DRAFT Telecomm Conduit Install_SOO.pdf
PDF 2 MB Posted
- Attached to
- 129 CS - Telecomm Conduit Install
- Solicitation number
- PANNGB-27-P-0000042962
About this file
This is a Statement of Objectives (SOO) for a telecommunications conduit installation project at Moffett Air National Guard Base, California.
The 129th Communications Squadron requires the engineering, furnishing, and installation (EF&I) of one new inside plant (ISP) telecommunications conduit in Building 653 extending approximately 50 feet between Rooms 16A and 21A. The conduit must be constructed of steel, measure 3 inches in diameter, be installed as a single continuous straight length above the existing hard-cap ceiling, and extend approximately 6 inches from the wall in Room 21A and 12 inches from the wall in Room 16A. The work will be performed at Moffett ANGB, 680 Macon Road, Santa Clara County, California 94035 (coordinates: 37°24'47.71"N, 122°02'19.39"W), and is designed to support the future installation of outside plant (OSP) fiber optic cable infrastructure. The project is identified as CIPS REQ# QMRA-2019-00001, authored by MSgt Thomas A. Courchaine, California Air National Guard.
The contractor is responsible for all on-site coordination with Base Civil Engineering, Wing Safety, and the 129th Communications Squadron; acquisition and delivery of all necessary tools and support equipment; and shipment of all associated equipment to 129 CS/SCXP, MSgt Thomas Courchaine, 680 Macon Road, Room 66, Moffett ANGB, California 94035. All contractor personnel must be United States citizens with a national background check in accordance with Air Force Directive 31-101, and security clearance information must be provided to the 129 CS no later than two weeks prior to installation commencement. The contractor must comply with the Computer Security Act of 1987 and DoD/USAF requirements for access to Sensitive but Unclassified Information.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF OBJECTIVES
TELECOMM CONDUIT INSTALL
CUSTOMER NAME 129TH RESCUE WING
PROJECT NAME TELECOMM CONDUIT INSTALL
CIPS REQ# QMRA-2019-00001
LOCATION 680 MACON RD., MOFFETT ANGB, CA 94035
AUTHOR(S) THOMAS A. COURCHAINE, MSgt, CA ANG
DRAFT
Telecomm Conduit Install for the 129th Communications Squadron
Background
The 129th Communications Squadron (129 CS) will be receiving new fiber optic cable infrastructure in support of building 653 that will terminate inside room 21A. However, it has been previously confirmed that additional conduit is necessary to pull the cable into the building and ultimately inside Rm 21A. All work accomplished in accordance with this Statement of Objectives (SOO) shall be performed on behalf of the 129 CS, located at Moffett Air National Guard Base, Santa Clara County CA 94035.
Overall Objective(s)
The objective of this effort is to engineer, furnish & install (EF&I) a new inside plant (ISP) telecomm conduit that the 129 CS will use to support the future install of a new outside plant (OSP) fiber optic cable (FOC). The primary necessity of this effort is to ensure that an ISP telecomm conduit pathway is already in place and available for use prior to the onset of the forthcoming OSP FOC install inside Rm 21A.
Technical Objectives
The following information is provided for additional clarification of the aforementioned objective(s).
EF&I one (1) new ISP telecomm conduit in Bldg 653 that extends between rooms 16A & 21A.
NOTE: All work to accomplish these objectives will occur at the following approximate location:
Lat: 37°24’47.71”N, Long: -122°02’19.39”W.
Engineering Objectives
EF&I all equipment and material necessary to provide the 129 CS with a new telecomm conduit that includes/retains the same or better specifications and capabilities as those listed below:
o Material/composite: steel o Length: Approx. 50ft.
o Diameter/width: 3in.
The conduit shall be straight without any bends, be one continuous length from end to end, and shall be installed above the existing hard-cap ceiling.
Government Furnished Equipment
There is/will not be any relevant Government Furnished Equipment (GFE) for this project.
Logistics Objectives
The Contractor shall be responsible for the on-site coordination of the install with all applicable third parties and agencies (i.e. Base Civil Engineering & Wing Safety) prior to any work being performed.
The Contractor shall coordinate with 129 CS to gain access to each respective area where work will be performed.
The Contractor shall be responsible for the acquisition/rental and delivery of all tools & support equipment and tools necessary to perform the installation.
The Contractor shall be responsible for shipment and delivery charges of all associated equipment. The
Contractor shall ensure delivery of all equipment and services performed in support of the project will occur at the following address:
129 CS/SCXP
Attn: MSgt Thomas Courchaine 680 Macon Road, Rm 66 Moffett ANGB, CA 94035
Security Requirements
The Contractor shall comply with the Computer Security Act of 1987 and all Department of DoD and USAF requirements for access to Sensitive but Unclassified Information in the event that such access is deemed necessary in order to satisfy the objectives outlined in this SOO. All Contractor personnel performing work under this SOO shall be United States citizens and have at least a national background check IAW Air Force Directive 31-101 before access to the work location can be granted and any work is started. The Contractor shall be responsible for coordinating with the 129 CS and all applicable third-party agencies and tenants on all security requirements necessary to gain access to the base and all areas impacted by the execution of this project. The Contractor shall provide the necessary security clearance information to the 129 CS no later than two weeks prior to installation commencement for contractor personnel being granted access to any work locations.
Attachments
The diagram(s)/visual aid(s) that follow are provided to assist the Contractor in defining the scope of the requirement.
Diagram 1
Visual Aid 1, Rm 21A
CONDUIT NEEDS
TO STOP HERE,
EXTENDING
APPROX. 6IN
FROM WALL
Visual Aid 2, Rm 21A
EXTENDING
APPROX. 6IN
FROM WALL DRAFT
Visual Aid 3, Rm 16A
Visual Aid 4, Rm 16A
Visual Aid 5, Rm 16A
Visual Aid 6, Rm 16A
EXTENDING
APPROX. 12IN
FROM WALL DRAFT
| Background |
| Overall Objective(s) |
| Technical Objectives |
| Engineering Objectives |
| Government Furnished Equipment |
| Logistics Objectives |