Palau IAP MAAS pads SOO for Materials.pdf
PDF 190 KB Posted
- Attached to
- Palau MAAS Pad Materials
- Solicitation number
- FA502526QA028
About this file
Summary: Statement of Objectives – Palau IAP MAAS pads Construction Project
This Statement of Objectives (SOO) outlines the requirements for the Palau International Airport Mobile Aircraft Arresting System (MAAS) Construction Project (Project Number ASZW245001). The project requires the Expeditionary Theater Engineer Group (ETSG) to construct concrete equipment pads at both ends of Runway 01 at Palau International Airport in Airai, Palau, with all work performed at that location.
The contractor must procure and deliver four categories of materials and equipment: (1) 220 cubic yards of 4000 PSI strength concrete with a concrete pump truck, delivered across four dates from November 19 to December 10, 2026, with slump testing per ASTM C143 prior to acceptance; (2) 145 cubic yards of aggregate materials (93 cubic yards of 3/4" Aggregate Base Course, 38 cubic yards of 6" Base Rock, and 14 cubic yards of 3/4" top Rock) deliverable no later than October 19, 2026; (3) construction materials including 140 sheets of 3/4" plywood, 380 pieces of 2"x4"x12" wood, 220 pieces of 2"x8"x12" wood, nails, screws, circular saw, table saw, and bull floats, all due October 19, 2026; and (4) one portable toilet and one handwash station with weekly service provision for a 60-day period from October 19 to December 17, 2026. The contractor is responsible for all delivery and transport costs, and all delivery dates must be confirmed at least 48 hours in advance with the Government representative. The technical point of contact is 1 Lt Nana Owusu-Nsiah at nana.owusu_nsiah@us.af.mil or +1 (671) 689-5361.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Statement of Objectives – Palau IAP MAAS pads Construction Project 19 August 2026
Palau IAP Mobile Aircraft Arresting System (MAAS) Construction Project Statement of
Objectives
Project Number: ASZW245001
1) PURPOSE/BACKGROUND: Project scope includes all material and equipment necessary for the
Expeditionary Theater Engineer Group (ETSG) to construct concrete equipment pads used for the
Mobile Aircraft Arresting System (MAAS) on both ends of Runway 01 at Palau International Airport
(ROR), Palau.
2) LOCATION OF ALL WORKS: Palau International Airport, Airai, Palau, 96940
a. All contractors shall deliver/mobilize and recover/demobilize from this location.
3) OBJECTIVES:
a. Procure 220 cubic yards (wet volume) of concrete and concrete pump truck: (Attachment 1)
a. 4000 PSI strength; contractor shall perform a Standard Test Method for Slump of
Hydraulic-Cement Concrete (i.e. Slump Cone Test) per ASTM C143 prior to acceptance of concrete.
b. Delivery days/times shall be coordinated between the Government representative and contractor a minimum of 48 hours prior to delivery.
c. Contractor is responsible for delivery and transport costs in accordance with the proposed delivery schedule in attachment 1.
b. Procure the following aggregate materials: (attachment 2)
a. 14 cubic yards of 3/4" top Rock
b. 38 cubic yards of 6” Base Rock
c. 93 cubic yards of Aggregate Base Course 3/4"
d. All aggregate materials shall be delivered no later than 19 October 2026, in consultation with government representative.
e. Contractor is responsible for delivery and transport costs.
c. Procure the following construction materials (attachment 3)
a. All construction materials shall be delivered to the job site on 19 October 2026
b. Contractor shall be responsible for the delivery of the construction materials
d. Procure the rental of one (1) portable toilet and one (1) handwash station (attachment 4)
a. The portable toilet and handwash station shall be delivered no later than 19 Oct 2026
b. Period of Performance will be for 60 Days 19 Oct 2026 to 17 Dec 2026
c. Contractors shall provide weekly services for the toilet and hand wash station.
4) TECHNICAL POINT OF CONTACT: 1 Lt Nana Owusu-Nsiah, (nana.owusu_nsiah@us.af.mil)
+1 (671) 689-5361
5) DELIVRY SCHEDULE (attachments)
Attachment (1) Concrete Schedule
Expected Delivery Date Volume (wet) Required Notes
19 Nov 26 40CY South MAAS pad
20 Nov 26 40 CY South MRES pad
9 Dec 26 80 CY North MASS Pad
10 Dec 26 80 CY North MRES Pad
Note: dates are “expected” and must be confirmed at least 48 hours prior to delivery.
Statement of Objectives – Palau IAP MAAS pads Construction Project 19 August 2026
Attachment (2) Aggregate Materials
Expected Delivery Date Unit Quantity
19 Oct 26 CY 93
19 Oct 26 CY 38
19 Oct 26 CY 14
Note: Delivery date shall be coordinated at least 48 hours prior to delivery.
Attachment (3) Construction Materials
Expected Delivery
Date
Item Unit Quantity
19 Oct 26 ¾” Plywood EA 140
19 Oct 26 Wood (2"X4"X12") EA 380
19 Oct 26 Wood (2"X8"X12") EA 220
19 Oct 26 20lb 16D 3" nails (860 per Box)
EA 4
19 Oct 26 20lb 16D Duplex 3" nails (860 per Box)
EA 4
19 Oct 26 20lb 3" construction screws (1600 per Box)
EA 2
19 Oct 26 Circular Saw EA 1
19 Oct 26 Table Saw EA 1
19 Oct 26 Bull Float 4’with 8 studs EA 4
Attachment (4): Toilet and handwash
Expected Delivery Date ITEM Unit Quantity
19 Oct 26 Portable Toilet EA 1
19 Oct 26 Handwash Station EA 1
File details come from the government source that posted it. Updated .