This document is a Statement of Work (SOW) for the deinstallation, removal, and disposal of rolling file systems located at the Evans Army Community Hospital in Fort Carson, Colorado. The SOW outlines the specific tasks required, including disassembly and removal of the rolling file systems from three buildings, transportation of the equipment off the base, and disposal of the systems. The contractor is required to provide documentation of the serial numbers of the removed equipment to the Space Utilization Specialist. The government will not be responsible for any damages or loss of contractor property or equipment.

The related federal contract opportunity is a pre-solicitation for a non-personnel, one-time service contract to provide the deinstallation, removal, and disposal of the rolling file systems at the Evans Army Community Hospital. The period of performance is within 90 days from award. The agency is the Department of the Army Materiel Command Mission and Installation Contracting Command Fort Hood.

View the file

Other files

File Type Posted
Rolling Shelves-SOW.pdf PDF
QASP_Rolling Shelves.docx DOCX document
EACH File Storage Removal 20240409 (002).pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK (SOW)

Deinstallation Removal and Disposal of Rolling Shelves

EVANS ARMY COMMUNITY HOSPITAL

Fort Carson, Colorado 80913

Part 1

General Information

1. Description of Services/Introduction: This is a non-personnel one time service(s) contract to provide the deinstallation, removal and disposal of the Rolling File System(s) located at the Evans Army

Community Hospital, 1650 Cochrane Circle, Fort Carson, Colorado 80913, Building 7500 R1963 & 1951A, Building 7503 R1506 and Building 7505 R125.

1.2. Scope: The Contractor Employee is required to check-in at Bldg 7500 Room 0507, Facilities Management Division, with the Space Utilization Specialist before proceeding to complete the service work.

• De-installation of the Rolling File System(s)

• Removal of Rolling File System(s)

• Transportation of de-installed Rolling File Systems out of the base

• Disposal of Rolling File System(s)

• Repairing the tracks to create a level surface

• Provide the Space Utilization Specialist a copy of all documentation containing the serial numbers of the removed equipment.

1.3.1. Contracting Officer's Representative (COR): A primary COR willl be appointed throughout the life of the Contract and will provide guidance on all things contract related to the Customer, Medical

Department or Equipment Management Branch/Property when requested.

1.3.2. Any service performed without the prior approval of one of the individuals outlined in 1.4, shall be at no cost to the Government.

2. Services Required and Specific Tasks:

2.1. De-Installation: Disassembly and removal of the Rolling File Systems from the Department of Emergency Medicine, Medical Records and Human Resources located at Buildings 7500, 7503 and 7505, 1650 Cochrane

Circle, Fort Carson, Colorado, 80913.

• Rolling file system from B7500 R1963 (Department of Emergency Medicine)

• Rolling file system from B7500 R1951A (Department of Emergency Medicine)

• Rolling file system from B7503 R1506 (Medical Records)

• Rolling file system from B7505 R125 (Human Resources)

2.1.1 Contractor shall provide documentation for the removed equipment specified in paragraph 2.1 to the Space Utilization Specialist. Documentation must specify the serial numbers for the equipment removed.

2.2. Disposal & Transportation: Contrator shall dispose or retain possession of the old equipment specified in section 2.1 and transport any and all equipment from the base.

2.4. The Government will not be responsible for any damages or loss of Contractor supplies, materials, or equipment nor is the Government responsible for any damages or loss of the Contractor employees' personal belongings, due to fire, theft, accidents or other causes.

2.5. The contractor shall report immediately to the COR, all accidents which may arise out of or in connection with the performance of services required within the scope of this contract.

2.6. Contractor is fully responsible for the security of any Contractor-furnished property, supplies, or equipment utilized in the performance of these contracted services and agrees to not hold the government liable for any damage or theft thereof.

2.7. The Contractor shall be responsible for safeguarding all Government property provided for Contractor use and information of a confidential or sensitive nature. Neither the Contractor nor any of its personnel shall disclose, or cause to be disseminated, any information concerning the operation of the MTF that could result in, or increase the likelihood of, the possibility of breach of security or interrupt the continuity of operations or which breach the requirements of the Federal Privacy Act of 1974. However, the Contractor may be required to provide testimony or deposition in lawsuits or other administrative, civil or criminal proceedings.

2.8. The Contractor is not responsible for the maintenance of equipment listed when damage resulted from act of God, or Government neglect/misuse/abuse, or when services from other than the Contractor's personnel have been performed.

2.9. Delays caused by Government will not be counted as contractor "down time" for the purpose of this requirement.

2.10. The Contractor shall establish and follow a procedural checklist when performing scheduled services.

Any updates shall be supplied to the COR.

2.11. The Contractor shall comply with applicable federal, state, and local laws and regulations.

2.12. The contractor shall use reasonable efforts to continue uninterrupted until the equipment is operational.

Equipment which is left unserviceable at the end of normal duty hours or until performance can be resumed, will be identified by the Contractor notifying the government POC and the COR. If the Contractor determines that additional parts are required, services will resume as soon as parts become available. The COR will be informed personally or in writing of the equipment status prior to the Contractor leaving the work site.

2.13. Contractor personnel shall leave job site in the same condition as found upon arrival.

3. Hours of Performance: Government facility office hours, facility operating hours, and the Contractor support hour requirements often coincide, however they may differ. Please refer to the following:

3.1. Government Facility Office Hours: For de-installation and installation the Government facility office hours are 0700-1600 except U.S. Holidays identified in paragraph 3.5 below or when the Government facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. The contractor may work during the weekends which include Saturday & Sunday.

3.3. Contractor Support Hours: The Contractor shall provide support between the hours of 0800-1630 Monday to Friday. The Contractor shall maintain an adequate workforce at all times, for the uninterrupted performance of all tasks defined within this PWS when the Government facility is not closed for the above reasons. When hiring personnel, the Contractor shall keep in mind that the stability and continuity of the workforce is essential.

3.4. Training Holidays: The government will observe training holdays and will notify contractor should any changes be made to scheduled maintenance.

3.5. Government Observed Holiday: Work shall not be performed on U.S. federally recognized holidays occurring during the normal workweek unless otherwise directed by the Contracting Officer. When a U.S.

holiday occurs on a Saturday or a Sunday, the holiday is observed on the preceding Friday or following

Monday, respectively.

9.5. Access & General Protection/Security Policy & Procedures. This standard language is for contractor employees with an area of performance within Army controlled installation, facility, or area. Contractor and all associated sub-contractors employees shall provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of

Emergency Services or Security Office. Contractor workforce must comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel) as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any individual facility or installation change, the Government may require changes in contractor security matters or processes. For Contracts that Require Handling or Access to Classified Information. Contractor shall comply with FAR 52.204-2, Security Requirements. This clause involves access to information classified "Confidential," "Secret," or "Top Secret" and requires contractors to comply with- The Security Agreement (DD Form 441), including the National Industrial Security Program Operating Manual (DoD 5220.22-M); any revisions to DOD 5220.22-M, notice of which has been furnished to the contractor. A Secret security clearance is required for the contract employee to perform the scope of work. The Contractor shall have a proper Facility Clearance (FCL). The Contractor's employee shall report to the workplace with a favorable National Agency Check with Law and Credit/T3/T3R and a Secret or Interim Secret clearance in order to gain access to the workplace. DD254 shall be processed at no added cost to the contract.

9.6. Freedom of Information Act Program (FOIA & PRIVACY ACT). The contractor shall comply with DOD Regulation 5400.7-R, DOD Freedom of Information Act Program requirements. The Freedom of Information Act sets policy and procedures for the disclosure of records to the public and for marking handling transmitting and safeguarding For Official Use Only materials.

9.7. Reporting Requirements. The contractor shall comply with DoD 5200.2-R, January 1987, Personnel Security Program and AR 380-67, 9 September 1988, Department of the Army Personnel Security Program Regulation. Contractor shall report to the BAMC Security Manager any information or circumstances which may pose a threat to DOD or contractor personnel, resources, or DOD information.

9.8. Removal of Contract Employee. The government reserves the right to require immediate temporary or permanent removal of any individual whose actions raise reasonable suspicion that patient care or services may be compromised in any way or that pose a threat of harm to other contractor/government personnel or self. The employee may be required to submit to drug/alcohol testing. The government reserves the right to require temporary or permanent removal of any individual who refuses testing. Notification of all removals will be made by the Contracting Officer Representative (COR). Removal of any individual does not relieve the contractor of any performance requirement.

10. Conduct.

10.1. The Contractor is responsible for its personnel’s conduct, who are expected to act and present themselves in a professional manner while within EACH property, and in the course of providing these contracted services.

10.2. Inquiries. Contractor shall ensure its personnel do not respond to any media inquiries, nor otherwise engage in any interview, nor provide any comment or response to media personnel regarding

Evans Army Community Hospital without the knowledge and written approval from the EACH commander.

10.3. Complaints. The Contractor shall have no more than one (1) substantiated complaint about any of its personnel providing these contracted services during any one (1) period of performance. Any complaints that are validated by the SPD Section Chief shall be reported in writing to the Contracting

Officer Representative (COR) for appropriate action.

(END OF STATEMENT OF WORK)