have agreed to receive and purchase the power under an executed power purchase agreement (PPA). The facilities may interconnect to a transmission grid system, a distribution system, a micro-grid, or other system that is used to ultimately deliver and distribute the power to rural and non-rural residents in Eligible Service Areas. The Awardee must collaterally assign the PPA to RUS as security, with the Off-Taker’s consent.

A Project Loan will be used to finance a Project in the amount that does not exceed any one of the following:

• 75 percent of the total capitalized cost of the Project;

• The total capitalized cost of the project minus both the project’s equity contribution

& other sources of capital financing (e.g., grant funds, loans for other lenders, etc.);

or

• The loan amount requested by the Borrower.

Unless otherwise approved, a Project Loan requires that the Applicant provide a 25 percent minimum cash equity investment in the Project prior to the release of any PART loan funds, and that the Applicant maintain an equity level at or above 25 percent throughout the life of the loan, unless otherwise agreed to by the agency. This must be reflected in the term of the loan in the Awardee’s Long Range Financial Forecast (LRFF).

The Administrator may consider tax credits or direct payments in lieu of tax credits the Awardee receives under the Internal Revenue Code when calculating equity investment requirements for a PART Applicant’s proposed Project. If the Administrator allows a PART Applicant to meet the financial equity requirement by utilizing applicable tax benefits, the Administrator may require additional credit support from the PART Applicant pending the PART Applicant’s receipt of the tax benefit.

Further, the Agency may utilize its authority under Section 306F of the RE Act and finance up to 100 percent of the cost of Projects benefiting SUTA areas. Project Award funds will only be released after commercial operation of the Project is commenced and RUS has confirmed that the Awardee has satisfied all other conditions specified in the Award.

The Awardee will need to establish and fund at least two separate reserve accounts.

These include: 1) an O&M Reserve Account in the amount equal to the operation & maintenance (O&M) expenses that the Borrower is expected to incur during one year of operation, and 2) a Debt Reserve Account in the amount equal to all principal and interest (P&I) that the Borrower would be required to pay for one year.

The Office of Loan Origination and Approval (OLOA) may require the establishment of other reserve accounts depending on the perceived risks of the project. The Borrower would need to make the appropriate deposits into the reserve accounts before closing.

RUS may allow a parent company guarantee to be used in lieu of or as a complement to

14 | P a g e establishing the reserve accounts. In addition to the reserve accounts, the Awardee may be required to establish a Sinking Fund to factor in the expected cost to replace major components during the term of the loan (e.g., inverters, wind turbine blades, battery cells, etc.).

D. Loan Forgiveness

Eligible projects receiving funding under this notice shall be eligible for loan forgiveness up to 40 percent. At the discretion of the Administrator, System Loan funds can be released to finance Projects for costs incurred during construction of the facilities;

however, loan forgiveness will not occur until the Project has been completed and RUS has confirmed that the Awardee has satisfied all other conditions specified in the Award.

E. Federal Requirements

1. Statutory and Regulatory Authority

PART is authorized under Section 22001 of the Inflation Reduction Act, (IRA) Public Law 117-169 (IRA). Other Federal statutes and regulations that apply to this notice are:

Section 317 of the Rural Electrification Act of 1936, 7 U.S.C. 940g (RE Act), 7 U.S.C. 8103, 7 CFR parts 1700-1730, 1767, 1773, and 1787, and 7 CFR part 1b.

The PART Program is to be carried out by the RUS pursuant to Section 22001 of the IRA.

Section 22001 of the IRA amends Section 9003 of the Farm Security and Rural Investment Act of 2002 by adding new subsection (h). Section 22001 of the IRA provides RUS with appropriated funds “for the cost of loans under Section 317 of the RE Act.” Additionally, Section 22001 of the IRA provides that PART funds may be utilized to finance Projects that store electricity generated from eligible energy sources listed under Section 317 of the RE Act. These Project Loans or System Loans will be forgiven up to forty percent (40%), provided the Awardee and the Project otherwise meet the terms and conditions of the loan forgiveness. Approximately $410 million in budget authority, or approximately $1.1 billion million in loans, is being made available under this Notice. The Administrator reserves the right to increase this funding level should additional funds become available or reduce funding in the event an insufficient number of high-quality projects are submitted for consideration.

Pursuant to Section 317(b) of the RE Act, loans shall be made for the purpose of constructing electric generation from renewable energy sources. Section 22001 of the IRA also provides that loan funds may be utilized for Projects that store electricity for such generation facilities. Further, Section 317(b) requires that the power generated from the eligible renewable energy source be for resale to rural and nonrural residents. Lastly, Section 317(c) requires that the rate of a loan shall be equal to the average tax-exempt municipal rate of similar maturities.

https://www.congress.gov/117/plaws/publ169/PLAW-117publ169.pdf https://www.congress.gov/117/plaws/publ169/PLAW-117publ169.pdf https://www.govinfo.gov/content/pkg/COMPS-10315/pdf/COMPS-10315.pdf chrome-extension://efaidnbmnnnibpcajpcglclefindmkaj/https:/www.govinfo.gov/content/pkg/USCODE-2024-title7/pdf/USCODE-2024-title7-chap31-subchapIII-sec940g.pdf https://www.govinfo.gov/content/pkg/USCODE-2024-title7/pdf/USCODE-2024-title7-chap107-sec8103.pdf https://www.govinfo.gov/content/pkg/CFR-2025-title7-vol11/pdf/CFR-2025-title7-vol11-part1700.pdf https://www.ecfr.gov/current/title-7/subtitle-B/chapter-XVII/part-1767 https://www.ecfr.gov/current/title-7/subtitle-B/chapter-XVII/part-1773 https://www.ecfr.gov/current/title-7/subtitle-B/chapter-XVII/part-1787 https://www.govinfo.gov/content/pkg/CFR-2025-title7-vol1/pdf/CFR-2025-title7-vol1-part1b.pdf https://www.govinfo.gov/content/pkg/COMPS-10315/pdf/COMPS-10315.pdf

15 | P a g e

This funding round will only provide awards for the construction of hydro, geothermal, or biomass energy generation, and/or storage systems charged with any energy source eligible under section 317 of the Rural Electrification Act.

2. Environmental and Historic Preservation Requirements

Projects to be financed with PART loan funds must meet the requirements of environmental review including but not limited to compliance with the National Environmental Policy Act of 1969, as amended (NEPA) (42 U.S.C 4321, et seq), implemented by USDA at 7 CFR part 1b, Section 7 of the Endangered Species Act (16 U.S.C.

1531 et seq.) (50 CFR part 402), and Section 106 of the National Historic Preservation Act (NHPA)(54 U.S.C. 300101 et seq.)(36 CFR Part 800).

3. Build America, Buy America Requirements

Infrastructure Project Awards under this announcement must meet the following domestic preference requirements:

(a) Funding to Non-Federal Entities. Awardees that are Non-Federal Entities shall be governed by the requirements of Section 70914 of the Build America, Buy America Act (BABAA) within the Infrastructure Investment and Jobs Act (IIJA), and its implementing regulations. The Act requires the following Buy America preference:

(i) All iron and steel used in the Project are produced in the United States. This means all manufacturing processes, from the initial melting stage through the application of coatings, occurred in the United States.

(ii) All manufactured products used in the Project are produced in the United States. This means the manufactured product was manufactured in the United States, and the cost of the components of the manufactured product that are mined, produced, or manufactured in the United States is greater than 55 percent of the total cost of all components of the manufactured product, unless another standard for determining the minimum amount of domestic content of the manufactured product has been established under applicable law or regulation.

(iii) All construction materials (excludes cement and cementitious materials, aggregates such as stone, sand, or gravel, or aggregate binding agents or additives) are manufactured in the United States. This means that all manufacturing processes for the construction material occurred in the United States.

BABAA only applies to articles, materials, and supplies that are consumed in, incorporated into, or affixed to an infrastructure project. As such, it does not apply to tools, equipment, and supplies, such as temporary scaffolding, brought to the construction site and removed at or before the completion of the infrastructure project. Nor does BABAA apply to equipment and furnishings, such as movable chairs, desks, and portable computer https://www.govinfo.gov/content/pkg/CFR-2025-title7-vol1/pdf/CFR-2025-title7-vol1-part1b.pdf https://www.ecfr.gov/current/title-50/chapter-IV/subchapter-A/part-402 https://www.ecfr.gov/current/title-36/chapter-VIII/part-800

16 | P a g e equipment, that are used at or within the finished infrastructure project. Any requests for waiver of these requirements must be submitted pursuant to USDA’s guidance available online at https://www.usda.gov/ocfo/federal-financial-assistance-policy/USDABuyAmericaWaiver.

(b) Funding to all other entities. All other Awardees shall be governed by the Agency’s Buy American requirement at 7 CFR part 1787. For -profit organizations are not considered Non-Federal Entities. However, this does not alter independent statutory authorities that USDA may have to include domestic content requirements in awards of Federal financial assistance issued to for-profit organizations. Any requests for waiver of these requirements must be submitted pursuant to those regulations.

4. Additional Federal Requirements

Other Federal requirements that applicants may be required to adhere to are listed in the table below with a brief description. This is not a comprehensive list and is provided for informational purposes only.

• Federal Funding Accountability and Transparency Act: All applicants, in accordance with 2 CFR part 25, must be registered in System for Award Management (SAM) and have a Unique Entity Identifier (UEI) number as stated in Section D.3 of the NOFO.

Additional information on SAM and UEI is detailed in Section III of this Guide. All recipients of Federal financial assistance are required to report information about first-tier sub-awards and executive total compensation in accordance with 2 CFR part 170.

• 2 CFR part 200: This regulation establishes the administrative requirements for the management of Federal grant programs, the principles for determining allowable costs incurred by Awardees, and the auditing requirements to establish consistency in the audit of potential Awardee.

• Parts to Title 7 of the CFR: Except as provided in the PART NOFO and in the executed loan agreements, all other generally applicable regulations contained in 7 CFR parts 1700-1730, 1767, 1773, and 1787, and 7 CFR part 1b will apply to PACE loans, as well as relevant Bulletins published by the RUS Electric Program.

• Disclosure of Foreign Entities: Pursuant to the Defense Production Act of 1950 and the Foreign Investment Risk Review Modernization Act of 2018, RUS will require PART Applicants to disclose any foreign person or foreign entity that has an ownership, management rights, or voting interest in the PART Applicant or the Project.

• Title VI of the Civil Rights Act of 1964: Federal agencies are responsible for ensuring that Federal funding assistance does not contribute to programs that discriminate https://www.usda.gov/ocfo/federal-financial-assistance-policy/USDABuyAmericaWaiver https://www.usda.gov/ocfo/federal-financial-assistance-policy/USDABuyAmericaWaiver https://www.ecfr.gov/current/title-7/subtitle-B/chapter-XVII/part-1787

17 | P a g e based on race, ethnicity, or national origin. If any recipient of Federal funding is found to have discriminated based on race, ethnicity, or national origin, the responsible Federal agency will take remedial action in accordance with Title VI of the Civil Rights Act.

18 | P a g e

Section III: The Letter of Interest (LOI) A. Submission through Grants.gov

An Applicant will be required to prepare and submit a Letter of Interest (LOI) that will be evaluated by RUS to determine if the Applicant can proceed with an Application for a PART loan.

The components of an LOI must be submitted electronically through Grants.gov.

This section describes the essential elements included in an LOI, and the criteria that RUS will use to evaluate all LOIs. The process for preparing and submitting an LOI using Grants.gov is detailed in Section IV.

B. Submission Dates and Times

LOIs can be submitted using Grants.gov beginning at 11:59 a.m. Eastern Time (ET) on September 8, 2026. The online window to submit LOIs will remain open until 11:59 a.m. ET October 9, 2026.

Submitters are advised that PART LOIs will be reviewed on a rolling basis as they are received and ranked accordingly reserving for the Administrator the right to take geographic diversity and substantially underserved trust area eligibility into account when ranking LOIs for further consideration and award.

RUS will consider only complete LOIs as they are received.

RUS reserves the right to ask PART Applicants for clarifying information on, or additional information related to, the LOI after it has been submitted on Grants.gov.

If an LOI submitter has been selected to proceed with the loan Application, they will receive an Invitation to Proceed instructing them to submit a completed loan Application within 60 days, or a time agreed to with the Agency.

C. Prerequisites to Submitting an LOI

It is vital that each Applicant understands and appropriately addresses the following items prior to submitting an LOI via Grants.gov:

• Registered Account via Grants.gov: You only need to register once in order to apply for

Federal funding opportunities on Grants.gov. But if you are applying for the first time, this is a key step in the process. A training video that guides users through the registration process is available (Intro to Grants.gov - How to Register with Grants.gov (Updated) - YouTube).

https://www.youtube.com/watch?v=sj3X2XPAQ5g https://www.youtube.com/watch?v=sj3X2XPAQ5g

19 | P a g e

• Federal Tax Identification Number: An Applicant must provide their Federal Tax Identification number as part of Standard Form 424 during the LOI submission.

• System for Award Management and Unique Entity Identifier:

(a) At the time of Application, each PART Applicant must have an active registration in the System for Award Management (SAM) before submitting its Application in accordance with 2 CFR part 25. In order to register in SAM, entities will be required to obtain a Unique Entity Identifier (UEI). Instructions for obtaining the UEI are available at https://sam.gov/content/entity-registration.

(b) PART Applicants must maintain an active SAM registration, with current, accurate and complete information, at all times during which it has an active Federal award or an Application under consideration by a Federal awarding agency.

(c) PART Applicants must ensure they complete the Financial Assistance General

Certifications and Representations in SAM.

(d) PART Applicants must provide a valid UEI in their Application, unless determined exempt under 2 CFR 25.110.

(e) The Agency will not make an Award until the PART Applicant has complied with all

SAM requirements. If a PART Applicant has not fully complied with the requirements by the time the Agency is ready to make an Award, the Agency may determine that the PART Applicant is not qualified to receive a Federal Award and use that determination as a basis for making a Federal Award to another PART Applicant.

(f) Prospective applicants are advised to secure the necessary registrations mentioned above well in advance of the submission of their LOI. Delays in submission due to incomplete, inaccurate or expired registrations could delay the submitter’s ability to submit an LOI which in turn could profoundly affect the likelihood of funding.

D. Other Submission Requirements and Limitations

A potential Applicant should also be aware of other submission requirements and limitations such as those listed below.

(1) An entity may only submit one LOI, which must be prepared and submitted using

Grants.gov. For more information see https://www.rd.usda.gov/programs-services/electric-programs/powering-affordable-clean-energy-pace-program.

Each LOI submitter may only submit one LOI, upon receiving an RUS Invitation to https://www.ecfr.gov/current/title-2/subtitle-A/chapter-I/part-25 https://sam.gov/content/entity-registration…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .