PWS ASRS Data Migration Services.pdf

PDF 698 KB Posted

Attached to
Sources Sought for Automated Storage & Retrieval System (ASRS) Data Migration Services
Solicitation number
PANRSA-24-P-0000002179
Issued by

About this file

This performance work statement outlines the requirements for providing automated storage and retrieval system data migration services. The contractor shall migrate data from an HP EVA storage database that has reached end of life to a Primera database. Key tasks include implementing a new storage area network, configuring and migrating the entire ASRS data from the EVA to Primera systems, confirming all systems have been successfully backed up, implementing and verifying the successful migration of all data to the new storage array, and executing a post-migration verification plan jointly with the government. The performance period is expected to last approximately two weeks at the Corpus Christi Army Depot in Corpus Christi, Texas. The contractor shall provide all necessary personnel, equipment, transportation, and other items to complete the migration except for workspace, utilities, and training, which will be government furnished.

View the file

Other files

File Type Posted
Requirements List.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Performance Work Statement for

ASRS Data Migration Services

PART I: GENERAL INFORMATION

1.0 General: This is a non-personal services contract to provide data migration services to migrate the Automated Storage & Retrieval System (ASRS) data, currently stored in the HP EVA database to the Primera database. Both data bases are located at the Corpus Christi Army Depot (CCAD), Corpus Christi, Texas. The objective is for procurement of professional Storage Area Network (SAN) data migration services to ensure that all infrastructure, hardware and networking is configured and that all start up services are complete. The Government will not exercise any supervision or control over the contract service providers performing the services herein. Such contract service providers shall be accountable solely to the Contractor who, in turn is responsible to the Government.

1.1 Description of Services: The Contractor shall perform the following services in support of the data migration project:

a. Storage Area Network (SAN) implementation.

b. Configuring/Migrating from EVA to Primera.

c. Reconfiguring ServiceGuard with iSCSI Migrated Luns.

d. Configuring/Migrating from EVA to Primera on 4 HPUX servers.

e. Reconfiguring ServiceGuard with fiber channel Migrated Luns.

f. Confirm that all systems to be migrated have been successfully backed up.

g. Implementation, monitoring, and verification of the migration of data to the new storage array.

h. Cutover to the new array.

i. Execution of post migration verification plan.

1.2 Background: The depot has a requirement for onsite services for migration of ASRS data from HPE EVA to Primera. ASRS is the storage and retrieval system that is utilized to retrieve parts from stock for delivery to the requiring work center as well as to place items into stock bins that are designated as stock replenishment.

1.3 Scope: The Contractor shall provide all personnel, equipment, supplies, transportation, tools, materials, supervision, quality control, and other items and non-personal services necessary to perform the ASRS data migration services. The Contractor shall provide all requirements as defined in this PWS, except for those items specified as government furnished. The Contractor shall perform to the standards of this contract.

1.4 Objectives: The objective of this contract is to provide migration of ASRS data from the HP EVA storage system to the Primera storage system. The EVA system has reached end of life and is no longer eligible for support.

1.4 Period of Performance: The Contractor shall perform at Corpus Christi Army Depot, Corpus Christi, TX. The required time period to complete the services is expected to be approximately2 weeks.

1.5 General Information:

1.5.1 Quality Control Plan (QCP): The Contractor’s existing quality assurance system shall be utilized in accordance with FAR 12.208.

1.5.2 Quality Assurance (QA): The Government will evaluate the contractor's performance under this contract in accordance with the requirements as defined in this SOW. This quality requirement is primarily focused on what the Government must do to ensure that the Contractor has provided the licenses and support necessary to ensure the Mastercam software remains in an operational status.

1.5.3 Recognized Holidays. The following are recognized US holidays. The Contractor shall ensure the necessary support is available on these days if required:

New Year’s Day Labor Day Martin Luther King Jr.’s Birthday Columbus Day

President’s Day Veteran’s Day Memorial Day Thanksgiving Day Independence Day Christmas Day Juneteenth

1.5.4 Operating Hours: The contractor shall provide services between the 0600 – 1800, Monday through Friday, with the exception of US Holidays or periods when the Government installation/facility is closed due to local or national emergencies, administrative closings or similar Government directed installation/facility closings.

1.5.5 Reserved

1.5.6 Place of Performance: The Contractor shall perform at Corpus Christi Army Depot, Corpus Christi, TX. The required time period to complete the services is expected to be approximately2 weeks.

1.6 Security Requirements: The following information is provided on security related matters.

1.6.1 Reserved

1.6.2 Reserved

1.6.3 Reserved

1.6.4 Installation Access: Access to U.S. installations, buildings and controlled areas is limited to personnel who meet security criteria and are authorized. Failure to submit required information/data and obtain required documentation or background investigations will be grounds for denying access to U.S. installations, buildings and controlled areas. The Contractor shall ensure that any subcontractors used in performance of this contract complies with these requirements and that all employees, of both the Contractor and any subcontractor utilized by the Contractor, are made aware of and comply with these requirements.

The Contractor shall be aware of and comply with the requirements associated with Installation Access Control. The Government is not liable for any costs associated with performance delays due solely to a firm’s failure to comply with Installation Access Control processing requirements.

The Contractor shall return installation and CCAD passes to the issuing Security office when the contract is completed or when a Contractor employee no longer requires access.

Contractor shall obtain a Guest Sponsorship through Navy Pass & Tag not to exceed contract expiration. The government Contracting Officer Representative (COR) will coordinate badging and briefing with Navy and CCAD Security. CCAD personnel will escort contractor at all times while onboard CCAD unless approved in advanced by CCAD Security. Contractors are not authorized to escort anyone on the installation or CCAD.

1.6.4.1 Installation Pass Log: In addition, the Contractor shall provide the Contracting Officer, via the COR, an Initial Installation Pass Log within three (3) calendar days after contract award. The log must at a minimum contain the following information Full Legal Name, type of access (e.g. CAC, DBIDS, base pass) and working hours. The log shall be updated as employees are added or removed. The Updated Installation Pass Log shall be current and available at any time upon request by the Government and submitted to the COR within five (5) days after any changes to the log.

1.6.4.2 Individual Termination or Expiration of Employment: The Contractor shall collect the installation access passes the same day employment of an individual has expired or has been terminated and shall return them to the issuing office within three (3) working days.

1.6.4.3 Contract Termination or Cancellation: Upon termination or cancellation of this contract, the Contractor shall collect all outstanding installation access passes and return them to the issuing office within three (3) working days.

1.6.4.4 Reserved

1.6.5 Reserved

1.6.5.1 U.S. Citizen: The Requiring Activity Manager will determine the extent of background checks required.

The Contractor employee may begin performance of the contract after receiving a favorable local background check.

The Contractor agrees to replace the employee should results of the background check, if required, be unfavorable as determined by the Requiring Activity Manager. The Contractor’s replacement of the employee with the unfavorable background check shall be within a timeframe provided by the Requiring Activity Manager. The Contractor shall also replace employees whose background check, during their tenure of employment, renders them with an unfavorable local or stateside background check, as determined by the Requiring Activity Manager. The Contractor shall forward a copy to the Contracting Officer via the COR and the Requiring Activity Manager of each favorable background check within two business days of receipt by the Contractor, identifying such with the appropriate contract number. The Contractor shall forward a copy to the Contracting Officer via the COR and the Requiring Activity Manager of each unfavorable background check within two business days of receipt by the Contractor, identifying such with the appropriate contract number. When the Government awards a non-personal services contract directly to an individual, the failure of the individual to provide a favorable background check would be grounds for termination.

1.6.5.2 Reserved

1.6.6 Physical Security: The Contractor shall safeguard all Government equipment, information, and property provided for Contractor use. At the close of each work period, Government facilities, equipment, and materials shall be secured IAW the Army Physical Security Program (AR 190-13).

1.6.7 Operations Security (OPSEC) Requirements: Contractor personnel shall adhere to facility security policies and restrictions. The Contractor shall immediately report suspicious activities to security personnel. Government issued access badges shall not be worn outside designated facilities where visible to the general public.

1.6.8 Safeguarding Covered Defense Information: Contractors and subcontractors are required to safeguard covered defense information that resides in or transits through covered contractor information systems by applying specified network security requirements and reporting of cyber incidents in accordance with 48 CFR 204.73. DoD Industry resources for Controlled Unclassified Information can be found at https://www.dcsa.mil/Industrial- Security/Controlled-Unclassified-Information-CUI/

1.7 Reserved

1.8 Post Award Conference/Periodic Progress Meetings: The Contractor shall attend any post award conference convened by the contracting activity or contract administration office in accordance with FAR Subpart 42.5. The Contracting Officer, COR, and other Government personnel, as appropriate, may meet periodically with the Contractor to review the Contractor's performance. At these meetings the Contracting Officer will apprise the Contractor of how the Government views the Contractor's performance and the Contractor shall apprise the Government of problems, if any, being experienced. Appropriate action shall be taken to resolve outstanding issues.

These meetings shall be at no additional cost to the Government.

1.8.1 The Contractor shall attend, participate in, and furnish input to scheduled and unscheduled meetings, conferences, and briefings that relate to the functions and services herein as required by the Government to provide effective communication and impart necessary information. The Contract Manager or designated representative shall attend meetings as requested by the Government. Meeting attendees shall at times include Contractor managerial, supervisory, and other personnel knowledgeable of the subject matter. Meetings may start or end outside of regular duty hours.

1.9 Contracting Officer’s Representative: Contracting Officer Representative (COR): The COR will be identified by a separate letter. The COR monitors all technical aspects of the contract and assists in contract administration. A letter of designation is sued to the COR, a copy of which is sent to the Contractor, states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates or changes in delivery dates.

The COR is not authorized to change any of the terms and conditions of the resulting order.

1.10 Key Personnel: The following personnel are considered key personnel by the Government: Program Manager and Alternate Program Manager. The Contractor shall provide a Program/Contract Manager who shall be responsible for the performance of the work. The name of this person and an Alternate Program/Contract Manager, who shall act for the Contractor when the Program/Contract Manager is absent, along with a Curriculum Vitae (CV) for each of these individuals, shall be provided in writing to the Contracting Officer no later than 5 days after contract award.

1.11 Identification of Contractor Employees: All Contractor personnel attending meetings, answering Government telephones, and working in other situations where their Contractor status is not obvious to third parties must identify themselves, to include proper marking of signature blocks in correspondence, to avoid creating an impression in the minds of members of the public that they are Government officials. The Contractor shall ensure that all documents or reports, produced by Contractors are suitably marked as Contractor products or that Contractor participation is appropriately disclosed.

1.12 Contractor workspace The staging site, on-site office, desk or work area, etc. shall contain a sign signifying the space is occupied by Contractor employee(s) to ensure that Government employees and the public know that they are not Government employees. The proposed sign shall be submitted to the Contracting Officer via the COR for review and acceptance (5) calendar days) after contract award. Workspace sign location shall be coordinated with the COR. Contractor employees shall identify themselves by name and company affiliation when answering the telephone, presenting briefings, conducting or attending meetings, and seminars. All Contractor correspondence (written, facsimile, and email display) shall include their company name. Requirements for Contractor vehicles is addressed under Part 4 paragraph 4.4.

1.12.1 Reserved

1.12.2 Reserved

1.13 Reserved

1.14 Reserved

1.15 Reserved

1.16 Non-Disclosure Requirements: Performance under this contract may require the Contractor to access data and information proprietary to a Government agency, another Government Contractor, or of such nature that its dissemination or use other than as specified in this work statement would be adverse to the interests of the Government or others. The Contractor and Contractor personnel, shall not divulge or release data or information developed, or obtained under performance of this PWS, except to authorized Government personnel or upon written approval of the Contracting Officer. The Contractor shall not use, disclose, or reproduce proprietary data, which bears a restrictive legend, other than as specified in this PWS. All documentation showing individual names or other personal information shall be controlled and protected under the provisions of the Privacy Act of 1974, Public Law 93-579, 5 United States Code (U.S.C.) Section 552a.

1.17 Protection of Government and Contract Information: Per Public Use Notice of Limitations stated by Defense imagery Management operations Center and contained at www.dimoc.mil/resources/limitations/, the Contractor shall not cite any information (e.g., contract information, pictures, locations, etc.) obtained through this contract on any hard copy or digital marketing tools to include its company website.

1.18 Non-Disclosure Statements: The Contractor shall provide signed non-disclosure agreements to the Government no later than ten (10) business days prior to commencement of work under the contract. Disclosure of information by Contractor personnel may result in removal of Contractor personnel from performance under this contract.

1.19 Reserved

1.20 Reserved

1.21 Safety: The following provides information pertaining to Safety and Accident Prevention:

1.21.1 Safety Laws and Regulations: The Contractor shall comply with FAR 52.236-13, Accident Prevention (November 1991), the references contained therein.

The requirements under FAR 52.236-13 and specifically of the EM 385-1-1 include, but are not limited to the following:

(a) Before initiation of work at the job site, an Accident Prevention Plan, written by the Contractor for the specific work and hazards of the contract and implementing in detail the pertinent requirements of EM 385-1-1; will be reviewed for acceptance by designated Government personnel. Specific requirements for development of the

1.21.1 Safety Laws and Regulations: Accident Prevention Plan are found in 01.A and Appendix A of EM 385-1-1.

EM 385-1-1 is available online at www.usace.army.mil.

(b) Before beginning each activity involving a type of work presenting hazards not experienced in previous project operations or where a new work crew or subcontractor is to perform work, activity hazard analysis (AHA) shall be prepared by the Contractor performing the work activity (See paragraph 01.a.09 of EM 385-1-1).

(c) The Contractor shall require subcontractors to submit their plan of operations showing methods they propose to use in accomplishing major phases of work.

(d) The Contractor shall discuss the plans in conferences convened by the Contracting Officer prior to starting work on each major phase of operation. Plans shall include all pertinent information such as layout of haul roads, access roads, storage areas, electrical distribution lines, methods of providing minimum exposure to overhead loads, and methods of access to work areas. The plan for accomplishing the initial work phase shall be submitted within fifteen (15) calendar days after award of the contract. Plans for subsequent major phases of work shall be submitted no later than fifteen (15) calendar days prior to initiation of work on each major phase; and

(e) In all areas where construction, demolition, alteration, building, or similar related activities take place, the Contractor shall have the following minimum personal protective clothing and equipment requirements in place for any person working on or visiting the site:

(i) Short sleeve shirt;

(ii) Long trousers;

(iii) Steel-toed safety boots; and

(iv) Hard hat.

1.21.1.1 In addition to other requirements for accident prevention specified in this contract, the Contractor shall comply with all Federal and State requirements governing safety and health protection on construction sites and other applicable occupational safety codes. The Contractor shall indicate its plan for compliance considering conditions of the work described by the design, technical proposal, operational activities of the Government or others in the area of the work, identification of the coordinator, and implementation of all other accident prevention provisions of this contract.

1.23 Required Training: The following provides information on training requirements.

1.23.1 Reserved

1.23.2 Reserved

1.23.3 iWATCH Training: The Contractor and all associated subcontractors shall brief all employees on the local iWATCH program (training standards provided by the requiring activity ATO). This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR. This training shall be completed within ten (10) calendar days after the contract is awarded and prior to work commencement, with the results reported to the COR within five (5) business days after the contract is awarded and within ten (10) calendar days after new employees commence contract performance. Verification of the training shall be provided to the COR prior to work commencement.

1.23.4 Reserved

1.23.5 Reserved

1.24 Reserved

1.24.1 Reserved

1.24.2 Reserved

1.24.3 Reserved

1.25 Reserved

1.26 Reserved

1.27 Reserved

PART 2: DEFINITIONS & ACRONYMS

2.0 DEFINITIONS AND ACRONYMS:

2.1 Definitions: Although not inclusive of every term used within this PWS, the following provides a list of definitions used throughout this PWS and commonly used in the acquisition field.

CONTRACTOR. A supplier or vendor awarded a contract to provide specific supplies to the Government. The term used in this contract refers to the prime.

CONTRACTING OFFICER (KO). A person with authority to enter into, administer, and/or terminate contracts, and make related determinations and findings on behalf of the Government. Note: The only individual who can legally bind the Government.

CONTRACTING OFFICER'S REPRESENTATIVE (COR). As defined in DFARS 202.101, means an individual designated and authorized in writing by the Contracting Officer to perform specific technical or administrative functions. DoD Instruction (DoDI) 5000.72, Part II Definitions states the following when defining a COR: “Defined in subpart 202.101 of Reference (f). Any individual delegated responsibilities pursuant to subpart 1.602-2 of Reference (e), regardless of local terminology, must be certified in accordance with this instruction. For example, local terminology can be COR, Contracting Officer’s technical representative, technical point of contact, technical representative, alternate COR, administrative COR, assistant COR, line item manager, task order manager, quality assurance personnel, quality assurance evaluator, or COR management.” In addition, Army Regulation 70-13, Chapter 2, paragraph 2-2g, states, in part, the following when providing other surveillance support personnel to assist the COR when needed, “…These other surveillance support personnel may serve as on-site representatives of the COR in performance of actual contract surveillance if they meet all COR requirements and have been appointed by the Contracting Officer as alternate CORs.”

DELIVERABLE. Anything that can be physically delivered and includes non-manufactured items such as meeting minutes or reports.

PHYSICAL SECURITY. means that part of security concerned with physical measures designed to safeguard personnel; to prevent unauthorized access to equipment, installations, material, and documents; and to safeguard against espionage, sabotage, damage, and theft.

QUALITY ASSURANCE. The Government procedures to verify that products being provided by the Contractor meet acceptable standards.

QUALITY CONTROL. All necessary measures taken by the Contractor to assure that the quality of an end product shall meet contract requirements.

SUBCONTRACTOR. One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.

WORKDAY. The number of hours per day the Contractor provides support in accordance with the contract.

WORK WEEK. Monday through Friday , unless specified otherwise.

2.2 Acronyms: Although not inclusive of every term used within this PWS, or that may be included in an acquisition, the following provides a list of acronyms commonly used in the acquisition field.

AR Army Regulation CCAD Corpus Christi Army Depot COR Contracting Officer’s Representative CAC Common Access Card DA Department of the Army DBIDS Defense Biometric Identification System

DD254 Department of Defense Contract Security Requirement List DOD Department of Defense IA Information Awareness IAC Installation Access Control IACO Installation Access Control Office ID Identification IT Information Technology KO Contracting Officer LMR Land Mobile Radio OPSEC Operations Security POC Point of Contact PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QAP Quality Assurance Program QASP Quality Assurance Surveillance Plan QC Quality Control QCP Quality Control Program TE Technical Exhibit WAWF Wide Area Workflow

PART 3: GOVERNMENT FURNISHED PROPERTY, EQUIPMENT AND SERVICES

3.0 GOVERNMENT PROPERTY AND SERVICES:

3.2 Facilities: The Government will provide necessary workspace for the Contractor to provide the support outlined in the PWS to include desk space, storage rooms, etc. The Contractor shall use reasonable care to avoid damaging existing buildings, equipment, and vegetation on the Government installation. If the Contractor’s failure to use reasonable care causes damage to any of this property, the Contractor shall replace or repair the damage at no expense to the Government as the Contracting Officer directs. If the Contractor fails or refuses to make such repair or replacement, the Contractor shall be liable for the cost, which may be deducted from the contract price.

3.3 Utilities: The Government will provide availability of all utilities in the facility for the Contractor’s use in performance of the tasks outlined in the PWS. The Contractor shall instruct employees in utilities conservation practices. The Contractor shall operate under conditions that preclude the waste of utilities, which include turning off the water faucets or valves, light switches, etc. after using the required amount to accomplish tasks requiring the use of the utilities.

3.4 Reserved

3.5 Reserved

3.6 Reserved

3.7 Training: The Government will provide the following training: iWatch training via link.

3.8 Identification Cards: The Government will provide base Access Passes and CCAD Visitor Badges.

PART4: CONTRACTOR FURNISHED ITEMS

4.0 CONTRACTOR FURNISHED IT EMS AND RESPONSBILITIES:

4.1 General: The Contractor shall furnish all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items necessary to perform services as described in the PWS and associated contract documents, except for those items specified in Part 3 Government Property and Services.

4.2 Reserved

4.3 Reserved

4.4 Reserved

4.5 Background Checks: The Contractor shall provide Background Checks in accordance with this PWS and as determined by the Government.

PART 5: SPECIFIC TASKS

5.0 REQUIREMENTS :

5.1 Basic Services: The Contractor shall provide services for the migration of ASRS data from the HP EVA database to the Primera database. The EVA storage database has reached end of life and is no longer eligible for maintenance & support.

5.2 Tasks: Tasks consist of the following:

5.2.1 SAN Implementation: The Contractor shall perform an onsite visit to perform necessary services to migrate ASRS data from the current system, HPE EVA to Primera. These services shall include implementation of the new Storage Area Network (SAN) required for the data migration.

5.2.2 Configuration/Migration: The Contractor shall configure and migrate the entire ASRS data contents from EVA to Primera. This will include reconfiguring ServiceGuard with iSCSI migrated Luns. In addition, this project shall include configuration/migration from EVA to Primera on 4 HPUX servers. Also included is reconfiguration of ServiceGuard with fiber channel migrated Luns.

5.2.3 Confirmation: The Contractor shall confirm with the Government that all systems to be migrated have been successfully backed up.

5.2.4 Storage Array: The Contractor shall implement, monitor and verify that all ASRS data has been successfully migrated to the new storage array. The Contractor shall also ensure proper cutover to the new array has been achieved.

5.2.5 Post Migration: The Contractor shall, jointly with the Government, execute the post migration verification plan.

5.3 Service Contract Reporting

5.3.1 System for Award Management (SAM) Service Contract Report (SCR): The Contractor shall report ALL Contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the Corpus Christi Army Depot via a secure data collection site. The Contractor is required to completely fill in all required data fields through the following web address: www.sam.gov. Reporting inputs will be for the labor executed during the period of performance during each Government FY, which runs from October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year. Contractors may direct questions to the help desk by clicking “View Assistance for SAM.gov” which is located at the top of the SAM.gov website. From there, you can the select “Contact Our Service Desk” which will allow you to contact SAM.gov directly. If contract period of performance ends prior to September 30, the Contractor has 30 calendar days from end date of the contract to complete the SAM SCR requirement.

Steps for Submitting a Service Contract Report (SCR)

1. Go to www.sam.gov and log in.

2. Select Entity Registrations and then select Service Contract Reporting.

3. SAM displays your entities which have service contracts and meet the reporting criteria. Select View by entity to see the service contracts for each entity.

4. Next, select Add for the service contract against which you want to create a Service Contract Report. Each service contract which meets the FAR Subpart 4.1703 reporting thresholds is displayed.

5. You will be taken to the Complete Service Contract Report page. SAM displays the contract details and allows you to report. You are required to enter the following information:

Total Amount Invoiced: Total dollar amount invoiced for services performed during the previous

Government fiscal year under the contract (this amount should include the prime and any subcontract amount).

Prime Contractor Hours Expended: Prime contractor direct labor hours expended on the services performed during the previous Government fiscal year. The amount you enter is automatically divided by 2,080 hours to calculate a Full Time Employee (FTE) equivalent, displayed under the Prime Contractor Hours Expended as Prime Contractor FTEs.

6. Report any required Tier 1 subcontractor information by selecting the Add Tier 1 Subcontract Information button.

7. When you are ready to submit the report, select Submit. This saves your report and returns you to the Select Service Contract page where you can create other SCRs or edit an existing SCR.

Steps for Editing a Submitted Report

1. Follow steps 1-4 above. Any previously submitted SCR will have a View/Edit button instead of an Add button.

2. Select View/Edit. You will be able to view the current SCR, edit available fields, and resubmit the record. You can also delete previously entered information altogether.

STD: All information provided by the Contractor shall be accurate, complete, and not exceed suspense dates noted in corresponding paragraph above.

AQL: 100% Compliant

PART 6 PUBLICATIONS

6.0 Applicable Publications (Current Editions): The following publications, manuals, regulations, etc. are mentioned in this PWS and are listed below.

6.1.1 Executive Order 13556, Controlled Unclassified Information

6.1.2 National Institute of Standards and Technology Special Publication 800-171, Protecting Controlled Unclassified Information in Nonfederal Systems and Organizations

6.1.3 32 Code of Federal Regulation (CFR) Part 2002, Controlled Unclassified Information

6.1.4 32 Code of Federal Regulation (CFR) Part 117 National Industrial Security Program Operating Manual

(NISPOM)

6.1.5 Federal Acquisition Regulation Subpart 24.1 CFR Part 24 and Part 39.105

6.1.6 Unified Facilities Criteria (UFC) 4-010-01 DoD Minimum Antiterrorism Standards for Buildings

6.1.7 Defense Acquisition Regulation 252.204-7008 Compliance with Safeguarding Covered Defense Information Controls

6.1.8 Defense Acquisition Regulation 252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting

6.1.9 DoDI 1000.13, Identification (ID) Cards for Members of the Uniformed Services, Their Dependents, and other Eligible Individuals

6.1.10 DoDM 1000.13, Volume 1, DoD Identification (ID) Cards: ID Card Life-Cycle

6.1.11 DoDM 5200.02 Procedures for the DoD Personnel Security Program

6.1.12 DoDI 5200.02 DoD Personnel Security Program

6.1.13 DoDI 5200.48, Controlled Unclassified Information

6.1.14 DoDD 5230.25, Withholding of Unclassified Technical Data from Public Disclosure

6.1.15 DoDD 5240.06 Counterintelligence Awareness and Reporting (CAIR)

6.1.16 DoD 8570-M Information Assurance Workforce Improvement Program

6.1.17 AR 25-1 Army Information Technology

6.1.18 AR 25-2 Army Cybersecurity

6.1.19 AR 25-55, The Department of the Army Freedom of Information Act

6.1.20 AR 70-31, Standards for Technical Reporting

6.1.21 AR 190-13 The Army Physical Security Program

6.1.22 AR 360-1, The Army Public Affairs Program

6.1.23 AR 380-5, Army Information Security Program

6.1.24 AR 380-10, Foreign Disclosure and Contact with Foreign Representatives

6.1.25 AR 380-49, Industrial Security Program

6.1.26 AR 380-67, Personnel Security

6.1.27 AR 530-1, Operations Security

6.1.28 AR 735-5 Property Accountability Policies

6.1.29 EM 385-1-1 U.S. Army Corps of Engineers Safety and Health Requirements

6.1.30 530-CCAD-001 CCAD Operations Security Plan (OPSEC)

6.1.31 CCAD Physical Security Plan

PART 7

ATTACHMENT AND TECHNICAL EXHIBIT LISTING

7.1 Technical Exhibit 1: Performance Requirements Summary

PWS Paragraph Task Performance Standard Acceptable Quality

Levels (AQL)

Surveillance Method /

By Whom

5.2.1

SAN Implementation

The Contractor shall implement the new SAN required for the data migration.

No failure rate for SAN implementation.

100% inspection by the COR

5.2.2 Configuration/Migration The Contractor shall

configure and migrate the entire ASRS data contents from EVA to Primera.

No failure rate for Configuration/Migration.

5.2.3 Confirmation The Contractor shall confirm

with the Government that all systems to be migrated have been successfully backed up.

No failure rate for migration confirmation.

5.2.4 Storage Array The Contractor shall

implement, monitor and verify that all ASRS data has been successfully migrated to the new storage array.

No failure rate for storage array data receipt.

5.2.5 Post Migration The Contractor shall, jointly

with the Government, execute the post migration verification plan.

No failure rate for the post migration verification plan.

7.2 Technical Exhibit 2: Deliverables Schedule

Deliverable Frequency

Num ber of Copi es

Medium/Format Submit To

1. Status Report As required 2 Email COR

2. Installation Pass Log, Initial within 3-calendar days and updates within 5-calendar days

One Hard copy or electronic)

COR

3. Individual Termination or Expiration of employment

Within 3-working days

N/A Access passes COR

4. Contract Termination or cancellation

Within 3-working days

N/A Access Passes COR

5. Contractor workspace signage and identity

Within (10) calendar days after contract award

As Need ed

COR

6. iWATCH Training

Within 30-calendar days of contract award and within 5-business days for new employees

One COR