Panel_SOW.docx

DOCX document 17 KB Posted

Attached to
LITCHFIELD LIVESTOCK PANELS Federal contract opportunity
Solicitation number
140L1221Q0050
Issued by
Department of the Interior Bureau of Land Management California Region

View the file

Other files for this federal contract opportunity

Other files attached to LITCHFIELD LIVESTOCK PANELS, newest first.
File Type Posted
Sol_140L1221Q0050.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work Litchfield Panels

1.0 General

The Bureau of Land Management (BLM) requires supplying panels, connecting posts and bow gates for the Litchfield Wild Horse and Burro Facility. The overall purpose of the contract is to provide a heavy-duty portable panel to contain wild horses and burros at the facility and maintain a safe environment. This will replace an old fence system consisting of wire and wood poles and reduce the time repairing fence lines as well as serve as a mobile adoption facility. All panels, bows and gates shall have a protective grade, powder coat finish.

2.0 SPECIFICATIONS

A. Panels:

1. Panels shall be constructed of no less than 2 inch outside diameter (OD), 14-gauge tubing.

2. All panels shall have the exposed ends capped to prevent moisture and rust from getting inside the tubing.

3. Panels shall have a finished height of 6 feet when attached to the connecting posts and there shall be no protruding welds or sharp edges on finished products.

4. All joint connections shall have a saddle cut connection to frames to prevent protrusions and animal safety.

5. All panels should consist of one upright bar in the middle of the panel and no more than 9-1/2 inch rail spacing for the horizontal rails.

B. Connecting posts:

1. Connecting post shall be constructed of no less that 2.38 OD, 11-gauge tubing with a .120 wall thickness and be able to allow the panels to have a finish height of 6 feet when connected to the post.

2. Shall have the exposed ends capped to prevent moisture and rust from getting inside the tubing

3. Drop pens shall be connected to the post.

3.0 SUPPLIES REQUESTED:

350 EACH – 12 feet Livestock Panels 20 EACH – 3 way connecting posts 400 EACH – 2 way connecting posts Vendor to supply trucking to the Litchfield Wild Horse and Burro Corrals.

4.0 GOVERNMENT WILL PROVIDE:

Equipment to unload delivery at Litchfield Wild Horse and Burro Facility.

5.0 PLACE OF DELIVERY

The shipment shall be delivered to the below location.

USDI, Bureau of Land Management Litchfield Wild Horse and Burro Facility 474-000 Highway 395 East Litchfield, CA, 96117

File details come from the government source that posted it. Updated .