PARKING GARAGE REPAIRS.pdf
PDF 8 MB Posted
- Solicitation number
- 02-2617 / PN# JB24-043
- Issued by
- Hartford County, Connecticut
About this file
This is a Project Manual for parking garage repairs at the Stamford Superior Court, prepared by the State of Connecticut Judicial Branch in partnership with HF Lenz Engineering. The project involves comprehensive rehabilitation and structural repairs at 123 Hoyt Street, Stamford, Connecticut, including plaza drains, trench drains, plaza slabs, driveway surfaces, and roof repairs, along with structural steel framing demolition and replacement, structural decking work, concrete wall and column repairs, and brick veneer repointing. The contractor must mobilize and commence construction no later than 14 calendar days after issuance of a Purchase Order and complete all work within 180 days from that date. Critical submittals including the Site Logistics Plan, Phasing/Sequence Plan, construction schedule, and schedule of values must be submitted within 7 calendar days of the Purchase Order issuance. Project closeout must be completed within 60 calendar days from substantial completion. The Engineer's Representative is Scott Kraynak at HF Lenz, with the Owner's Representative identified as Brian A. Dillon, Deputy Director of Judicial Branch Facilities.
The contract includes five allowances totaling $75,000: $10,000 for third-party material testing and inspections, $5,000 for unforeseen MEP repairs, $20,000 for additional modified bitumen roof systems, $10,000 for additional masonry repointing, and $30,000 for additional concrete cutting and patching. Two unit prices are established for concrete cutting and patching (per 300 square feet) and miscellaneous structural steel (per 1,000 pounds). Contractors must maintain 10 percent retainage on all payments and comply with work hour restrictions of 7 a.m. to 5 p.m. Monday through Friday, with weekend work permitted from 9 a.m. to 4 p.m. The Owner reserves the right to halt work if operations become disruptive to court proceedings and may require completion of disruptive activities outside normal business hours at no additional cost. All contractor personnel require identification tags, may be subject to drug screening, and must sign in/out daily with Owner representatives. The project operates under full Owner occupancy, requiring 72-hour advance notice for activities affecting operations.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT MANUAL
PARKING GARAGE REPAIRS
AT
STAMFORD SUPERIOR COURT
123 HOYT STREET
STAMFORD, CONNECTICUT 06905
STATE OF CONNECTICUT
JUDICIAL BRANCH FACILITIES
90 WASHINGTON STREET
HARTFORD, CONNECTICUT 06106
Judicial Branch PN# JB24-043
ENGINEER:
HF Lenz
Engineer’s PN# 2025-1807.01
April 13, 2026
HON. RAHEEM L. MULLINS
CHIEF JUSTICE
HON. JOAN K. ALEXANDER
CHIEF COURT ADMINISTRATOR
SEALS PAGE
SECTION 000105
JUDICIAL BRANCH
HF Lenz Stamford Parking Garage Repairs
2025-1807.01 JB24-043
SECTION 000105 – SEALS PAGE
ARCHITECT:
Architectural Firm Name
(Seal and Signature)
Architect Professional Certi-fication:
I hereby certify that these documents were prepared or approved by me and that I am a duly registered Architect.
Civil Engineer Professional
Certification:
I hereby certify that these documents were prepared or approved by me and that I am a duly registered Professional
Engineer.
(Print Consultant Name) (Print Consultant Name)
License No. License No.
Expiration Date Expiration Date
Structural Engineer Profes-sional Certification:
I hereby certify that these documents were prepared or approved by me and that I am a duly registered Professional
Electrical Engineer Profes-sional Certification:
I hereby certify that these documents were prepared or approved by me and that I am a
David A. Blackner
26877
License No. License No.
01/31/2027
Mechanical Engineer Profes-sional Certification:
I hereby certify that these documents were prepared or approved by me and that I am a duly registered Professional
Fire-Protection Engineer
Professional Certification:
I hereby certify that these documents were prepared or approved by me and that I am a
License No. License No.
END OF SECTION 000105
TABLE OF CONTENTS
SECTION 000110
SECTION 000110 – TABLE OF CONTENTS
Section No. Title Page Count Not Used
00 00 00 Manual Cover 1 □ 00 01 05 Project Team Seals Page 1 □ 00 01 10 Table of Contents & Checklist 2 □ 00 01 15 List of Drawing Sheets 1 □ 00 01 20 Project Team List 1 □
DIVISION 01 GENERAL REQUIREMENTS
01 10 00 Summary of Work 5 □ 01 21 00 Allowances 4 □ 01 22 00 Unit Prices 2 □ 01 23 00 Alternates - X 01 25 00 Substitution Procedures 4 □ 01 26 00 Contract Modification Procedures 3 □ 01 29 00 Payment Procedures 5 □ 01 31 00 Project Management and Coordination 9 □ 01 32 00 Construction Progress Documentation 7 □ 01 32 33 Photographic Documentation 3 □ 01 33 00 Submittal Procedure 8 □ 01 35 16 Alteration Project Procedures 6 □ 01 40 00 Quality Requirements 10 □ 01 40 01 Statement of Special Inspections 11 □ 01 50 00 Temporary Facilities and Controls 6 □ 01 60 00 Product Requirements 7 □ 01 73 00 Execution 9 □ 01 77 00 Closeout Procedures 6 □ 01 78 23 Operation and Maintenance Data 5 □ 01 78 39 Project Record Documents 4 □
DIVISION 02 EXISTING CONDITIONS
02 41 19 Selective Demolition 6
2025-1807.01 JB24-043
DIVISION 03 CONCRETE
03 01 30 Maintenance of Cast-in-place Concrete 15 03 10 00 Concrete Forming and Accessories 8 03 20 00 Concrete Reinforcing 6 03 30 00 Cast-in-place Concrete 26
DIVISION 04 MASONRY
04 01 20.64 Brick Masonry Repointing 6 04 22 00 Concrete Unit Masonry 19 04 26 13 Masonry Veneer 19
DIVISION 05 METALS
05 12 00 Structural Steel Framing 9 05 31 00 Steel Decking 6 05 50 00 Metal Fabrications 8
DIVISION 07 THERMAL AND MOISTURE PROTECTION
07 01 50.19 Preparation for Reroofing 8 07 14 16 Cold Fluid-Applied Waterproofing 12 07 21 00 Thermal Insulation 3 07 62 00 Sheet Metal Flashing and Trim 17 07 81 00 Applied Fire Protection 6 07 95 13.16 Exterior Expansion Joint Cover Assemblies 7
DIVISION 09 FINISHES
09 63 13 Brick Flooring 9 09 63 40 Stone Flooring 13
DIVISION 22 PLUMBING
22 14 23 Storm Drainage Piping Specialties 6
DIVISION 32 EXTERIOR IMPROVEMENTS
32 14 00 Unit Paving 10
DIVISION 33 SITE UTILITIES
33 46 00 Subdrainage 5
END OF SECTION 000110
DRAWING LIST
SECTION 000115
SECTION 000115 – LIST OF DRAWING SHEETS
GENERAL PROJECT INFORMATION
G001 Cover Sheet
G101 Scope of Work
STRUCTURAL
S100 Overall Building Plan
S101 Structural General Notes
S102 Ground Level Floor Rehabilitation Plan
S103 Connector Building Plaza Floor Rehabilitation Plan
S104 First Floor Plaza Rehabilitation Plan
S201 Basement Level Slab-on-Grade Plan
S202 Ground Level Framing Plan
S203 Connector Building Framing Plan
S204 First Floor Framing Plan
S301 Floor Rehabilitation Sections and Details
S302 Framing Sections and Details
S501 Typical Rehabilitation Details
S502 Typical Concrete and Masonry Details
S503 Typical Steel Details
S901 3D Representations
END OF SECTION 000115
TEAM LIST
SECTION 000120
SECTION 000120 –PROJECT TEAM LIST
PRIME CONSULTANT
ENGINEER:
H. F. Lenz 101 Centerpoint Dr Suite 237 Middletown, CT 06457
Project Contact:
Scott Kraynak, PE skraynak@hflenz.com
(860) 316-2124
Project Engineer:
David A. Blackner, PE dblackner@hflenz.com
(814) 269-9300
Project Designer:
Christopher M. Reighard, PE creighard@hflenz.com
(814) 269-9300
END OF SECTION 000120
SUMMARY
SECTION 011000
2025-1807.01 JB24-043
SECTION 011000 - SUMMARY
PART ONE – GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Project information.
2. Work covered by Contract Documents.
3. Phased construction.
4. Contractor's use of site and premises.
5. Coordination with occupants.
6. Work restrictions.
7. Specification and Drawing conventions.
8. Miscellaneous provisions.
B. Related Requirements:
1. Section 015000 "Temporary Facilities and Controls" for limitations and procedures governing temporary use of Owner's facilities.
2. Section 017300 "Execution" for coordination of Owner-installed products.
1.3 PROJECT INFORMATION
A. Project Identification:
1. Stamford Parking Garage Repairs
2. JB24-043
3. 123 Hoyt Streeet, Stamford, CT 06905
B. Owner: State of Connecticut, Judicial Branch, Office of the Chief Court Administrator, 90 Washington Street, Hartford, CT 06106.
1. Owner’s Representative:
a) Brian A. Dillon
Deputy Director
Judicial Branch Facilities
90 Washington Street
2025-1807.01 JB24-043
Hartford, CT 06106
Office: 860-706-5272
Cell: 860-549-2731 brian.dillon@jud.ct.gov
C. Engineer: H. F. Lenz
1. Engineer's Representative: Scott Kraynak, 860.316.2124
1.4 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work of Project is defined by the Contract Documents and includes, but is not limited to, the following:
1. Rehabilitation Scope of Work for the following:
a. Plaza drains and trench drains.
b. Plaza slabs.
c. Marshall staff entrance driveway, surface and lower ejector pump room roof.
2. Structural Scope of Work for the following:
a. Structural steel framing demolition and replacement.
b. Structural decking demolition and replacement.
c. Removal of existing fireproofing or concrete encasement and evaluate existing member condition for erosion.
d. Structural testing and evaluation of concrete walls.
e. Drill weep holes into existing concrete wall to release hydrostatic pressure.
f. Concrete wall and column repair.
g. Repair spalled and/or cracked brick veneer and mortar joints.
1.5 WORK SEQUENCE
A. Construct the Work in one single phase.
B. Mobilization
1. Project shall mobilize, and construction started no later than fourteen (14) calendar days after issuance of a Purchase Order.
2. The project shall be completed within 180 days from issuance of the purchase order.
C. Submittals
1. The following shall be submitted at the earliest possible date, but no later than seven (7) calendar days from issuance of a “Purchase Order”.
a. Site Logistics Plan
b. Phasing/Sequence Plan
2025-1807.01 JB24-043
c. Contractor’s Construction Schedule
d. Schedule of Values
e. Key Personnel and Contact Information
f. Subcontract List
g. Submittal Log
2. Remaining project submittals shall start no later than seven (7) calendar days from issuance of a Purchase Order, including but not limited to:
a. Project/Site Safety Plan
b. Product/Material submittals
D. Closeout
1. Closeout shall be completed within 60 calendar days from substantial completion.
E. Before commencing Work of each phase, submit an updated copy of Contractor's construction schedule, showing the sequence, commencement and completion dates for all phases of the
Work.
1.6 CONTRACTOR'S USE OF SITE AND PREMISES
A. Limits on Use of Site: Limit use of Project site to Work in areas indicated or resultant areas based on testing and exploratory requirements. Do not disturb portions of Project site beyond areas in which the Work is indicated.
B. Condition of Existing Building: Maintain portions of existing building affected by construction operations in a weathertight condition throughout construction period.
Repair damage caused by construction operations.
C. Condition of Existing Grounds: Maintain portions of existing grounds, landscaping, and hardscaping affected by construction operations throughout construction period. Repair damage caused by construction operations.
1.7 COORDINATION WITH OCCUPANTS
A. Full Owner Occupancy: Owner will occupy Project site and existing building during entire construction period. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's day-to-day operations. Maintain existing exits unless otherwise indicated.
1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and approval of authorities having jurisdiction.
2. Notify Owner not less than 72 hours in advance of activities that will affect
Owner's operations.
2025-1807.01 JB24-043
3. Remove furniture and portable equipment, which interferes with the execution of the Work, and store where directed. Reset such items when directed.
1.8 WORK RESTRICTIONS
A. Comply with restrictions on construction operations.
1. Comply with limitations on use of public streets, Work on public streets, rights of way, and other requirements of authorities having jurisdiction.
B. On-Site Work Hours: Limit Work to between 7 a.m. to 5 p.m., Monday through Friday, unless otherwise indicated. Work hours may be modified to meet Project requirements if approved by Owner and authorities having jurisdiction.
1. Weekend Hours: Weekend Hours: 9 a.m. to 4 p.m.
C. Owner reserves the right to stop Work if it becomes disruptive to the daily business/operation of the Court, court operations facility, and/or detention center.
Disruptive work must be completed outside of normal business hours at no cost to the
Owner.
D. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by
Owner or others unless permitted under the following conditions and then only after arranging for temporary utility services according to requirements indicated:
1. Notify Owner not less than four days in advance of proposed utility interruptions.
2. Obtain Owner's written permission before proceeding with utility interruptions.
E. Noise, Vibration, Dust, and Odors: Coordinate operations that may result in high levels of noise and vibration, dust, odors, or other disruption to Owner occupancy with Owner.
1. Notify Engineer and Owner not less than two days in advance of proposed disruptive operations.
2. Obtain Owner's written permission before proceeding with disruptive operations.
F. Smoking and Controlled Substance Restrictions: Use of tobacco products, alcoholic beverages, and other controlled substances is not permitted.
G. Employee Identification: Provide identification tags and/or company branded clothing for
Contractor personnel working on Project site. Require personnel to use these at all times.
H. Employee Screening: Comply with Owner's requirements for drug and screening of
Contractor personnel working on Project site.
I. Contractor’s personnel shall sign in/out daily with Owner representatives.
2025-1807.01 JB24-043
1.9 SPECIFICATION AND DRAWING CONVENTIONS
A. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:
1. Imperative mood and streamlined language are generally used in the
Specifications. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
2. Text Color: Text used in the Specifications, including units of measure, manufacturer and product names, and other text may appear in multiple colors or underlined as part of a hyperlink; no emphasis is implied by text with these characteristics.
3. Hypertext: Text used in the Specifications may contain hyperlinks. Hyperlinks may allow for access to linked information that is not residing in the
Specifications. Unless otherwise indicated, linked information is not part of the
Contract Documents.
4. Specification requirements are to be performed by Contractor unless specifically stated otherwise.
B. Division 00 Contracting Requirements: General provisions of the Contract, including
General and Supplementary Conditions, apply to all Sections of the Specifications.
C. Division 01 General Requirements: Requirements of Sections in Division 01 apply to the
Work of all Sections in the Specifications.
D. Drawing Coordination: Requirements for materials and products identified on Drawings are described in detail in the Specifications. One or more of the following are used on
Drawings to identify materials and products:
1. Terminology: Materials and products are identified by the typical generic terms used in the individual Specifications Sections.
2. Abbreviations: Materials and products are identified by abbreviations scheduled on Drawings.
PART TWO – PRODUCTS (Not Used)
PART THREE – EXECUTION (Not Used)
END OF SECTION 011000
ALLOWANCES
SECTION 012100
ECTION 012100 – ALLOWANCES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements governing allowances.
Types of allowances include the following:
1. Unit-cost Allowance.
2. Value Allowance.
3. Quantity Allowance.
B. Related Requirements:
1. Section 012200 "Unit Prices" for procedures for using unit prices, including adjustment of quantity allowances when applicable.
Section 012600 "Contract Modification Procedures" for procedures for submitting and handling Change Orders.
1.3 DEFINITIONS
A. Allowance: A quantity of work or dollar amount included in the Contract, established in lieu of additional requirements, used to defer selection of actual materials and equipment to a later date when direction will be provided to Contractor. If necessary, additional requirements will be issued by Change Order.
1.4 SELECTION AND PURCHASE
A. At the earliest practical date after award of the Contract, advise Engineer of the date when final selection, or purchase and delivery, of each product or system described by an allowance must be completed by the Owner to avoid delaying the Work.
At Engineer's request, obtain proposals for each allowance for use in making final selections. Include recommendations that are relevant to performing the Work.
Purchase products and systems selected by Engineer from the designated supplier.
2025-1807.01 JB24-043
1.5 ACTION SUBMITTALS
A. Submit proposals for purchase of products or systems included in allowances in the form specified for Change Orders.
1.6 INFORMATIONAL SUBMITTALS
A. Submit invoices or delivery slips to show actual quantities of materials delivered to the site for use in fulfillment of each allowance.
Submit time sheets and other documentation to show labor time and cost for installation of allowance items that include installation as part of the allowance.
Coordinate and process submittals for allowance items in same manner as for other portions of the Work.
1.7 QUANTITY ALLOWANCES
A. Allowance shall include cost to Contractor of specific products and materials ordered by Owner or selected by Engineer under allowance and shall include taxes, freight, and delivery to Project site.
Unless otherwise indicated, Contractor's costs for receiving and handling at Project site, labor, installation, overhead and profit, and similar costs related to products and materials ordered by Owner or selected by Engineer under allowance shall be included as part of the Contract Sum and not part of the allowance.
Unused Materials: Return unused materials purchased under an allowance to manufacturer or supplier for credit to Owner, after installation has been completed and accepted.
If requested by Engineer, retain and prepare unused material for storage by Owner.
Deliver unused material to Owner's storage space as directed.
1.8 ADJUSTMENT OF ALLOWANCES
A. Allowance Adjustment: To adjust allowance amounts, prepare a Change Order proposal based on the difference between purchase amount and the allowance, multiplied by final measurement of work-in-place where applicable. If applicable, include reasonable allowances for cutting losses, tolerances, mixing wastes, normal product imperfections, required maintenance materials, and similar margins.
Include installation costs in purchase amount only where indicated as part of the allowance.
2025-1807.01 JB24-043
If requested, prepare explanation and documentation to substantiate distribution of overhead costs and other markups.
Submit substantiation of a change in scope of Work, if any, claimed in Change Orders related to unit-cost allowances.
Owner reserves the right to establish the quantity of work-in-place by independent quantity survey, measure, or count.
Submit claims for increased costs due to a change in the scope or nature of the allowance described in the Contract Documents, whether for the purchase order amount or Contractor's handling, labor, installation, overhead, and profit.
Do not include Contractor's or subcontractor's indirect expense in the Change Order cost amount unless it is clearly shown that the nature or extent of Work has changed from what could have been foreseen from information in the Contract Documents.
No change to Contractor's indirect expense is permitted for selection of higher- or lower-priced materials or systems of the same scope and nature as originally indicated.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine products covered by an allowance promptly on delivery for damage or defects.
Return damaged or defective products to manufacturer for replacement.
3.2 PREPARATION
A. Coordinate materials and their installation for each allowance with related materials and installations to ensure that each allowance item is completely integrated and interfaced with related work.
3.3 SCHEDULE OF ALLOWANCES
A. This allowance includes material, receiving, handling, and installation costs, and Contractor overhead and profit.
A. Allowance No. 01: Owner-directed testing/inspections.
Value Allowance: Include the sum of ten-thousand dollars ($10,000) for third-party material testing and site inspections. Work shall be directed by the Owner and coordinated and executed by the Contractor.
2025-1807.01 JB24-043
B. Allowance No. 02: Repair of unforeseen MEP issues and related latent conditions.
Value Allowance: Include the sum of five-thousand dollars ($5,000) for Repair of unforeseen MEP issues and related latent conditions. Work shall be directed by the Owner and coordinated and executed by the Contractor.
C. Allowance No. 03: Additional Modified Bitumen Roof system.
Value Allowance: Include the sum of twenty-thousand dollars ($20,000) for removal and installation of modified bitumen roof system Polyisocyanurate insulation, base coat and topcoat where insulation is saturated with water as specified in Section 070150.19 Preparation for Reroofing and as shown on Drawings.
This allowance includes material cost receiving, handling, and installation and
Coordinate quantity allowance adjustment with corresponding unit-price requirements in Section 012200 "Unit Prices."
D. Allowance No. 04: Additional re-pointing of Masonry (Stone).
Value Allowance: Include the sum of ten-thousand dollars ($10,000) for removal and installation of mortar at stone masonry units, as specified in Section 040127 Repointing with Cement Lime Mortar and as shown on Drawings.
E. Allowance No. 05: Additional Concrete Work
Value Allowance: Include the sum of thirty-thousand dollars ($30,000) for any additional cutting and patching of concrete pads, columns, and walls as directed by the owner.
END OF SECTION 012100
UNIT PRICES
SECTION 012200
2025-1807.01 JB24-043
SECTION 012200 - UNIT PRICES
PART ONE – GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for unit prices.
B. Related Requirements:
1. Section 012100 "Allowances" for procedures for using unit prices to adjust quantity allowances.
2. Section 012600 "Contract Modification Procedures" for procedures for submitting and handling Change Orders.
1.3 DEFINITIONS
A. Unit price is an amount incorporated into the Agreement, applicable during the duration of the Work as a price per unit of measurement for materials, equipment, or services, or a portion of the Work, added to or deducted from the Contract Sum by appropriate modification, if the scope of Work or estimated quantities of Work required by the
Contract Documents are increased or decreased.
1.4 PROCEDURES
A. Measurement and Payment: See individual Specification Sections for work that requires establishment of unit prices. Methods of measurement and payment for unit prices are specified in those Sections.
B. Owner reserves the right to reject Contractor's measurement of work-in-place that involves use of established unit prices and to have this work measured, at Owner's expense, by an independent surveyor acceptable to Contractor.
C. List of Unit Prices: A schedule of unit prices is included in Part 3. Specification Sections referenced in the Part 3 "Schedule of Unit Prices" article contain requirements for materials described under each unit price.
UNIT PRICES
SECTION 012200
2025-1807.01 JB24-043
PART TWO – PRODUCTS (Not Used)
PART THREE – EXECUTION
3.1 SCHEDULE OF UNIT PRICES
D. Unit Price No. 1: Cutting and patching of concrete slabs, columns, and walls.
1. Description: Cutting of existing concrete slabs, columns, or walls up to 6 inches thick, removal and patching of concrete in accordance with Section 017300
"Execution." not otherwise indicated in the Contract Documents.
2. Unit of Measurement: 300 square feet of concrete removed.
E. Unit Price No. 2: Miscellaneous and structural steel.
1. Description: Miscellaneous lintels and other supports not otherwise indicated in the Contract Documents, in accordance with Section 051200 "Structural Steel
Framing" and Section 055000 "Metal Fabrications."
2. Unit of Measurement: Cost in place of 1000 pounds of fabricated steel, as indicated on itemized invoice of steel supplier.
END OF SECTION 012200
SUBSTITUTION PROCEDURES
SECTION 012500
2025-1807.01 JB24-043
SECTION 012500 - SUBSTITUTION PROCEDURES
PART ONE – GENERAL
1.1 RELATED DOCUMENTS
A. Section includes administrative and procedural requirements for substitutions.
B. Related Requirements:
1. Section 012100 "Allowances" for products selected under an allowance.
2. Section 016000 "Product Requirements" for requirements for submitting comparable product submittals for products by listed manufacturers.
1.3 DEFINITIONS
A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents.
1. Substitutions for Cause: Changes proposed by Contractor that are required due to changed Project conditions, such as unavailability of product, regulatory changes, or unavailability of required warranty terms.
2. Substitutions for Convenience: Changes proposed by Contractor or Owner that are not required to meet other Project requirements but may offer advantage to
Contractor or Owner.
1.4 ACTION SUBMITTALS
A. Equals and Substitution Request Submittals: The Owner will consider requests for equals or substitutions if made prior to the Receipt of the Competitive Bid. The information on all materials shall be consistent with the information herein. After the contract award, substitutions will be considered for materials or systems specified that are no longer available. It will not be considered if the product was not purchased in a reasonable time after award.
B. Submit documentation identifying product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.
1. Documentation: Show compliance with requirements for substitutions and the following, as applicable:
a. Statement indicating why specified product or fabrication or installation method cannot be provided, if applicable.
2025-1807.01 JB24-043
b. Coordination of information, including a list of changes or revisions needed to other parts of the Work and to construction performed by
Owner and separate contractors that will be necessary to accommodate proposed substitution.
c. Detailed comparison of significant qualities of proposed substitutions with those of the Work specified. Include annotated copy of applicable
Specification Section. Significant qualities may include attributes, such as performance, weight, size, durability, visual effect, sustainable design characteristics, warranties, and specific features and requirements indicated. Indicate deviations, if any, from the Work specified.
d. Product Data, including drawings and descriptions of products and fabrication and installation procedures.
e. Samples, where applicable or requested.
f. Certificates and qualification data, where applicable or requested.
g. Material test reports from a qualified testing agency, indicating and interpreting test results for compliance with requirements indicated.
h. Detailed comparison of Contractor's construction schedule using proposed substitutions with products specified for the Work, including effect on the overall Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery.
i. Cost information, including a proposal of change, if any, in the Contract
Sum.
j. Contractor's certification that proposed substitution complies with requirements in the Contract Documents, except as indicated in substitution request, is compatible with related materials and is appropriate for applications indicated.
k. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.
2. If necessary, the Engineer will request additional information or documentation for evaluation within seven (7) days of receipt of the original request for equal or substitution request. The Engineer will notify the Construction Administrator who will notify the Owner of recommended acceptance or rejection of the proposed equal or substitution, within fourteen (14) days of receipt of the request, or seven (7) days of receipt of additional information or documentation, whichever is later. The Construction Administrator will give final acceptance or rejection by the Owner not less than seven (7) days after notification.
a. Any request deemed an "Equal" and accepted by the Construction
Administrator, Engineer, Owner, and Agency will result in written notification to the Contractor and will not be in the form of a change order for an "Equal".
b. Any request deemed a "Substitution" and rejected or approved by
Construction Administrator, Engineer, and Owner may result in written notification to the Contractor and may be in the form of a change order if the "Substitution" is approved.
2025-1807.01 JB24-043
1.5 QUALITY ASSURANCE
A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage a qualified testing agency to perform compatibility tests recommended by manufacturers.
B. Warranties: Substituted product warranties shall meet or exceed the requirements of the originally specified product. If necessary to meet the requirements of the originally specified product, the contractor shall pay for extended warranties at no additional cost to the Owner.
1.6 PROCEDURES
A. Coordination: Revise or adjust affected work as necessary to integrate work of the approved substitutions.
1.7 SUBSTITUTIONS
A. Submit requests for substitution immediately on discovery of need for change, but not later than fourteen (14) working days prior to time required for preparation and review of related submittals.
1. Conditions: Engineer will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Engineer will return requests without action, except to record noncompliance with these requirements:
a. The proposed request does not require extensive revisions to the Contract
Documents.
b. The proposed request is in accordance with the general intent of the
Contract Documents.
c. The proposed request is timely, fully documented, and/or properly submitted.
d. The proposed request can be provided within the Contract Time.
However, the Engineer will not consider the proposed request if it is a result of the Contractor’s failure to pursue the Work promptly or coordinate activities properly.
e. The proposed request will offer the Owner a substantial advantage, in cost, time, energy conservation, or other considerations, after deducting additional responsibilities the Owner must assume. However, if the proposed request requires the Owner to incur additional responsibilities, including but not limited to, additional compensation to the Engineer for redesign and evaluation services, increased cost of other construction by the Owner or similar considerations, then the Owner will have just cause to reject the request for Equal or Substitution.
f. The proposed request can receive the necessary approvals, in a timely manner, required by governing authorities having jurisdiction.
2025-1807.01 JB24-043
g. The proposed request can be provided in a manner that is compatible with the Work as certified by the Contractor.
h. The proposed request can be coordinated with the Work as certified by the Contractor.
i. The proposed request can uphold the warranties required by the Contract
Documents as certified by the Contractor, at no additional cost to the
Owner.
B. The Contractor’s submission and the Engineer's review of Submittals, including but not limited to, Samples, Manufacturer’s Data, Shop Drawings, or other such items, which are not clearly identified as a request for an Equal or Substitution, will not be considered or accepted as a valid request for an Equal or Substitution, nor does it constitute an approval.
PART TWO – PRODUCTS (Not Used)
END OF SECTION 012500
CONTRACT MODIFICATION
PROCEDURES
SECTION 012600
2025-1807.01 JB24-043
SECTION 012600 – CONTRACT MODIFICATION PROCEDURES
PART ONE – GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for handling and processing
Contract modifications.
B. Related Requirements:
1. Section 012100 “Allowances” for administrative and procedural requirements governing allowances.
2. Section 012500 "Substitution Procedures" for administrative procedures for handling requests for substitutions made after the Contract award.
3. Section 013100 "Project Management and Coordination" for requirements for forms for contract modifications provided as part of web-based project management software.
1.3 ENGINEER’S SUPPLEMENTAL INSTRUCTIONS
A. Engineer will issue supplemental instructions authorizing minor changes in the Work, not involving adjustment to the Contract Sum or the Contract Time, on AIA Document G710.
1.4 PROPOSAL REQUESTS
A. Owner-Initiated Proposal Requests: Engineer will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract
Time. If necessary, the description will include supplemental or revised Drawings and
Specifications.
1. Work Change Proposal Requests are not instructions either to stop work in progress or to execute the proposed change.
2. Within time specified in Proposal Request or fourteen (14) calendar days, when not otherwise specified after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change.
2025-1807.01 JB24-043
a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
c. Include costs of labor and supervision directly attributable to the change.
d. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
e. Quotation Form: Use forms acceptable to Engineer.
B. Contractor-Initiated Proposals: If latent or changed conditions require modifications to the Contract, Contractor may initiate a claim by submitting a request for a change to the
Engineer.
1. Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.
2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
4. Include costs of labor and supervision directly attributable to the change.
5. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
6. Comply with requirements in Section 012500 "Substitution Procedures" if the proposed change requires substitution of one product or system for product or system specified.
7. Proposal Request Form: Use form acceptable to Engineer.
1.5 ADMINISTRATIVE CHANGE ORDERS
A. Allowance Adjustment: See Section 012100 "Allowances" for administrative procedures for preparation of Change Order Proposal for adjusting the Contract Sum to reflect actual costs of allowances.
B. Unit-Price Adjustment: See Section 012200 "Unit Prices" for administrative procedures for preparation of Change Order Proposal for adjusting the Contract Sum to reflect measured scope of unit-price work.
2025-1807.01 JB24-043
1.6 CHANGE ORDER PROCEDURES
A. On Owner's approval of a Work Change Proposal Request, the Engineer/Engineer will issue a Change Order for signatures of Owner, Engineer and Contractor on
AIA Document G701, or substantially similar document by mutual agreement.
1.7 CONSTRUCTION CHANGE DIRECTIVE
A. Construction Change Directive: The Engineer may issue a Construction Change Directive on AIA Document G714 (or substantially similar document by mutual agreement).
Construction Change Directive instructs Contractor to proceed with a change in the
Work, for subsequent inclusion in a Change Order.
1. Construction Change Directive contains a complete description of change in the
Work. It also designates method to be followed to determine change in the
Contract Sum or the Contract Time.
B. Documentation: Maintain detailed records on a time and material basis of work required by the Construction Change Directive.
1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.
PART TWO – PRODUCTS (Not Used)
END OF SECTION 012600
PAYMENT PROCEDURES
SECTION 012900
2025-1807.01 JB24-043
SECTION 012900 - PAYMENT PROCEDURES
PART ONE – GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements necessary to prepare and process Applications for Payment.
B. Related Requirements:
1. Section 012100 "Allowances" for procedural requirements governing the handling and processing of allowances.
2. Section 012600 "Contract Modification Procedures" for administrative procedures for handling changes to the Contract.
1.3 DEFINITIONS
A. Schedule of Values: A statement, in AIA Document A201 format (or substantially similar document by mutual agreement), furnished by Contractor allocating portions of the
Contract Sum to various portions of the Work and used as the basis for reviewing
Contractor's Applications for Payment.
1.4 SCHEDULE OF VALUES
A. Coordination: Coordinate preparation of the schedule of values with preparation of
Contractor's construction schedule.
1. Coordinate line items in the schedule of values with items required to be indicated as separate activities in Contractor's construction schedule.
2. Submit the schedule of values to Engineer within four weeks of receipt of
Purchase Order from the Judicial Branch.
B. Format and Content: Use Project Manual table of contents as a guide to establish line items for the schedule of values. Provide at least one line item for each Specification
Section.
1. Identification: Include the following Project identification on the schedule of values:
a. Project name and location.
b. Owner's name: Judicial Branch
c. Judicial Branch's Project number.
2025-1807.01 JB24-043
d. Name of Engineer.
e. Engineer's Project number.
f. Contractor's name and address.
g. Date of submittal.
2. Arrange schedule of values consistent with format of AIA Document G703 (or substantially similar document by mutual agreement).
3. Arrange the schedule of values in tabular form, with separate columns to indicate the following for each item listed:
a. Related CSI Division.
b. Description of the Work.
c. Change Orders (numbers) that affect value.
d. Dollar value of the following, as a percentage of the Contract Sum to nearest one-hundredth percent, adjusted to total 100 percent. Round dollar amounts to whole dollars, with total equal to Contract Sum.
1) Labor.
2) Materials.
3) Equipment.
4. Retainage: include 10% retainage.
5. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Applications for Payment and progress reports. Provide multiple line items for principal subcontract amounts in excess of five percent of the
Contract Sum.
6. Provide a separate line item in the schedule of values for each part of the Work where Applications for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed.
a. Differentiate between items stored on-site and items stored off-site.
7. Allowances: Provide a separate line item in the schedule of values for each allowance. Show line-item value of unit-cost allowances, as a product of the unit cost, multiplied by measured quantity. Use information indicated in the Contract
Documents to determine quantities.
8. Overhead Costs, Separate Line Items: Show cost of temporary facilities and other major cost items that are not direct cost of actual work-in-place as separate line items.
9. Temporary Facilities: Show cost of temporary facilities and other major cost items that are not direct cost of actual work-in-place as separate line items.
10. Closeout Costs. Include separate line items under Contractor and principal subcontracts for Project closeout requirements in an amount totaling five percent of the Contract Sum and subcontract amount.
11. Schedule of Values Revisions: Revise the schedule of values when Change
Orders or Construction Change Directives result in a change in the Contract Sum.
Include at least one separate line item for each Change Order and Construction
Change Directive.
1.5 APPLICATIONS FOR PAYMENT
A. Each Application for Payment following the initial Application for Payment shall be consistent with previous applications and payments, as certified by Engineer and paid for by Owner.
2025-1807.01 JB24-043
B. Payment Application Times: Submit Application for Payment to Engineer by the last day of the month. The period covered by each Application for Payment is one month, ending on the last day of the month.
1. Submit draft copy (“pencil copy”) of Application for Payment seven (7) days prior to due date for review by Engineer.
C. Application for Payment Forms: Use AIA Document G702 and AIA Document G703 (or substantially similar documents by mutual agreement) as the forms for Applications for
Payment.
D. Application Preparation: Complete every entry on Application for Payment form.
Notarize and execute by a person authorized to sign legal documents on behalf of
Contractor. Engineer will return incomplete applications without action.
1. Entries shall match data on the schedule of values and Contractor's construction schedule. Use updated schedules if revisions were made.
2. Include amounts for work completed following previous Application for
Payment, whether or not payment has been received. Include only amounts for work completed at time of Application for Payment.
3. Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application.
4. Indicate separate amounts for work being carried out under Owner-requested project acceleration.
5. When directed by the Owner, provide Certified Payrolls reports attesting that employees have been paid according to prevailing wage regulations.
E. Stored Materials: Include in Application for Payment amounts applied for materials or equipment purchased or fabricated and stored, but not yet installed. Differentiate between items stored on-site and items stored off-site.
1. Provide certificate of insurance, evidence of transfer of title to Owner, and consent of surety to payment for stored materials.
2. Provide supporting documentation that verifies amount requested, such as paid invoices. Match amount requested with amounts indicated on documentation; do not include overhead and profit on stored materials.
3. Provide summary documentation for stored materials indicating the following:
a. Value of materials previously stored and remaining stored as of date of previous Applications for Payment.
b. Value of previously stored materials put in place after date of previous
Application for Payment and on or before date of current Application for
Payment.
c. Value of materials stored since date of previous Application for Payment and remaining stored as of date of current Application for Payment.
F. Transmittal: Electronic processing and digital signatures are preferred by the Judicial
Branch. Submit signed and notarized Applications for Payment to Engineer with a copy to the Judicial Branch Project Manager. Include waivers of lien and similar attachments if required.
G. Initial Application for Payment: Administrative actions and submittals that must precede submittal of first Application for Payment include the following:
2025-1807.01 JB24-043
1. List of subcontractors.
2. Schedule of values.
3. Contractor's construction schedule (preliminary if not final).
4. Schedule of unit prices.
5. Submittal schedule (preliminary if not final).
6. List of Contractor's staff assignments.
7. List of Contractor's principal consultants.
8. Copies of building permits.
9. Copies of authorizations and licenses from authorities having jurisdiction for performance of the Work.
10. Initial progress report.
11. Report of preconstruction conference.
12. Certificates of insurance and insurance policies.
13. Performance and payment bonds.
H. Application for Payment at Substantial Completion: After Engineer issues the Certificate of Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete.
1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum.
a. Complete administrative actions, submittals, and Work preceding this application, as described in Section 017700 "Closeout Procedures."
2. This application shall reflect Certificate(s) of Substantial Completion issued previously for Owner occupancy of designated portions of the Work.
I. Final Payment Application: After completing Project closeout requirements, submit final
Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following:
1. Evidence of completion of Project closeout requirements.
2. Certification of completion of final punch list items.
3. Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid.
4. Updated final statement, accounting for final changes to the Contract Sum.
5. AIA Document G706 Contractor’s Affidavit of Payment of Debts and Claims.
6. AIA Document G706A Contractor’s Affidavit of Release of Liens.
7. AIA Document G707 Consent of Surety to Final Payment (if applicable).
8. Evidence that claims have been settled.
9. Final meter readings for utilities, a measured record of stored fuel, and similar data as of date of Substantial Completion or when Owner took possession of and assumed responsibility for corresponding elements of the Work.
10. Final liquidated damages settlement statement.
11. Proof that taxes, fees, and similar obligations are paid.
12. Waivers and releases.
2025-1807.01 JB24-043
PART TWO – PRODUCTS (Not Used)
END OF SECTION 012900
PROJECT MANAGEMENT
AND COORDINATION
SECTION 013100
2025-1807.01 JB24-043
SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on
Project, including, but not limited to, the following:
1. General coordination procedures.
2. Coordination drawings.
3. RFIs.
4. Digital project management procedures.
5. Web-based Project management software package.
6. Project meetings.
B. Related Requirements:
1. Section 017300 "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
2. Section 017700 "Closeout Procedures" for coordinating closeout of the Contract.
1.3 DEFINITIONS
A. BIM: Building Information Modeling.
B. RFI: Request for Information. Request from Owner, Engineer, or Contractor seeking information required by or clarifications of the Contract Documents.
1.4 INFORMATIONAL SUBMITTALS
A. Subcontract List: if not defined in other Judicial Branch procurement documents, prepare a written summary identifying individuals or firms proposed for each portion of the
Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:
2025-1807.01 JB24-043
1. Name, address, telephone number, and email address of entity performing subcontract or supplying products.
2. Number and title of related Specification Section(s) covered by subcontract.
3. Drawing number and detail references, as appropriate, covered by subcontract.
B. Key Personnel Names: per timing set forth in Section 011000 Summary, submit a list of key personnel assignments, including superintendent and other personnel in attendance at
Project site. Identify individuals and their duties and responsibilities; list addresses, cellular telephone numbers, and e-mail addresses. Provide names, addresses, and telephone numbers of individuals assigned as alternates in the absence of individuals assigned to Project.
C. Site Logistics Plan(s) showing: per timing set forth in Section 011000 Summary prepare a Site Logistics Plan depicting the entire project area and limits; all routes into and out of site; all staging and stockpiling and lay-down areas; all aspects of phasing/staging; all parking, and fencing; and all specific provisions to satisfy requirements of Division 01
Sections, including but not limited to Temporary Facilities and Controls. The Site
Logistics Plan(s) shall be drawn at a scale no smaller than 1"=40'.
1.5 GENERAL COORDINATION PROCEDURES
A. Coordination: Coordinate construction operations included in different Sections of the
Specifications to ensure efficient and orderly installation of each part of the Work.
Coordinate construction operations included in different Sections that depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results, where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
4. The prime contractor shall have a superintendent on site during the execution of all subcontracted work.
B. Administrative Procedures: Coordinate scheduling and timing of…