MANA_Drawings_214078.pdf
PDF 4 MB Posted
- Attached to
- Roof Rehabilitation Federal contract opportunity
- Solicitation number
- P16PS01438
About this file
MANA Drawings 214078
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| MANA_Roof_SOW_214078.pdf | ||
| VA112.txt | TXT text file | |
| Sol_P16PS01438.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
kbenson Text Box
DRAWING FOR INFORMATIONAL PURPOSES ONLY
kbenson Text Box +/- 27' kbenson Text Box +/- 15' kbenson Text Box +/- 12' kbenson Text Box +/- 32' kbenson Text Box +/- 15' kbenson
+/- 47'
DRAWING FOR INFORMATIONAL PURPOSES ONLY
Brawner House
NOTES:
1. Remove all existing gutters and downspouts where applicable and carefully store them on site for re-installation.
2. Remove existing wood shingles and associated flashing, and related roofing material.
3. Repair or replace existing deteriorated roofing components to include sheathing or wood skip sheathing.
4. Infill existing skip sheathing to make sheathing solid a minimum of 24” on all sides of all chimneys.
5. Install self-adhering underlayment around all chimneys.
6. Install new wood shingles and associated flashing.
7. Reinstall gutters and downspouts using original gutters and downspouts.
8. Install chimney caps on all chimneys.
9. Minimize the construction limits of the project to reduce the project’s impact on the site. No ground disturbance is allowed.
10. Toxic Chemicals: Avoid materials that can leach into the ground water.
11. Waste Management: Employ processes that ensure the generation of as little waste as possible.
Recycling is a requirement of this project. All material unsuitable for recycling must be disposed of, in a legal manner, at public or private dumping areas outside the park. Waste management plan shall be submitted in draft for approval prior to Preconstruction meeting.
12. Staging area shall be determined in the field with the government.
13. Construction zone shall be marked with banner guard imprinted with "CAUTION:
CONSTRUCTION AREA", manufactured by Reef Industries, Inc., Houston, Texas, or approved equal.
14. Contractor shall protect tree trunks and root systems of trees in or adjacent to work area.
15. Observe and enforce standards of fire prevention. No open fires are permitted. Provide one fire extinguisher on each vehicle. Do not store flammable or combustible liquids in existing structures. Equip all gasoline and diesel powered equipment used in grass fire locations with spark arresters approved by U.S. Forest Service.
Line
16. Smoking within buildings or temporary storage sheds is prohibited.
17. Potable water is not available on site.
18. Provide and maintain temporary toilet facilities in accordance with State Health Department and
National Park service regulations.
PITCH
+/- 12/12 kbenson Text Box
LENGTH +/- 17'
kbenson Text Box
LENGTH +/- 37'
kbenson Text Box +/- 15.5' kbenson Text Box
WIDTH BUILDING +/- 18.5'
kbenson Text Box
LENGTH +/- 20'
kbenson Text Box +/- 3' kbenson Text Box
PITCH
+/- 12/12
Dogan House
1. Remove existing wood shingles and associated flashing, and related roofing material.
2. Repair or replace existing deteriorated roofing components to include sheathing or wood skip
3. Infill existing skip sheathing to make sheathing solid a minimum of 24” on all sides of all
4. Install self-adhering underlayment around all chimneys.
5. Install new wood shingles and associated flashing.
6. Install chimney caps on all chimneys.
7. Minimize the construction limits of the project to reduce the project’s impact on the site. No
8. Toxic Chemicals: Avoid materials that can leach into the ground water.
9. Waste Management: Employ processes that ensure the generation of as little waste as possible.
10. Staging area shall be determined in the field with the government.
11. Construction zone shall be marked with banner guard imprinted with "CAUTION:
12. Contractor shall protect tree trunks and root systems of trees in or adjacent to work area.
13. Observe and enforce standards of fire prevention. No open fires are permitted. Provide one fire structures. Equip all gasoline and diesel powered equipment used in grass fire locations with spark arresters approved by U.S. Forest Service.
14. Smoking within buildings or temporary storage sheds is prohibited.
15. Electricity is not available at Dogan House. If needed, contractor shall provide.
16. Potable water is not available on site.
17. Provide and maintain temporary toilet facilities in accordance with State Health Department and
Bradley
Notes:
1. Remove existing wood shingles and associated flashing; Remove all existing gutters and downspouts and carefully store them on site for re-installation.
2. Repair or replace existing deteriorated wood skip sheathing.
3. Install new wood shingles and associated flashing.
4. Replace gutters and downspouts.
5. Minimize the construction limits of the project to reduce the project's impact on the site. No ground disturbance is allowed.
6. Toxic Chemicals: Avoid materials that can leach into the ground water.
7. Waste Management: Employ processes that ensure the generation of as little waste as possible. Recycling is a requirement of this project. All material unsuitable for recycling must be disposed of, in a legal manner, at public or private dumping areas outside the park. Waste management plan shall be submitted in draft for approval prior to Preconstruction meeting.
8. Staging area shall be determined in the field with the government.
9. Construction zone shall be marked with banner guard imprinted with "CAUTION: CONSTRUCTION AREA", manufactured by Reef Industries, Inc, Houston, Texas, or approved equal.
10. Contractor shall protect tree trunks and root systems of trees in or adjacent to work area.
kbenson Text Box
PITCH
+/- 9/12 kbenson Text Box
+/- 40' LENGTH
kbenson
+/- 16' WIDE
Bradley
Temporary Services:
1. Observe and enforce standards of fire prevention. No open fires are permitted. Provide one fire extinguisher on each vehicle. Do not store flammable or combustible liquids in existing structures. Equip all gasoline or diesel powered equipment used in grass fire locations with spark arresters approved by the U.S. Forest Service.
2. Smoking within buildings or temporary storage sheds is prohibited.
3. Electrical power is available on site.
4. Potable water is not available on site.
5. Provide and maintain temporary toilet facilities in accordance with State Health Department and National Park Service regulations.
PITCH
+/- 9/12 kbenson
+/- 40' LENGTH X 22' WIDE
Stone House
15. For sites where electricity is available government will pay for electricity uses.
PITCH
+/- 12/12 kbenson Text Box
BUILDING
+/- 35' LENGTH X 15' WIDE
Thornberry House
Thornberry was partially reroofed in 2015. Only the remaining section of the roof shall be included in this contract.
Line kbenson
Park will furnish shingles to match existing for this building only
15. For sites where electricity is available government will pay for electricity uses. If needed, contractor shall provide.