The document is a Special Provisions and Technical Specifications section for the City of Pasadena's FY26 Sewer Relining and Point Repair Project. The project involves comprehensive sewer infrastructure maintenance, including cleaning and CCTV inspection of sanitary sewer pipes ranging from 2 to 20 inches in diameter across various locations, with a specific focus on the hillside area of District 6. Work includes CIPP (Cured-In-Place Pipe) lining, point repairs, lateral connection seals, manhole reconstructions, and related infrastructure improvements. The project covers activities such as pipe cleaning, video inspections, lateral reconnections, and manhole condition evaluations.
The contract includes multiple bid items with unit pricing, covering tasks like pipe cleaning, CCTV inspections, point repairs, sectional repairs, liner installations, lateral connection seals, manhole reconstructions, and condition assessments. An allowance of $100,000 is included for unforeseen circumstances. The specifications provide detailed requirements for each work type, including technical standards, material specifications, installation procedures, and quality control measures. The project emphasizes maintaining continuous access for residents and businesses, requires specific notification procedures, and includes provisions for traffic control and site restoration. Contractors must adhere to NASSCO (National Association of Sewer Service Companies) standards and provide comprehensive documentation and GPS-referenced data for all work performed.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PART II-2 – FY26 SEWER RELINING & POINT REPAIR PROJECT II-1 05/08/2025
PART II-2
SPECIAL PROVISIONS
TECHNICAL SPECIFICATIONS AND CONSTRUCTION METHODS
The work to be performed consists of the CONTRACTOR furnishing all materials, equipment, tools, labor, and incidentals necessary for the construction of the proposed project, complete in place in accordance with the contract drawings and specification and subject to the terms and conditions of the FY26 Sewer Relining and Point Repair Project Agreement.
The work includes:
Cleaning and CCTV inspection of existing 2-, 4-, 6-, 8-, 10-, 12-, 14-, 15-, 16-, 18- and 20-inch diameter sanitary sewer pipes at various locations including hillside area of District 6; CIPP lining and point repairs of 4-, 6-, 8-, 10-, 12-, 15-, and 18-inch diameter sanitary sewer pipes at various locations; installation of sectionals; post-lining video inspections; reopening of existing lateral connections; installation of service lateral connection seals known as “Top Hats”; trimming of protruding laterals and other obstructions; reconstruction of manhole channel; removal and reconstruction of manhole; adjustment to grade of manhole frame and covers; sewer manhole condition evaluation; and miscellaneous appurtenant work.
Such other items or details not mentioned above that are required by the Standard Specifications, or these Special Provisions, shall be performed, placed, constructed, or installed, and the total contract bid price submitted shall include the cost of all such incidentals even though they are not specifically mentioned in the preceding description of work or in the Bidder’s Proposal.
CONTRACTOR shall provide safe and adequate pedestrian access at all times. Vehicular movement at and around all construction sites shall be provided and maintained at all times. Approved barriers and signs (traffic flagging personnel, if necessary) shall be furnished and utilized by the CONTRACTOR to ensure safety and public access to businesses at all times.
Contract Documents – The following documents are also included on this contract:
Drawing No. 6873 – FY26 Sewer Relining & Point Repair Project
Pasadena Standard Plans:
S-299 Supporting Water Pipes Encountered during Excavation Operations S-301 Saddles for House Laterals S-382 Precast Concrete Sewer Manhole S-384 Manhole Top Reconstruction S-408 Adjustment of Street Manhole Frame S-416 Restoration of Asphalt Street Excavations S-417 Restoration of Concrete Street Excavations S-422 PCC Pavement Jointing and Details S-426 Minimum Public Safety Requirement for Open Excavations
SPPWC Standard Plans:
205-3 Sewer Manhole Adjustment 206-2 Manhole Raising Rings 207-3 Precast Reinforced Concrete Manhole Base
PART II-2 – FY26 SEWER RELINING & POINT REPAIR PROJECT II-2 05/08/2025
224-3 Support for Conduits across Trenches
Los Angeles County Department of Public Works (LACDPW)
2021-1 Bedding for Sewer Pipe 2027-1 Allowable Trench Widths
BID ITEM 1. PIPE CLEANING AND CCTV INSPECTION
Payment for Bid Item 1 will be made at the contract unit price per Linear Foot which shall include:
All costs for furnishing all labor, materials, tools, equipment and for doing all the work involved in pipe cleaning and CCTV inspection, complete in place, 2- to 20-inch diameter vitrified clay pipe sanitary sewer including mainline wyes, where required.
Payment for cleaning and CCTV inspection of the sewer pipes shall be made at the unit prices paid per Bidder’s Proposal for various diameter pipes for cleaning and shall be based on the actual length of the pipe between manholes. If the City directs the Contractor to perform additional or heavy cleaning, payment for the work will be made at the unit bid price and shall be based on the hours of work performed on the cleaning procedure in order to achieve the above requirements per Bid Item
20. All payments shall constitute full compensation for mobilization and traffic control, furnishing all labor, materials, equipment, debris disposal, and incidentals required to complete the work, and no additional payment will be made therefor.
SEWER LINE CLEANING
Cleaning of the sewer lines shall be done in accordance with Section 500-3 of the Standard Specifications.
A. Protection of Existing Facilities - The Contractor shall ensure that the cleaning equipment does not damage or cause flooding of public or private property. Care shall be exercised to prevent pipe damage.
B. Cleaning Procedure - A minimum of two passes shall be made with hydrocleaning equipment.
Cleaning shall continue until the pipeline is restored to a minimum of 95 percent of the original diameter for all sewer pipes.
C. Root cutting - A minimum of two passes shall be made with equipment for root removal where roots are encountered, and shall include rodding machines, bucket machines, root cutters, porcupines, pigs, high-velocity jet cleaners, and chain-beaters as necessary to remove roots.
Roots shall be removed until the pipeline is restored to a minimum of 95 percent of the original diameter.
D. Material Removal - All sludge, dirt, sand, rocks, roots, grease, and other solid or semi-solid material resulting from the cleaning operation shall be removed at the downstream manhole of the reach being cleaned. Passing material from sewer reach to sewer reach which could cause line stoppages or accumulations of sand in sewer manholes is not permitted.
E. Material Disposal - All solids or semi-solids resulting from the cleaning operations shall be removed from the site and disposed of at a suitable sanitary landfill site as defined by Titles 22 and 23 of the California Administrative Code. All materials shall be removed from the site no less often than at the end of each workday. Under no circumstances shall the Contractor be allowed to accumulate debris at the work site beyond a single workday, except in totally enclosed
PART II-2 – FY26 SEWER RELINING & POINT REPAIR PROJECT II-3 05/08/2025
containers and as approved by the City. All material shall be disposed at an adequate disposal site. Contractor shall select disposal location and dispose material and no additional payment will be made therefor.
TELEVISION INSPECTION
Closed Circuit Television (CCTV) inspection shall be done after sewer pipe cleaning. CCTV shall be done in accordance with Section 500-3.4 of the Standard Specifications. Pan-and-tilt cameras are the only video camera system allowed to perform such operation.
The Contactor shall provide the City a Closed Circuit Television (CCTV) inspection video prior to rehabilitation and post cleaning of the pipe. Video inspections and reports shall be recorded on a digital storage device that follows NASSCO’s Pipeline Assessment Certification Program (PACP).
BID ITEM 2. POST LINING CCTV INSPECTION
Payment for Bid Item 2 will be made at the contract unit price per Linear Foot which shall include:
All costs for furnishing all labor, materials, tools, equipment and for doing all the work involved in post lining CCTV inspection, complete in place, 4- to 18-inch diameter vitrified clay pipe sanitary sewer including mainline wyes, where required.
The Contactor shall provide the City a Closed Circuit Television (CCTV) inspection video of the complete lining work and sewer lateral connection sealing system “Top Hat” installation, including the reopening of the sewer house connections in accordance with Section 500-9 of the Standard Specifications. The video shall have description of the pipe and dated with incremented footage markings. All material or workmanship defects found in the installation of the service lateral connection sealing system and the installation of the finished liner, including, but not limited to, holes, foreign inclusions, dry spots, pinholes, wrinkles, fins, delamination, deflections, sags, or voids between the liner and pipe, shall be repaired. If any material or workmanship defects are discovered during inspection, the Contractor will be responsible for the repair with the Engineer’s approval on the repair procedure at no additional cost to the City.
The Contactor shall provide the City a Closed Circuit Television (CCTV) inspection video post-lining of the pipe. Video inspections shall be recorded on a digital storage device that follows NASSCO’s Pipeline Assessment Certification Program (PACP).
Payment for the post lining CCTV inspection of 4- to 18-inch diameter pipes shall be based on unit price per Bidder’s Proposal and shall constitute full compensation for mobilization and traffic control, the furnishing of all labor, materials, equipment, and incidentals necessary to complete the work and no additional payment will be made therefor.
BID ITEM 3-9. POINT REPAIR 4- TO 18-IN DIA. PIPE
Payment for Bid Item 3-9 will be made at the contract unit price per Linear Foot which shall include:
Full compensation for the pipes, couplings, excavation, shoring and bracing, pipe and coupling installation, backfilling, pipe bedding, trench compaction, asphalt street restoration, concrete street restoration, restoration of private improvements through easements, reconnection of building/house
PART II-2 – FY26 SEWER RELINING & POINT REPAIR PROJECT II-4 05/08/2025
connection sewers, refurbishment of any obliterated or damaged traffic striping, the restoration of traffic signal loops, the restoration of any other public improvement disturbed during the construction of the point repair, and incidentals required to perform the work.
Payment for the installation of 4- to 18-inch Vitrified Clay Pipe shall be based on unit price per Bidder’s Proposal and shall constitute full compensation for mobilization, the furnishing all labor, materials, equipment, and incidentals necessary to complete the work and no additional payment will be made therefor.
PIPE BEDDING/BACKFILL
Pipe bedding material shall consist of imported crushed sands or gravels conforming to Section 306-6 of the Standard Specifications.
Unless otherwise shown on the Plans or provided in the Special Provisions, the trench excavation and pipe bedding shall conform to Los Angeles County Department of Public Works Standard Plan 2021-
1. Bedding material shall also conform to the sand equivalent and permeability requirements of the Standard Specifications. The bedding for sewer pipes shall be in accordance with LACDPW Standard Plan 2021-1.
Any cobble, boulders, and soft, loose, or disturbed soil at the bottom of the trench shall be excavated and replaced with suitable bedding material. Native soils may be used as backfill material above the pipe bedding zone. However, cobbles and boulders larger than six inches shall not be used as backfill, and the Contractor shall have a licensed Geotechnical representative onsite to provide compaction testing. In lieu of compaction testing requirements, Contractor may use a one-sack slurry for backfill.
If soil is imported for use as backfill, it shall meet the requirements of Section 306-12 and subsection 301-1.3 of the Standard Specifications.
Backfill materials shall not be placed and compacted over utilities until the backfill under the utility has been compacted to the required density and provides firm support.
TRENCH BACKFILL
One sack cement sand slurry trench backfills shall be done in accordance with the City of Pasadena Standard Drawing No. S-416 and S-417. Payment for the trench backfill shall be included in the various unit prices paid for the vitrified clay pipes.
PIPE SUPPORTS
The cost of pipe supports shall be included in the unit prices paid for the replacement of vitrified clay pipes and no additional payment shall be made therefor. Water pipes shall be supported per City of Pasadena Standard Drawings No. S-299. All other pipes shall be supported per APWA Standard Plan 224-3.
SHORING AND BRACING
Shoring and bracing shall be provided as required by Section 7-10.4.2 of the Standard Specifications and LACDPW Standard Plan 3090-1.
All other excavations five (5) or more feet in depth shall be shored such that the sides will be supported in accordance with the requirements set forth on LACDPW Standard Plan 3090-1, which has been approved by the Division of Industrial Safety of the California Department of Industrial Relations. Such shoring shall be designed by a Civil or Structural Engineer, registered as such in the State of California. Wherever in Standard Plan 3090-1, the term Department is used, it shall be
PART II-2 – FY26 SEWER RELINING & POINT REPAIR PROJECT II-5 05/08/2025
understood to mean Department of Public Works of the City of Pasadena.
Excavations less than five (5) feet in depth need not be shored unless they are made at locations or in types of soil where hazardous ground movement may be expected, in which case the excavations shall be shored as specified herein above.
The provision of shoring and bracing in accordance with the above shall not relieve the Contractor of his responsibility for the full protection of his workmen, the general public, and existing facilities, in connection with excavation operations.
PAVEMENT REMOVAL AND RESTORATION
Asphalt concrete and concrete pavement shall be removed in accordance with Section 401 of the Standard Specifications. Bituminous resurfacing of trenches and other excavations in streets or alleys shall be done in accordance with Pasadena Standard Plan S-416. Asphalt concrete pavement shall be restored in accordance with Standard Specification Section 306-13.2, City of Pasadena Standard Drawing S-416, and the following paragraphs. Concrete pavement shall be restored in accordance with Standard Specification Section 306-13.2, City of Pasadena Standard Drawing S-417, S-422, and the following paragraphs.
Unless otherwise shown on the Plans or specified in the Project Special Provisions, the thickness of bases, subbases, and Portland cement concrete pavement, drive aprons, and sidewalk shall be as follows:
• Base and Subbase - Equal to existing
• Asphalt Concrete Pavement – 1” thicker than existing (minimum = 4" for local/collector streets and 6” for major streets)
• Portland Cement Concrete - 1” thicker than existing (minimum = 6" for alleys and 8” for streets)
• Drive Aprons - Equal to existing (minimum = 6")
• Sidewalk - Equal to existing (minimum = 4")
For composite pavement, the asphalt concrete portion shall match the thickness of existing asphalt concrete overlay, and the Portland cement concrete portion shall be equal to existing plus (minimum 6” thick).
For Portland Cement Concrete pavement, see Pasadena Supplement 302-6.
Where work is within a State highway right-of-way, California Department of Transportation requirements shall govern only if greater than the above thickness.
It is the responsibility of the contractor to check to utility lines that may be interfering with locations of repair. Any damage to utility lines in the process of repairing sanitary sewer pipes shall be repaired immediately by the contractor with no additional payment from the City.
RESTORATION OF PRIVATE IMPROVEMENTS
When private improvements must be altered or temporarily removed in order to provide construction access, such improvements shall be restored to their prior condition. Private improvements through easements can consist of landscaping, irrigation systems, driveways, walkways, miscellaneous concrete, fences, walls, retaining walls, and other improvements.
PART II-2 – FY26 SEWER RELINING & POINT REPAIR PROJECT II-6 05/08/2025
All private driveway improvements shall be restored to existing conditions and replaced in kind. No additional payment will be made for the use of high early strength concrete or other material.
REOPEN BUILDING/HOUSE CONNECTION
Upon completion of the replacement, point repair, or the installation of pipe liner, the Contractor shall reopen all existing active sewer building/house connections in accordance with Section 500-8 of the Standard Specifications. The Contractor is responsible for determining the exact number and locations of all active house connections during the pre-lining video inspection. Any uncertain house connection or opening will be considered active.
Sewer connections to all businesses shall be operational during normal business hours; sewer connections to all residences shall be operational between the hours of 6:00 a.m. and 10:00 p.m.;
and sewer connections to all restaurants and bars shall be operational from one hour before opening time to one hour after closing time.
BID ITEM 10. INSTALL 4-FT SECTIONALS
Payment for Bid Item 10 will be made at the contract unit price per Each which shall include:
Installation of Sectional Point Repair Cured-In-Place-Pipe (CIPP) Rehabilitation System may be needed for locations where surface excavated point repairs are not practical, generally 2-10 feet areas on average but up to 30 feet. The material shall be pulled into place through existing manholes and ambient cured or heat cured.
Sectional price shall be paid as ‘each’ which includes sectionals up to 4 feet, and include full compensation for the pipes, couplings, excavation, shoring and bracing, pipe and coupling installation, backfilling, pipe bedding, trench compaction, asphalt street restoration, concrete street restoration, restoration of private improvements through easements, reconnection of building/house connection sewers, refurbishment of any obliterated or damaged traffic striping, the restoration of traffic signal loops, the restoration of any other public improvement disturbed during the construction of the point repair, and incidentals required to perform the work and will be considered full compensation for placement of the sectional and any required appurtenant work including mobilization, traffic control, labor, equipment and materials.
BID ITEM 11-15. INSTALL 4- TO 18-IN DIA. CIPP LINER
Payment for Bid Item 11-15 will be made at the contract unit price per Linear Foot which shall include:
All costs for furnishing all labor, materials, tools, and equipment, and for doing all the work involved in installation of 4- to 18-inch diameter Cured-In-Place (CIPP) Liner, complete in place, in accordance with Section 500-5.5 of the Standard Specifications, including reconnection of laterals, trimming protruding laterals or other obstructions, and all incidentals, as directed by the Engineer.
The liner when cured shall extend the full length of the original pipe and provide a structurally sound, smooth, joint-less and watertight pipe. All lining materials are required to be in accordance with ASTM D5813 and use either ASTM F1216, inversion process, or F1743, pull-in-place process, and are subject to review and approval by the Engineer.
PART II-2 – FY26 SEWER RELINING & POINT REPAIR PROJECT II-7 05/08/2025
The structural performance of the finished pipe shall be adequate to accommodate all anticipated loads throughout a 50-year design life. No cured-in-place pipe rehabilitation technology will be allowed that requires bonding to the existing pipe for any part of its structural strength. To ensure the thinnest wall possible, allow for future rehabilitation of the remaining pipeline, and enable adequate mitigation of shrinkage, the liner shall conform to the minimum structural standards of ASTM D-790 and ASTM D-638.
Any defect, which will or could affect the structural integrity, strength, capacity, or future maintenance of the installed liner, shall be repaired at the Contractor’s expense, in a manner approved by the Engineer.
Both ends of the cured liner shall be cut flush at the inlet and outlet points in the manhole and sealed with an epoxy or resin mixture compatible with the liner/resin system, providing a watertight seal. Sealing material and installation method shall be submitted and approved by the Engineer prior to start of construction.
After the liner has been properly cured, the Contractor shall internally reopen the existing building/house sewer connections per Bid Item 3-8 of these specifications. Internal reinstatement of laterals shall be performed by a qualified individual with experience in successful internal lateral cuttings. The cutting device shall produce a neat, clean and smooth opening of at least 95% of the existing side sewer lateral circumference.
Post-lining video inspection, per Bid Item 2 of these Specifications, shall be done demonstrate that the liner has adhered to the host pipe and is free of defects.
Payment for the installation of 4- to 18-inch diameter Cured-In-Place-Pipe (CIPP) Liner shall be based on unit price per Bidder’s Proposal and shall constitute full compensation for mobilization, the furnishing all labor, materials, equipment, and incidentals necessary to complete the work and no additional payment will be made therefor.
BID ITEM 16. INSTALL TOP HAT LATERAL SEALS
Payment for Bid Item 16 will be made at the contract unit price per Each which shall include:
Installation of Service lateral connection sealing systems or commonly known as “Top Hats” in active sewer lateral connections with root intrusion or as directed by the Engineer in accordance with Section 500-5.5 of the Standard Specifications and this section. Contractor shall conduct pre-cleaning video inspection of the sewer main lines to identify sewer lateral locations with root intrusion.
Service lateral connection sealing systems are to be installed without excavation, by using resin-impregnated flexible fiberglass inserts with sealing epoxy elements in the form of a top hat that will be installed into the existing sewer lateral utilizing a pressure apparatus and steam or hot water curing device positioned in the sewer mainline pipe. Sewer lateral connections consist of tee's, wye's or break-in taps of varying size and angle from 30 to 90 degrees and may include over-cut lateral openings, pilot holes or defects in relined sewer pipe. The resin shall be rapidly cured to transform the flexible insert into a hard, impermeable top hat seal around and in the lateral connection. The service lateral connection sealing system shall extend from the mainline into the lateral connection in a continuous tight fitting, watertight pipe-within-a-pipe to eliminate any visible ground water leakage and future root growth at the sewer lateral to sewer mainline connection.
PART II-2 – FY26 SEWER RELINING & POINT REPAIR PROJECT II-8 05/08/2025
The service lateral connection sealing system shall be a fiberglass laminate impregnated with a polyester-resin which when cured is chemically resistant to domestic sewage over the expected lifetime of the rehabilitated pipe. The service lateral connection sealing system shall be compatible with the lining system utilized for the main sewer line and/or lateral sewer lines.
The flexible fiberglass service lateral connection sealing system insert shall be fabricated to a size that when installed will key into the internal surface irregularities of the lateral joint and neatly fit tight to the internal circumference of the sewer lateral. The service lateral connection sealing system shall be a laminate made of non-woven fiberglass materials that allow for circumferential stretching and angular alignment with the lateral pipe connection geometry during insertion. The insert laminate shall seal to the inside wall of the sewer main 3 inches around the sewer lateral opening and to the sewer lateral wall 6 inches up into the sewer lateral pipe from the main. Unless otherwise specified, the installer shall furnish a specially formulated polyester resin and catalyst system compatible with the service lateral connection sealing system process that provides cured physical strength at least to the same level as required for the sewer lateral liner if specified. A secondary epoxy-sealing component shall be used to form a sealing bond between the service lateral connection sealing system and the host lateral and main sewer pipe walls.
The service lateral connection sealing system shall be fabricated from materials which when cured will be chemically resistant to withstand internal exposure to domestic sewage and shall meet the chemical resistance requirements of Section 500-5.5.4 of the Standard Specifications for Public Works Construction (Chemical Resistance Test, “Pickle Jar Test”). The structural performance of the finished pipe must be adequate to accommodate all anticipated loads throughout its design life. The service lateral connection sealing system shall conform to ASTM 0790.
Prior to the installation of the service lateral connection sealing system, the area around the lateral sealing surface in both the sewer mainline and the sewer lateral, shall be cleaned by using high pressure water jetting or a robotic cleaner when necessary. Contractor is to remove roots and debris at the sewer lateral connections to clearly show the sewer lateral in the video. Break-in connections and/or lateral pipes protruding into the mains shall be ground back to no more than a 1/8-inch protrusion into the mainline. Built-up deposits on the sewer main and sewer lateral pipe walls shall be removed. The removal shall reach at least one foot beyond the service lateral connection sealing system to allow the bladder to inflate tightly against the pipe walls ensuring a smooth transition from the service lateral connection sealing system to the existing pipe wall. In relined pipes the sewer lateral must be opened 95 percent or more and edges finished without "teeth". Over-cuts shall not exceed one inch beyond the internal diameter of the lateral. The Contractor shall be responsible, if needed, for bypassing of sewage during the installation of the service lateral connection sealing system. In cases where the temporary backup of sewage is accepted as a replacement for bypassing, the Contractor is responsible for all damage caused by the backup. City must approve sewer bypass prior to installation. Contractor is to operate and maintain service of sewer main at locations where the service lateral connection sealing systems are to be installed per Bid Item 3-8 of these specifications.
During construction, a City inspection is required to confirm means, methods, and materials.
Installation of the service lateral connection sealing systems shall not, in any way, damage or adversely affect the sewer mainline. The resin impregnated service lateral connection sealing system shall be loaded on the applicator apparatus, attached to a robotic manipulator device and positioned in the mainline pipe at the service connection that is to be rehabilitated. The robotic device together with a television camera will be used to align the service lateral connection sealing system with the sewer lateral connection opening. Air pressure, supplied to the applicator through an air hose, shall be used to insert the resin impregnated connection repair product into the sewer lateral pipe. The insertion pressure will be adjusted to fully deploy the service lateral connection sealing system into
PART II-2 – FY26 SEWER RELINING & POINT REPAIR PROJECT II-9 05/08/2025
the sewer lateral connection and hold the service lateral connection sealing system tight to the main and lateral pipe walls. The inserted product will then be inspected using a CCTV camera to confirm that the service lateral connection sealing system is correctly positioned and/or centered in the sewer lateral opening prior to curing.
The pressure apparatus shall include a bladder of sufficient length in both the main and lateral lines such that the inflated bladder extends beyond the ends of both the lateral tube and main line brim segments of the service lateral connection sealing system pressing the end edges flat against the internal pipe wall thus forming a smooth transition from the service lateral connection sealing system to pipe diameters without a step, ridge or gap between the service lateral connection sealing system and the inner diameters of the lateral and mainline pipes. After insertion is completed, recommended pressure must be maintained on the impregnated service lateral connection sealing system for the duration of the curing process. The packer is then deflated, removed from connection and returned to the manhole to repeat the cycle. The finished service lateral connection sealing system shall be free of dry spots, lifts and delamination. The installed service lateral connection sealing system should not inhibit the post installation video inspection, using a closed-circuit television camera, of the sewer mainline and sewer lateral pipes or future pipe cleaning operations. After the work is completed, the Contractor will provide the City with an electronic picture and recorded data identifying the location and showing the completed work and restored condition of all the rehabilitated sewer lateral connections with service lateral connection sealing systems. During the warranty period any defects with the service lateral connection sealing systems “Top Hats” that affect the performance or cleaning of the sewer lateral connection shall be repaired at the Contractor's expense in a manner acceptable to the City. A post construction video of the repair in the sewer lateral and in the sewer main is required prior to a passing inspection. If the post construction video fails, a new service lateral connection sealing system “Top Hat” will be required at the discretion of the inspector or Engineer.
Payment for service lateral connection sealing systems “Top Hats” shall be based on an each unit price paid in the Bidder’s Proposal and shall include full compensation for all labor, the removal of roots and soft deposits inside the lateral pipe for a distance of 2 feet up the lateral from the mainline connection, sewer lateral connection preparation including rounding or removing sharp or pointed cutout edges in are lined or break-in lateral opening, the removal of protruding sewer lateral pipes materials down to within 1/8 inch of mainline sewer wall, the installation of service lateral connection sealing system lateral inserts, the pre and post CCTV inspections for service lateral connection sealing system installations, mobilization, traffic control, equipment, material, and any appurtenant work.
BID ITEM 17. INSTALL NEW MANHOLE
Payment for Bid Item 17 will be made at the contract unit price per Each which shall include:
The construction of new sanitary sewer manhole shall be done in accordance with City of Pasadena Standard Plan S-382.
Payment for the reconstruction of sanitary sewer manhole shall be based on unit price per Bidder’s Proposal and shall constitute full compensation for mobilization and traffic control, the furnishing of all labor, materials, equipment, and incidentals necessary to complete the work and no additional payment will be made therefor.
PART II-2 – FY26 SEWER RELINING & POINT REPAIR PROJECT II-10 05/08/2025
BID ITEM 18. RECONSTRUCT MANHOLE CHANNEL
Payment for Bid Item 18 will be made at the contract unit price per Each which shall include:
The reconstruction of the manhole channel shall be done in accordance with APWA Standard Plan 207-3.
Payment for the reconstruction of the sewer manhole channel shall be based on the unit price paid in the Bidder’s Proposal and shall include full compensation for all mobilization, traffic control, labor, equipment, material, and any appurtenant work.
BID ITEM 19. REMOVE AND RECONSTRUCT MANHOLE
Payment for Bid Item 19 will be made at the contract unit price per Each which shall include:
The removal and reconstruction of sanitary sewer manhole shall be done in accordance with City of Pasadena Standard Plan S-382.
Payment for the removal and reconstruction of sanitary sewer manhole shall be based on unit price per Bidder’s Proposal and shall constitute full compensation for mobilization and traffic control, the furnishing of all labor, materials, equipment, and incidentals necessary to complete the work and no additional payment will be made therefor.
BID ITEM 20. SEWER MANHOLE FRAME AND COVER ADJUSTMENT
Payment for Bid Item 20 will be made at the contract unit price per Each which shall include:
The manhole adjustment shall be done in accordance with APWA Standard Plan 205-3. Manholes located within Portland Cement Concrete or asphalt concrete pavement shall be adjusted in accordance with Section 403 of the Standard Specifications. The frames and covers for manholes located within unimproved areas shall be raised to 2 inches above the adjacent grade.
The Contractor shall protect existing landscaping and private improvements from damage during construction. Any damage caused by the Contractor shall be repaired to the Engineer's satisfaction at the expense of the Contractor. Heavy equipment such as backhoe or bulldozer shall not be used on the private properties.
Payment for sewer manhole adjustment shall be based on the unit price paid in the Bidder’s Proposal and shall include full compensation for all mobilization, traffic control, labor, equipment, material, And any appurtenant work.
BID ITEM 21. ADDITIONAL HEAVY CLEANING
Payment for Bid Item 21 will be made at the contract unit price per Hour which shall include:
Any Additional or heavy cleaning beyond the cleaning and root cutting procedures listed above may be necessary to televise and install liners for sewer reaches that are seriously infested with roots or have debris or deposits in them. At the City’s discretion, the additional or heavy cleaning may be
PART II-2 – FY26 SEWER RELINING & POINT REPAIR PROJECT II-11 05/08/2025
performed by the Contractor. No additional or heavy cleaning shall be undertaken by the Contractor without prior approval of the City.
Material Removal - All sludge, dirt, sand, rocks, roots, grease, and other solid or semi-solid material resulting from the cleaning operation shall be removed at the downstream manhole of the reach being cleaned. Passing material from sewer reach to sewer reach which could cause line stoppages or accumulations of sand in sewer manholes is not permitted.
Material Disposal - All solids or semi-solids resulting from the cleaning operations shall be removed from the site and disposed of at a suitable sanitary landfill site as defined by Titles 22 and 23 of the California Administrative Code. All materials shall be removed from the site no less often than at the end of each workday. Under no circumstances shall the Contractor be allowed to accumulate debris at the work site beyond a single workday, except in totally enclosed containers and as approved by the City. All material shall be disposed at an adequate disposal site. Contractor shall select disposal location and dispose material, and no additional payment will be made therefor.
Payment for heavy cleaning shall be based on the unit price paid in the Bidder’s Proposal and shall include full compensation for all mobilization, traffic control, labor, equipment, material, and any appurtenant work.
BID ITEM 22. SEWER MANHOLE CONDITION EVALUATION
Payment for Bid Item 22 will be made at the contract unit price per Each which shall include:
All costs for furnishing all labor, materials, tools, equipment and for doing all the work involved in sewer manhole condition assessment, where required.
Payment for the assessment of the sanitary sewer manhole shall be made at the unit prices paid per Bidder’s Proposal for various condition and location of the manholes, city-wide. All payments shall constitute full compensation for mobilization and traffic control, furnishing all labor, materials, equipment, debris disposal, and incidentals required to complete the work, and no additional payment will be made therefor.
This scope is to conduct visual, non-entry assessments of selected sanitary sewer manholes using NASSCO’s Manhole Assessment Certification Programs (MACP) Level 1 standards. The data collected will support condition evaluation, asset inventory, and GIS-based planning. The city will provide a GIS map application of the city’s sanitary sewer manholes for data gathering purposes. All manholes will be geolocated, and inspection results will be documented using this system.
SEWER MANHOLE CONDITION EVALUATION
A. Field Inspections - The Contractor shall perform visual inspections (NASSCO MACP Level 1) of sewer manholes located within the public right-of-way or City-owned easements and record the following information per NASSCO’s MACP Level 1 Standards:
a. Manhole material and construction (frame, cone, barrel, bench, channel)
b. Defects (cracks, corrosion, infiltration, root intrusion, missing steps, etc.)
c. Operational conditions (blockages, sediment, surcharge evidence)
d. Surface access conditions (locked lids, buried covers, traffic hazards)
PART II-2 – FY26 SEWER RELINING & POINT REPAIR PROJECT II-12 05/08/2025
B. GPS Location and GIS Integration - Record high-accuracy GPS coordinates (sub-meter preferred;
1–3 meter minimum) for each manhole, and correct GIS mapping as needed. Contractor shall provide GIS shapefile or geodatabase with manhole condition scores, defect codes, notes, inspection dates, and media links. Attribute fields must match City schema, or a mapping table must be provided.
C. Data Management and Deliverables – Code defects noted by the Contractor shall be in compliance with NASSCO’s MACP Level 1 standards. Contractor to provide MACP-compliant digital inspection database, geo-referenced photo log or video stills of significant findings, PDF summary report that includes overview of inspected assets and condition distribution, photos of typical defects or issues, and recommendations for further assessment or repairs, and a QA/QC plan and summary of how inspections were reviewed for accuracy. Contractor shall provide in-person presentation of the summary of the inspection findings.
D. Submittals – Contractor shall submit the following requirements prior to start of work:
a. List of NASSCO-certified staff who will be assigned to this project.
b. Summary of recent, similar projects completed in the last 3 years.
c. Description of equipment used for inspection and GPS capture.
d. Sample of MACP report and GIS integration from a previous project.
e. Estimated project schedule.
BID ITEM 23. ALLOWANCE
Payment for Bid Item 23 will consist of time and material, or cost proposal work due to unforeseen circumstances that may arise during construction. The costs associated with time and material, or cost proposals shall not exceed the $100,000 limit established herein.
TRAFFIC CONTROL
All traffic control procedures shall be implemented according to guidelines as set forth in the Work Area Traffic Control Handbook (W.A.T.C.H.) Manual.
In addition to the requirements of the Work Area Traffic Control Handbook (WATCH) manual, latest edition, and the California Manual on Uniform Traffic Control Devices (CAMUTCD) handbook, the Engineer may require flatter traffic taper for maintaining traffic control. In addition, the Contractor will be required to provided traffic control devices such as barricades, delineators, advance warning signs, flagman and other signing in order to ensure driver awareness and safety in the construction area. Payment for this work is deemed to be included in the various related bid items in the Bidder’s proposal.
The Contractor shall maintain continuous access for residents and businesses within the project limits. Any closed access or drive approach shall be immediately restored when the construction operation that necessitated such closure is completed. The following is a partial list of factors required to comply with this access requirements:
a. Where a business or residence has more than one two-way drive, continuous access to at least one two-way drive shall be maintained at all times.
PART II-2 – FY26 SEWER RELINING & POINT REPAIR PROJECT II-13 05/08/2025
b. A business or residence that has a drive approach that is at least 22 feet wide shall be poured in halves in order to maintain continuous access.
c. In addition to the above, the Contractor shall be required to construct temporary ramps at excavated area and utilize other construction methods such as temporary backfilling areas and surfacing with temporary A.C. paving, in order to comply with the requirements of continuous access unless otherwise directed by the Engineer.
d. The posting of "NO PARKING" signs within the construction limits is permitted with the approval of the Engineer. "NO PARKING" signs shall contain a "TOW AWAY" warning.
These signs shall be furnished and maintained by the Contractor and shall be of the type approved by the Engineer. Each sign posted shall have the date and time indicating the duration of the "NO PARKING" prohibition printed clearly in a manner acceptable to the Engineer, and not handwritten. New signs shall be posted when changes occur in the parking prohibitions indicated on the previously posted signs. Signs must be posted a minimum 48 hours in advance of construction or they are invalid. Signs shall not be attached to trees or taped to street lights or traffic signal poles. The signs shall be removed at the end of the day the paving is completed.
e. In the event of full closure, advance notice through the placement of changeable message signs shall be required at least 3 business days in advance. Payment for furnishing and installing the changeable message signs shall be included in the various related bid items in the Bidder’s Proposal and no additional payment will be made.
The cost for traffic control including changeable message signs shall be considered as included in the base bid of the project.
Notification of Affected Residents/Businesses - The Contractor shall be responsible for distribution of the general information letter in a door hanger as prepared by the Contractor for City’s approval to all affected residents and businesses. Notification shall include information about material, installation procedures, duration of the project, contractor’s contact information, and sewer lining Frequently Asked Questions such as odor during construction, what should be done if odor is encountered, limit of sewer facility use during construction. Notification shall be at least two (2) working days in advance for regular work hours, and at least five (5) working days in advance for night work. No work on street shall begin unless said notification has been made. The failure of the Contractor to strictly comply with the notification requirements may result in the Engineer initiating a suspension of work without time extension until the problem is resolved.
Additional notification to the affected businesses and residents shall be prepared and distributed by the Contractor, as approved by the City, for driveway closures and roadway paving operation five working days in advance of the work. No removals work is allowed until the additional notification has been distributed to the affected residents and businesses.
PART II-2 – FY26 SEWER RELINING & POINT REPAIR PROJECT II-14 05/08/2025
In the event there is a disconnect in coordination for driveway accessibility, the Contractor shall be responsible for providing steel plates for immediate driveway accessibility, as required by business and residents. Contractor shall provide a detail map of locations where Notices have been distributed the same day.
For sewer mains and manholes within easements, the Contractor shall be responsible for preparation and distribution of Right-of-Entry (ROE) letters for City’s approval to all affected residents and businesses.
All notifications used on this project shall be reviewed and approved by the Engineer prior to their issuance by the Contractor to affected businesses and residents. Also, a copy of each notification issued shall be provided to the Engineer.
Where existing delineation is obscured, damaged, removed, or reflectivity reduced; or where detours or temporary traffic lanes have been created through the construction zone, the CONTRACTOR shall place and maintain temporary delineation until permanent striping is placed.
The cost for “notification to affected residents/businesses” shall be included in the various bid items, and no additional compensation will be allowed therefor.