AO2 - PWS - Paint Inspection 4-16-24.docx

DOCX document 29 KB Posted

Attached to
TEAD FY24 - Paint Inspection
Solicitation number
PANROC24P0000005179
Issued by

About this file

This document is a Performance Work Statement (PWS) for a federal contract opportunity related to the inspection and painting of 400 mercury ton containers.

The key details are:

  • The contractor will need to be onsite daily to observe and document the surface preparation, primer mixing/application, and paint mixing/application for groups of 30 containers until all 400 containers are completed. This may require up to 25 trips.
  • The exterior surfaces must be blasted to achieve a commercial blast cleaning standard and primed with a zinc-rich primer to a specified thickness. The exterior must then be coated with a polyurethane topcoat to a specified thickness. All paint work must be inspected and documented by a NACE-certified coating inspector.
  • The related federal contract opportunity is a pre-solicitation for market research purposes, with the solicitation number PANROC24P0000005179. It is being issued by the Department of the Army Materiel Command Contracting Command Rock Island Arsenal.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Mercury Ton Container Paint Inspection Performance Work Statement

Container Paint Inspection Requirements

Project Schedule A minimum of four hundred (400) containers will be tested. The number of containers available for testing will be broken down to groups of 30 each. Due to the nature of the required inspections, the contractor will need to be onsite daily during the processing of each group of 30 containers to observe and document the surface preparation steps, primer mixing and application steps and paint mixing, and application steps as detailed below. This process will continue as necessary, until 400 containers are successfully manufactured. Depending on weather and Tooele Army Depots schedule this may take up to 25 trips to complete this project.

Surface Preparation for exterior surfaces of each carbon steel container shall be blasted to achieve the Society for Protective Coatings (SSPC), Surface Preparation (SP) 6, Commercial Blast Cleaning. The inner surfaces of the MC 6 x 18 channel shall be blasted and painted to the best ability of Tooele Army Depot. These surfaces do not need to satisfy the primer and paint thickness requirements.

Any oil, grease or other deleterious material shall be removed by chemical solvent from the container surfaces before assembly. For example: acetone followed by alcohol dry wipe. The container internals shall be kept covered by the plug, dust cap, or other suitable means during fabrication and throughout assembly up until delivery, to ensure no foreign material enters the inside of the container. The completed container shall be vacuumed clean prior to closure and shipping. Cleanliness shall be inspected and documented.

Primer—All exterior surfaces shall be primed with PPG ZNP-300/301 ZINC RICH PRIMER (color gray: 0700) to a minimum dry thickness of 3.0 mils and maximum thickness of 4.0 mils. Inspection within 24 hours.

Topcoat—After primer is fully dry, all exterior surfaces shall be painted with one coat of PPG AUE-370 POLYURETHANE TOPCOAT SAFETY BLUE One coat shall be a minimum of 4.0 mils to a maximum thickness of 6.0 mils.

Coating Inspection—A calibrated coating thickness meter shall be used to verify the dry thickness of each layer of paint at a minimum of four locations (~90 apart) on the side and one on the top plate within two inches of the plug. If the thickness of the paint is out of acceptable range, the container shall be blasted to SSPC SP 6, reprimed, and re-painted. Each container shall have the surface prep, primer, and topcoat inspected and documented. Finished painted surfaces, upon visual inspection, shall appear smooth and free of any visible pits or imperfections. Container(s) shall be allowed time to completely dry prior to delivery. All paint inspection to be completed by a National Association of Corrosion Engineers (NACE) Coating Inspector (level II or III) , with current certification.

(viii) Note Inspection forms required:

1. Blast booth temp/humidity and items blasted. (Tooele Army Depot (TEAD) Sand Blast Daily Conditions Tracker)

1. Daily Temp/Humidity of Paint Booth Readings prior to use. (Daily Environmental Readings form)

1. Blast Profile Measurement worksheet averages annotated on Process 9 record. (blast profile measurement worksheet)

1. SAND BLASTING INSPECTION REPORT (SSPC-SP6/NACE 3 Commercial Blast Cleaning 2006) (Process 9 Sand Blast Inspection record))

1. Dry Film coating thickness measurements averages documents on Process 11 record. (Paint Thickness worksheet)

1. PAINT INSPECTION REPORT. (Process 11 Protective Coating Inspection Record)

1. Solvent cleaning (SSPC-SP1 Solvent Cleaning 2016) (Process 10 Painting Inspection record)