This Statement of Work (SOW) details a contract for the 76th Maintenance Group at Tinker Air Force Base to procure Zoller RFID Hardware and Adapters. The specific requirements include one Z96910713 Read/Write Head-Balluff with handhold BIS-C-600, one Z96910500-05 Plug-in Connector/Connection Cable, one Z6001C06 Tool Post Size I/PSC 63, one Z6015950 Tool Post Size I/HSK A50-F63, one KON01 Special Tool post size 1-Starrag, and one day of standard installation and testing services. The contractor must deliver the equipment to Building 3001, Post F91 at Tinker Air Force Base, Oklahoma, and be responsible for offloading, moving, and installing the hardware in accordance with original equipment manufacturer specifications.
The SOW includes extensive environmental, safety, and base access requirements. The contractor must comply with Tinker Air Force Base regulations, including hazardous material management, safety procedures, emergency protocols, and foreign object damage prevention. Work is to be performed Monday through Friday from 0700-1500 hours, with prior approval required for work outside these hours. The contract was prepared by OBCA/PZIMC and is dated 23 June 2025, with a NAICS code of 332510. Key compliance areas include environmental protection, safety training, visitor passes, and communication of workplace hazards.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1 SCOPE. This Statement of Work (SOW) defines the effort required for the purchase of Zoller RFID Hardware and Adapters to include Delivery, Installation, Performance Verification, and Testing in Tinker Air Force Base, OK.
2 REQUIREMENTS
2.1 General. The Contractor shall provide to the Government Point of Contact (GPOC) the date that the Delivery, Installation, Performance Verification, and testing will begin five (5) business days prior to installation beginning. The Contractor shall be responsible for ensuring all services, parts and components provided under this contract are in accordance with (IAW) the terms and conditions outlined in this SOW.
2.2 Item Description. The 76 PMXG is requesting Zoller RFID Hardware and Adapters.
This requirement must have the following specifications:
One (1) Z96910713 Read/Write Head- Balluff with handhold BIS-C-600
One (1) Z96910500-05 Plug-in0.3m (118.11”) Connector/ Connection Cable for Balluff BIS V-6102 cable
One (1) Z6001C06 Tool Post Size I/PSC 63 Polygonal taper shank according to ISO 26623, loss in measuring range Z axis 52mm (2.05”)
One (1) Z6015950 Tool Post Size I/HSK A50-F63 HSK-T/ICTM compliant loss in measuring range Z axis 50mm (1,97”)
One (1) KON01 Special Tool post size 1- Starrag cone/face 1:5 73mm (2.87”) diameter spring-loaded taper support-> due to taper and flat support, Support surface with diameter 175mm (6.89”) Automatic clamping/integrated clamping on the tightening bolt measuring loss Z-axis 80-120mm (3.15-4.72”)
One (1) SERVICE1 1 day of service standard for Installation and Testing
2.3 Contractor Requirements
• The Contractor shall deliver one (1) Z96910713 (Second read/write head – Balluff), one (1)
Z96910500-05 (Plug-in Connector/Connection), one (1) Z6001C06 (Tool Post Size I/PSC 63, one (1) Z6015950 (Tool Post Size I/HSK A50-F63), one (1) KON01 (Special construction Special Tool post size 1 – Starrag) one (1) (STANDARD SERVICE)
• The Contractor shall provide Installation, Performance Verification, and Testing.
• The Contractor shall make all necessary adjustments to the Zoller RFID Hardware and
Adapters until the item is fully operational IAW the Original Equipment Manufacturer (OEM) specifications and to what is stated in this SOW.
2.4 Installation: The Contractor shall be responsible for delivery and installation required to provide the Government with full operational Zoller RFID Hardware and Adapters that is ready for immediate operation. This shall include the following:
2.4.1 The Contractor shall be responsible for hardware and adapters delivery to Building (3001 Post F91) at Tinker AFB, OK 73145. The Contractor shall be responsible for offloading equipment and moving equipment to installation are (Building 3001, Post F91). The Government shall provide power to the area where the Zoller RFID Hardware and Adapters will be installed.
The Contractor shall provide the installation services, that is IAW the OEM’s specifications.
2.4.2 The Government will provide power, water and compressed air within 25 feet of the equipment installation area. The Contractor shall be responsible for final connection of power, water, and compressed air (as applicable) IAW Tinker Facility Standards and Tinker Electrical Standards.
2.4.3 The Contractor shall verify to the Government SME that installation has been completed IAW standards listed in 2.4.2. and IAW the OEM’s specifications. In addition, the Contractor shall demonstrate to the Government SME that the Zoller RFID Hardware and Adapters is fully operational before leaving the facility.
2.5 Zoller RFID Hardware and Adapters Performance Verification
2.5.1 After installation, the Contractor shall demonstrate that the Zoller RFID Hardware and Adapters meets or exceeds all OEM specifications, and the requirements listed in section 2.2 of this SOW. The Contractor shall be present for the entirety of acceptance testing.
2.6 Hours of Operation: The Contractor shall perform the work required under this contract during the following days and hours: Monday through Friday, 0700 - 1500. If work hours are required outside the hours stated, the Contractor shall contact the Government POC for approval from the CO. Upon approval from the CO, the SME or GPOC escort Contractor personnel at all times.
2.6.1 These dates and hours exclude Federal Holidays, base closures due to inclement weather, and furlough days, as applicable.
3.0 On-Base Requirements
3.1 Environmental Protection & Safety: The Contractor shall be knowledgeable of and comply with all applicable federal, state, and local laws, regulations, instructions and requirements regarding environmental protection and occupational safety and health. The Contractor shall comply with any laws, instructions, or regulation changes during the term of this contract.
Contractors shall be compliant Tinker Air Force Base (TAFB) Supplement to Air Force Instruction (AFI) 32-7086, “Hazardous Materials Management”, Tinker AFB procedures per Tinker Air Force Base Hazardous Waste Management Plan (TAFB HWMP), and Complex procedures per Oklahoma City Air Logistics Complex (OC-ALC) Sup to AFI 32-7086, “Hazardous Material Management” and OC-ALCI 32-101 “Air Quality Record Keeping Procedure”. Publications are available digitally on e-Publishing website at www.e-publishing.af.mil for downloading or ordering.
3.1.2 Hazardous Material (HAZMAT): If no HAZMAT will be brought on base or used in performance on this contract, the Contractor shall certify “No HAZMAT will be brought on base” or “No HAZMAT Usage” by official correspondence. This certification shall be provided to the COR within ten (10) days of the award. Upon COR receipt of the certification, the requirements of this section no longer apply. Appropriate penalties for the Contractor, or administrative and disciplinary action for the later shall be assessed if found in violation of above certification.
The Contractor shall not store chemicals or hazardous material (HAZMAT) on Tinker AFB. Contractors shall be compliant with HAZMAT management procedures per Oklahoma City Air Logistics Complex (OC-ALC) Supplement to AFI 32-7086, “Hazardous Materials Management”. The Contractor shall maintain a log of all HAZMAT that is used on base. This usage log shall be provided to the COR monthly, the last business day of each month, or when the required work is completed. The COR will forward the records to the Unit Environmental Coordinator (UEC) no later than the fourth (4th) day of the following month or the first (1st) subsequent business day.
3.1.3 Safety Data Sheet (SDS) and Labeling: Upon COR receipt of the “No HAZMAT Usage” certification, the requirements of this section no longer apply.
The Contractor shall not transport, ship, or use any chemical, material or substance used in the performance of this PWS on Tinker AFB before written approval is provided by 72 ABW/CEIE, Natural Infrastructure Management (Environmental Compliance). The Contractor shall submit to the COR, ten (10) calendar days after contract award date all Safety Data Sheets (SDSs) and a completed OC-ALC Form 152, SDS Information Sheet. The Contractor shall receive approval from the COR prior to shipping any chemical, material, or substance to Tinker AFB. A copy of the manufacturer SDS shall accompany the shipment. Contractor shall comply with the effective dates for SDS requirements IAW the Occupational Safety and Health Administrations (OSHA) Hazardous Communication Standard, Title 29, Code of Federal Regulation (CFR) Part
1910.1200. The Contractor shall ensure containers of hazardous chemicals are labeled with the following information, prior to shipping to Tinker AFB IAW OSHA Hazardous Communication Standard, Title 29, CFR Part 1910.1200 (2012): product identifier; signal word; hazard statement(s); precautionary statement(s); pictogram(s); and name, address and telephone number of the chemical manufacturer, importer, or other responsible party. The COR will forward all SDS submittals to 72 ABW/CEIE for approval. A current manufacturer SDS shall be submitted to the COR if the Contractor changes manufacturer or vendor for any chemicals that were prior approved. The Contractor shall maintain copies of manufacturer SDSs for all chemicals and SDSs shall be readily accessible at all times by Contractor personnel as well as government employees.
3.1.4 Hazardous Waste: If no HAZWASTE will be generated during performance of this contract, the Contractor shall certify “NO Hazardous Waste Generation” by official correspondence. This certification shall be provided to the COR within ten (10) days after award. Upon COR receipt of the “No Hazardous Waste Generation” certification, the requirements of this section no longer apply. Appropriate penalties for the Contractor, or administrative and disciplinary action for the later shall be assessed if found in violation of above certification.
The Contractor shall dispose of contaminated solid waste, spent or processed chemical solutions, used rags and hazardous waste in government furnished waste containers located in the shop or area the work is being performed. The Contractor shall notify the COR if the required waste containers are not available on site.
3.1.5 Discharges: Any discharges into Tinker’s industrial waste treatment plant (IWTP) or sanitary sewer shall be approved and done IAW Tinker Industrial Wastewater Discharge Permit as instructed by 72 ABW/CEIE, Natural Infrastructure Management (Environmental Compliance). Notice of intent documentation shall be provided to the COR within ten (10) days after the award. The COR will submit the required notice of intent documentation to the UEC for 72 ABW/CEIE approval. The Contractor shall not discharge into IWTP and sanitary sewer prior to approval issued by 72 ABW/CEIE. The Contractor shall maintain records of written approval issued by 72 ABW/CEIE for discharges into IWTP and sanitary sewer.
3.1.6 Off-Site Discharges: For discharges outside of Tinker AFB, the Contractor shall ensure wastewater discharges, that may contain pollutants resulting from any contracted service, go to a state or federal permitted treatment facility such as a municipal Publicly Owned Treatment Works (POTW). The Contractor shall provide official correspondence ten (10) calendar days after contract award date to the COR from the POTW that states the POTW is permitted for all pollutants that the Contractor may discharge during the contracted service.
3.1.7 Spills: Upon occurrence of any spill that could enter the storm system or cause any harmful environment effects, the Contractor shall immediately call 911 to report the incident. When possible, the Contractor shall use a base telephone to receive help from Tinker AFB 911. If using a cell phone, the Contractor shall request Tinker AFB 911. The Contractor shall immediately report all environmental violations to the COR and UEC. The Contractor shall provide five (5) copies of a typed or written report about the incident within four (4) clock hours as follows:
One (1) copy to CO, two (2) copies to the COR, a copy for UEC and one (1) copy for record. The format of the report shall be left up to the Contractor, but the report shall contain the following information:
1.) Name and contact number of person reporting the spill 2.) Date and time of incident 3.) Location and source of spill 4.) Substance or pollutant spilled 5.) Amount spilled and rate of discharge 6.) Any damages or injuries involved 7.) Extent of area impacted 8.) Potential hazards 9.) Actions taken 10.) Organizations contacted 11.) Remarks Section - that addresses the cause of the spill (e.g. human error, equipment, etc.) and whether 911 was called and which agencies responded.
3.2 Reserved
3.3 Housekeeping: The Contractor shall keep the work areas clean and neat IAW industry standards, OSHA, fire and safety standards, and this SOW.
3.4 Foreign Object Damage (FOD) and Dropped Object Prevention: Contractor personnel who work in or travel though areas near operational and production aircraft, engines, munitions, missiles, drones, space systems, support equipment, Aerospace Ground Equipment (AGE), trainers, and the Contactor personnel operating vehicles and equipment on flight lines, runways, taxiways, parking ramps, and in aircraft hangers and maintenance areas are required to receive the FOD/DOP training and to comply with AFI 36-2650, AFMC Supplement 1, paragraph 9.2., and trafficking in their supply chains and to publish information for consumer awareness.
d. Periodically access the Department of State’s Trafficking in Person (TIP) website for updates and to view the latest reports. http://www.state.gov/g/tip
3.10 Commanders Safety Intent: The safety of everyone on Tinker AFB is our top priority. All Individuals must accept personal responsibility for safety and seek opportunities for improving the safety of our work environment. Everyone working on Tinker AFB is challenged to find, fix (if able) and report all hazards and near-misses. It is our shared duty to take every reasonable step and precaution to prevent accidents and preserve the health/safety of each Contractor and government employee.
3.11 Speak up for safety: Safety surety is an integral part of our overall goal of establishing a world class safety and health program. Our “Speak Out for Safety” initiative ensures a partnership with Contractors and government employees to further enhance safety to ensure we are looking out for all our partners and empowers all employees to actively participate in each other’s safety.
A safe workplace is everyone's business. As part of the contract team, military, civilian and Contractor personnel are empowered to Speak Out for Safety (S.O.S.) when they observe an unsafe act. Events that present imminent danger to personnel or catastrophic damage to property we empower our employees to intercede to ensure continued safe operations.
3.12 Communicating Hazards of Workplace (CHOW): Contractor’s onsite representative communicates all hazards being introduced to the worksite by the Contractor. This is accomplished prior to commencement of work and refreshed daily during performance, IAW Contractor’s Site Safety Plan.
3.13 Emergency Procedures: The Contractor personnel shall follow the direction of the Government personnel with regard to emergency procedures, such as fire, tornado, active shooter, bomb threats, or other emergency. It is the responsibility of the Contractor to provide guidance and to establish procedures for its employees to respond to an emergency. It is the Contractor’s responsibility to account for their employees following an emergency evacuation. The Contractor personnel shall participate with the Government personnel in all fire and tornado drills at no additional cost to the Government.