SCOPE OF WORK
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| WD_15-4679_Rev-1_03.14.2017.pdf | ||
| BID_SCHEDULE_-_MACA_REFUSE_COLLECTION.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
May 03, 2017
REFUSE COLLECTION AND DISPOSAL
MAMMOTH CAVE NATIONAL PARK
One Year – Extend able to a Total of Four Years
SECTION 1 -- GENERAL CONDITIONS
1.1 1.1 Scope of Work
The work performed under this contract consists of furnishing materials, equipment, transportation, and labor necessary to collect refuse in accordance with the stated pick-up schedule and disposal of same at a state licensed sanitary landfill located outside of Mammoth Cave National Park.
1.2 Location
The work described in this contract is to be performed at all of the designated pick-up sites within the boundaries of Mammoth
Cave National Park. Pick-up sites and schedules are detailed on the Collection Schedule (Exhibit 1) and are shown on Exhibits 2.
1.3 Bid Schedule and Proposal
This work will be performed a yearly basis – extend-able a year at a time to a total of four years.
The Contractor will provide a quote for work period for each year they propose to collect refuse at Mammoth Cave National Park.
For example, if the Contractor proposes to collect refuse only in
2018 – the Contractor must provide a quote for each month in the refuse collection schedule.
In addition, Contractors will provide detail description of all equipment to be used as part of this Contract.
The proposal submitted by Contractors will be evaluated on the following scale:
1. Bid price: 80 points
2. Equipment: 20 points
The Contractor may also provide recommendations that included changes to the collection methodology contained herein. These changes could include, but are not limited to:
a. Equipment
b. Frequency of collection
These recommendations will be considered separately from the overall price and equipment proposals.
1.4 Personnel
1.4.1 Contractor's Supervision
The Contractor shall provide on-site supervision sufficient to assure the adequate performance of the specified work.
1.4.2 Number of Personnel
The Contractor shall provide personnel to efficiently perform the work of this contract. Failure to provide a sufficient number of qualified employees will not be grounds for any modification or waiver of contract requirements.
1.4.3 Qualifications
All employees assigned by the Contractor to perform work under this contract, including subcontractors and their employees, shall be physically able and capable of carrying out the assigned work. Person(s) operating Contractor owned equipment shall hold a current, valid State of Kentucky motor vehicle operator's license appropriate to the type of vehicle driven.
1.4.4 Notification
The Contractor shall provide the Contracting Officer with a list of all employees, including subcontractors that will be working within the park. It shall be the responsibility of the Contractor to keep the list up-to-date.
1.4.5 Training
Within two weeks of employment, all employees of the Contractor, including subcontractors, who shall be working within the park, shall meet with park staff. This includes new employees. The purpose of this meeting is to develop an understanding of the
Contractor’s role in the accomplishment of the mission, vision, and goals of the National Park Service and Mammoth Cave National
Park. This training will last up to four hours and will be scheduled through the Contracting Officer.
1.4.6 Regulations
All persons employed under this contract shall be subject to all applicable federal, state and county regulations and laws. It shall be the Contractor's responsibility to inform his/her employees of such regulation and laws, and to assure their compliance.
1.4.7 Dismissal
The Contracting Officer shall have the authority to require the
Contractor to dismiss any of his/her employee(s) working in the park that demonstrate incompetence, flagrant disregard for safety or other regulations, disorderly conduct, or
Insubordination.
1.5 Hours of Operation
All work will be accomplished between the hours of 7:00 am and
3:30 PM Central Time, unless otherwise approved by the
Contracting Officer.
1.6 Payments
1.6.1 Invoices and Payments
On the first of each month, or as approved by the Contracting
Officer, the Contractor shall provide an electronic copy of the proposed invoice for review and concurrence by the Contracting
Officer.
The Contracting Officer will have 5 working days review, comment, and/or accept the invoice. If there are issues related to non-performance and/or unacceptable work (see section 1.6.2 – these issues will be discussed with the Contractor and appropriate adjustments will be made to the invoice.
After the Contractor and the Contracting Office agree upon the invoice the Contractor will submit the invoice through the
Internet Payment Program (IPP.
The Contracting Officer will provide the Contractor with information and instructions related to the use of this system.
The Government will make monthly payments in accordance with the Prompt Payment Act based on invoices submitted by the
Contractor. Invoices must be based on the applicable portion(s) of the Bid Schedule in effect during the period covered by the invoice. Payment shall be at the applicable unit prices bid in the Contract Bid Schedule, adjusted as necessary according to
1.6.2 and shall constitute full compensation for all labor, materials, equipment, and incidentals necessary in performing the work specified.
11..66..22 Unacceptable and Non-performance
Unacceptable Work: The contracting officer may reduce the monthly payment by an appropriate amount when it has been determined that
Services performed have been less than Satisfactory and the
Contractor has been so notified in writing by issuance of a Contract
Deficiency Report (CDR). Upon the notification the Contractor will be given a specified number of workdays to correct the deficiency.
Non-Performance: The contracting officer may deduct from the
Contractor's payment an amount equal to services which the
Contractor has refused or neglected to perform.
The amount deducted from the payment will be equivalent to the cost incurred by Mammoth Cave National Park to perform the work.
1.8 Changes in Collection Schedule
The collection schedules for Areas A, B, C, D, and E are shown on Exhibit 1. The Collection Schedule provides the following information for each site:
a. Day of Collections on a month-by-month basis.
b. Number of cans or dumpsters.
Exhibit 2 and 3 provides detailed information regarding dumpster and garbage can location throughout the park.
1.9 Collection of Garbage
In accordance with the collection schedule, the Contractor shall empty “all” garbage from the dumpsters and garbage cans and change the liners in each can.
1.10 Safety
1.10.1 Accident Prevention
The Contractor shall conduct the operations, including those involving machinery and self-propelled vehicles and equipment, so as to prevent accidents, injuries, and damages, and shall observe all pertinent provisions of the
Occupational Safety and Health Act (OSHA) and shall comply with applicable state and local safety, health and sanitation laws.
1.10.2 Safety Equipment
All Contractor personnel must use approved safety equipment appropriate to the contract work being performed. Safety equipment must conform to OSHA Safety and Health Standards.
1.10.3 Accident Reporting
The Contractor shall immediately notify the Superintendent or his representative of any and all accidents to which the
Contractor's employees are a party or witness; and, of any and all accidents involving his/her employees or equipment working under this contract.
1.11 Lost and Found Property
It shall be the responsibility of the Contractor to insure that all articles found by the Contractor's employees are turned in to the Superintendent or his representative for recording and proper disposition. Items should be turned in within one working day of the time they are found.
1.12 Insurance
1.12
The Contractor must maintain insurance as required by the
Contracting Officer.
The Government will not be responsible in any way for damage to
Contractor's equipment, vehicles, tools or materials or the
Contractor's employees and their belongings brought onto the
Government's premises, occasioned by fire, theft, accident, or otherwise. Nor will the Government accept any liability as a result of Contractor or Contractor employee negligence.
Compensation
Before commencing any work, the Contractor shall furnish compensation insurance for employees engaged in this work, shall comply with the Workman's Compensation Laws of the State of
Kentucky, and shall give proof of such insurance satisfactory to the Contracting officer.
Liability
The Contractor shall maintain such insurance as will protect him/her and the Government from any claims because of bodily injury (including death) and property damage which may arise from and during the operation of this contract, and shall give proof of such insurance satisfactory to the contracting officer.
1.13 Public Contact
The Contractor and his/her employees are an extension of the park staff. Consequently, the Contractor and all of his/her employees and subcontractors shall treat all members of the visiting public with respect and courtesy, shall refer any questions to Park Employees, and shall in no instance ignore any member of the public seeking assistance or direction.
1.14 Preservation of Structures and Natural Features
The Contractor shall confine his/her activities to the specific areas to be worked. Damage to or destruction of any structure or natural feature by the Contractor shall require repair or replacement, as the Contracting Officer may direct, at the
Contractor's expense.
1.15 Temporary Suspension of Work
The Contracting Officer has the right to suspend the work wholly or in part, for such periods as may be deemed in the best interest to the Government.
The Contractor shall not suspend the work without such written authority and shall immediately resume work when conditions are favorable or when deficiencies have been corrected to the satisfaction of the Contracting Officer.
1.16 Subcontracts
The Contractor shall be as fully responsible to the Government for the acts and omissions of any subcontractors, and of the persons directly or indirectly employed by the Contractor.
Nothing contained in the contract documents shall create any contracted relationship between any subcontractors and the
Government.
1.17 Legal Obligations
The Contractor shall be responsible for the observance of all laws. ordinances, statutes, and regulations pertaining to the collection and disposal of the refuse. The Contractor shall obtain any and all licenses and pay all fees for the contracted services.
The Contractor agrees to save the Government harmless from any and all claims, demands, actions, debts, liabilities, judgments, costs and attorney's fees arising out of, claimed on account of, or in any manner predicated upon loss or damage to property or injuries to or the death of any and all persons whatsoever, in any manner caused or contributed to by the Contractor, his/her agents, servants, or employees while in, upon, or about the Mammoth Cave
National Park, on which the work upon this contract is to be done, or while going to or departing from the same, and to save the
Government harmless from and on the account of any and all damages of any kind which the Government, its officers, agents, and employees may suffer as the result of the act of the Contractor, or the act of any of the Contractor's assignees or transferees or performance, if any, his/her agents, servants, and employees in or about said Mammoth Cave National Park.
1.18 Specific Tasks
1.18.1 Dumpsters and containers listed in the pick-up schedule shall be emptied on each scheduled day.
1.18.2 Adequate measures shall be taken to prevent spillage of refuse during pick-up operation. All refuse spilled during this operation shall be cleaned up prior to leaving the site. In addition, the Contractor shall collect and dispose of all liter within 5 feet of any dumpster and/or garbage can.
1.18.3 The Contractor shall also collect and dispose of all
litter encountered while walking to the garbage cans along trails in the developed areas.
1.18.4 As stated in item 1.9, each refuse container shall be
completely emptied of its contents each time the container is scheduled for pick-up. Failure to completely empty the container will result in reduced monthly payments, as outlined in section 1.6.2. This reduction will be determined by the
Contracting Officer and will be equivalent to the costs incurred by the National Park Service to empty the container and dispose of the contents.
1.18.5 The Contractor will immediately notify the Contracting
Officer of any material too large to fit in any dumpster. The
Contractor is not responsible for the disposal of materials that will not fit reasonably into one of the park’s dumpsters.
1.18.6 After emptying, the Contractor shall return the
dumpsters and other containers to their proper station. Cans shall be lined with a new plastic liner, be in an upright position, and have the lid securely in place.
1.18.7 The Contractor and his/her employees shall work as
quietly and inconspicuously as possible while in the presence of Park visitors.
1.18.8 The Contractor and his/her employees shall work to
reduce liquid spills as a result of compaction of refuse in the
Contractor’s equipment. No compaction in the Campground
Headquarters area.
1.19 Telephone Communication
The Contractor will be available by telephone, email, and text messages during normal working hours (8:00am to 4:30pm) seven days a week.
The Contractor will also provide contact information for after hour emergencies.
1.20 Missed Containers
Should the Contracting Officer become aware of any container(s) the Contractor has missed, the Contracting Officer will inform the Contractor, by telephone. The Contractor will then have 4 hours to send a crew back to Mammoth Cave National Park to empty the container(s).
1.21 Damage to Containers
The Contractor shall take reasonable precautions to prevent damage to the containers or lids. Any containers, which are damaged during the Contractor's collection and disposal operations, shall be replaced by the Contractor to the satisfaction of the Contracting Officer, at no added expense to the government. This does not apply to normal wear and tear.
1.22 Plastic Bag Installation
Plastic bags will be installed in the garbage cans as directed by the Contracting Officer. Every effort will be made to assure the installation of the bags has a minimal impact on the visual quality of the park.
Some of the garbage cans in the park are installed within a circular wood container with a metal lid. The plastic bags shall be installed into and around the garbage cans so they do not extend over the wood container. They shall not be visible until the lid is opened.
1.23 Cleaning of Dumpsters
As required by the Contracting Officer the Contractor will clean all dumpsters. Dumpsters to be cleaned will be taken out of
Mammoth Cave National Park, thoroughly cleaned, inside and out, and disinfected. This work will be done at a site that conforms to all applicable federal, state, and local regulations related to the work.
While the dumpster is being cleaned, the Contractor will provide and place a spare dumpster. The spare dumpster will be in good condition and shall provide adequate space for storage of waste materials while the original dumpster is being cleaned. The cleaning frequency shall be twice a year for all dumpsters, in
May and October.
SECTION 2 -- DEFINITIONS
2.1 Refuse
Items thrown away and intended for disposal, including garbage, rubbish, fire place ashes, street cleanings and solid industrial wastes.
2.2 Garbage
Solid or semi-solid, animal and vegetable wastes resulting from the handling preparing, dispensing, cooking and consumption of food. This includes but is not limited to waste food, non-edible portions of food stuff, food wrappings and containers.
2.3 Rubbish
Solid wastes consisting of both combustible and non-combustible wastes such as paper, cardboard, tin cans, yard clippings, wood, glass, bedding, crockery, and similar materials.
2.4 Dumpster
A steel receptacle for the temporary retention of refuse.
Container is steel, box-like and varies in size from 1 to 6 yards.
2.5 Can
A closeable receptacle for the temporary retention of refuse.
Container is 32 gallon, cylinder shape with lid.
2.6 Contracting Officer
Contracting Officer refers to the Contracting Officer and/or the designated representative.
SECTION 3 -- GOVERNMENT FURNISHED EQUIPMENT
3.1 Containers
Unless otherwise approved by the Contracting Officer, Mammoth Cave
National Park shall furnish all cans as detailed in the pick-up schedule. Contractor will be responsible for supplying and installing all dumpsters.
SECTION 4 -- CONTRACTOR FURNISHED EQUIPMENT
4.1 Equipment
The Contractor shall provide all necessary equipment of the
Size, type and quality necessary to accomplish the requirements of this contract. Failure to provide adequate equipment will not be grounds for any modifications or waiver of contract requirements.
All of the Contractor's equipment shall be equipped with proper safety and noise limiting devices and shall be in a safe operating condition.
All vehicles shall meet applicable federal, state and county regulations and laws. Hauling equipment shall be a fully enclosed collection truck, compaction type, designed to prevent loss of refuse in transit. All equipment must be approved in writing by the
Contracting Officer before being place in service at Mammoth Cave
National Park.
All equipment shall be kept clean and present a good appearance. No leakage of any motor vehicle fluids, hydraulic fluid, trash, or liquids will be allowed. The leak must be repaired, at no expense to the National Park Service, before it can return to service with the park.
The Contractor will clean areas where fluids have leaked from the
Contractor’s equipment.
4.2 Plastic Bags
The Contractor shall provide all plastic bags required to line the garbage cans. The Contractor shall submit to the Contracting
Officer four (4) bags for the Contracting Officer’s review and approval. The Contracting Officer shall have s e v e n (7) calendar days to review and approve/disapprove the plastic bags.
The bags will conform to the following requirements:
Heavy Duty Minimum Thickness: 2 mil, Size: 33 inches by 43 inches
Color: Clear Rip resistant
4.3 Garbage Dumpsters
The Contractor will provide all dumpsters required for this work, as outlined in the Collection Schedule. The dumpsters will be clean, free of dents, and shall all be the same color.
The Contracting Officer will coordinate installation of new dumpsters. The Contracting Officer will coordinate installation of the Contractor’s dumpsters. Every effort will be made to ensure easy access to the dumpster by the Contractor’s equipment.
As required by the Contracting Officer, or as determined by the
Contractor, the Contractor will clean all dumpsters. Dumpsters to be cleaned will be taken out of Mammoth Cave National Park, thoroughly cleaned, inside and out, and disinfected. This work will be done at a site that conforms with all applicable federal, state, and local regulations related to the work.
While the dumpster is being cleaned, the Contractor will provide and place a spare dumpster. The spare dumpster will be in good condition and shall provide adequate space for storage of waste materials while the original dumpster is being cleaned.
The cleaning frequency, at a minimum, shall be twice a year for all dumpsters, in May, and in October.
4.4 Contracting Officer’s Approval
The Contractor will provide the Contracting Officer, for his approval, a list of equipment to be used within Mammoth Cave
National Park. The Contracting Officer reserves the right to inspect the equipment before approving or disapproving the equipment.
SECTION 5 -- MEASUREMENT AND PAYMENT
Acceptance of the work will be based on strict compliance with the work specifications and with the Contract Bid Schedule. Non-compliance with any specification will constitute unsatisfactory performance and the Contractor will be required to correct any deficiencies.
MAMMOTH CAVE NATIONAL PARK - REFUSE COLLECTION SCHEDULE
2018 THROUGH 2022
Exhibit 1
AREA
Location
Number
(attach 3)
(not all sites shown)
GARBAGE
CANS
DUMPSTERS
QUANTITY
DUMPSTERS
SIZE
OCT NOV
DEC thru
FEB
MAR thru
May
JUN thru
AUG
SEP
AREA "A" - MAPLE SPRINGS AREA
Maple Springs Research Complex 1 ea 6 cubic yard MO MO MO MO MO MO
Maple Springs Campground 2 ea 6 cubic yard MO MO MO MO MO
Maple Springs Picnic Area 1 ea 4 cubic yard MO MO MO MO MO MO
AREA "B" - HOUCHINS FERRY
CAMPGROUND AND PICNIC AREA
1 ea 4 cubic yard MO,TH MO MO MO,TH MO,TH,SA MO,TH
AREA "C" - VISITOR CENTER, OPERATIONS AREA, QUARTERS, CAMPGROUND AND PICNIC AREA
Headquarters - Picnic Area D1, D5, &
D6 3 ea 6 cubic yard MO, TH MO MO, TH MO,TH,SA MO, TH
Headquarters - Picnic Area D3 & D4 2 ea 4 cubic yard MO, TH MO MO, TH MO,TH,SA MO, TH
Headquarters Campground D8 2 ea 6 cubic yard MO, TH MO MO, TH MO,TH,SA MO, TH
Quarters - Seasonal D9 1 ea 6 cubic yard MO, TH MO MO MO, TH MO,TH,SA MO, TH
Warehouse - Maintenance Area D11 1 ea 6 cubic yard MO, TH MO MO MO, TH MO,TH,SA MO, TH
Facility Management - Maintenance Area D10 1 ea 6 cubic yard MO, TH MO MO MO, TH MO,TH,SA MO, TH
Visitor Center - SW Corner Parking Lot D7 1 ea 6 cubic yard MO, TH MO MO MO, TH MO,TH,SA MO, TH
Post Office-Camp store Parking Lot D12 1 ea 4 cubic yard MO MO MO MO MO MO
PARKING AREAS, WAYSIDES, AND OVERLOOKS
AREA “D” - Doyle Vally Overlook 1 MO, TH MO MO MO, TH MO,TH,SA MO, TH
AREA “E” - Sloans Crossing Picnic Area 1 MO, TH MO MO MO, TH MO,TH,SA MO, TH
Legend:
MO - Monday
TH - Thursday
SA - Saturday
MAMMOTH CAVE NATIONAL
PARK AREA LOCATION MAP
Exhibit 2
AREA "A"
MAPLE SPRINGS
AREA "C"
Visitor Center, Operations Area, Campground and Picnic
Area
AREA "B"
HOUCHINS FERRY
AREA "D"
Doyle Valley
Overlook
Area "F: Green River
Ferry Parking Lot
Dumpster Removed
AREA "E"
Sloans Crossing
Picnic Area
MAMMOTH CAVE NATIONAL PARK
GARBAGE COLLECTION
AREA C – AROUND VISITOR CENTER
DUMPSTER LOCATION
Exhibit 3
D1
D4 D5
D3
D6
D7
D12
D8
D9
D10
D11