About this file

The document is a Request for Proposals (RFP) issued by Park County's Department of Heritage & Tourism for the Paris Mill Rehabilitation – Phase 8 Accessibility and Interior Rehabilitation project. The RFP seeks a licensed Colorado architect to provide architectural and engineering services for rehabilitating the historic 1895 Paris Mill, located three miles west of Alma, Colorado. The project scope includes ADA accessibility improvements in the West Wing, reinstalling interior bead board finishes, rehabilitating the north entrance, reconstructing six windows, providing access to an additional building level, and installing electrical components. Proposals must be submitted via email to Katie Dirksen by February 11, 2025, with all work to be completed by December 31, 2025.

The project is subject to funding availability and requires contractors to meet the Secretary of the Interior's Standards for Rehabilitation. Proposal submissions must include a timeline for deliverables, a cost estimate and payment schedule, a list of potential subcontractors, demonstration of meeting rehabilitation standards, and client references. The Paris Mill is described as a significant historic resource, an industrial timber-framed structure measuring approximately 114 by 76 feet, with multiple building wings including a tramway tower, ore bin, concentration section, and other historical industrial components. Interested parties can contact Kate McCoy at 719-836-4237 to schedule a site visit or ask questions about the project.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Park County Department of Heritage &Tourism 418 Main Street, PO Box 1373 Fairplay, Colorado 80440

Request for Proposals:

Paris Mill Rehabilitation – Phase 8 Accessibility and Interior Rehabilitation—

Architecture & Engineering

Background

Park County is seeking an architect to provide architectural services and coordinate engineering services for the next phase of rehabilitation at the Paris Mill located on the eastern slope of the Mosquito Range.

This 1895 mill is an important historic resource of the area and a priority preservation project for the community. The proposed scope of work, phase 8, addresses accessibility and interior rehabilitation. The

Paris Mill is one of the few intact mills remaining from this era in Colorado due to its extensive machinery, engineered systems, structural elements and architectural aspects. Phase 8 construction of the mill is a natural continuation of work and another important step in this multi-phase preservation project.

Location

This project is located three miles west of the town of Alma, CO on Park County Road 8. The Mill property adjoins Pike National Forest and is situated at the foot of Mount Bross to the north and Loveland

Mountain to the south. Buckskin Creek lies to the south of the Mill.

Description

The Paris Mill is a an industrial, timber framed structure including three additions that form a complex roof line and irregular footprint measuring approximately 114 by 76 feet and rising to more than 40 feet at its highest point. The Mill’s roof line is comprised of multiple shed and gable roofs covered in corrugated metal. The walls of the Mill are wood framed with vertical wood sheathing covered in rolled asphalt. The

Mill complex includes a tramway tower, ore bin, crushing section, concentration section, engine wing, tank house, storeroom, assay office, gold precipitation wing, and cyanidation wing.

Architecture and Engineering Scope of Work:

Phase 8 Accessibility and Interior Rehabilitation

8 A&E1. Provide drawings and pre-construction and contract/construction administration for the following scope of work, coordinating architectural and structural and electrical engineering services:

Scope of Work

1. Accessibility / Interior Rehabilitation

a. Provide ADA accessibility to West Wing by creating level floor surfaces and removing hindering building materials.

b. Reinstall interior bead board finish at walls and ceiling in the east wing

2. North Entrance Rehabilitation

a. Construct door to be installed in existing north entrance opening

b. Construct exterior stairs and landing to provide access to north entrance

3. Window Rehabilitation

a. Rehabilitate six (6) windows in the center section of the building – note that windows require full reconstruction to be based on original historic window sashes

b. Rehabilitate wood frames and trim associated with rehabilitated windows

4. Level 05 Access

a. Provide access to additional level of the building by rehabilitating stairs and wood flooring and installing handrails where necessary for safety

5. Electrical Rehabilitation

a. Install lights and receptacles in publicly accessible areas of the building where not currently installed.

Dropbox

Documents

• Paris Mill Historic Structure Assessment (excerpts)

• Paris Mill Master Plan

• Paris Mill Construction Documents and Specs 90% Complete. Note that the complete scope for this project is not included in these documents. The drawings for this scope will be completed before construction takes place.

• Paris Mill Structural Engineering Report

Qualifications

Proposals must be submitted by contractors licensed in the state of Colorado, and attest that work performed will meet the Secretary of the Interior’s Standards for Rehabilitation.

https://www.nps.gov/tps/standards/rehabilitation/rehab/stand.htm

Proposals

Submit proposals via email to Katie Dirksen at katie.dirksen@parkcountyco.gov before February 11, 2025.

Proposals must include:

• A timeline for submission of the deliverables.

• WORK MUST BE COMPLETED BY December 31, 2025

• An estimate and payment schedule for the work to be performed.

• A list of proposed subcontractors (if needed)

• Demonstration of the consultant’s ability to meet the Secretary of the Interior’s Standards for

Rehabilitation

• References from previous clients for completion of similar projects.

Questions & Site Visits

Contact Kate McCoy, 719-836-4237, kate.mccoy@parkcountyco.gov with any questions or to schedule a site visit.

This project is subject to funding availability.

https://www.dropbox.com/scl/fo/n1sr8cuc0d8xungnrpw4c/ACRRso-HLOp91WSI1WoHqFs?rlkey=sem0e08af6mqm2va7ven7maq6&st=3aqw98bc&dl=0 http://www.nps.gov/tps/standards/rehabilitation/rehab/stand.htm http://www.nps.gov/tps/standards/rehabilitation/rehab/stand.htm http://www.nps.gov/tps/standards/rehabilitation/rehab/stand.htm mailto:katie.dirksen@parkcountyco.gov mailto:elockhart-borman@parkco.us mailto:elockhart-borman@parkco.us