P27-04 Legion Pond Dam - Addendum # 1.pdf
PDF 9 MB Posted
- Attached to
- Legion Pond Dam
- Solicitation number
- 323-P27-04
- Issued by
- Harnett County, Charlotte City, North Carolina
About this file
Legion Pond Dam - Addendum #1
This addendum to Request for Bids (RFB) P27-04 is issued by the Town of Chapel Hill, North Carolina, Purchasing & Contracts Manager for the Legion Pond Dam project. The addendum provides modifications to the bidding documents and responses to prospective contractor questions regarding the dewatering of an existing three-acre pond, demolition of the existing dam embankment, and construction of a replacement detention basin with associated stormwater management infrastructure. Key deliverables include erosion and sediment control measures, tree removal with root ball excavation to three-foot depths, grading and fill placement with geotechnical observation, installation of a 24-inch reinforced concrete pipe (RCP) outlet system with an outlet riser structure, concrete emergency spillway construction, rip rap protection, temporary and permanent seeding, and site stabilization. The addendum updates the Unit Price Bid sheet (Section 3.02) and modifies four drawing sheets (Cover Sheet, ES101, CG102, and CD101). The project is awarded on a lump-sum basis with allowances, requires three responsive sealed bids before opening, and has a Notice to Proceed (NTP) expected by November 2026 to comply with tree-clearing seasonal restrictions. Substantial completion is required within 120 calendar days of NTP, with final completion within 140 calendar days, subject to liquidated damages of $250 per day for delay.
The addendum clarifies that the Town has obtained a Letter of Approval for coverage under North Carolina's statewide erosion and sediment control permit (NCG01) and will submit the Notice of Intent and pay associated fees, eliminating the need for the contractor to obtain E&SC and Certificate of Coverage permits. No other permits are required to be obtained by the contractor. Regarding site-specific construction concerns, the addendum confirms that debris shields will be installed on the four-inch inlet orifice to prevent clogging, with buoyancy analysis already performed during design; all trees identified on the Tree Survey sheet must be completely removed including root balls as documented in the geotechnical report; muck and loose sediment must be removed from under the outlet control structure and 24-inch barrel to one foot below existing ground surface or firm subgrade, whichever is deeper; precast structures are permitted for the winged endwall and riser/intake structure; on-site soil is expected to be suitable for backfilling but the contractor must test materials for compliance, with potential change orders if in-situ soil fails to meet specifications; and construction period extensions beyond 120 days may be granted for material lead times or weather delays but not for means and methods scheduling. Tree protection fencing must be installed around the entire project perimeter prior to any demolition work and maintained throughout construction, with visibility fencing limited to Legion Road frontage.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Legion Pond Dam Bid Document and Project Manual.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Addendum 1 – Legion Pond Dam RFP: P27-04, Town of Chapel Hill, NC 1 August 17, 2026
ADDENDUM 1
FOR
LEGION POND DAM
TOWN OF CHAPEL HILL, NORTH CAROLINA
BID: P27-04
TO: All Prospective Companies
FROM: Lenore Bishop, Purchasing & Contracts Manager
SUBJECT: Addendum 1 – Legion Pond Dam
DATE: August 17, 2026
This Addendum is being issued to provide additional information and answer the questions received from prospective Companies regarding the above-referenced Request for Bids. All other terms and conditions remain unchanged.
Modifications:
1. In Legion Pond Dam Project Manual; overall page 16 of 412; page 2 of 7 on the Bid Form for Construction Contract; Section 3.02 Unit Price Bids:
a. Remove and replace this sheet in its entirety with the new Unit Price Bid sheet attached as file [Bid Tab Update from PM_08.13.26].
2. In the Drawing Set – ZCP-25-36 Zoning Approved Plan:
a. Remove and replace with the attached new Bid Set Drawing pages the following Sheets:
Cover Sheet, ES101, CG102, and CD101. Attached as file [Modified Sheets From Drawings
– Bidding Revisions – 081326].
Questions:
Listed below are the questions received and the responses:
1. Is the contractor responsible for obtaining the E&SC and COC permits?
A. A Letter of Approval for coverage under NCG01 has been obtained by the Town. The Town will submit the required notice of intent and pay relevant fees for the final Certificate of Coverage.
RFP: P27-04, Town of Chapel Hill, NC 2 August 17, 2026
2. Are there any other permits the contractor needs to obtain and pay for on this project?
A. No.
3. Is NTP expected in November 2026 to comply with TOY restrictions for tree clearing, or can this be delayed to avoid construction through the winter?
A. Yes, NTP is expected by November.
4. Is this project being awarded as a lump sum or unit price contract?
A. The contract will be awarded on a Lump Sum basis with Allowances [See Project Manual, Article 12.01].
5. Are you requiring (3) bids before opening bids?
A. Yes. Three responsive sealed bids are required to be submitted before opening any bids, or the project may be re-bid at a later date.
6. Is there a concern that the 4-inch inlet orifice will get stopped up and create a flotation effect for the structure and outlet pipe?
A. No. A debris shield is specified for the 4-inch inlet orifice to reduce clogging. See CD102 Detail 3 for the debris shield to prevent clogging. In addition, a buoyancy analysis was performed during the design of the outlet riser system to account for clogging of riser orifice. Debris shields are not proposed for the remaining orifices on the OCS. A clarifying note has been added to Detail 1 on Sheet CD101.
7. Are all trees identified on Sheet #TS101 being removed completely? If so, the root mat on some of these is extensive and will cause significant damage when removed from locations where grading isn't taking place. What are the expectations for repairing the banks and other areas where grading isn't proposed, where cavities are left by stump removal?
A. Yes, all trees are to be removed along with their respective root balls as documented in the geotechnical report. A note has been added to Sheet CG102 under Dam Embankment Notes:
“THE EXISTING SLOPES ARE COVERED BY MATURE TREES. FOR SLOPE PREPARATION, TREES
SHOULD BE CUT, AND THE ENTIRE ROOT BALL SHOULD BE REMOVED FROM THE EXISTING
EMBANKMENT. EXCAVATE A MINIMUM 3-FOOT DEPTH INTO THE EXISTING EMBANKMENT
TO ACCOUNT FOR TREE ROOT BALL REMOVAL, BUT THE ROOT BALLS SHOULD BE REMOVED
SO THAT ALL ROOTS ONE-HALF INCH AND LARGER IN DIAMETER ARE REMOVED.
EXCAVATIONS MADE FOR REMOVAL OF TREES SHOULD FOLLOW EXCAVATION,
COMPACTION, AND BENCHING DETAILS.”
8. Regarding the fill of the existing pond basin up to the 300' contour elevation, will the existing bottom require any form of removal and disposal before placing fill? At what point in the sequence of construction is this fill dirt to be placed? Are we just spreading the fill over top of the muck? Please elaborate on fill placement requirements within the basin.
RFP: P27-04, Town of Chapel Hill, NC 3 August 17, 2026
A. Yes, muck and loose sediment should be removed from under the OCS and 24” barrel to a depth one foot (1’- 0") below existing ground surface or foundation subgrade, or to a firm and stable subgrade, whichever is deeper. Sheet CG102 has been updated to reflect this clarification. Fill may be placed directly over the existing pond bottom outside of these specific areas. The construction sequence on the Cover Sheet has been updated to provide information on when this is to occur.
9. Please confirm that precast structures can be used for the winged endwall and riser/intake structure.
A. Precast structures are allowed.
10. Please confirm that the contours on the face of the dam (west side) reflect finish grades, including the toe drain berm.
A. Grades shown on CG101 are final grades; see Toe Drain detail on CD105 for 3H:1V and 5H:1V sections.
11. Is on-site soil expected to be suitable for backfilling the 24" RCP? If not, will importing fill be addressed as a change order if needed, based on the geotech's reporting?
A. Based on the limited borings, it will likely meet requirements. However, the contractor should test the material to confirm it meets the specified requirements. We cannot guarantee that all excavated material (or a specific quantity) will be suitable. Additional information on the placement of fill within the embankment is provided under “Dam Embankment Notes” on sheet CG-102. In the event that in-situ soil from the site does not meet these requirements a change order may be necessary.
12. Can consideration be given to extending the construction period beyond 120 calendar days?
A. An extension of the construction period may be considered in the event of long lead times for construction materials or weather delays, not for means and methods reasoning in the schedule.
13. Can clarification be provided for the extent of perimeter fencing and the visibility fencing shown on Sheet ES101?
A. Tree protection fencing is to be installed around the entire perimeter of the project site per Town of Chapel Hill Building Department Regulations. A modified Sheet ES101 is provided in this addendum along with an updated bid tab which includes the updated quantity of this fence type. The fencing shall be erected prior to any demolition efforts beginning and shall be in place and maintained throughout the length of the project. Visibility fencing (shown on Sheet ES101 and in detail 8 on sheet CD104) is only proposed along Legion Rd.
Town of Chapel Hill, North Carolina Legion Pond Dam – Bid # P27-04
EJCDC® C-410, Bid Form for Construction Contract.
Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.
Lump Sum for Cash Allowance 1 $
Lump Sum for Cash Allowance 2 $
Lump Sum for Cash Allowance 3 $
Total for all Lump Sum for Cash Allowances $
3.02 Unit Price Bids
A. Bidder will perform the following Work at the indicated unit prices:
Item No. Spec. Section Description Unit Estimated
Quantity Bid Unit Price Bid Amount
Demolition, Dewatering and Erosion Control
1 NCDOT 1101 Work Zone Traffic Control LS 1 $ $
2 NCDOT 226 Grading for Comprehensive Grading LS 1 $ $
3 SS-2
Dewatering
Control and Monitoring of Dewatering Activities (Dewatering Pump)
LS 1 $ $
4 NCDOT 1607 Stone for Erosion Control, Class A (Gravel Construction Entrance) TN 27 $ $
5 NCDOT 1607 Geotextile for Drainage, Type 2 (Gravel Construction Entrance) SY 80 $ $
6 NCDOT 876 Rip Rap, Class B (Guide for Rip Rap at Pipe Outlets) TN 5 $ $
7 NCDOT 876 Geotextile for Drainage, Type 2 (Guide for Rip Rap at Pipe Outlets) SY 8 $ $
8 NCDOT 1605 Temporary Silt Fence LF 900 $ $
9 TOCH Detail -
EC-12.00
Orange, UV Resistant High Tensile Strength Polyethylene Laminar Barricade Fabric, Steel Posts, and a Sign for Tree Protection Fence
LF 2,900 $ $
10 NCDOT 1631
Matting for Erosion Control (Matting Blanket, Matting Installation)
SY 4,200 $ $
11 NCDOT 1660 Seeding and Mulching (Temporary Seed) AC 6.6 $ $
12 NCDOT 230 Borrow Excavation (Topsoil) CY 273 $ $
Bid Tab Update from PM - 8.13.2026
Addendum 1 – Legion Pond Dam RFP: P27-04, Town of Chapel Hill, NC August 17, 2026
Blake Cary Highlight www.tetratech.com
CLIENT INFORMATION:PROJECT LOCATION:
PROJECT DESCRIPTION / NOTES:
Tt PROJECT No.: CLIENT PROJECT No.:
ISSUED:
ENGINEERING, P.C.
Legion Pond Dam Alternative Selection Town of Chapel Hill, North Carolina
100% Progress Plans 1714 Legion Rd, Chapel Hill, NC 27517
100-WTR-T43655
To w n of
C ha pe l H ill
Town of Chapel Hill 6850 Millhouse Rd, Chapel Hill, NC 27516-8173 xx-xx-xx
4000 Sancar Way, Suite 135
Research Triangle Park, NC 27709
Phone: (919) 485-8278
6.87 TOTAL ACRES DISTURBED
FOR BIDDING:
JULY 13, 2026
VICINITY MAP:
NC License: C-2644
Call 811 Before You Dig SCALE: 1" = 500'
SHEET LIST TABLE
Sheet
Number Sheet Title SHEET DESCRIPTION
1 C101 COVER SHEET
2 G101 GENERAL NOTES
3 CX101 EXISTING CONDITIONS
4 DP101 DEMOLITION PLAN
5 ES101 EROSION AND SEDIMENT CONTROL PLAN
6 ES102 GROUND STABILIZATION AND MATERIALS HANDLING
7 ES103 INSPECTION, RECORDKEEPING, AND REPORTING
8 CG101 GRADING PLAN
9 CG102 GRADING SECTION AND STEEP SLOPE PLAN
10 CD101 CONSTRUCTION DETAILS - 1
11 CD102 CONSTRUCTION DETAILS - 2
12 CD103 CONSTRUCTION DETAILS - 3
13 CD104 CONSTRUCTION DETAILS - 4
14 CD105 CONSTRUCTION DETAILS - 5
15 TS101 TREE SURVEY
A PARCEL OWNED BY THE TOWN OF CHAPEL HILL LOCATED AT 1714 LEGION RD IN CHAPEL HILL, NORTH CAROLINA CONTAINS A 3-ACRE POND AND DAM, ORIGINALLY IMPLEMENTED AS A FARM POND MORE THAN 60 YEARS AGO, AS WELL AS THE FORMER HEADQUARTERS OF THE LOCAL CHAPTER OF THE AMERICAN LEGION. JURISDICTIONAL DETERMINATIONS BY NCDWR AND USACE HAVE BEEN CONDUCTED ON THE PROJECT SITE AND DETERMINED NO JURISDICTIONAL WATERS OR STREAM BUFFERS WITHIN THE PROPOSED AREA. THE PROJECT SITE DRAINS TO AN UNNAMED TRIBUTARY TO BOOKER CREEK (WS-V, NSW) WHICH FLOWS INTO THE JORDAN LAKE WATERSHED WHICH IS PART OF THE CAPE FEAR RIVER BASIN. THE TOWN SEEKS TO BREACH THE EXISTING POND EMBANKMENT AND REBUILD IN ITS PLACE A DETENTION BASIN WHICH PROVIDES SIMILAR STORMWATER PEAK FLOW MANAGEMENT
TO THAT WHICH THE EXISTING POND CURRENTLY PROVIDES.
PROJECT NARRATIVE
PROJECT AREA
1. OBTAIN NECESSARY PERMITS.
1.1. EROSION AND SEDIMENT CONTROL (E&SC) PERMIT AND A CERTIFICATE OF COVERAGE (COC) MUST BE OBTAINED BEFORE ANY LAND DISTURBING ACTIVITIES
(INCLUDING TIMBERING AND DEMOLITION) OCCUR. THE COC CAN BE OBTAINED BY FILLING OUT THE ELECTRONIC NOTICE OF INTENT (e-NOI) FORM AT https://www.deq.nc.gov/NCG01. PLEASE NOTE, THE e-NOI FORM MAY ONLY BE FILLED OUT ONCE THE PLANS HAVE BEEN APPROVED. A COPY OF THE E&SC PERMIT, THE COC, AND A HARD COPY OF THE PLAN MUST BE KEPT ON SITE, PREFERABLY IN A PERMITS BOX, AND ACCESSIBLE DURING INSPECTION.
2. CONTRACTOR SHALL BE RESPONSIBLE TO SCHEDULE PRE AND POST CONSTRUCTION STORMWATER INSPECTION.
3. SET UP PRE-CONSTRUCTION MEETING AT LEAST ONE WEEK BEFORE ANY CONSTRUCTION ACTIVITY BEGINS.
4. CONTRACTOR TO NOTIFY THE NORTH CAROLINA DIVISION OF ENERGY, MINERAL, AND LAND RESOURCES (DEMLR) RALEIGH REGIONAL OFFICE AT LEAST 48 HOURS
PRIOR TO COMMENCING ANY LAND-DISTURBING ACTIVITY. THE CONTACT NUMBER IS (919) 791-4200.
5. HAVE THE PROJECT CLEARING LIMITS FLAGGED.
6. MOBILIZATION.
7. ERECT CONTRACTOR STAGING AREAS.
7.1. STOCKPILES, LAYDOWN OR WASTE AREAS, CONCRETE WASHOUTS, PORTABLE TOILETS, AND FUELS MUST BE LOCATED AT LEAST 50 FEET AWAY FROM ANY OPEN WATER CONVEYANCES, SUCH AS BASINS, DITCHES, STORM DRAIN INLETS, ETC. THE LOCATION OF THESE ACTIVITIES MAY BE FIELD ADJUSTED IF THE
DISTANCE REQUIREMENTS ARE MET.
8. INSTALL TREE PROTECTION, SILT FENCE, CONSTRUCTION ENTRANCE, AND ALL EROSION AND SEDIMENT CONTROL MEASURES AS INDICATED ON PLANS. LIMIT CLEARING AND LAND DISTURBING ACTIVITY TO ONLY THE AREA NECESSARY TO INSTALL PERMITTED MEASURES. ONLY MINIMAL CLEARING SHOULD BE PERFORMED
AS NEEDED TO INSTALL THE FENCING.
8.1. TAKE PRECAUTION TO AVOID CAUSING ROOT DAMAGE TO TREES JUST OUTSIDE OF THE CLEARING LIMITS. IF ROOT DAMAGE TO A TREE OUTSIDE OF THE CLEARING LIMITS IS UNAVOIDABLE, CONSULT WITH THE ENGINEER TO DETERMINE THE NEED TO REMOVE IT. THIS WILL BE CONSIDERED INCIDENTAL TO THE
LUMP SUM GRADING AND/OR CLEARING AND GRUBBING.
9. INSTALL PUMP IN POND AND STILLING BASIN ON NORTHERN SIDE OF ROAD.
10. DRAIN POND.
11. DEMOLISH SITE AS INDICATED ON PLANS.
12. INSTALL RISER STRUCTURE, TRASH RACK, AND OUTLET PIPE.
13. INSTALL BAFFLES AND SKIMMERS INSIDE SEDIMENT POND.
14. CONSTRUCT CONCRETE EMERGENCY SPILLWAY AND RIP RAP PROTECTION.
15. FILL DIRT TO BE PLACED AND PERFORM ROUGH GRADING OF THE SITE ONCE THE SITE IS DRAINED, DEMOLISHED, THE OCS IS INSTALLED, AND ALL EROSION
CONTROL MEASURES ARE INSTALLED.
16. MAINTAIN EROSION CONTROL MEASURES AS WORK PROGRESSES. ALL EROSION CONTROL MEASURES SHALL BE INSPECTED AND MAINTAINED, IF NEEDED, AT LEAST
ONCE PER WEEK AND AFTER EVERY QUALIFYING RAINFALL EVENT.
17. INSTALL TEMPORARY SEEDING IMMEDIATELY FOLLOWING ALL ROUGH GRADING.
18. STABILIZATION IS REQUIRED WITHIN 14 CALENDAR DAYS OF COMPLETION OF ANY GRADING OR INACTIVITY ON PROJECT SITE.
19. INSTALL ALL PROPOSED UTILITIES, STORM DRAINAGE, STRUCTURES, AND PIPES.
20. FINE GRADE REMAINING SITE.
21. INSTALL TEMPORARY SEEDING IN ALL DENUDED AREAS AS NEEDED IF PERMANENT SEEDING AND LANDSCAPING NOT READY TO BE INSTALLED.
22. SITE STABILIZATION IS REQUIRED PRIOR TO FINAL APPROVAL. GRASS UTILIZED AS PERMANENT GROUND COVER MUST BE AT A MOWABLE HEIGHT THAT GENERALLY
PROVIDES AT LEAST 80% COVERAGE THROUGHOUT THE SITE, WITH NO LARGE BARE PATCHES OR EVIDENCE OF EROSION.
23. INSTALL HARDSCAPE, INCLUDING SIDEWALK AND PAVING OPERATIONS (IF REQUIRED).
24. INSTALL LANDSCAPING.
25. CLEAN STORM SEWER PIPES, DROP INLETS, AND STORM STRUCTURES OF DEBRIS AND ERODED MATERIAL DURING THE LAST STAGES OF CONSTRUCTION.
26. ALL EXCAVATED MATERIAL SHALL BE DISPOSED OF IN A LAWFUL MANNER.
27. REMOVE TEMPORARY EQUIPMENT, CONSTRUCTION MATERIALS, AND DEBRIS FROM SITE.
28. AFTER SITE IS STABILIZED, REMOVE ALL TEMPORARY CONTROL MEASURES AND INSTALL PERMANENT VEGETATION ON ANY REMAINING DISTURBED AREAS. ALL
TEMPORARY EROSION AND SEDIMENT CONTROL MEASURES SHALL BE REMOVED WITHIN 30 DAYS OF FINAL STABILIZATION OR AS DIRECTED BY CIVIL INSPECTOR.
NO EROSION CONTROL MEASURES SHOULD BE REMOVED UNTIL THE SITE IS INSPECTED AND STABILIZATION IS CONFIRMED.
29. THE CONTRACTOR IS RESPONSIBLE FOR THE DISPOSAL OF ANY WASTE SOIL FROM THE PROJECT TO ANOTHER SITE INCLUDING APPROVED EROSION AND SEDIMENT
CONTROL. PLAN FOR THE DISPOSED MATERIAL.
30. CONTACT TOWN OF CHAPEL HILL TO SUBMIT INSPECTION REQUEST. CONTRACTOR SHALL BE RESPONSIBLE TO SCHEDULE A STORMWATER FINAL INSPECTION.
31. WHEN THE PROJECT IS COMPLETE AND PERMANENT STABILIZATION IS ACHIEVED, THE PERMITTEE SHALL CONTACT DEMLR TO CLOSE OUT THE E&SC PLAN. AFTER
DEMLR INFORMS THE PERMITTEE OF THE PROJECT CLOSE OUT, VIA INSPECTION REPORT, THE PERMITTEE SHALL VISIT https://www.deq.nc.gov/NCG01 TO SUBMIT AN ELECTRONIC NOTICE OF TERMINATION (E-NOT). A $127 ANNUAL GENERAL PERMIT FEE WILL BE CHARGED UNTIL THE E-NOT HAS BEEN FILLED OUT.
SEQUENCE OF CONSTRUCTION
USA USGS QUADRANGLE: CHAPEL HILL (35079-H1)
Modified Sheets From Drawings – Bidding Revisions – 081326
Addendum 1 – Legion Pond Dam RFP: P27-04, Town of Chapel Hill, NC August 17, 2026
BLAKE.CARY
Cloud
TOWN OF CHAPEL HILL
PIN: 9799467392
DB 6282-545
PARCEL 1
LIBERTY HEALTHCARE PROPERTIES OF
ORANGE COUNTY LLC
PIN:9799562741
DB 6013-204
PB 59-23
TOWN OF CHAPEL HILL
PIN: 9799555951
DB 6282-545
PARCEL 2
WM
UT
UT
UT
UT
UT
UT
UT
UT
UT
UT
W
W
W
W
W
OE
OE
OE
OE
OE
OE
OE
OE
OE
OE
O T
O T
SS
SS
SS
SS
SS
LEGIO
N R
OAD
VARIA
BLE W
ID
TH PUBLIC
R /W
EDGE OF POND
EDGE O
F P
OND
EDGE OF POND
ED
G
E O
F PO
N D
300'
300'
305'
310'
315'
300'305'
310'
315'
305'
310'
315'
320'
320'
318'
297'
LONGLEAF TRACE LLC
PIN: 9799456975
DB 6874/1448
SE/S AMERICAN
LEGION RD
P. & I.
CALINGAERT
PIN: 9799459807
DB 4381/259
PB 34-142
LOT 406
316'
315'
314'
313'
312'
316'
315'
314'
313'
310'305' 300'
300'
100+00
101+00
102+00
103+00
104+00
105+00
106+00106+33 xx xx xx xx xx xxxx xx xx xx xxxx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xxxx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xxxx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xxxxxx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xxxxxxxx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xxxxxxxx xx xx xx xx xx xxxx xx xx xx xx xx xxxx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xxxxxxxxxx xx xx xx xx xxxx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xxxxxxxxxxxxxxxxxx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xxxx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xxxx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xxxx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx xx
SF
SF
SF
SF
SF SF
SF
SF
SF
SF
BAFFLES,
SEE DETAIL 5 ON SHEET CD104
(TYP.)
CONSTRUCTION ENTRANCE,
SEE DETAIL 1 ON SHEET CD103
STAGING AREA
RISER STRUCTURE,
SEE DETAIL 1 ON SHEET CD101
RIPRAP APRON,
L=8FT, W1: 4FT, W2:8FT
SEE DETAIL 2 ON SHEET CD103
REINFORCED CONCRETE
HEADWALL, SEE
DETAILS 6-7 ON SHEET CD102
130 LF 24" RCP,
UPSTREAM INVERT ELEV = 300'
DOWNSTREAM INVERT ELEV = 299.5'
SILT FENCE, SEE
DETAIL 1 ON SHEET CD104
TREE PROTECTION FENCE, SEE
DETAIL 4 ON SHEET CD104
DEWATERING BAG. ENSURE BAG DRAINS AWAY
FROM THE POND. SEE DETAIL 5 ON SHEET CD103
DEWATERING PUMP, MAX PUMP
RATE OF 1CFS OR 448GPM. POND
SHALL NOT DRAIN MORE THAN
ONE VERTICAL FOOT PER DAY
SILT FENCE, SEE DETAIL 1
AND 3 ON SHEET CD104
SKIMMER,
SEE DETAIL 6 ON SHEET CD104
TEMPORARY SEED AND
PERMANENT GRASS
ON ALL DISTURBED AREAS
MATTING BLANKET
ON ALL 3:1 SLOPES,
SEE DETAIL 2 CD104
SEWER LINE MUST REMAIN
ACCESSIBLE. NO EQUIPMENT OR
MATERIALS SHALL BE STAGED
WITHIN 15' OF SEWER MAIN.
ACCESS DRIVEWAY TO
REMAIN OPEN THROUGHOUT
CONSTRUCTION
LIMITED VISIBILITY FENCE
SEE DETAIL 8 ON SHEET CD104
LO
D
LO
D
LO
D
LO
D
LO
D
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LO
D
LO
D
LO
D
LO
D
LO
D
LO
D
LOD LOD LOD LOD LOD
LO
D
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LO
D
LO
D
LO
D
LO
D
LO
D
LO
D
LO
D
LO
D
LO
D
LO
D
LO
D
LO
D
LO
D
LO
D
LOD
LOD
LODLOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LO
D
LO
D
LO
D
LO
D
LO
D
LO
D
LO
D
LO
D
LO
D
LO
D
LO
D
LOD
LOD
LOD
LO
D
LO
D
LO
D
LO
D
LO
D
LOD
LOD
SF
SF
SF
SF
SF
SF
SF
SF
SF
SF
SF
SF
SF
SF
SF
SF
SF
SF
SF
SF
SF
CONTOURS IN THIS AREA WERE DERIVED FROM THE 3DEP
USGS DEM AND ARE PROVIDED TO INDICATE
GENERAL TOPOGRAPHY. NO GRADING IS PROPOSED
WITHIN THIS AREA.
RAIN GAUGE AND PERMITS/RECORD
BOX LOCATION.
CONCRETE WASHOUT STRUCTURE,
SEE SHEET ES102.
SILT FENCE OUTLET EVERY 100 LF,
SEE DETAIL 3 ON SHEET CD104
SILT FENCE OUTLET, SEE
DETAIL 3 ON SHEET CD104
COMPOST FILTER SOCK,
SEE DETAIL 7 ON SHEET CD104
STEVEN FUNTE
PIN: 9799459784
DB 5607
PB 33-107
LOT 405
MEADOWS OF CHAPEL HILL
HOMEOWNERS ASSOC INC
PIN: 9799550548
DB 457-246
TOWN OF CHAPEL HILL
PIN: 9799555951
DB 6282-545
PARCEL 2
UT
UT
OE
EDGE O
F P
OND
EDGE OF POND
ED
G
E O
F PO
N D
300'
305'
310'
315'
300'305'
310'
315'
305'
310'
315'
320'
320'
297'
P. & I.
CALINGAERT
PIN: 9799459807
DB 4381/259
PB 34-142
LOT 406
310'305' 300'
300'
SF
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LO
D
LO
D
LODLOD
LOD
LOD
LO
D
LO
D
LO
D
LO
D
LOD
LOD
LOD
LODSF
SF
USGS DEM DERIVED FLOW LINE
Checked By:
Drawn By:
Project No.:
Designed By:
M
AR
K D
AT
E
D
ES
C R
IP
TI
O N
BY
8/
/2
4:
:1
PM
C
:\U
SE
R S\
BL
AK
E.
C
AR
Y\
O N
ED
R
IV
E
- T
ET
R A
TE
C
H , I
N C
\P R
O
JE
C
TS
\N O
R
TH
C
AR
O
LI
N A\
LE
G
IO
N
P O
N D
D
AM
\C
AD
V
ER
SI
O
N S\
.1
3.
V
ER
SI
O
N
BI
D
D
IN
G P
H
AS
E R
EV
IS
IO
N
S\
SH
EE
T
SE
T\
ES
_E
R O
SI
O
N A
N D
S
ED
IM
EN
T C
O N
TR
O
L.
D
W G
C
AR
Y, B
LA
KE
A
B
C
D
E
F
2 3 4 5 6 7
Bar Measures 1 inch
C op yr ig ht : T et ra
T ec h
EN
GI
NE
ER
IN
G, P C
N C
L ic en se
C -2 w w w .te tra te ch .c om
T43655
IS
SU
ED
F
O R
P
ER
M
IT
TI
N
G
Le gi on P on d
S an ca r W ay , S ui te
R es ea rc h Tr ia ng le P ar k, N C
Ph on e:
(9
) 4
-8 of Sheets
Sheet
JULY 13, 2026
RELEASED FOR BIDDING
DO
WH
DS
0 25 50 100
ER
O
SI
O
N A
N D
S
ED
IM
EN
T C
O N
TR
O
L
PL
AN
ES101SCALE: 1"=50'
EROSION AND SEDIMENT CONTROL PLAN
LOD LOD LOD
LEGEND
LIMIT OF DISTURBANCE
PROPOSED CONTOUR
EXISTING CONTOUR
EXISTING CONTOUR (USGS DEM)
SILT FENCE
TREE PROTECTION FENCE
PROPOSED STORM SEWER
SF
SD
N
1. CONTRACTOR SHALL MAINTAIN PUBLIC ACCESS TO THE LEGION BUILDING DURING ALL
PHASES OF CONSTRUCTION.
2. CONTOURS FROM THE UNITED STATES GEOLOGICAL SURVEY (USGS) 3D ELEVATION
PROGRAM (3DEP) PROVIDE EXISTING CONDITION GRADE BEYOND SURVEY LIMITS FOR
DE-WATERING PLACEMENT.
3. APPROVAL OF THIS EROSION AND SEDIMENTATION CONTROL PLAN DOES NOT AUTHORIZE
IMPACTS TO WETLANDS, COASTAL MARSH, STREAMS OR OTHER WATERS OF THE STATE OR
UNITED STATES OR SUPERSEDE ANY OTHER PERMITTING REQUIREMENT OF ANY FEDERAL,
STATE OR LOCAL AGENCY.
4. THE DEVELOPER IS RESPONSIBLE FOR THE CONTROL OF SEDIMENT ON-SITE. IF THE
APPROVED EROSION AND SEDIMENTATION CONTROL MEASURES PROVE INSUFFICIENT, THE
DEVELOPER MUST TAKE THOSE ADDITIONAL STEPS NECESSARY TO STOP SEDIMENT FROM
LEAVING THIS SITE.
5. CONCRETE WASHOUT FACILITIES SHOULD BE INSPECTED DAILY AND AFTER HEAVY RAINS TO
CHECK FOR LEAKS, IDENTIFY ANY DAMAGE CAUSED BY CONSTRUCTION ACTIVITIES, AND
DETERMINE WHETHER THEY ARE FILLED TO OVER 75 PERCENT CAPACITY. WHEN THE
WASHOUT CONTAINER IS FILLED TO OVER 75 PERCENT OF ITS CAPACITY, THE WASH WATER
SHOULD BE VACUUMED OFF OR ALLOWED TO EVAPORATE TO AVOID OVERFLOWS. WHEN
THE REMAINING CEMENTITIOUS SOLIDS HAVE HARDENED, THEY SHOULD BE REMOVED AND
RECYCLED. DAMAGES TO THE CONTAINER SHOULD BE REPAIRED PROMPTLY. BEFORE
HEAVY RAINS, THE WASHOUT CONTAINER’S LIQUID LEVEL SHOULD BE LOWERED, OR THE
CONTAINER SHOULD BE COVERED TO AVOID AN OVERFLOW DURING THE RAIN EVENT. SEE
SHEET ES102 FOR ADDITIONAL CONCRETE WASHOUT DETAILS.
NOTES
XX
COMPLETE PARCEL VIEW
0 0.5 1 2
SCALE: 1/16"=1'
N
Addendum 1 – Legion Pond Dam RFP: P27-04, Town of Chapel Hill, NC August 17, 2026
BLAKE.CARY
Cloud
Station
101+50 102+00 102+50
103+00 103+50
104+00
4'
7' x 7' x 1' ANTI-FLOTATION CONCRETE SLAB.
ELEV. TOP OF SLAB = 299.0'
TOP OF RISER
ELEV = 315'
TRASH RACK,
SEE DETAIL 1 ON SHEET CD102
BOTTOM OF BASIN
ELEV = 300'
SKIMMER, SEE DETAIL
6 ON SHEET CD104
CONSTRUCT ORIFICES THAT CAN
ACCOMODATE UP TO 6" DIAM. PIPE WITH
INVERT ELEVATIONS OF 310' AND 312' FOR
USE IN FUTURE RISER MODIFICATIONS.
TEMPORARILY PLUG OPENINGS.
4" DIAM. ORIFICE
INVERT ELEV = 300'
FILTER DIAPHRAGM,
TOP ELEV = 312'
BOTTOM ELEV =295.5'
SEE DETAIL 4 ON SHEET CD105
REINFORCED CONCRETE
HEADWALL, SEE DETAIL
5-6 ON SHEET CD102
EXCAVATE TO 1' BELOW FOOTING ELEVATION OR TO A FIRM
AND STABLE IN SITU SUBGRADE, WHICHEVER IS DEEPER, TO
BE APPROVED BY GEOTECHNICAL ENGINEER OR THEIR
REPRESENTATIVE, PLACE NCDOT 1016 CLASS III, TYPE 3
SELECT MATERIAL AND COMPACT 98% OF ASTM D698.
EXISTING SURFACE
PROPOSED SURFACE
3" TOPSOIL SEED MIX
12' UPPER LIMIT = 314.5'
LOWER
LIMIT = 308'
PERMANENT TURF
REINFORCEMENT
MAT (TRM)
3:1
CLASS V 24" RCP
OUTLET PIPE
INV OUT ELEV. = 300'
PROPOSED 5:1
SLOPE WITH TOE
DRAIN, SEE
DETAIL 1 ON
SHEET CD105
3:1
GROUT PAVED INVERT TO ALLOW
POSITIVE DRAINAGE WITHIN
RISER STRUCTURE
EMBANKMENT FILL
PROPOSED DETAILS
AROUND OUTLET PIPE,
SEE DETAIL 4 ON SHEET
CD105
ELEV = 316'
INSTALL GATE VALVE AT THE 4" ORIFICE
AS SHOWN IN DETAIL 2 OF CD102.
OUTLET RISER STRUCTURE,
SEE DETAIL 1 ON SHEET CD101.
EXCAVATE TO 1' BELOW EXISTING GROUND SURFACE OR TO A
FIRM AND STABLE IN SITU SUBGRADE, WHICHEVER IS DEEPER,
TO BE APPROVED BY GEOTECHNICAL ENGINEER OR THEIR
REPRESENTATIVE, PLACE NCDOT 1016 CLASS III, TYPE 3
SELECT MATERIAL AND COMPACT 98% OF ASTM D698.
TOWN OF CHAPEL HILL
PIN: 9799467392
DB 6282-545
PARCEL 1
TOWN OF CHAPEL HILL
PIN: 9799555951
DB 6282-545
PARCEL 2
UT
UT
UT
UT
OE
OE
OE
EDGE OF POND
EDGE O
F P
OND
EDGE OF POND
ED
G
E O
F PO
N D
300'
300'
305'
310'
315'
300'305'
310'
315'
305'
310'
315'
320'
320'
318'
297'
LONGLEAF TRACE LLC
PIN: 9799456975
DB 6874/1448
SE/S AMERICAN
LEGION RD
P. & I.
CALINGAERT
PIN: 9799459807
DB 4381/259
PB 34-142
LOT 406
316'
315'
314'
313'
312'
316'
315'
314'
313'
310'305' 300'
300'
LO
D
LO
D
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LO
D
LO
D
LO
D
LOD LOD
LOD
LOD
LOD
LOD
LOD
LO
D
LO
D
LO
D
LO
D
LO
D
LO
D
LO
D
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LOD
LO
D
LO
D
LO
D
LO
D
LO
D
LO
D
LOD
LO
D
LO
D
LOD
Checked By:
Drawn By:
Project No.:
Designed By:
M
AR
K D
AT
E
D
ES
C R
IP
TI
O N
BY
8/
/2
5:
:2
PM
C
:\U
SE
R S\
BL
AK
E.
C
AR
Y\
O N
ED
R
IV
E
- T
ET
R A
TE
C
H , I
N C
\P R
O
JE
C
TS
\N O
R
TH
C
AR
O
LI
N A\
LE
G
IO
N
P O
N D
D
AM
\C
AD
V
ER
SI
O
N S\
.1
3.
V
ER
SI
O
N
BI
D
D
IN
G P
H
AS
E R
EV
IS
IO
N
S\
SH
EE
T
SE
T\
C G
_G R
AD
IN
G .D
W G
C
AR
Y, B
LA
KE
A
B
C
D
E
F
2 3 4 5 6 7
Bar Measures 1 inch
C op yr ig ht : T et ra
T ec h
EN
GI
NE
ER
IN
G, P C
N C
L ic en se
C -2 w w w .te tra te ch .c om
T43655
IS
SU
ED
F
O R
P
ER
M
IT
TI
N
G
Le gi on P on d
S an ca r W ay , S ui te
R es ea rc h Tr ia ng le P ar k, N C
Ph on e:
(9
) 4
-8 of Sheets
Sheet
JULY 13, 2026
RELEASED FOR BIDDING
DO
WH
DS
G R
AD
IN
G S
EC
TI
O N
A N
D
ST
EE
P
SL
O
PE
P
LA
N
CG102
GRADING SECTION
DAM EMBANKMENT NOTES
A. PLACEMENT OF ANY FILL MATERIAL MUST BE CONDUCTED UNDER THE OBSERVATION OF A QUALIFIED LICENSED GEOTECHNICAL ENGINEER AND UPON COMPLETION OF THE EARTHWORK ACTIVITIES, THE TOWN OF CHAPEL HILL STORMWATER MANAGEMENT OFFICE MUST BE PROVIDED WITH A FINAL GRADING REPORT THAT INCLUDES THE CORRESPONDING COMPACTION TEST RESULTS
AND CERTIFIES THE TYPE OF FILL MATERIAL AND ITS PROPER PLACEMENT WITH AS-BUILT.
B. ALL FILL MATERIAL TO BE USED FOR THE DAM EMBANKMENT SHALL BE TAKEN FROM BORROW AREAS APPROVED BY THE ON-SITE GEOTECHNICAL ENGINEER. EMBANKMENT FILL IS USCS CLASSIFICATION OF CL (LEAN CLAY), ML (SILT), CL-ML (LEAN SILTY CLAY), SM (SILTY SAND), OR SC (CLAYEY SAND) WITH A MINIMUM OF 40 PERCENT FINES (LESS THAN #200 SIEVE). EMBANKMENT FILL MATERIAL SHALL BE CONSTRUCTED OF CLEAN STRUCTURAL SOIL, FREE OF ROOTS, STUMPS, WOODS, STONES GREATER THAN 2'' AND OTHER OBJECTIONABLE MATERIAL. EMBANKMENT FILL SHALL BE PLACED IN 6” LOOSE LAYERS (3” LOOSE LAYERS WITHIN 3' ON EITHER SIDE OF THE PRINCIPAL PIPE TO A DEPTH OF 2” OVER THE PIPE) COMPACT TO AT LEAST 98% STANDARD PROCTOR MAXIMUM DRY DENSITY WITHIN -1 TO +3 PERCENT OF OPTIMUM MOISTURE CONTENT. ALL COMPACTION IS TO BE DETERMINED BY
ASTM D698 (STANDARD PROCTOR)
C. ALL FILL MATERIAL TO BE USED FOR THE RISER STRUCTURE SHALL BE TAKEN FROM BORROW AREAS APPROVED BY THE ON-SITE GEOTECHNICAL ENGINEER. GRADATION MUST BE IN ACCORDANCE WITH NCDOT 1016 CLASS III, TYPE 3 SELECT MATERIAL. RISER FILL MATERIAL SHALL BE CONSTRUCTED OF CLEAN STRUCTURAL SOIL, FREE OF ROOTS, STUMPS, WOODS, STONES GREATER THAN 2'' AND OTHER OBJECTIONABLE MATERIAL. RISER FILL SHALL BE PLACED IN 6” LOOSE LAYERS (3” LOOSE LAYERS WITHIN 3' ON EITHER SIDE OF THE PRINCIPAL PIPE TO A DEPTH OF 2” OVER THE PIPE) COMPACT TO 98% OF STANDARD PROCTOR MAXIMUM DRY DENSITY WITHIN -1 TO +3 PERCENT OF OPTIMUM MOISTURE CONTENT. ALL COMPACTION IS TO BE DETERMINED BY ASTM
D698 (STANDARD PROCTOR).
D. THE GEOTECHNICAL ENGINEER SHALL OBSERVE AND CERTIFY ALL ASPECTS OF THE CONSTRUCTION OF THE EMBANKMENT (I.E., PREPARATION OF FOUNDATION, INSTALLATION OF THE CUT-OFF TRENCH, INSTALLATION OF PRINCIPAL SPILLWAY PIPE, INSTALLATION OF INTERNAL DRAINAGE, INSTALLATION OF COMPACTED FILL, ETC.). THE FREQUENCY OF OBSERVATION AND TESTING MUST BE SUFFICIENT FOR THE GEOTECHNICAL ENGINEER TO STATE IN HIS/HER OPINION, THAT THE SPECIFIC ITEMS OBSERVED AND TESTED WERE INSTALLED IN ACCORDANCE WITH THE APPROVED CONSTRUCTION DRAWINGS AND
SPECIFICATIONS.
E. LIFTS OF FILL SHOULD BE INTEGRATED (E.G., BENCHED OR KEYED) INTO ADJACENT SLOPES AND THE UNDERLYING LIFT OF FILL
(E.G. VIA SCARIFICATION OR ROUGHENING OF THE SURFACE).
F. THE EXISTING SLOPES ARE COVERED BY MATURE TREES. FOR SLOPE PREPARATION, TREES SHOULD BE CUT, AND THE ENTIRE ROOT BALL SHOULD BE REMOVED FROM THE EXISTING EMBANKMENT. EXCAVATE A MINIMUM 3-FOOT DEPTH INTO THE EXISTING EMBANKMENT TO ACCOUNT FOR TREE ROOT BALL REMOVAL, BUT THE ROOT BALLS SHOULD BE REMOVED SO THAT ALL ROOTS ONE-HALF INCH AND LARGER IN DIAMETER ARE REMOVED. EXCAVATIONS MADE FOR REMOVAL OF TREES SHOULD FOLLOW
EXCAVATION, COMPACTION, AND BENCHING DETAILS.
STEEP SLOPE SCHEDULE
EXISTING CONDITIONS
+25%: 2.22 ACRE
TO BE DISTURBED
0-10%: 0.18 ACRE
10-25%: 0.31 ACRE
+25%: 0.48 ACRE (22% OF EXISTING AREA GREATER THAN 25%)
GENERAL NOTES
1. HATCHES DRAWN IN THE STEEP SLOPE PLAN ARE NOT
EXACT AND WERE DRAWN FOR DISPLAY PURPOSES ONLY.
REGIONS DERIVED FROM EXISTING GRADE SURVEY.
SCALE: 1"=100'
STEEP SLOPE PLAN
N
0 50 100 200
STEEP SLOPE LEGEND
0-10% SLOPE
10-25% SLOPE
+25% SLOPE
Addendum 1 – Legion Pond Dam RFP: P27-04, Town of Chapel Hill, NC August 17, 2026 7
BLAKE.CARY
Cloud
4" DIAM. ORIFICE
INVERT ELEV = 300'
DESIGN NOTES:
1. SEE NCDOT DETAIL 840.45 ON CD101 FOR CONSTRUCTION STANDARDS, THE SOLID WALL CONFIGURATION.
2. INSTALL 0.5" X 12" HOT-DIP GALVANIZED J-BOLTS AT 8" SPACING THROUGHOUT INTERIOR OF RISER PLACEMENT. EMBED 6" IN TO
PROVIDE MINIMUM 6" SPACING FROM WALL OF RISER.
3. RISER STRUCTURE TO BE EQUIPPED WITH STEPS AS SHOWN IN NCDOT DETAIL 840.66 ON CD101.
4. DETAILS 1 (TRASH RACK), 2 (SLIDE GATE), AND 3 (DEBRIS SHIELD ON 4" ORIFICE) ON SHEET CD102 TO ADDITIONALLY BE FITTED
TO THE RISER STRUCTURE.
5. CONTRACTOR TO PROVIDE SHOP DRAWINGS OF RISER STRUCTURE FOR ENGINEER APPROVAL.
6. INSPECTION AND MAINTENANCE OF THE RISER STRUCTURE IS NECESSARY TO MAINTAIN PERFORMANCE.
4'-0"
24" RCP OUTLET PIPE
INV OUT ELEV. = 300'
5' x 5' PEDESTAL INLET
WITH TRASH RACK DETAIL
SEE DETAIL 1 ON CD102
6" REINFORCED
CONCRETE
315'
6" DIAM. ORIFICE
INVERT ELEV = 312'
2" DIAM. ORIFICE
INVERT ELEV = 310'
BOTTOM SECTION OF RISER
TO BE OPEN BOTTOMANTI-FLOTATION CONCRETE SLAB,
SEE NOTE 2
Checked By:
Drawn By:
Project No.:
Designed By:
M
AR
K D
AT
E
D
ES
C R
IP
TI
O N
BY
8/
/2
4:
:5
PM
C
:\U
SE
R S\
BL
AK
E.
C
AR
Y\
O N
ED
R
IV
E
- T
ET
R A
TE
C
H , I
N C
\P R
O
JE
C
TS
\N O
R
TH
C
AR
O
LI
N A\
LE
G
IO
N
P O
N D
D
AM
\C
AD
V
ER
SI
O
N S\
.1
3.
V
ER
SI
O
N
BI
D
D
IN
G P
H
AS
E R
EV
IS
IO
N
S\
SH
EE
T
SE
T\
C D
_C O
N
ST
R U
C
TI
O N
D
ET
AI
LS
.D W
G
C
AR
Y, B
LA
KE
A
B
C
D
E
F
2 3 4 5 6 7
Bar Measures 1 inch
C op yr ig ht : T et ra
T ec h
EN
GI
NE
ER
IN
G, P C
N C
L ic en se
C -2 w w w .te tra te ch .c om
T43655
IS
SU
ED
F
O R
P
ER
M
IT
TI
N
G
Le gi on P on d
S an ca r W ay , S ui te
R es ea rc h Tr ia ng le P ar k, N C
Ph on e:
(9
) 4
-8 of Sheets
Sheet
JULY 13, 2026
RELEASED FOR BIDDING
DO
WH
DS
C O
N
ST
R U
C
TI
O N
D
ET
AI
LS
CD101
1 RISER STRUCTURE (NOT TO SCALE)
Addendum 1 – Legion Pond Dam RFP: P27-04, Town of Chapel Hill, NC August 17, 2026 8
BLAKE.CARY
Cloud
| Modified Sheets from Drawings - Bidding Revisions - 081326.pdf |
| Sheets and Views |
| 1 C101 |
| 2 G101 |
| 3 CX101 |
| 4 DP101 |
| 5 ES101 |
| 6 ES102 |
| 7 ES103 |
| 8 CG101 |
| 9 CG102 |
| 10 CD101 |
| 11 CD102 |
| 12 CD103 |
| 13 CD104 |
| 14 CD105 |
| 15 TS101 |
File details come from the government source that posted it. Updated .