Soo Lock - NLC - Briefing to Industry - 1 Oct 20 For Posting on Beta.Sam.pdf
PDF 20 MB Posted
- Solicitation number
- PANGLR20P0000001990-NewSooLockChamber-IndustryEngagement
About this file
This document outlines an industry engagement process for the construction of a new lock chamber at the Soo Locks in Sault Ste. Marie, Michigan. The U.S. Army Corps of Engineers, Detroit District, will share 70% design plans on August 28, 2020 and require security clearance to access them. An overview webinar of the chamber design will take place on October 1, 2020 and require preregistration. A site visit is scheduled for October 6, 2020 and also requires preregistration. Individual meetings will be held with contractors from October 6 through 8, 2020 to gather feedback on the plans from a constructability perspective. Appointments for the meetings must be scheduled in advance. A list of discussion questions will be posted on August 28, 2020. The engagement events aim to seek contractor input to improve clarity and constructability prior to finalizing plans for the new lock chamber construction project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Site Visit Roster.pdf | ||
| NLC Industry Engagement_Final_29Jul2020.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
.59
“The views, opinions and findings contained in this report are those of the authors(s) and should not be construed as an official Department of the Army position, policy or decision, unless so designated by other official documentation.”
INFORMATION CONTAINED IN THIS DOCUMENT IS PRE-DECISIONAL
AND NOT TO BE RELEASED OUTSIDE THE DEPARTMENT OF THE ARMY
Sandra Kenzie Darin H. White, P.E.
1 Oct 20
NEW LOCK AT THE SOO
NEW 3RD LOCK
INDUSTRY DAY PRESENTATION
Procurement Process Justin Bennett & Sandy Kenzie– Contract Specialists Louisville & Detroit districts Office Phone: 502-315-6203 (J. Bennett) & 313-226-6819 (S. Kenzie) Email Justin.K.Bennett@usace.army.mil & Sandra.M.Kenzie@usace.army.mil mailto:Justin.K.Bennett@usace.army.mil mailto:Sandra.M.Kenzie@usace.army.mil
PROCUREMENT SCHEDULE
DATES ARE APPROXIMATE AND SUBJECT TO CHANGE
ISSUE SOLICIATION (STAGGER 1) EARLY JUNE 2021
SOLICITATION CLOSES (STAGGER 1) LATE JULY 2021
EVALUATION BOARD (STAGGER 1) AUGUST 2021
ISSUE STAGGER 2 AMENDMENT AUGUST 2021
SOLICITATION CLOSES (STAGGER 2) OCTOBER 2021
EVALUATION BOARD (STAGGER 2) NOV/DEC 2021
PREPARE FOR AWARD JANUARY 2022
AWARD FEBRUARY 2022
File Name
How to obtain the solicitation:
• BETA.SAM – BETA.SAM.GOV
• Solicitation Number is W911XK20R0013.
• View interested vendors list and register as an interested vendor.
• Register to receive notifications and updates / amendments.
• RFP technical information will be posted on the BETA.SAM website at: beta.SAM.gov.
http://www.fbo.gov/
Obtaining the Issue Documents
• Requirements to download Technical Data Package
1) Need to be registered in Beta.SAM and System for Award Management (SAM)
• Any amendments issued to the RFP will also be posted here.
• Pre-Solicitation Notice – posted to FBO at least 15 days prior to the planned date of advertisement.
• Advertisement – minimum of 30 days to prepare proposals for EACH stagger phase. Offerors must submit a Stagger 1 Proposal in order to be eligible to submit a Stagger 2 proposal.
The Procurement process
• This project will be a Design-Bid-Build (D-B-B) Request for Proposals (RFP).
• Project award will be made on a “Best Value Trade-off” basis as described in the evaluation criteria.
• Proposals must be submitted on time.
* The Detroit District is in the Eastern time zone.
• The Source Selection Evaluation Board (SSEB) will evaluate contractors’ proposals based on specific factors which are defined in the RFP Package.
Proposal Requirements
• Source Selection Criteria for an Unrestricted “Best Value Trade-off” usually consists of these elements:
• Volume I – Factor I: Project Management, Quality Control, Key Personnel, and Schedule
• Volume I – Factor II: Planned Technical Execution of Key Work Elements
• Volume I – Factor III: Past Performance Confidence
• Volume I – Factor IV: Project Labor Agreements
• Volume I – Factor V: Small Business Participation Plan
Submit your best proposal the 1st time. Discussions may not be opened, if we receive an initial proposal that is awardable.
Proposal Requirements (cont.)
• Each offeror is to submit a Small Business Participation Plan
• This is an evaluated element in your proposal (Reference Section 00 22 12 in the RFP).
• Must be submitted by both Large AND Small business offerors.
• Large Business offerors MUST also submit a Small Business Subcontracting Plan.
• Although this is not a rated element as a part of the Source Selection process, it is a condition of award.
Proposal Requirements (cont.)
• Instructions for submitting a Request for Information (RFI) will be included in the solicitation.
• RFIs for these projects will be received and answered through the Projnet system: www.projnet.org o Any RFIs submitted directly to the project team will not receive a response, and will be directed to the Projnet system.
• Each project will have a Projnet Bidder’s Key, which is used to post your RFIs to the proper project.
o The project Bidder’s Key will be included in the Projnet Instructions section of the RFP.
• Requests for Information and their responses will be available for public review through Projnet.
http://www.projnet.org/
Q&A
SOO LOCKS LOCATION & IMPORTANCE 11
Soo Locks
The New Soo Lock would eliminate the single point of failure in our Nation’s iron ore supply chain
BACKGROUND – SOO LOCKS COMPLEX
UNIT 10 &
SLUICEWAY
NORTH
POWER
PLANT
(NPP)
1943 1968 1914 1919
800’ 1200’ 1350’ 1350’
80’ 110’ 80’ 80’
31’ 32’ 23.1’ 23.1’
MacArthur Poe Davis Sabin
Built
Length
Width
Depth
Sault BACKGROUND – SOO LOCKS COMPLEX
NEW LOCK STATUS
FY19 FY20 FY21 FY22 FY23 FY24 FY25 FY26 FY27 FY28 FY29 FY30
* Early completion could be realized with approval of continuing contracts clause, efficient funding, and favorable weather conditions
Design
Contract Procurement
Construction
Phase
Phase
Phase
Upstream Channel Deepening (UCD)
Upstream Approach Walls (UAW)
New Lock Chamber (NLC)
WE ARE HERE
UCD 2020
Work AreaUCD 2021 Work Area
UAW 2021
Work Area
NLC 2022 Forward Work AreaN
UAW 2022 & 2023
Work Area
BACKGROUND - SITE PLAN – OVERVIEW – NEW LOCK
Poe 2.0
INITIAL ACTIVITIES - ACCESS
• Access to the “Island” will primarily be by water for labor, equipment and materials (red arrows)
• During winter months (15 Jan – 25 Mar) navigation ceases and water transportation will not be possible due to ice
• Limited access will be provided through the facility during winter months (yellow arrow)
• Check the weather – it gets cold!
INITIAL ACTIVITIES - SECURITY
• Soo Locks is a secure DoD facility.
• Personnel are subject to rules/regulations to work at an international port and within a DoD facility.
• All Contractor personnel will be subject to a National
Crime Information Center (NCIC) check and FBI fingerprint check.
• Contractor personnel needing access to SCADA and other sensitive areas (Buildings, Operating Shelters, Galleries, Deep Service Tunnel) will require a more extensive background check.
• Contractor personnel must carry picture ID.
• Contractor shall keep a Security Access List.
• Contractor personnel will be issued access cards which will be programmed appropriately.
INITIAL ACTIVITIES - FENCING
• Establish New Fence Line
• Erect a Construction Fence on the South Wall of the Davis Lock
• Erect a Construction Fence south of the Unit 10 Powerhouse
• Erect a Secure Gate at the end of the Bridge to the Main Powerhouse
• Establish concertina wire along Unit 10 Tail Race as needed to establish secure perimeter
• Demolish Existing Security Fence along North Wall of the Sabin Lock
FIRST STEP….GET TO A DEWATERED CHAMBER
Key Activities
• Cofferdam
• Electrical Relocation
• NPP Bridge
• South Davis Wall Stability
COFFERDAMMING SURFACE 20
• Cofferdam Cells – 65’ and 78’ Diameter
• Soil-Cement-Bentonite Wall (green), 1100’ Long, 10’ – 20’ Deep
• Grout Curtain (red) – Top of rock down
• Pipe Pile / Z-Pile Hybrid Wall (pink), 30” Pipe Piles with AZ14 Z-Piles
• South Davis Lock Wall - stability mitigation required
Sabin Lock
Davis Lock
Existing cutoff wall
Cofferdam Cells Cofferdam Cells
Upper Pool 601.6
Lower Pool 580.1
COFFERDAM STRUCTURE AND GROUT CURTAIN
O ld p ow er ho us e
Remove existing timber crib cofferdam
Utilize existing clay cofferdam
Utilize existing concrete training wall
Utilize old powerhouse New
SCB
slurry wall
New SCB slurry wall
New hybrid wall
New Grout Curtain (green)
COFFERDAM STRUCTURE AND GROUT CURTAIN
New Lock Grout Curtain
• Primary holes on 20’ centers, with secondary split spaced between (10’ centers), tertiaries will be installed based on results of the other holes
• The majority are battered at 20°and extend to approximately 10-feet below the nearest monolith foundation elevation
New Well Grout Curtain
UPSTREAM COFFERDAM CELLS
Existing Cell
(To be Removed) Installed by UAW Contractor
DOWNSTREAM COFFERDAM CELLS
Cofferbox: 1) Space truss w/skin
2) Contains discharge pipes
3) Filled with concrete
HYBRID WALL
Existing Cell
Installed by UAW Contractor
U/S Cofferdam Cells
(to be removed)
Upstream Approach
Walls
New Lock Chamber
NPP BRIDGE
Ramp to Crib Dam
Platform
Utility/Pedestrian Bridge
Vehicular Bridge
- Abutment and Piers on Drilled Shafts to rock
- N. Pier in close proximity to existing power plant wall.
- Designed for staged construction with Red portion as Base and Remainder as options
- Design is at 30% phase
SOUTH DAVIS WALL STABILITY
• Rock Anchors
– 28 Monoliths, 54 anchors total.
– (6) 140 kip, 4-strand anchors
– (26) 300 kip, 9-strand anchors
– (8) 440 kip, 13-strand anchors
– (14) 880 kip, 25-strand anchors
• Tie-Bars (South Davis Wall to North Poe Wall) 26 Monoliths, 330K per monolith, 2 per monolith, 165K each
• Alternate Design – Struts in lieu of Tie-Bars
NEXT STEP….DEMOLITION/ROCK EXCAVATION
NEW PUMPWELL
CIVIL
• Demolition of North/South Sabin Wall
• Demolition of Existing F&E System
• Rock Excavation
• Soil Excavation – South Sabin/North Davis
• Fill Davis Chamber
• Disposal: NW Pier, Davis Chamber, North Wall
N
SOO LOCKS- SITE UTILIZATION
• Haul roads/access routes are conceptual and not required by the Contractor
SOO LOCKS - DEMOLITION
Sabin Chamber to be Removed
SOO LOCKS – DEMOLITION/EXCAVATION
Prior to Dewatering
SOO LOCKS – DISPOSAL
Disposition of Materials:
Demolished Concrete – NW Pier/Unit 10 Spoil Site Rock Excavation – NW Pier/Davis Chamber/Haul Roads Soil Excavation – NW Pier/Davis Chamber/North Chamber Fill Area
NW Pier Spoil Site
Unit 10 Spoil Site
North Chamber Fill Area
Davis Chamber Fill
GEOLOGICAL MATERIALS 37
LOCK FOUNDATION CONSIDERATIONS 38
Foundation Elevation sheet series
• Rock bedding dips towards upstream (west) at approximately 3’ per 100’ and towards north approximately 1’ per 100’.
• All rock sections and profiles were interpreted between borings, so much uncertainty exists between borings.
• Based on those interpretations and assumptions, any monolith foundation within 5-feet of a clay seam or weathered shale zone was lowered for their removal.
Upstream Downstream
Stair-stepped foundation trying to maintain consistent elevation
LOCK EXCAVATION METHODS AND CONSIDERATIONS
Excavation Method sheet series • Currently, we anticipate using very controlled excavation, including line-drilling, saw-cutting, and mechanical methods, to avoid dip influenced over-break and to not aggravate locked-up internal stresses which could cause lateral off-set and vertical rebound.
• Poe Excavation required closely spaced line-drilling and “broaching” techniques.
• We currently have many inside and outside corners with different foundation elevations stepping through the foundation, including a centerline drain excavation, resulting in intricate excavation geometries.
Saw cutting Line Drilling
SHAFT #6 EXCAVATION
View Looking Downstream
View Looking South • Geology is assumed based on few nearby borings.
Drilling will be done next month.
• Shaft excavation Is approximately 31’ diameter and 63’ deep.
• Assume vertical shaft excavation will be drill and blast with light charges. Nearby critical structures will have low PPV requirements and seismic recording.
• Initial support will be contractor designed based on their methods.
• Previous shaft excavations were successful (Davis Pump Well, MacArthur, and Poe Pump Well).
LOCK FOUNDATION ELEVATION CONSIDERATIONS 42
Verification Boring sheet series
• Verification borings (PQ core and downhole tele-viewer) will be conducted to verify design foundation elevations prior to excavation.
• It will be encouraged to have the foundation try to stay at the foundation elevation as much as possible, except when chasing clay/weak seams.
• Mud mat placement required for leveling/cover exposed rock.
For Official Use Only
EXISTING PUMPING SYSTEM & NEW PUMP WELL
350 ft between valve vault and cofferdam All discharge lines include flap valve, knife gate valve and check valve.
• Located in the existing Davis Lock chamber just north of the Davis Well
• Replaces Davis Well and Poe Well for dewatering capacity
• Ability to muck in the New Pump Well and the Davis Well
• Dry well when not in use
• Discharge east through DS cofferbox
NEW PUMP WELL
Discharge lines
DS Cofferbox
NEW PUMP WELL EXCAVATION (DAVIS FLOOR)
Contractor will have to cut through steel reinforced concrete floor and culverts to get to the top of rock.
Vertical 2-7/8” twisted steel dowels (10” on center) are 4’-5’ into rock.
• Large amount of structural geometry of features with reinforced steel will need to be demolished prior to rock removal.
• Some of the culverts need to be plugged with some flowable fill or bulkheads to propagate removal in drier conditions within the pits.
• Assume demolition will be conducted with mechanical methods.
NEW PUMP WELL EXCAVATION (BEDROCK)
• Large amount of structural geometry of features with reinforced steel will need to be demolished prior to rock removal.
• Some of the culverts need to be plugged with some flowable fill or bulkheads to propagate removal in drier conditions within the pits.
• Assume demolition will be conducted with mechanical methods.
• Grout curtain will be installed from the floor of the dewatered footprint. There may be some high pressure flow coming back into the boreholes with which will have to be contended.
• The Davis Tunnel will be plugged and abandoned (possibly still used during construction), the Sabin Tunnel will be deepened on both south and north ends adjacent to the New Pump Well to achieve required grade.
Areas of brand new rock excavation areas (red) and rock adjacent to previous excavations (yellow)
Sabin tunnel
Davis tunnel
VARIOUS TUNNEL EXCAVATIONS
• Tunnels associated with the Davis Pump Well and New Lock Dewatering System will involve modification of the interior of existing tunnels, deepening of the floors, and re-establishing a deeper configuration of the tunnel.
• Initial support will be contractor designed based on their methods.
• Previous tunnel excavations have been successful (Davis Pump Well, MacArthur, and Poe Pump Well).
Max area of new rock excavation (red)
• 4’ x 7’ tunnel minimum (same dimensions as existing dewatering tunnels)
• New Lock dewatering pit drains south through new wide wall monoliths, connects to existing North Sabin Tunnel, and into the New Pump Well
• Removable bulkhead located in monolith S36 to provide a positive closure that can be safely inspected
NEW LOCK DEWATERING TUNNEL
• Demo existing pumps, walkway framing, and sluice gates
• Plug existing discharge line and Davis Lock Dewatering Tunnel
• Raise floor of well to match tunnels
• Install staircase
• Install overhead 2 ton monorail crane and construct new floor with opening for mucking
• Dry well when not passing water through to New Pump Well
DAVIS PUMP WELL
Crossover Tunnel South Sabin Tunnel
Concrete fill
New floor (same EL as existing)
Existing discharge (to be plugged)
Mucking opening
POE PUMP WELL
• Demo existing pumps, walkway framing, sluice gates, and plug discharge pipe
• Connect existing dewatering tunnels with 54” diameter pipes and discharge into Crossover Tunnel
• Bonneted knife gate for each dewatering tunnel to control dewaterings
• Removable bulkhead for safety closure
• New 2 ton jib crane
• Final well shape to be “somewhat” circular, built up with new concrete
Poe Dewatering Tunnel
MacArthur Dewatering Tunnel
Bonneted Knife Gate Valves
Crossover Tunnel
Bulkhead
Bulkhead Slot
Ladder
Jib Crane
Existing Discharge Pipe
Sump Pump
For Official Use Only
ELECTRICAL – PUMP WELLS
• New pump well
• Fed from Shaft 6 13.8kv switchgear.
• Power distribution utilizes 5kv switchgear and a 480V MCC.
• Pump motor control via 5kv Allen-Bradley VFD’s
• Poe Well
• Existing MCC A to be demolished and replaced with new.
• Davis Well
• Existing MCC B reused.
• New breakers to be added for new loads.
BREAK
**********TAKE A 10 MINUTE BREAK***********
NEXT STEP….LOCK STRUCTURE:
CONCRETE STRUCTURE/HYDRAULIC STEEL
STRUCTURES/MECHANICAL/ELECTRICAL
CONCRETE STRUCTURES 54
Soo Locks
Crescent Monoliths
Chamber Monoliths
Transition Monoliths
Retaining Wall
Compressor Tunnel
Widewall Monoliths
CONCRETE LOCK WALLS 55
• Widewall Monoliths: Monoliths on the U/S and D/S end of the chamber that house the Bulkhead Recesses, Ship Arrestors, Miter Gates and Culvert Valves. Also, these monoliths have the intake and discharge for the filling and emptying system.
• Chamber Monoliths: Monoliths toward the middle of the chamber that primarily have a culvert and gallery.
CONCRETE LOCK WALLS 56
• Widewall Monoliths: Vary depending on location and purpose.
CONCRETE LOCK WALLS 57
• Chamber Monoliths: Typical.
FILLING AND EMPTYING SYSTEM 58
FLOW
FLOW
Laterals
• Poe Lock Design
• 13’ x 14’ Culverts
• Each wall “feeds” a set of laterals
Intake Discharge
Reverse Tainter Valves
Miter Gates
CULVERT VALVES AND MACHINERY
• Exact copy of existing Poe Lock.
• Reverse Tainter style.
• Vertically-framed.
• Minimal deviation from Poe design as to not affect flow geometry.
HSS – TRASH SCREENS 60
• Culvert intake geometry identical to Poe Lock.
• Existing Poe Lock trash screens have functioned properly.
• New Lock trash screen is identical to Poe Lock using current materials and member sizes.
HSS – U/S & D/S MITER GATES 61
GATE LEAFS
• Same control dimensions as the existing Poe U/S and D/S miter gates.
• Gates are meant to be interchangeable with the Poe Lock.
HSS – U/S & D/S MITER GATES 62
GATE LEAFS
• Horizontally framed miter gates.
• 62’-11” between leaf contact points.
• Horizontal girder depth of 5’-5 1/2” o/o girder flanges.
Downstream Miter Gate Leaf
56.5 ft c/c top/bottom girders
13 horizontal girders
Upstream Miter Gate Leaf
34.8 ft c/c top/bottom girders
8 horizontal girders
MITER GATE MACHINERY
• Poe Lock Design (Rehabilitated)
HSS – CULVERT BULKHEADS 64
• Based on Poe Lock culvert bulkheads.
• Interchangeable with the Poe Lock.
• Designed to dewater culvert valve for maintenance while continuing lock operation.
• Installation and removal under equal hydrostatic head. Cannot be raised or lowered through flow.
• Incorporates sluice gate similar to MacArthur Lock culvert bulkheads for re-watering.
• ASTM A709 Grade 50 Zone 3 material.
• Member size and spacing is optimized to fit within narrow recess.
Sluice Gate
Section
HSS – MAINTENANCE BULKHEAD RECESS
FILLER AND LINER
• Maintenance bulkhead recess geometry required to be similar to existing Poe Lock.
• Poe Lock maintenance bulkheads will be used for dewatering of the New Lock chamber.
• New Lock filler is a 3-D trussed arrangement with skin plate face.
• Entire recess will be lined with steel plate.
New Lock Recess
Poe Lock Recess
Existing Poe Lock Filler
SHIP ARRESTORS
• Intended to protect miter gates from collision with a vessel.
Ship Arrestor
SHIP ARRESTORS
• Consists of an aluminum boom (sacrificial) which carries a 3.5” wire rope.
• 3.5” wire rope is connected to a spiral drum on each Lock Wall
(recessed). Spiral drum has 2 Low Speed High Torque (LSHT) Hydraulic motors (arresting force).
HSS – SHIP ARRESTOR BOOM 68
• Similar design as Poe Lock (see picture)
• Aluminum boom
• Latching issues on the Poe Lock due to excessive lateral displacement from solar thermal effects. Aluminum heat shields shown along sides of the boom.
MECHANICAL – HYDRAULIC SYSTEM
• 4-corner setup with 4 Hydraulic Power Units
– HPUs resemble Poe’s but one pump can run entire corner
– 2nd pump as backup
• Oil overflow tank in gallery with level alarms, breather, and leak shutdown
• Slightly higher working pressure
– Allows higher operating head while maintaining interchangeability with Poe
MECHANICAL - UTILITIES
• Air/steam distribution throughout chamber from compressor tunnel
– Sufficient valving to close off small sections for maintenance without loss of service
• Gallery ventilation
• Two sump pumps per pit for redundancy
ELECTRICAL – LOCK LIGHTING
• High Mast Lighting
• Modeled Using Acuity Visual Lighting Software
• Design Criteria – Minimum of 3 FC at low pool.
• 8 – 80 ft. poles for lock chamber
• 6 – 85,000 Lumen LED Fixtures/Pole (1000 Watt Equivalent)
BUILDINGS
Building Locations
Lock Control Houses
New Lock Chamber Outline
Cells to Close off Davis Chamber
BUILDINGS
Lock Control Houses •Load Bearing wall system consists of pre-cast concrete “sandwich” panels •Roof system will be steel trusses/joists with metal deck and rigid insulation •Buildings are approximately 60ft (E-W), 30ft (N-S) •Finished floor of bldgs will be secondary pour
HANDS FREE MOORING
• Hands free mooring will be partially incorporated into the new lock chamber construction. Recesses and fillers will be installed.
• Dynamic units are used to “grab” the vessels instead of tying the vessels off to the lock walls with lines.
• 4 units will be required on the North and and 3 units on the South.
• Option in the construction contract for equipment
TRAFFIC/PAVE PLAN
• Mobile Crane access to Maintenance Bulkhead slots and closure cells.
• Truck/cart access around lock structure.
• Truck/cart access to Unit 10 tailrace
• Truck/cart access to North Power Plant
From Plans drawings 01-RF101-10
CONCURRENT STEP….APPROACH WALLS
DOWNSTREAM WORK
320LF of End cells w/ fenders both sides; bollards
1200LF Pile & Lagging Wall w/ Bollards at 60’.
1040LF Pile & Lagging Wall w/ Bollards at 60’
DOWNSTREAM APPROACH WALL
New 45’ to 65’ Dia.
Cells with fenders on 3 sides and bollards
New Pile & Lagging Wall (rehab existing timber cribs)
Tie-backs to Poe Guardwall
Tie-backs to Drilled Shafts
PILE AND LAGGING TYPE WALL WITH TIE-BACK
3’ Dia. Rock Core
W18x311 at 8’ spacing
1’ x 4’ Precast Panels
4’ dia. At 8’ spa.
RC Drilled Pier for tie-back
2.5” Dia. Rods
Existing Timber Crib Walls
New Cap and Bollard Foundations, Ductbank, lighting
BASE AND OPTIONS – STRATEGY
BASE:
1. Shaft 6
2. NPP Bridge
3. Damming Surface
4. Unit 10 Electrical
5. South Wall
Stability
6. Dewater
OPTION 4a & 4b:
1. Chamber
Monoliths
2. LateralsOPTION 3:
1. U/S Widewalls
OPTION 2:
1. D/S Widewalls
2. Fabricate MG, CV, SA
4a & 4b3 2
OPTION 1:
1. Demolition of
Existing Sabin Walls
2. Rock Excavation
3. Mud Mat
OPTION 5:
1. Commissioning
2. Installation of MG, CV, SA
3. Site Work
4. Lock Floor
5. Removal of
CofferCells
OPTION 6:
1. D/S Approach
Wall
OPTION 7:
1. East Center Pier
Rehab
5 6
“OTHER OPTIONS”
Option 8: New Pumpwell – Remaining scope.
Option 9: HFM – Equipment including Dynamic Units, Electrical, etc.
Option 10: D/S Ship Arrestors – Equipment (arresting machines, fender boom, etc.)
Option 11: NPP Bridge Ramp – Ramp to Center Pier Option 12: NPP Bridge Widening – “Highway” portion of bridge.
VIRTUAL REALITY
| New LOCK at the SOO�New 3rd Lock �INDUSTRY DAY PRESENTATION�� |
| Procurement Process�Justin Bennett & Sandy Kenzie– Contract Specialists�Louisville & Detroit districts�Office Phone: 502-315-6203 (J. Bennett) & 313-226-6819 (S. Kenzie)�Email Justin.K.Bennett@usace.army.mil & Sandra.M.Kenzie@usace.army.mil |
| PROCUREMENT SCHEDULE�Dates are approximate AND SUBJECT TO CHANGE |
| How to obtain the solicitation:�� |
| Obtaining the Issue Documents� |
| The Procurement process�� |
| Proposal Requirements� |
| Proposal Requirements (cont.)� |
| Proposal Requirements (cont.)� |
| Q&A |
| Soo Locks location & Importance |
| Slide Number 12 |
| Slide Number 13 |
| New Lock Status |
| Background - Site Plan – overview – NEW LOCK |
| Initial activities - access |
| Initial activities - Security |
| Initial activities - FENCING |
| First step….get to a dewatered chamber |
| COFFERDamming surface |
| COFFERDam Structure and grout curtain |
| COFFERDam Structure and grout curtain |
| UPSTREAM COFFERDAM CELLS |
| DOWNSTREAM COFFERDAM CELLS |
| HYBRID WALL |
| Electrical relocation – Unit 10 |
| Electrical Relocation – Existing |
| Electrical relocation – New lock |
| Slide Number 29 |
| South davis wall stability |
| NEXT step….Demolition/rock excavation � New pumpwell |
| Civil |
| Soo Locks- Site Utilization |
| Soo Locks - Demolition |
| Soo Locks – Demolition/Excavation |
| Soo Locks – Disposal |
| Geological materials |
| Lock Foundation considerations |
| Lock Excavation methods and considerations |
| Shaft #6 Excavation |
| Tunnel ExcavatioN – Shaft 6 |
| Lock Foundation Elevation considerations |
| EXISTING PUMPING SYSTEM & new pump well |
| New Pump Well |
| New Pump Well Excavation (Davis Floor) |
| New Pump Well Excavation (Bedrock) |
| Various Tunnel Excavations |
| New Lock Dewatering Tunnel |
| Davis Pump Well |
| Poe Pump Well |
| Electrical – Pump Wells |
| BREAK |
| NEXT step….LOCK STRUCTURE:��Concrete structure/hydraulic steel structures/mechanical/electrical |
| Concrete structures |
| Concrete lock walls |
| Concrete lock walls |
| Concrete lock walls |
| Filling and Emptying System |
| Culvert valves and Machinery |
| HSS – trash screens |
| HSS – U/S & D/S Miter gates |
| HSS – U/S & D/S Miter gates |
| Miter gate machinery |
| HSS – Culvert bulkheads |
| HSS – maintenance bulkhead recess�filler and liner |
| Ship Arrestors |
| SHIP ARRESTORS |
| HSS – Ship arrestor boom |
| Mechanical – hydraulic system |
| MECHANICAL - UTILITIES |
| Electrical – New Lock Power |
| Electrical – LOCK control system |
| Electrical - CCTV |
| Electrical – LOCK lighting |
| Slide Number 75 |
| BUILDINGS |
| Hands Free Mooring |
| Traffic/Pave Plan |
| Concurrent step….approach walls |
| Downstream Work |
| Downstream approach wall |
| Pile and lagging type wall with tie-back |
| Base and Options – STRATEGY |
| Base and Options – STRATEGY |
| base and options – STRATEGY |
| Virtual reality |
File details come from the government source that posted it. Updated .