This file is a Questions and Answers document for a Rathbun and Long Branch Master Blanket Purchase Agreement (BPA) solicitation issued by the USACE Kansas City District. The Master BPA covers lawn service and chemical application services at two lake projects: Rathbun Lake (approximately 34,000 acres, office in Centerville, Iowa) and Long Branch Lake (approximately 3,600 acres, office in Macon, Missouri). The Master BPA has a 5-year period of performance, with individual call orders typically lasting one year/season for mowing or for the duration of specific jobs. Pricing is submitted per call order, with the USACE Kansas City Contracting Office issuing individual RFQs via email to all Master BPA holders, each containing a Performance Work Statement to quote. The minimum number of Master BPAs to be awarded is 5, with no stated maximum.
Submissions are due December 20, 2026 at 6:00 PM New York Time and must be emailed to Seth.B.Balsters@usace.army.mil. Questions are due by 11:59 PM on December 14, 2026. Offerors must be registered in SAM at the time of BPA submission and must maintain SAM registration with NAICS code 561730 at the time of call award. Pesticide applicator licenses or certifications are not required at the BPA submission stage but are mandatory when performing chemical application services; individual performers of this work must hold the license rather than the prime contractor. Relevant past performance from proposed subcontractors may be used to satisfy related experience requirements, with subcontractors identified by name at submission when used for experience documentation, or identified when competing for individual calls otherwise. Pricing templates, wage determinations, and FAR Clause 52.219-14 (limitation on subcontracting) will apply to individual calls. No site visit is planned.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment for Sources Sought.pdf | ||
| Copy of Previous Master BPA.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Rathbun and Long Branch Master BPA Questions and Answers (19-NOV)
Q1: Can relevant past performance from a proposed subcontractor or teaming partner be used to satisfy the related experience requirement?
A1: Yes, but please include the sub’s information as well as your own when using sub exp.
Q2: Will individual BPA calls be competed among established BPA holders?
A2: Yes, calls will be competed among all the BPA holders.
Q3: Are any pesticide applicator licenses or certifications required at the initial BPA submission stage, or only when performing chemical application services?
A3: Correct, if you have them now is good, but only required when performing a call contract for chemical applications.
Q4: The Related Experience form refers to specifications in "Section C," but we could not find a Section C among the posted documents. Could you please post or share the Section C specifications, or confirm which document the form is referring to?
A4: Section C refers to performance work statement (PWS) or scope of work (SOW) in the UCF format---and there is not one. As this is not for specific contracted work but an agreement. We simply want to know what lawn service and chemical application experience you have.
Q5: Pricing. Is any price due with this submission, or are prices given only when a BPA call is competed?
A5: Price Sheets are not part of this submission. When contracted work is needed, the USACE Kansas City Contracting OƯice will send out an RFQ, via email with a PWS, to all Master BPA holders for quoting the individual calls contracts.
Q6: Closing time. The notice reads "6:00 pm EDT 20-DEC-2026". December 20 falls on a Sunday and Eastern Daylight Time is not in eƯect that day. Please confirm the date and time submissions are due.
A6: Confirming, 6pm New York Time on Sunday 20-DEC-2026.
Q7: Related experience. Your answer on subcontractor experience reads "please include the sub's information as well as your own when using sub exp." When a submission relies on a subcontractor's experience, is the Vendor Information Sheet enough for "your own" information, or do you need something more from the oƯeror?
A7: The information included in the Vendor Information should be the company that is making the Master BPA. If you're using a sub-contractor's performance on a Relative Experience Form, then note that in the Description of Duties/Work comments section. No, not really. If there is something you'd like to provide, then feel free to include it.
Q8: Pricing structure — is the price schedule per call order, per acre, or monthly? How are BPA calls issued, and how often?
A8: Per Call, as each Call RFQ will have a PWS to quote.
Q9: Period of performance.
A9: Master BPA runs 5 years. Calls at most would be a year/season, typical for mowing. And for other work is for the job.
Q10: Scope — could you confirm the mowing acreage, herbicide and pesticide areas, and tree-line trimming mileage at each lake project?
A10: Information about the lakes:
Rathbun Lake OƯice is in Centerville, IA. The Rathbun Project Area is roughly 34,000 acres. https://www.nwk.usace.army.mil/Locations/District-Lakes/Rathbun-Lake/
Long Branch Lake OƯice is in Macon, MO. Long Branch Project Area is roughly 3,600 acres. https://www.nwk.usace.army.mil/Locations/District-Lakes/Long-Branch-Lake/
Q11: Herbicide and pesticide application — must the prime contractor hold the applicator license, or is it suƯicient for the licensed applicator performing the work to hold it?
A11: It is suƯicient that the individuals performing the work hold the license.
Q12: Submission method — please confirm how oƯers should be submitted, and that oƯers are due December 20, 2026 at 6:00 PM EST.
A12: Emailed to Seth.B.Balsters@usace.army.mil
Q13: Could you point me to the full solicitation package (statement of work and price schedule) if it is posted separately from the notice?
A13: Nothing posted separately or elsewhere.
Q14: Questions are due December 14, 2026 — what time of day is the cutoƯ?
A14: 11:59 pm 14-DEC-26
Q15: Must an oƯeror be registered in SAM under NAICS 561730 at the time of BPA submission, or only at the time of a call award?
A15: Registered in SAM at time of BPA submission, and registered in SAM with NAICS at time of call award.
Q16: How many Master BPAs does the Kansas City District intend to award under this solicitation?
A16: Technically no maximum, while there is a minimum of 5.
Q17: The Q&A confirms subcontractor past performance may be used for the related experience requirement. Must the subcontractor be identified by name at the BPA submission stage, or only when competing for a call?
A17: Yes, Identified at submission when using for Relative Experience. Otherwise, Identified when competing for a call.
Q18: Will each BPA call include its own wage determination, and will the limitation on subcontracting (FAR 52.219-14 / 13 CFR 125.6) apply to calls under this BPA?
A18: Yes, individual wage determinations. Yes, FAR Clause 52.219-14 will be included in the Master BPA, and apply to calls.
Q19: Is a site visit or pre-proposal conference planned for either lake? If so, please advise the date.
A19: No site visit.